Transmission tower installation assembly

Through the combination of sealing, limiting and prompt components of screw and nut structures, the problem of loosening and rusting of transmission tower connection accessories in harsh environments is solved, achieving higher installation stability and reducing maintenance costs.

CN118970795BActive Publication Date: 2024-12-31JIANGSU YINHAI STEEL STRUCTURE ENG CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411430447.2
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2024-10-14
Publication Date
2024-12-31
Estimated Expiration
2044-10-14

AI Technical Summary

Technical Problem

The existing transmission tower connection accessories are prone to loosening and rust in harsh environments, and the limited installation environment at high places leads to increased maintenance costs.

Method used

Using screw and nut structure, combined with sealing components, limiting components and prompt components, the limiting components are driven to run through the sealing components on the nut, increasing friction to prevent loosening, and making the prompt components emit a prompt sound through airflow to ensure the installation status unified.

Benefits of technology

It effectively prevents rainwater erosion from connecting accessories, improves installation stability and firmness, reduces looseness, and reduces maintenance costs.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118970795B_ABST
    Figure CN118970795B_ABST
Patent Text Reader

Abstract

The present invention discloses a transmission tower installation component, belonging to the field of transmission towers. A transmission tower installation component comprises a component a and a component b, wherein a screw is inserted into the component a and the component b, a nut is fixed at one end of the screw, a nut matched therewith is arranged at the threaded end of the screw, and is used to install and fix the component a and the component b, and a sealing component arranged on the nut; during installation, the present invention drives the sealing component on the nut to run synchronously through the tightening and fixing of the bolt structure, thereby sealing and protecting the rain-exposed part of the top of the accessory, avoiding erosion by rainwater after installation, and extending its service life, and the mutual cooperation of the components during the installation process increases the firmness during the installation process, reduces the occurrence of loosening, and can send a prompt sound through the cooperation of the components during the installation process to remind the staff to understand the tightness of the installation, prevent the occurrence of over-tightening or over-loosening, and effectively reduce its maintenance cost.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of transmission towers, and in particular to a transmission tower installation assembly. Background Art

[0002] Transmission towers are the supporting points of overhead lines. With the development of society, the transmission of electricity has become more and more popular. The connecting components between the top of the transmission tower and the transmission line play an important role in the safety of the transmission process. Generally, the structural parts at the top transmission connection position are installed with bolts to facilitate disassembly and assembly.

[0003] In the prior art, after the connection accessories of the transmission tower are installed at a high altitude, although anti-corrosion and anti-rust coatings are applied on the surface of the accessories, they are easily loosened and rusted due to long-term exposure to harsh external environments and external influences such as vibrations caused by earthquakes. In addition, it is not easy to achieve a unified installation state under the limited high-altitude installation environment, which increases subsequent maintenance costs. Summary of the invention

[0004] The purpose of the present invention is to solve the problem in the prior art that, under the harsh external environment for a long time and the external influences such as earthquake-induced vibration, the bolt accessories are easily loosened and rusted, and the installation state is not easy to be unified under the limited high-altitude installation environment, which increases the subsequent maintenance cost. A transmission tower installation component is proposed to solve the problem that

[0005] In order to achieve the above object, the present invention adopts the following technical solutions:

[0006] A transmission tower installation assembly comprises a component a and a component b, wherein a screw is inserted into the component a and the component b, a nut is fixed at one end of the screw, a nut matched with the screw is arranged at the threaded end of the screw, and is used for installing and fixing the component a and the component b, a sealing assembly arranged on the nut is symmetrically installed on both sides of the screw, and is used for sealing and protecting the contact part between the nut and the component a when the component a and the component b are installed; a limiting assembly is arranged in the screw, one end of which extends to the outside and is connected to the sealing assembly, and drives the limiting assembly to move when the sealing assembly is in operation, and is used for limiting the screw and the component a and the component b to prevent loosening; a prompting assembly is installed on the sealing assembly, and is used for prompting the tightness of the installation of the component a and the component b when the sealing assembly is in operation.

