Power system optimization method and device, storage medium and electronic equipment

By obtaining the output prediction curve and power load data of thermal power generator sets and distributed power generation equipment, calculating the power gap curve, and optimizing the power supply system, the problem of poor power supply optimization effect under manual adjustment method is solved and the power supply quality is improved.

CN118967361AActive Publication Date: 2024-11-15GUANGDONG POWER GRID CO LTD +1

Patent Information

Application Number
CN202411007915.5
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-07-25
Publication Date
2024-11-15
Estimated Expiration
2044-07-25

AI Technical Summary

Technical Problem

In the prior art, the power supply system is optimized through manual adjustment, resulting in poor power supply optimization effect.

Method used

By obtaining the output prediction curves of thermal power generator sets and distributed power generation equipment, combining the historical power load data on the user side, the power consumption gap curve is calculated, and based on this curve, a power supply optimization function is constructed and solved, and a power supply optimization strategy is formulated to optimize the power system. power supply.

Benefits of technology

The utilization rate of distributed power generation equipment and thermal power generator sets has been improved, the power supply quality has been improved, and the problem of poor power supply optimization effect under manual adjustment method has been solved.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118967361A_ABST
    Figure CN118967361A_ABST
Patent Text Reader

Abstract

The invention discloses a power system optimization method and device, a storage medium and electronic equipment. The method relates to the technical field of data processing, and comprises the following steps: obtaining a first output prediction curve of a thermal generator set in a target power system and obtaining a second output prediction curve of distributed power generation equipment in the target power system; performing prediction according to historical electrical load data of a user side to obtain a target electrical load prediction curve; calculating according to the first output prediction curve, the second output prediction curve and the target electrical load prediction curve to obtain an electrical gap curve; and performing power supply optimization on the target power system according to the power utilization gap curve. According to the method and the device, the problem of poor power supply optimization effect caused by performing power supply optimization on the power system through a manual adjustment mode in related technologies is solved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present application relates to the field of data processing technology, and in particular to an optimization method and device for an electric power system, a storage medium, and an electronic device. Background Art

[0002] With the rapid development of the economy, the gap between peak and trough electricity consumption is getting bigger and bigger, which will lead to a decrease in the load factor. In serious cases, it will lead to large-scale power outages, and the electricity demand on the user side cannot be guaranteed. Providing customers with stable, uninterrupted, high-quality electricity to meet production needs is an important goal of the power sector. In order to meet the growing load, the installed capacity needs to be continuously increased, but the blind increase in installed capacity will lead to a decrease in the annual utilization hours of power generation and transmission equipment and a continuous increase in the cost of power generation and supply, which is extremely unfavorable for the rational use of social resources. Therefore, peak control of electricity consumption is of great significance to the efficient and stable operation of the power system. In the prior art, the power supply of the power system is often optimized by manual adjustment to achieve stable operation of the power grid. However, this method has the problem of poor power supply optimization effect.

[0003] Currently, no effective solution has been proposed to solve the problem that power supply optimization of the power system is performed through manual adjustment in related technologies, resulting in poor power supply optimization effect. Summary of the invention

[0004] The main purpose of the present application is to provide a method and device for optimizing an electric power system, a storage medium and an electronic device, so as to solve the problem in the related art that the power supply optimization of the electric power system is performed by manual adjustment, resulting in poor power supply optimization effect.

[0005] In order to achieve the above-mentioned purpose, according to one aspect of the present application, a method for optimizing a power system is provided. The method comprises: obtaining a first output prediction curve of a thermal power generating unit in a target power system and obtaining a second output prediction curve of a distributed power generation device in the target power system; performing prediction based on historical power load data on the user side to obtain a target power load prediction curve; performing calculation based on the first output prediction curve, the second output prediction curve and the target power load prediction curve to obtain a power gap curve; and optimizing the power supply of the target power system based on the power gap curve.

[0006] Furthermore, obtaining a second output prediction curve of the distributed power generation equipment in the target power system includes: obtaining historical environmental data and historical output data of the area where the distributed power generation equipment is located, and constructing a training sample set based on the historical environmental data and the historical output data; training an initial output prediction model based on the training sample set to obtain a target output prediction model; and processing the current environmental data of the distributed power generation equipment through the target output prediction model to obtain the second output prediction curve.

[0007] Furthermore, predicting based on historical electricity load data on the user side to obtain a target electricity load forecast curve includes: clustering the historical electricity load data to obtain a first type of historical electricity load data and a second type of historical electricity load data; processing the first type of historical electricity load data through a first type of sequence prediction model to obtain a first electricity load forecast curve within a target time period; processing the second type of historical electricity load data through a second type of sequence prediction model to obtain a second electricity load forecast curve within the target time period; and determining the target electricity load forecast curve based on the first electricity load forecast curve and the second electricity load forecast curve.

[0008] Furthermore, calculating based on the first output forecast curve, the second output forecast curve and the target power load forecast curve to obtain the power gap curve includes: obtaining the power purchase plan curve of the target power system to the superior power grid; calculating based on the first output forecast curve, the second output forecast curve, the target power load forecast curve and the power purchase plan curve to obtain the power gap curve.

[0009] Furthermore, based on the electricity gap curve, power supply optimization for the target power system includes: constructing a power supply optimization function based on the electricity gap curve; solving the power supply optimization function to obtain a power supply optimization strategy for the target power system; and optimizing the power supply for the target power system based on the power supply optimization strategy.

[0010] Furthermore, based on the electricity gap curve, constructing a power supply optimization function includes: obtaining a demand response device on the user side, and determining a load regulation curve of the demand response device based on the type of the demand response device, wherein the demand response device is a device that can adjust the power load in response to the demand of the target power system; obtaining the capacity parameters of the energy storage device of the target power system, the operating cost of the thermal power generating set, the operating cost of the distributed power generation equipment, and the cost of purchasing electricity from the superior power grid to the target power system; constructing the power supply optimization function based on the load regulation curve, the capacity parameters, the operating cost of the thermal power generating set, the operating cost of the distributed power generation equipment, the cost of purchasing electricity from the superior power grid to the target power system, and the electricity gap curve.

[0011] Furthermore, the power supply optimization function is solved to obtain a power supply optimization strategy for the target power system, including: obtaining a first output upper limit value and a first output lower limit value of the thermal power generating set and a second output upper limit value and a second output lower limit value of the distributed power generation equipment, and determining a first output constraint condition based on the first output upper limit value, the first output lower limit value, the second output upper limit value and the second output lower limit value; obtaining a dispatching load threshold value of the demand response device based on the load regulation curve, and determining a response load constraint condition based on the dispatching load threshold value; obtaining a second output constraint condition corresponding to the energy storage device based on the capacity parameter; solving the power supply optimization function based on the first output constraint condition, the response load constraint condition and the second output constraint condition to obtain the power supply optimization strategy.

[0012] In order to achieve the above-mentioned purpose, according to another aspect of the present application, a device for optimizing a power system is provided. The device comprises: an acquisition unit, used to acquire a first output prediction curve of a thermal power generating unit in a target power system and a second output prediction curve of a distributed power generation device in the target power system; a prediction unit, used to perform prediction based on historical power load data on the user side to obtain a target power load prediction curve; a calculation unit, used to perform calculation based on the first output prediction curve, the second output prediction curve and the target power load prediction curve to obtain a power gap curve; and an optimization unit, used to optimize the power supply of the target power system based on the power gap curve.