[0007] Preferably, the sealing assembly includes a sliding groove opened on the bottom surface of the nut, a sliding block is slidably connected in the sliding groove, a lifting rod is fixed to the bottom of the sliding block, a first piston is fixed to the bottom of the lifting rod, the first piston is slidably connected in a connecting cylinder, the connecting cylinder is installed on the surface of a cushion block, the cushion block is slidably connected to the surface of the screw, and a protective piece is connected to one end of the connecting cylinder.

[0008] Preferably, the protective member includes an air pipe connected to one end of the connecting tube, one end of the air pipe passes through the cushion block and is connected to a first air bag, the first air bag is arranged in a limiting ring, the limiting ring is installed on the top surface of the cushion block, and a concave ring is fixed to the bottom of the nut.

[0009] Preferably, the limiting assembly includes a shunt tube fixed at the end of the connecting tube, the shunt tube is fixed on a fixing plate, the fixing plate is fixed on a screw, one end of the shunt tube passes through the screw and extends to a second airbag fixed inside, the second airbag is arranged in a cavity, the cavity is opened in the screw, and the surface of the screw is provided with symmetrically distributed notches, and the notches are connected to the cavity.

[0010] Preferably, the prompt assembly includes a connecting tube fixed at one end of the connecting tube, one end of the connecting tube passes through a cushion block and is fixed with a prompt tube, the prompt tube is installed on the cushion block, a second piston is slidably connected inside the prompt tube, and a moving part is provided on the top of the second piston.

[0011] Preferably, the movable part includes a movable plate slidably connected to the surface of the second piston, an arc block is fixed to one side of the movable plate, an extrusion spring is fixed to the other side of the movable plate, a fixed block is fixed to the end of the extrusion spring, the fixed block is fixed to the surface of the second piston, and a sound part is arranged inside the prompt tube.

[0012] Preferably, the sound component comprises a concave block fixed inside the prompt tube, the concave block is in a concave shape, an arc-shaped copper sheet is installed on the concave surface of the concave block, and a protruding opening is opened on the top surface of the prompt tube.

[0013] Preferably, the surrounding surfaces of the nut are inclined surfaces, and the nut is a trapezoidal structure.

[0014] Preferably, the side surface of the cushion block is inclined, and a rubber cover is fixed to the bottom surface of the nut.

[0015] Preferably, a protective layer is provided on the surface of the shunt pipe located on the fixed plate sleeve, and the protective layer is made of wear-resistant rubber material.

[0016] Compared with the prior art, the present invention provides a transmission tower installation assembly, which has the following beneficial effects:

[0017] 1. This transmission tower installation component can seal and protect the connection parts between components a at the nut through the sealing component arranged on the nut during installation, so as to prevent the connection accessories from being eroded by rainwater in the external high-altitude environment, thereby improving the stability of the overall installation of the accessories.

[0018] 2. In the transmission tower installation component, during the sealing process of the sealing component, the sealing component drives the limiting component to operate synchronously, so that the limiting component expands inside the screw rod, and after expansion, it fits tightly with the installation holes of components a and b, increasing its friction, playing a good limiting role, preventing loosening, and providing multiple relaxation effects.

[0019] 3. During the installation of the transmission tower installation component, when the sealing component is sealed, part of the conveying airflow generated can be used to make the prompt component run synchronously, and a "click" sound of sound vibration is generated when the prompt component is running, so as to remind the installation staff to know the installation tightness status of the accessories, so that the staff can unify the installation status of the accessories at each installation location.

[0020] The parts not involved in the device are the same as the prior art or can be implemented by the prior art. During installation, the present invention drives the sealing component on the nut to run synchronously through the tightening and fixing of the bolt structure, thereby sealing and protecting the rain-exposed part of the top of the accessory to avoid erosion by rain after installation and extending its service life. During the installation process, the mutual cooperation of various components increases the firmness of the installation process and reduces the occurrence of looseness. During the installation process, a prompt sound can be emitted through the cooperation of the components to remind the staff to understand the tightness of the installation, prevent over-tightening or over-loosening, and effectively reduce its maintenance cost. BRIEF DESCRIPTION OF THE DRAWINGS

[0021] Figure 1 This is a schematic diagram of the overall structure of a transmission tower installation assembly proposed by the present invention;

[0022] Figure 2 A schematic diagram of a side cross-sectional three-dimensional structure of a transmission tower installation assembly proposed by the present invention;

[0023] Figure 3 This is a schematic diagram of a front cross-sectional structure of a transmission tower installation assembly proposed by the present invention;

[0024] Figure 4 For the present invention Figure 3 A schematic diagram of the enlarged structure of area A;

[0025] Figure 5 It is a schematic diagram of a partially cutaway three-dimensional structure of a prompt component in the present invention;

[0026] Figure 6It is a schematic diagram of a partial cross-sectional structure of the screw structure in the present invention;

[0027] Figure 7 It is a schematic diagram of the partial bottom view of the nut structure in the present invention;

[0028] Figure 8 This is a schematic diagram of the top structure of a transmission tower installation assembly proposed by the present invention.

[0029] In the figure: 1. component a; 2. component b; 3. nut; 31. screw; 32. nut; 4. sealing assembly; 41. sliding groove; 42. sliding block; 43. lifting rod; 44. connecting tube; 45. first piston; 46. cushion block; 47. air pipe; 48. first air bag; 49. limiting ring; 491. concave ring; 5. limiting assembly; 51. shunt pipe; 52. fixing plate; 53. second air bag; 54. cavity; 55. notch; 6. prompt assembly; 61. connecting pipe; 62. prompt tube; 63. second piston; 64. fixing block; 65. extrusion spring; 66. movable plate; 67. arc block; 68. concave block; 69. arc-shaped copper sheet; 691. extension port; 7. inclined surface; 8. rubber cover. DETAILED DESCRIPTION

[0030] The technical solutions in the embodiments of the present invention will be described clearly and completely below in conjunction with the drawings in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, rather than all the embodiments.

[0031] In the description of the present invention, the term "multiple" refers to two or more. Unless otherwise clearly defined, the orientation or positional relationship indicated by the terms "upper", "lower", etc. is based on the orientation or positional relationship shown in the drawings. It is only for the convenience of describing the present invention and simplifying the description, and does not indicate or imply that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation. Therefore, it cannot be understood as a limitation of the present invention. The terms "connection", "installation", "fixation", etc. should be understood in a broad sense. For example, "connection" can be a fixed connection, a detachable connection, or an integral connection; it can be directly connected or indirectly connected through an intermediate medium. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to the specific circumstances. In addition, the terms "first", "second", etc. are only used for descriptive purposes, and cannot be understood as indicating or implying relative importance or implicitly indicating the number of technical features indicated. Therefore, the features defined as "first", "second", etc. can explicitly or implicitly include one or more of the features. In the description of the present invention, unless otherwise specified, the meaning of "multiple" is two or more.

[0032] In the description of this specification, the description of the terms "one embodiment", "some implementations", "specific embodiments", etc. is intended to indicate that the specific features, structures, materials or characteristics described in conjunction with the embodiment or example are included in at least one embodiment or example of the present invention. In this specification, the schematic representation of the above terms does not necessarily refer to the same embodiment or example. Moreover, the specific features, structures, materials or characteristics described can be combined in any one or more embodiments or examples in a suitable manner.