[0013] Furthermore, the acquisition unit includes: a first acquisition module, used to acquire historical environmental data and historical output data of the area where the distributed power generation equipment is located, and construct a training sample set based on the historical environmental data and the historical output data; a training module, used to train the initial output prediction model based on the training sample set to obtain a target output prediction model; a first processing module, used to process the current environmental data of the distributed power generation equipment through the target output prediction model to obtain the second output prediction curve.

[0014] Furthermore, the prediction unit includes: a clustering module, which is used to cluster the historical power load data to obtain a first type of historical power load data and a second type of historical power load data; a second processing module, which is used to process the first type of historical power load data through a first type of sequence prediction model to obtain a first power load prediction curve within a target time period; a third processing module, which is used to process the second type of historical power load data through a second type of sequence prediction model to obtain a second power load prediction curve within the target time period; and a determination module, which is used to determine the target power load prediction curve based on the first power load prediction curve and the second power load prediction curve.

[0015] Furthermore, the calculation unit includes: a second acquisition module, used to obtain the power purchase plan curve of the target power system to the superior power grid; a calculation module, used to calculate according to the first output forecast curve, the second output forecast curve, the target power load forecast curve and the power purchase plan curve to obtain the power gap curve.

[0016] Furthermore, the optimization unit includes: a construction module, used to construct a power supply optimization function based on the electricity consumption gap curve; a solution module, used to solve the power supply optimization function to obtain a power supply optimization strategy for the target power system; and an optimization module, used to optimize the power supply of the target power system based on the power supply optimization strategy.

[0017] Furthermore, the construction module includes: a first acquisition submodule, used to acquire the demand response device on the user side, and determine the load regulation curve of the demand response device based on the type of the demand response device, wherein the demand response device is a device that can adjust the power load in response to the demand of the target power system; a second acquisition submodule, used to acquire the capacity parameters of the energy storage device of the target power system, the operating cost of the thermal power generating set, the operating cost of the distributed power generation equipment and the cost of purchasing electricity from the superior power grid to the target power system; a construction submodule, used to construct the power supply optimization function based on the load regulation curve, the capacity parameters, the operating cost of the thermal power generating set, the operating cost of the distributed power generation equipment, the cost of purchasing electricity from the superior power grid to the target power system and the electricity gap curve.

[0018] Furthermore, the solution module includes: a third acquisition submodule, used to obtain the first output upper limit value and the first output lower limit value of the thermal power generating set and the second output upper limit value and the second output lower limit value of the distributed power generation equipment, and determine the first output constraint condition based on the first output upper limit value, the first output lower limit value, the second output upper limit value and the second output lower limit value; a fourth acquisition submodule, used to obtain the dispatching load threshold value of the demand response device based on the load regulation curve, and determine the response load constraint condition based on the dispatching load threshold value; a fifth acquisition submodule, used to obtain the second output constraint condition corresponding to the energy storage device based on the capacity parameter; a solution submodule, used to solve the power supply optimization function based on the first output constraint condition, the response load constraint condition and the second output constraint condition to obtain the power supply optimization strategy.

[0019] In order to achieve the above-mentioned purpose, according to one aspect of the present application, a computer-readable storage medium is provided, wherein the storage medium stores a program, wherein when the program is running, the device where the storage medium is located is controlled to execute any one of the above-mentioned methods for optimizing the power system.

[0020] In order to achieve the above-mentioned purpose, according to another aspect of the present application, an electronic device is also provided, the electronic device includes one or more processors and a memory, and the memory is used to store one or more processors to implement any one of the above-mentioned power system optimization methods.

[0021] Through this application, the following steps are adopted: obtaining the first output prediction curve of the thermal power generating set in the target power system and obtaining the second output prediction curve of the distributed power generation equipment in the target power system; predicting according to the historical power load data on the user side to obtain the target power load prediction curve; calculating according to the first output prediction curve, the second output prediction curve and the target power load prediction curve to obtain the power gap curve; optimizing the power supply of the target power system according to the power gap curve, solving the problem of poor power supply optimization effect caused by optimizing the power supply of the power system by manual adjustment in the related technology. In this scheme, the first output prediction curve and the second output prediction curve of the thermal power generating set and the distributed power generation equipment are obtained, and the target power load prediction curve is obtained according to the historical power load data on the user side, and then the current power gap curve is determined by the target power load prediction curve, the first output prediction curve and the second output prediction curve, and finally the power supply of the target power system is optimized according to the power gap curve. The power supply control and optimization through the power gap curve can improve the utilization rate of the distributed power generation equipment and the thermal power generating set, thereby achieving the effect of improving the power supply quality. BRIEF DESCRIPTION OF THE DRAWINGS

[0022] The drawings constituting a part of the present application are used to provide a further understanding of the present application. The illustrative embodiments and descriptions of the present application are used to explain the present application and do not constitute an improper limitation on the present application. In the drawings:

[0023] Figure 1 The process of the power system optimization method provided in the embodiment of the present application is as follows Figure 1 ;

[0024] Figure 2 The process of the power system optimization method provided in the embodiment of the present application is as follows Figure 2 ;

[0025] Figure 3 is a schematic diagram of an optimization device for a power system provided according to an embodiment of the present application;

[0026] Figure 4 is a schematic diagram of a scheduling automation system provided according to an embodiment of the present application;

[0027] Figure 5 is a schematic diagram of an electronic device provided according to an embodiment of the present application. DETAILED DESCRIPTION

[0028] It should be noted that, in the absence of conflict, the embodiments and features in the embodiments of the present application can be combined with each other. The present application will be described in detail below with reference to the accompanying drawings and in combination with the embodiments.

[0029] In order to enable those skilled in the art to better understand the solution of the present application, the technical solution in the embodiments of the present application will be clearly and completely described below in conjunction with the drawings in the embodiments of the present application. Obviously, the described embodiments are only part of the embodiments of the present application, not all of the embodiments. Based on the embodiments in the present application, all other embodiments obtained by ordinary technicians in this field without creative work should fall within the scope of protection of the present application.

[0030] It should be noted that the terms "first", "second", etc. in the specification and claims of the present application and the above-mentioned drawings are used to distinguish similar objects, and are not necessarily used to describe a specific order or sequential order. It should be understood that the data used in this way can be interchanged where appropriate, so that the embodiments of the present application described here. In addition, the terms "including" and "having" and any of their variations are intended to cover non-exclusive inclusions, for example, a process, method, system, product or device comprising a series of steps or units is not necessarily limited to those steps or units clearly listed, but may include other steps or units that are not clearly listed or inherent to these processes, methods, products or devices.

[0031] It should be noted that the relevant information (including but not limited to user device information, user personal information, etc.) and data (including but not limited to data for display, data for analysis, etc.) involved in this disclosure are all information and data authorized by the user or fully authorized by all parties. For example, an interface is set between this system and the relevant user or organization. Before obtaining relevant information, it is necessary to send an acquisition request to the aforementioned user or organization through the interface, and obtain relevant information after receiving the consent information fed back by the aforementioned user or organization.