[0033] Reference Figure 1-8 A transmission tower installation assembly includes a component a1 and a component b2. A screw 31 is inserted into the component a1 and the component b2. A nut 3 is fixed at one end of the screw 31. A nut 32 matched with the screw 31 is provided at the threaded end of the screw 31 for installing and fixing the component a1 and the component b2. A sealing assembly 4 is symmetrically installed on both sides of the screw 31. When the component a1 and the component b2 are installed, it is used to seal and protect the contact part between the nut 3 and the component a1; a limiting assembly 5 is arranged in the screw 31, one end of which extends to the outside and is connected to the sealing assembly 4. When the sealing assembly 4 is running, it drives the limiting assembly 5 to move, and is used to limit the screw 31 and the components a1 and b2 to prevent loosening; a prompting assembly 6 is installed on the sealing assembly 4. When the sealing assembly 4 is running, it is used to prompt the tightness of the installation of the components a1 and the components b2.

[0034] During the installation of the transmission tower, the components are generally fixed and installed by splicing and fixing the pipes with bolt components. A small number of components are fixed by welding, but it is not convenient to disassemble and the maintenance is troublesome. The installation and disassembly method of the bolt structure is more convenient to inspect, but considering the use environment of the transmission tower, the structural accessories installed in the bottom area of ​​the tower are convenient for the staff to inspect and repair, but the bolt accessories used to connect the components at the top of the tower are eroded by rain, which is very inconvenient for the staff to repair. Therefore, in the present invention, after the screw rod 31 penetrates the component a1 and the component b2, the nut 32 is screwed to cooperate with the nut 3 to tighten and fix the components a1 and b2, and the sealing component 4 arranged between the nut 3 and the component a1 can be synchronously operated by the tightening force, so that the first airbag 48 in the sealing component 4 is expanded, and the nut 3 and the structural component a2 are tightened and fixed. The gap between the components a1 is sealed and protected, so as to prevent rainwater falling from the top of the nut 3 from leaking into the gap and causing erosion and damage to the bolt structure, thereby increasing its service life. During the sealing process of the sealing component 4, the sealing component 4 drives the limit component 5 to run synchronously, so that the limit component 5 expands inside the screw rod 31. After expansion, it fits tightly with the installation holes of the components a1 and b2, increasing its friction, playing a good limiting role, preventing loosening, and providing multiple relaxation effects. When the sealing of the sealing component 4 is completed, part of the conveying airflow generated can be used to make the prompt component 6 run synchronously, and a "click" sound of sound vibration is generated when the prompt component 6 is running, thereby prompting the installation staff to know the installation tightness of the accessories, so that the staff can unify the installation status of the accessories at each installation location.

[0035] In a preferred embodiment, referring to Figure 3 , Figure 4 , Figure 7 and Figure 8 The sealing assembly 4 includes a sliding groove 41 opened on the bottom surface of the nut 3, a sliding block 42 is slidably connected in the sliding groove 41, a lifting rod 43 is fixed to the bottom of the sliding block 42, a first piston 45 is fixed to the bottom of the lifting rod 43, the first piston 45 is slidably connected in the connecting tube 44, the connecting tube 44 is installed on the surface of the cushion block 46, the cushion block 46 is slidably connected to the surface of the screw 31, one end of the connecting tube 44 is connected to a protective member, the protective member includes an air pipe 47 connected to one end of the connecting tube 44, one end of the air pipe 47 passes through the cushion block 46 and is connected to a first air bag 48, the first air bag 48 is arranged in a limiting ring 49, the limiting ring 49 is installed on the top surface of the cushion block 46, a concave ring 491 is fixed to the bottom of the nut 3, the surrounding surfaces of the nut 3 are inclined surfaces 7, the nut 3 is a trapezoidal structure, the side surface of the cushion block 46 is inclined, and a rubber cover 8 is fixed to the bottom surface of the nut 3.