[0032] The present invention is described below in conjunction with preferred implementation steps. Figure 1 The process of the power system optimization method provided in the embodiment of the present application is as follows Figure 1 ,like Figure 1 As shown, the method comprises the following steps:

[0033] Step S101, obtaining a first output prediction curve of a thermal power generating set in a target power system and obtaining a second output prediction curve of a distributed power generation device in the target power system.

[0034] Optionally, the target power system includes distributed power generation equipment, thermal power generating units, energy storage equipment, conventional energy-consuming equipment on the user side, and demand response equipment on the user side. It should be noted that the demand response equipment on the user side is a device that can adjust the power load in response to the demand of the target power system. Demand response means that when the power supply is tight (or excessive) and there is a periodic shortage (or surplus) of electricity, the power grid company, based on the supply and demand situation, uses measures mainly based on economic incentives to invite power users with load regulation capabilities to actively reduce (or increase) the power load during a specific period agreed upon by both parties, effectively achieving peak shaving and valley filling, and alleviating the contradiction between power supply and demand.

[0035] Optionally, the first output prediction curve of the thermal power generating set and the second output prediction curve of the distributed power generation equipment in the target power system can be obtained through the data acquisition module. It should be noted that the first output prediction curve can be determined according to the historical output of the thermal power generating set, and the second output prediction curve can be determined according to the historical output of the distributed power generation equipment. It should be noted that the first output prediction curve can be the output prediction curve of the thermal power generating set in the next week. The first output prediction curve and the second output prediction curve can accurately predict the amount of electricity produced in the future.

[0036] Step S102: forecasting is performed based on the historical power load data at the user side to obtain a target power load forecasting curve.

[0037] Optionally, the historical power load data of the user side can be collected through the data collection module, and the power consumption of the user side in the future (for example, within a week) can be fitted and calculated through the historical power load data, that is, the above-mentioned target power load prediction curve. It should be noted that the above-mentioned target power load prediction curve is the estimated power consumption of conventional energy-consuming equipment on the user side.

[0038] Step S103, calculating according to the first output forecast curve, the second output forecast curve and the target power load forecast curve to obtain a power shortage curve.

[0039] Optionally, the electricity shortage curve for a period of time in the future is calculated by using the first output forecast curve, the second output forecast curve and the target power load forecast curve.

[0040] Step S104: optimizing the power supply of the target power system according to the power shortage curve.

[0041] Optionally, the target power system is optimized for power supply according to the power gap curve, for example, the output (power output) of the distributed power generator equipment and the thermal power generator set, the charging and discharging of the energy storage, and the power of the demand response equipment are optimized and adjusted.

[0042] In summary, the first output prediction curve and the second output prediction curve of the thermal power generating set and the distributed power generation equipment are obtained, and the target power load prediction curve is obtained according to the historical power load data on the user side. Then, the current power gap curve is determined by the target power load prediction curve, the first output prediction curve and the second output prediction curve. Finally, according to the power gap curve, the power supply of the target power system is optimized. Power supply control and optimization through the power gap curve can improve the utilization rate of distributed power generation equipment and thermal power generating sets, thereby achieving the effect of improving the power supply quality.

[0043] Optionally, in the power system optimization method provided in the embodiment of the present application, obtaining the second output prediction curve of the distributed power generation equipment in the target power system includes: obtaining historical environmental data and historical output data of the area where the distributed power generation equipment is located, and constructing a training sample set based on the historical environmental data and historical output data; training an initial output prediction model based on the training sample set to obtain a target output prediction model; and processing the current environmental data of the distributed power generation equipment through the target output prediction model to obtain a second output prediction curve.

[0044] In an optional embodiment, the second output prediction curve can be obtained by the following steps: collecting historical environmental data and historical output data of the area where the distributed power generation equipment is located. It should be noted that the historical environmental data includes but is not limited to the historical wind speed, historical irradiation, etc. of the area where the distributed power generation equipment is located. Then, a training sample set is constructed through the historical environmental data and historical output data, and the distributed power generation equipment prediction model (i.e., the initial output prediction model mentioned above) is trained using the training sample set to obtain the optimal model parameters.

[0045] Finally, the trained distributed power generation equipment prediction model (i.e., the above-mentioned target output prediction model) is used to perform power prediction of the distributed power generation equipment, that is, the current environmental data of the distributed power generation equipment is processed by the target output prediction model to obtain a second output prediction curve.

[0046] The target output prediction model can be used to accurately evaluate and predict the output prediction curve of distributed generation equipment.

[0047] Optionally, in the power system optimization method provided in the embodiment of the present application, prediction is performed based on historical power load data on the user side to obtain a target power load prediction curve, including: clustering the historical power load data to obtain a first type of historical power load data and a second type of historical power load data; processing the first type of historical power load data through a first type of sequence prediction model to obtain a first power load prediction curve within a target time period; processing the second type of historical power load data through a second type of sequence prediction model to obtain a second power load prediction curve within the target time period; and determining the target power load prediction curve based on the first power load prediction curve and the second power load prediction curve.

[0048] In an optional embodiment, in order to improve the accuracy of the prediction of electricity consumption on the user side, the optimization method of the power system provided in the embodiment of the present application also includes: collecting historical electricity load data on the user side. It should be noted that the historical electricity load data is the historical electricity consumption of conventional energy-consuming equipment on the user side.

[0049] After obtaining the historical power load data on the user side, the historical power load data can be clustered and divided into the first type of historical power load data and the second type of historical power load data through a clustering algorithm. For example, the data can be clustered into two types: working days and non-working days. Sequence prediction models are established respectively. The historical power load data is fused with the local meteorological data as training samples. CNN is used to extract feature vectors from the training samples. The extracted feature vectors are constructed in a time series manner and the constructed data is used as the input data of the LSTM network (i.e., the above-mentioned sequence prediction model). The LSTM network is then used for short-term load prediction. That is, the first type of historical power load data is processed by the first type of sequence prediction model to obtain the first power load prediction curve within the target time period; the second type of historical power load data is processed by the second type of sequence prediction model to obtain the second power load prediction curve within the target time period.

[0050] Finally, the final target power load forecast curve is obtained by using the first power load forecast curve and the second power load forecast curve.

[0051] Optionally, in the power system optimization method provided in the embodiment of the present application, calculation is performed based on the first output forecast curve, the second output forecast curve and the target power load forecast curve to obtain the power gap curve, including: obtaining the power purchase plan curve of the target power system to the superior power grid; calculation is performed based on the first output forecast curve, the second output forecast curve, the target power load forecast curve and the power purchase plan curve to obtain the power gap curve.

[0052] In an optional embodiment, during actual power supply, the target power system may need to purchase a certain amount of electricity from the superior power grid in order to maintain the stability of power supply. Therefore, the following steps are included when calculating the power gap curve: obtaining the power purchase plan curve of the target power system from the superior power grid, and then calculating through the first output forecast curve, the second output forecast curve, the target power load forecast curve and the power purchase plan curve to obtain the power gap curve.

[0053] In an optional embodiment, the above-mentioned power consumption gap curve can be calculated by the following formula (1):

[0054] P q,t =P load,t -P buy,t -P dg,t -P gt,t (1)

[0055] Among them, P q,t is the power shortage of the power grid at time t (i.e. the power shortage curve mentioned above), P load,t is the predicted power of the conventional energy-consuming equipment load on the user side at time t (i.e., the target power load prediction curve mentioned above), P buy,t is the planned power purchase power at time t (i.e. the above-mentioned planned power purchase curve), P dg,t , P gt,t They are respectively the output of the distributed power generation equipment and the output of the thermal power generation unit at time t (ie, the first output prediction curve and the second output prediction curve mentioned above).

[0056] Optionally, in the power system optimization method provided in the embodiment of the present application, power supply optimization of the target power system is performed based on the power gap curve, including: constructing a power supply optimization function based on the power gap curve; solving the power supply optimization function to obtain a power supply optimization strategy for the target power system; and optimizing the power supply of the target power system based on the power supply optimization strategy.

[0057] In an optional embodiment, the following steps are adopted to optimize the power supply of the target power system: construct a power supply optimization function according to the power gap curve, for example, construct a power deviation minimum function according to the power gap curve, and use the power deviation minimum function as the power supply optimization function, and then solve the power supply optimization function to obtain the power supply optimization strategy, that is, how to adjust the output (power output) of the distributed generators and thermal generators at the power equipment layer, the charging and discharging of energy storage, and the power of the demand response equipment. Finally, according to the power supply optimization strategy, the power supply of the target power system is optimized.

[0058] The power supply optimization function can more accurately and efficiently determine how to optimize the power supply of the target power system.

[0059] Optionally, in the power system optimization method provided in the embodiment of the present application, constructing a power supply optimization function based on the power gap curve includes: obtaining a demand response device on the user side, and determining a load regulation curve of the demand response device based on the type of the demand response device, wherein the demand response device is a device that can adjust the power load in response to the demand of the target power system; obtaining the capacity parameters of the energy storage device of the target power system, the operating cost of the thermal power generating set, the operating cost of the distributed power generation equipment, and the cost of purchasing electricity from the superior power grid to the target power system; constructing a power supply optimization function based on the load regulation curve, the capacity parameters, the operating cost of the thermal power generating set, the operating cost of the distributed power generation equipment, the cost of purchasing electricity from the superior power grid to the target power system, and the power gap curve.

[0060] In an optional embodiment, the above-mentioned power supply optimization function is obtained by the following steps: obtaining the demand response device on the user side, and then determining the load regulation curve of the demand response device according to the type of the demand response device. It should be noted that there are two main types of demand response devices: price-type response and incentive-type response load. The incentive-type load response method generally formulates a responsive scheduling plan for the load according to the supply and demand situation in the microgrid, and gives a certain compensation fee to the load participating in the response. The price-type load response generally guides users to formulate reasonable power consumption plans by setting time-of-use electricity prices, thereby reducing the peak load power consumption in certain periods of the microgrid.

[0061] In an optional embodiment, the load regulation curve of the price-based demand response device is shown in formula (2):

[0062]

[0063] in, is the price-based demand response load value at the initial moment, is the price-based demand response load value at time t after participating in the load response, is the adjustable load value of price-based demand response at time t, η t is the load response rate of price-based demand response at time t, are the minimum incentive electricity price and the maximum incentive electricity price respectively, ε is the electricity price incentive coefficient of price-type demand response, and α is the power exponent.

[0064] In an optional embodiment, the load regulation curve of the price-based demand response device is as shown in formula (3):

[0065]

[0066] in, is the load value of the excitation load response at the initial moment, The load value of the incentive load response at time t after participating in the load response, is the adjustable load value of the excitation load response at time t, is the proportion of load transferred out at time t, is the proportion of load transfer entering at time t, is the ratio of load removal at time t.

[0067] After obtaining the above-mentioned load regulation curve, the capacity parameters of the energy storage equipment of the target power system, the operating cost of the thermal power generating units, the operating cost of the distributed power generation equipment and the cost of purchasing electricity from the target power system to the superior power grid are obtained. Finally, according to the load regulation curve, capacity parameters, the operating cost of the thermal power generating units, the operating cost of the distributed power generation equipment, the cost of purchasing electricity from the target power system to the superior power grid and the electricity gap curve, a power supply optimization function is constructed.

[0068] In an optional embodiment, the minimum peak-shifting regulation cost F1 and the minimum peak-shifting control power deviation F2 are used as the power supply optimization function. Specifically, it is:

[0069]

[0070] Where T represents the number of time periods, C gt,t , C dg,t They represent the operating costs of distributed generation equipment and thermal power generation units in period t, respectively, grid,t , P grid,t They represent the electricity price and power (i.e., the amount of electricity purchased) from the upper power grid during the period t, respectively. sc,t is the charging and discharging electricity price of energy storage equipment in period t, P dis,t , P chr,t represents the energy storage discharge power and charging power in time period t, λ ibdr,t , pbdr,t They represent the incentive load response electricity price and price demand response electricity price in period t, respectively. ibdr,t , P pbdr,t They represent the incentive-type load response regulation power (obtained according to the load regulation curve) and the price-type demand response regulation power in period t respectively; P q,t is the power shortage of the power grid at time t.

[0071] By using the lowest peak-shifting regulation cost F1 and the smallest peak-shifting control power deviation F2 as the power supply optimization function, the power supply optimization strategy can be determined more accurately and reasonably, and the power supply stability of the power system can be improved.

[0072] Optionally, in the power system optimization method provided in the embodiment of the present application, the power supply optimization function is solved to obtain the power supply optimization strategy for the target power system, including: obtaining the first output upper limit value and the first output lower limit value of the thermal power generating set and the second output upper limit value and the second output lower limit value of the distributed power generation equipment, and determining the first output constraint condition based on the first output upper limit value, the first output lower limit value, the second output upper limit value and the second output lower limit value; obtaining the dispatching load threshold of the demand response device based on the load regulation curve, and determining the response load constraint condition based on the dispatching load threshold value; obtaining the second output constraint condition corresponding to the energy storage device based on the capacity parameter; solving the power supply optimization function based on the first output constraint condition, the response load constraint condition and the second output constraint condition to obtain the power supply optimization strategy.

[0073] In an optional embodiment, when solving the power supply optimization function, in order to avoid unreasonable power supply optimization strategies, the following steps are used to solve the function:

[0074] First, obtain the first output upper limit value and the first output lower limit value of the thermal power generating set and the second output upper limit value and the second output lower limit value of the distributed power generation equipment, and then determine the first output constraint condition according to the first output upper limit value, the first output lower limit value, the second output upper limit value and the second output lower limit value.

[0075] In an optional embodiment, the first output constraint condition may be as shown in formula (5):

[0076] P gt,min ≤P gt,t ≤P gt,max

[0077] P dg,min ≤P dg,t ≤P dg,max (5)

[0078] Among them, P gt,min , P gt,max and P dg,min , P dg,max They are the upper and lower output limits of the thermal power unit and the distributed power generation unit, namely the first output upper limit value, the first output lower limit value, the second output upper limit value and the second output lower limit value mentioned above.

[0079] Then, the dispatching load threshold of the demand response device is determined according to the load regulation curve, and the response load constraint condition is determined according to the dispatching load threshold.

[0080] In an optional embodiment, the response load constraint condition is as shown in formula (6):

[0081] P ibdr,min <P ibdr,t<P ibdr,max

[0082] P pbdr,min <P pbdr,t <P pbdr,max (6)

[0083] Among them, P ibdr,min , P ibdr,max and P pbdr,min , P pbdr,max They respectively represent the minimum and maximum dispatchable powers of the incentive-type load response device and the price-type demand response device (i.e., the dispatch load thresholds mentioned above).

[0084] Finally, according to the capacity parameters of the energy storage device, the second output constraint condition corresponding to the energy storage device is obtained. Based on the first output constraint condition, the power supply optimization function is solved in response to the load constraint condition and the second output constraint condition to obtain the power supply optimization strategy.

[0085] In an optional embodiment, the second output constraint condition is as shown in formula (7):

[0086]

[0087] Among them, SOC t , SOC t-1 Respectively represent the SOC value of the energy storage device at time t and time t-1; Respectively represent the charging and discharging capacity of the energy storage device at time t; η chr , η dis They represent the charging efficiency and discharging efficiency of the energy storage device at time t; SOC min , SOC max Respectively represent the minimum and maximum SOC values ​​of the energy storage device; Indicates the minimum and maximum discharge values ​​of the energy storage device at time t; Indicates the minimum and maximum charging values ​​of the energy storage device at time t.

[0088] In an optional embodiment, when solving the power supply optimization function, the constraints of the transmission power value of the power grid and the upper power grid tie line may also be considered. For example, the constraints are shown in formula (8):

[0089] 0<P tline,t <P tline,max (8)

[0090] Among them, P tline,t represents the transmission power value of the tie line between the power grid and the upper power grid at time t, P tline,max Indicates the maximum power limit of the power grid and the upper power grid tie line

[0091] In an optional embodiment, the Figure 2 The flowchart shown realizes the control of the power system, specifically including: obtaining the output forecast curve of the thermal power generating unit and the capacity configuration of the energy storage equipment at the power equipment layer of the power grid and the adjustable curve of the demand response equipment on the user side, as well as obtaining the output forecast curve of the distributed power generation equipment and the load forecast curve of the conventional energy-consuming equipment on the user side. Obtain the power purchase plan curve to the superior power grid. Then, according to the power purchase plan curve, the output forecast curve of the distributed power generation equipment, the output forecast curve of the thermal power generating unit and the load forecast curve, the power gap curve is determined, and finally the peak shifting optimization is performed based on the power gap curve.

[0092] The optimization method of the power system provided in the embodiment of the present application obtains the first output prediction curve of the thermal power generator set in the target power system and obtains the second output prediction curve of the distributed power generation equipment in the target power system; predicts according to the historical power load data on the user side to obtain the target power load prediction curve; calculates according to the first output prediction curve, the second output prediction curve and the target power load prediction curve to obtain the power gap curve; according to the power gap curve, the power supply of the target power system is optimized, which solves the problem that the power supply optimization of the power system is performed by manual adjustment in the related technology, resulting in poor power supply optimization effect. In this scheme, the first output prediction curve and the second output prediction curve of the thermal power generator set and the distributed power generation equipment are obtained, and the target power load prediction curve is obtained according to the historical power load data on the user side, and then the current power gap curve is determined by the target power load prediction curve, the first output prediction curve and the second output prediction curve, and finally the power supply of the target power system is optimized according to the power gap curve. The power supply control and optimization through the power gap curve can improve the utilization rate of the distributed power generation equipment and the thermal power generator set, thereby achieving the effect of improving the power supply quality.

[0093] It should be noted that the steps shown in the flowcharts of the accompanying drawings can be executed in a computer system such as a set of computer executable instructions, and that, although a logical order is shown in the flowcharts, in some cases, the steps shown or described can be executed in an order different from that shown here.

[0094] The embodiment of the present application also provides an optimization device for a power system. It should be noted that the optimization device for a power system in the embodiment of the present application can be used to execute the optimization method for a power system provided in the embodiment of the present application. The optimization device for a power system provided in the embodiment of the present application is introduced below.

[0095] Figure 3 Schematic diagram of an optimization device for a power system according to an embodiment of the present application. Figure 3As shown, the device includes: an acquisition unit 301, a prediction unit 302, a calculation unit 303 and an optimization unit 304.

[0096] An acquisition unit 301 is used to acquire a first output prediction curve of a thermal power generating unit in a target power system and to acquire a second output prediction curve of a distributed power generating device in the target power system;

[0097] The prediction unit 302 is used to make a prediction based on the historical power load data of the user side to obtain a target power load prediction curve;

[0098] A calculation unit 303 is used to calculate according to the first output prediction curve, the second output prediction curve and the target power load prediction curve to obtain a power shortage curve;

[0099] The optimization unit 304 is used to optimize the power supply of the target power system according to the power shortage curve.

[0100] The power system optimization device provided in the embodiment of the present application obtains the first output prediction curve of the thermal power generating set in the target power system and the second output prediction curve of the distributed power generation equipment in the target power system through the acquisition unit 301; the prediction unit 302 predicts according to the historical power load data on the user side to obtain the target power load prediction curve; the calculation unit 303 calculates according to the first output prediction curve, the second output prediction curve and the target power load prediction curve to obtain the power gap curve; the optimization unit 304 optimizes the power supply of the target power system according to the power gap curve, which solves the problem of poor power supply optimization effect caused by optimizing the power supply of the power system through manual adjustment in the related art. In this scheme, the first output prediction curve and the second output prediction curve of the thermal power generating set and the distributed power generation equipment are obtained, and the target power load prediction curve is obtained according to the historical power load data on the user side. Then, the current power gap curve is determined by the target power load prediction curve, the first output prediction curve and the second output prediction curve. Finally, according to the power gap curve, the power supply of the target power system is optimized. Power supply control and optimization through the power gap curve can improve the utilization rate of the distributed power generation equipment and the thermal power generating set, thereby achieving the effect of improving the power supply quality.

[0101] Optionally, in the optimization device of the power system provided in the embodiment of the present application, the acquisition unit includes: a first acquisition module, used to acquire historical environmental data and historical output data of the area where the distributed power generation equipment is located, and construct a training sample set based on the historical environmental data and historical output data; a training module, used to train the initial output prediction model based on the training sample set to obtain a target output prediction model; a first processing module, used to process the current environmental data of the distributed power generation equipment through the target output prediction model to obtain a second output prediction curve.

[0102] Optionally, in the optimization device of the power system provided in the embodiment of the present application, the prediction unit includes: a clustering module, used to cluster the historical power load data to obtain a first type of historical power load data and a second type of historical power load data; a second processing module, used to process the first type of historical power load data through a first type of sequence prediction model to obtain a first power load prediction curve within a target time period; a third processing module, used to process the second type of historical power load data through a second type of sequence prediction model to obtain a second power load prediction curve within the target time period; a determination module, used to determine the target power load prediction curve based on the first power load prediction curve and the second power load prediction curve.

[0103] Optionally, in the power system optimization device provided in the embodiment of the present application, the calculation unit includes: a second acquisition module, used to obtain the power purchase plan curve of the target power system to the superior power grid; a calculation module, used to calculate based on the first output forecast curve, the second output forecast curve, the target power load forecast curve and the power purchase plan curve to obtain the power gap curve.

[0104] Optionally, in the power system optimization device provided in the embodiment of the present application, the optimization unit includes: a construction module, used to construct a power supply optimization function based on the power consumption gap curve; a solution module, used to solve the power supply optimization function to obtain a power supply optimization strategy for the target power system; and an optimization module, used to optimize the power supply of the target power system based on the power supply optimization strategy.

[0105] Optionally, in the power system optimization device provided in the embodiment of the present application, the construction module includes: a first acquisition submodule, used to acquire the demand response device on the user side, and determine the load regulation curve of the demand response device based on the type of the demand response device, wherein the demand response device is a device that can adjust the power load in response to the demand of the target power system; a second acquisition submodule, used to acquire the capacity parameters of the energy storage device of the target power system, the operating cost of the thermal power generating set, the operating cost of the distributed power generation equipment and the cost of purchasing electricity from the superior power grid to the target power system; a construction submodule, used to construct a power supply optimization function based on the load regulation curve, capacity parameters, the operating cost of the thermal power generating set, the operating cost of the distributed power generation equipment, the cost of purchasing electricity from the superior power grid to the target power system and the power gap curve.

[0106] Optionally, in the optimization device of the power system provided in the embodiment of the present application, the solution module includes: a third acquisition submodule, used to obtain the first output upper limit value and the first output lower limit value of the thermal power generating set and the second output upper limit value and the second output lower limit value of the distributed power generation equipment, and determine the first output constraint condition based on the first output upper limit value, the first output lower limit value, the second output upper limit value and the second output lower limit value; a fourth acquisition submodule, used to obtain the dispatching load threshold of the demand response device based on the load regulation curve, and determine the response load constraint condition based on the dispatching load threshold value; a fifth acquisition submodule, used to obtain the second output constraint condition corresponding to the energy storage device based on the capacity parameter; a solution submodule, used to solve the power supply optimization function based on the first output constraint condition, the response load constraint condition and the second output constraint condition to obtain the power supply optimization strategy.

[0107] The optimization device of the power system includes a processor and a memory. The above-mentioned acquisition unit 301, prediction unit 302, calculation unit 303 and optimization unit 304 are all stored in the memory as program units, and the processor executes the above-mentioned program units stored in the memory to realize corresponding functions.

[0108] The processor includes a kernel, which calls the corresponding program unit from the memory. One or more kernels can be set, and the power system can be efficiently optimized by adjusting the kernel parameters.

[0109] The memory may include non-permanent memory in a computer-readable medium, random access memory (RAM) and / or non-volatile memory, such as read-only memory (ROM) or flash RAM, and the memory includes at least one memory chip.

[0110] In an optional embodiment, a scheduling automation system is also provided, such as Figure 4As shown, the dispatching automation system specifically includes: a power equipment layer 40, a data terminal layer 41, a data transmission layer 42 and a power grid dispatching layer 43; the power equipment layer 40 includes distributed generator sets, thermal power generator sets, energy storage equipment, user-side conventional energy-consuming equipment and user-side demand response equipment.

[0111] The data terminal layer 41 includes a data acquisition module 410, an output prediction module 411, a load prediction module 412 and an equipment control module 413. The data acquisition module 410 is used to obtain the output curve of the thermal power generating units and the capacity configuration of the energy storage equipment at the power equipment layer of the power grid and the adjustable curve of the demand response equipment on the user side. The output prediction module 411 is used to obtain the output prediction curve of the distributed power generation equipment. The load prediction module 412 is used to obtain the load prediction curve of the conventional energy-consuming equipment on the user side. The equipment control module 413 is used to receive the peak-shifting control instructions of the power grid dispatching layer. The equipment control module is also used to control the equipment at the power equipment layer.

[0112] The data transmission layer 42 is used to provide data communication services for the data collection layer 41 and the power grid dispatching layer 43. It uploads the output curve of the thermal power generating unit and the output forecast curve of the distributed power generation equipment collected by the data collection layer, the load forecast curve of the conventional energy-consuming equipment on the user side, and the adjustable curve of the demand response equipment on the user side to the power grid dispatching layer, and transmits the control instructions of the power grid dispatching layer to the power equipment layer 40;

[0113] The power grid dispatching layer 43 includes a module 430 for determining a power gap curve and a power grid peak shifting control optimization module 431. The module 430 for determining a power gap curve is used to analyze and save data from the data transmission layer. The module 430 for determining a power gap curve is also used to obtain a power purchase plan curve from a superior power grid, and determine a power gap curve based on the power purchase plan curve, the output forecast curve of distributed power generation equipment, the output curve of thermal power generation units, and the conventional load energy consumption curve. The power grid peak shifting control optimization module 431 performs peak shifting optimization based on the power gap curve, forms a peak shifting control instruction, and issues the instruction through the data transmission layer.

[0114] An embodiment of the present invention provides a computer-readable storage medium having a program stored thereon, and the program implements a method for optimizing a power system when executed by a processor.

[0115] An embodiment of the present invention provides a processor, which is used to run a program, wherein the program executes an optimization method for a power system when the program is running.

[0116] like Figure 5As shown, an embodiment of the present invention provides an electronic device, the device includes a processor, a memory, and a program stored in the memory and executable on the processor, and the processor implements the following steps when executing the program: obtaining a first output prediction curve of a thermal power generator set in a target power system and obtaining a second output prediction curve of a distributed power generation device in the target power system; performing prediction based on historical power load data on the user side to obtain a target power load prediction curve; performing calculation based on the first output prediction curve, the second output prediction curve, and the target power load prediction curve to obtain a power gap curve; and optimizing power supply to the target power system based on the power gap curve.

[0117] Optionally, obtaining a second output prediction curve of distributed power generation equipment in the target power system includes: obtaining historical environmental data and historical output data of the area where the distributed power generation equipment is located, and constructing a training sample set based on the historical environmental data and historical output data; training an initial output prediction model based on the training sample set to obtain a target output prediction model; and processing the current environmental data of the distributed power generation equipment through the target output prediction model to obtain a second output prediction curve.

[0118] Optionally, making predictions based on historical electricity load data on the user side to obtain a target electricity load prediction curve includes: clustering the historical electricity load data to obtain a first type of historical electricity load data and a second type of historical electricity load data; processing the first type of historical electricity load data through a first type of sequence prediction model to obtain a first electricity load prediction curve within a target time period; processing the second type of historical electricity load data through a second type of sequence prediction model to obtain a second electricity load prediction curve within the target time period; and determining the target electricity load prediction curve based on the first electricity load prediction curve and the second electricity load prediction curve.

[0119] Optionally, calculating based on the first output forecast curve, the second output forecast curve and the target power load forecast curve to obtain the power gap curve includes: obtaining the power purchase plan curve of the target power system to the superior power grid; calculating based on the first output forecast curve, the second output forecast curve, the target power load forecast curve and the power purchase plan curve to obtain the power gap curve.

[0120] Optionally, optimizing power supply to the target power system based on the power gap curve includes: constructing a power supply optimization function based on the power gap curve; solving the power supply optimization function to obtain a power supply optimization strategy for the target power system; and optimizing power supply to the target power system based on the power supply optimization strategy.

[0121] Optionally, based on the electricity gap curve, constructing a power supply optimization function includes: obtaining a demand response device on the user side, and determining a load regulation curve of the demand response device based on the type of the demand response device, wherein the demand response device is a device that can adjust the power load in response to the demand of the target power system; obtaining the capacity parameters of the energy storage device of the target power system, the operating cost of the thermal power generating set, the operating cost of the distributed power generation equipment, and the cost of purchasing electricity from the superior power grid to the target power system; constructing a power supply optimization function based on the load regulation curve, capacity parameters, the operating cost of the thermal power generating set, the operating cost of the distributed power generation equipment, the cost of purchasing electricity from the superior power grid to the target power system, and the electricity gap curve.

[0122] Optionally, solving the power supply optimization function to obtain a power supply optimization strategy for the target power system includes: obtaining a first output upper limit value and a first output lower limit value of the thermal power generating set and a second output upper limit value and a second output lower limit value of the distributed power generation equipment, and determining a first output constraint condition based on the first output upper limit value, the first output lower limit value, the second output upper limit value and the second output lower limit value; obtaining a dispatching load threshold value of the demand response device based on the load regulation curve, and determining a response load constraint condition based on the dispatching load threshold value; obtaining a second output constraint condition corresponding to the energy storage device based on the capacity parameter; solving the power supply optimization function based on the first output constraint condition, the response load constraint condition and the second output constraint condition to obtain a power supply optimization strategy.

[0123] The devices in this article can be servers, PCs, PADs, mobile phones, etc.

[0124] The present application also provides a computer program product, which, when executed on a data processing device, is suitable for executing a program that initializes the following method steps: obtaining a first output prediction curve of a thermal power generator set in a target power system and obtaining a second output prediction curve of a distributed power generation device in the target power system; making a prediction based on historical power load data on the user side to obtain a target power load prediction curve; calculating based on the first output prediction curve, the second output prediction curve and the target power load prediction curve to obtain a power gap curve; and optimizing the power supply of the target power system based on the power gap curve.

[0125] Optionally, obtaining a second output prediction curve of distributed power generation equipment in the target power system includes: obtaining historical environmental data and historical output data of the area where the distributed power generation equipment is located, and constructing a training sample set based on the historical environmental data and historical output data; training an initial output prediction model based on the training sample set to obtain a target output prediction model; and processing the current environmental data of the distributed power generation equipment through the target output prediction model to obtain a second output prediction curve.

[0126] Optionally, making predictions based on historical electricity load data on the user side to obtain a target electricity load prediction curve includes: clustering the historical electricity load data to obtain a first type of historical electricity load data and a second type of historical electricity load data; processing the first type of historical electricity load data through a first type of sequence prediction model to obtain a first electricity load prediction curve within a target time period; processing the second type of historical electricity load data through a second type of sequence prediction model to obtain a second electricity load prediction curve within the target time period; and determining the target electricity load prediction curve based on the first electricity load prediction curve and the second electricity load prediction curve.

[0127] Optionally, calculating based on the first output forecast curve, the second output forecast curve and the target power load forecast curve to obtain the power gap curve includes: obtaining the power purchase plan curve of the target power system to the superior power grid; calculating based on the first output forecast curve, the second output forecast curve, the target power load forecast curve and the power purchase plan curve to obtain the power gap curve.

[0128] Optionally, optimizing power supply to the target power system based on the power gap curve includes: constructing a power supply optimization function based on the power gap curve; solving the power supply optimization function to obtain a power supply optimization strategy for the target power system; and optimizing power supply to the target power system based on the power supply optimization strategy.

[0129] Optionally, based on the electricity gap curve, constructing a power supply optimization function includes: obtaining a demand response device on the user side, and determining a load regulation curve of the demand response device based on the type of the demand response device, wherein the demand response device is a device that can adjust the power load in response to the demand of the target power system; obtaining the capacity parameters of the energy storage device of the target power system, the operating cost of the thermal power generating set, the operating cost of the distributed power generation equipment, and the cost of purchasing electricity from the superior power grid to the target power system; constructing a power supply optimization function based on the load regulation curve, capacity parameters, the operating cost of the thermal power generating set, the operating cost of the distributed power generation equipment, the cost of purchasing electricity from the superior power grid to the target power system, and the electricity gap curve.

[0130] Optionally, solving the power supply optimization function to obtain a power supply optimization strategy for the target power system includes: obtaining a first output upper limit value and a first output lower limit value of the thermal power generating set and a second output upper limit value and a second output lower limit value of the distributed power generation equipment, and determining a first output constraint condition based on the first output upper limit value, the first output lower limit value, the second output upper limit value and the second output lower limit value; obtaining a dispatching load threshold value of the demand response device based on the load regulation curve, and determining a response load constraint condition based on the dispatching load threshold value; obtaining a second output constraint condition corresponding to the energy storage device based on the capacity parameter; solving the power supply optimization function based on the first output constraint condition, the response load constraint condition and the second output constraint condition to obtain a power supply optimization strategy.

[0131] Those skilled in the art will appreciate that the embodiments of the present application may be provided as methods, systems, or computer program products. Therefore, the present application may adopt the form of a complete hardware embodiment, a complete software embodiment, or an embodiment in combination with software and hardware. Moreover, the present application may adopt the form of a computer program product implemented in one or more computer-usable storage media (including but not limited to disk storage, CD-ROM, optical storage, etc.) that include computer-usable program code.

[0132] The present application is described with reference to the flowcharts and / or block diagrams of the methods, devices (systems), and computer program products according to the embodiments of the present application. It should be understood that each process and / or box in the flowchart and / or block diagram, as well as the combination of the processes and / or boxes in the flowchart and / or block diagram, can be implemented by computer program instructions. These computer program instructions can be provided to a processor of a general-purpose computer, a special-purpose computer, an embedded processor, or other programmable data processing device to generate a machine, so that the instructions executed by the processor of the computer or other programmable data processing device generate instructions for implementing the processes in the flowchart and / or block diagram. Figure 1 A process or multiple processes and / or boxes Figure 1 A device that provides the functions specified in a block or multiple blocks.

[0133] These computer program instructions may also be stored in a computer-readable memory capable of directing a computer or other programmable data processing device to operate in a specific manner, so that the instructions stored in the computer-readable memory produce an article of manufacture comprising an instruction device, which implements the process Figure 1 A process or multiple processes and / or boxes Figure 1 A function specified in one or more boxes.

[0134] These computer program instructions can also be loaded onto a computer or other programmable data processing device so that a series of operating steps are executed on the computer or other programmable device to produce a computer-implemented process, thereby providing instructions for implementing the process. Figure 1 A process or multiple processes and / or boxes Figure 1 The steps for the functions specified in one or more boxes.

[0135] In a typical configuration, a computing device includes one or more processors (CPU), input / output interfaces, network interfaces, and memory.

[0136] The memory may include non-permanent memory in a computer-readable medium, random access memory (RAM) and / or non-volatile memory in the form of read-only memory (ROM) or flash RAM. The memory is an example of a computer-readable medium.

[0137] Computer readable media include permanent and non-permanent, removable and non-removable media that can be implemented by any method or technology to store information. Information can be computer readable instructions, data structures, program modules or other data. Examples of computer storage media include, but are not limited to, phase change memory (PRAM), static random access memory (SRAM), dynamic random access memory (DRAM), other types of random access memory (RAM), read-only memory (ROM), electrically erasable programmable read-only memory (EEPROM), flash memory or other memory technology, compact disk read-only memory (CD-ROM), digital versatile disk (DVD) or other optical storage, magnetic cassettes, magnetic tape disk storage or other magnetic storage devices or any other non-transmission media that can be used to store information that can be accessed by a computing device. As defined herein, computer readable media does not include temporary computer readable media (transitory media), such as modulated data signals and carrier waves.

[0138] It should also be noted that the terms "include", "comprises" or any other variations thereof are intended to cover non-exclusive inclusion, so that a process, method, commodity or device including a series of elements includes not only those elements, but also other elements not explicitly listed, or also includes elements inherent to such process, method, commodity or device. In the absence of more restrictions, the elements defined by the sentence "comprises a ..." do not exclude the existence of other identical elements in the process, method, commodity or device including the elements.

[0139] Those skilled in the art will appreciate that the embodiments of the present application may be provided as methods, systems or computer program products. Therefore, the present application may adopt the form of a complete hardware embodiment, a complete software embodiment or an embodiment in combination with software and hardware. Moreover, the present application may adopt the form of a computer program product implemented on one or more computer-usable storage media (including but not limited to disk storage, CD-ROM, optical storage, etc.) that contain computer-usable program code.

[0140] The above are only embodiments of the present application and are not intended to limit the present application. For those skilled in the art, the present application may have various changes and variations. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the present application should be included within the scope of the claims of the present application.

Claims

1. A method for optimizing a power system, characterized in that: include: Acquire a first output prediction curve of a thermal power generating unit in a target power system and acquire a second output prediction curve of a distributed power generating device in the target power system; Based on the historical power load data on the user side, a forecast is made to obtain the target power load forecast curve; Calculating according to the first output forecast curve, the second output forecast curve and the target power load forecast curve to obtain a power shortage curve; The target power system is optimized for power supply according to the power shortage curve.

2. The method according to claim 1, characterized in that Acquiring a second output prediction curve of the distributed power generation equipment in the target power system includes: Acquire historical environmental data and historical output data of the area where the distributed power generation equipment is located, and construct a training sample set based on the historical environmental data and the historical output data; Training the initial output prediction model according to the training sample set to obtain a target output prediction model; The current environmental data of the distributed power generation equipment is processed by the target output prediction model to obtain the second output prediction curve.

3. The method according to claim 1, characterized in that Based on the historical power load data on the user side, the target power load forecast curve is obtained, including: Clustering the historical power load data to obtain first-category historical power load data and second-category historical power load data; Processing the first type of historical power load data by using a first type of sequence prediction model to obtain a first power load prediction curve within a target time period; Processing the second type of historical power load data by using a second type of sequence prediction model to obtain a second power load prediction curve within the target time period; The target power load forecast curve is determined based on the first power load forecast curve and the second power load forecast curve.

4. The method according to claim 1, characterized in that: Calculating according to the first output forecast curve, the second output forecast curve and the target power load forecast curve to obtain a power gap curve includes: Obtaining a power purchase plan curve of the target power system from a higher-level power grid; The electricity gap curve is obtained by performing calculations based on the first output forecast curve, the second output forecast curve, the target power load forecast curve, and the power purchase plan curve.

5. The method according to claim 4, characterized in that According to the power shortage curve, optimizing the power supply of the target power system includes: According to the electricity gap curve, construct a power supply optimization function; Solving the power supply optimization function to obtain a power supply optimization strategy for the target power system; According to the power supply optimization strategy, power supply optimization is performed on the target power system.

6. The method according to claim 5, characterized in that According to the electricity consumption gap curve, constructing a power supply optimization function includes: Obtaining a demand response device at the user side, and determining a load adjustment curve of the demand response device according to the type of the demand response device, wherein the demand response device is a device capable of adjusting the power load in response to the demand of the target power system; Acquire the capacity parameters of the energy storage equipment of the target power system, the operating cost of the thermal power generating unit, the operating cost of the distributed power generation equipment, and the cost of purchasing electricity from the target power system to the upper power grid; The power supply optimization function is constructed based on the load regulation curve, the capacity parameter, the operating cost of the thermal power generating set, the operating cost of the distributed power generation equipment, the power purchase cost of the target power system from the upper power grid and the power gap curve.

7. The method according to claim 6, characterized in that Solving the power supply optimization function to obtain a power supply optimization strategy for the target power system includes: Obtaining a first output upper limit value and a first output lower limit value of the thermal power generating set and a second output upper limit value and a second output lower limit value of the distributed power generation equipment, and determining a first output constraint condition according to the first output upper limit value, the first output lower limit value, the second output upper limit value and the second output lower limit value; According to the load regulation curve, a dispatching load threshold of the demand response device is obtained, and according to the dispatching load threshold, a response load constraint condition is determined; According to the capacity parameter, obtaining a second output constraint condition corresponding to the energy storage device; The power supply optimization function is solved according to the first output constraint condition, the response load constraint condition and the second output constraint condition to obtain the power supply optimization strategy.

8. An optimization device for a power system, characterized in that: include: An acquisition unit, used to acquire a first output prediction curve of a thermal power generating unit in a target power system and to acquire a second output prediction curve of a distributed power generating device in the target power system; A prediction unit, used to make predictions based on historical power load data on the user side to obtain a target power load prediction curve; a calculation unit, configured to calculate according to the first output prediction curve, the second output prediction curve and the target power load prediction curve to obtain a power shortage curve; The optimization unit is used to optimize the power supply of the target power system according to the power shortage curve.

9. A computer-readable storage medium, characterized in that: The computer-readable storage medium includes a stored program, wherein when the program is executed, the storage medium is controlled to execute the power system optimization method according to any one of claims 1 to 7 on a device.

10. An electronic device, characterized in that: It includes one or more processors and a memory, wherein the memory is used to store one or more programs, wherein when the one or more programs are executed by the one or more processors, the one or more processors implement the power system optimization method described in any one of claims 1 to 7.

Citation Information

Patent Citations

  • High energy-consuming enterprise peak regulation control method used in new energy power generation mode

    CN104376412A

  • Power load prediction method and device, equipment and storage medium

    CN112365098A

  • Integrated energy system planning method and system based on hybrid artificial fish swarm algorithm

    CN112785065A

  • Control management method, device and equipment and storage medium

    CN113839423A

  • Short-term power load prediction method and device, equipment and storage medium

    CN114066068A

Cited By

  • Load demand prediction method and system for distributed new energy power generation system

    CN119338205A

  • Power grid operation control system

    CN121602520A

  • Multi-energy fusion power generation scheduling method and system based on power gap prediction

    CN121939535A

  • A multi-energy fusion power generation scheduling method and system based on power gap prediction

    CN121939535B