[0036] By adopting the above scheme, when the nut 32 is screwed, the screw rod 31 moves downward due to the limitation of the structure. When the screw rod 31 moves downward, the lifting rod 43 at the bottom of the nut 3 moves downward synchronously, so that the first piston 45 at the bottom of the lifting rod 43 squeezes the air inside the connecting tube 44, and part of the squeezed air is transported to the first air bag 48 through the air pipe 47, so that the first air bag 48 expands. The first air bag 48 expands to form a straight cylinder shape, which cooperates with the concave ring 491 to form a sealing protection ring, which has a good sealing and protection effect on the surrounding of the screw rod 31. When the connected and installed accessories are in the air, rainwater can flow away along the inclined surface 7 on the side of the nut 3 to prevent the accumulation of rainwater. As the rainwater continues to flow, after the gap is sealed during the operation of the sealing component 4, the rubber cover 8 moves synchronously with the downward movement of the nut 3 and fits with the side of the gasket 46, so as to form an outer layer of protection, improve the protection effect of the sealing component 4, reduce the occurrence of faults, and the falling rainwater can be well diverted.

[0037] In a preferred embodiment, referring to Figure 3 , Figure 4 and Figure 6 The limiting assembly 5 includes a shunt tube 51 fixed to the end of the connecting tube 44, the shunt tube 51 is fixed on the fixing plate 52, the fixing plate 52 is fixed on the screw 31, one end of the shunt tube 51 passes through the screw 31 and extends to the inside where a second airbag 53 is fixed, the second airbag 53 is arranged in a cavity 54, the cavity 54 is opened in the screw 31, and the surface of the screw 31 is provided with symmetrically distributed notches 55, the notches 55 are connected with the cavity 54, the surface of the shunt tube 51 is located on the fixing plate 52 and is provided with a protective layer, and the protective layer is made of wear-resistant rubber material.

[0038] By adopting the above scheme, during installation, the first piston 45 moves downward to squeeze the air in the connecting tube 44, and the connecting tube 44 is connected through the shunt tube 51. Part of the squeezed air can be transported to the shunt tube 51, and then transported to the inside of the second airbag 53 through the shunt tube 51. The second airbag 53 expands due to the delivery of gas, and a notch 55 is provided at the cavity 54. The expanded second airbag 53 is squeezed out through the notch 55 and protrudes to the outside of the screw 31, increasing the friction around the screw 31, thereby improving the upper limit effect of the screw 31 on the components a1 and b2, and preventing displacement and loosening. In this scheme, through the mutual cooperation of the sealing component 4 and the limiting component 5, the bolt structure has a good sealing effect during installation, and can also provide a better limiting effect for the middle area of ​​the bolt structure, and cooperate with the nut 32 to form a double limit, which reduces the influence of loosening of the transmission tower under vibration and other conditions and extends its service life.

[0039] It should be noted that the diverter tube 51 is made of rubber hose material, and when the screw rod 31 is displaced, the use effect of the diverter tube 51 is not affected. A protective layer is provided on the surface of the diverter tube 51 fixed on the fixed plate 52 to protect the diverter tube 51 and avoid damage during squeezing.

[0040] In a preferred embodiment, referring to Figure 4 and Figure 5 The prompt assembly 6 includes a connecting pipe 61 fixed to one end of the connecting tube 44, one end of the connecting pipe 61 passes through the cushion block 46 and is fixed with a prompt tube 62, which is installed on the cushion block 46, and the inside of the prompt tube 62 is slidably connected to the second piston 63, and a moving part is arranged on the top of the second piston 63, and the moving part includes a movable plate 66 slidably connected to the surface of the second piston 63, an arc block 67 is fixed to one side of the movable plate 66, and an extrusion spring 65 is fixed to the other side of the movable plate 66, and a fixed block 64 is fixed to the end of the extrusion spring 65, and the fixed block 64 is fixed on the surface of the second piston 63, and an acoustic part is arranged inside the prompt tube 62, and the acoustic part includes a concave block 68 fixed inside the prompt tube 62, and the concave block 68 is in a concave shape, and an arc-shaped copper sheet 69 is installed on the concave surface of the concave block 68, and a protrusion port 691 is opened on the top surface of the prompt tube 62.

[0041] By adopting the above scheme, when the gas in the connecting tube 44 is squeezed, part of the gas can be delivered to the connecting tube 61, and then delivered to the inside of the prompt tube 62. The second piston 63 slides inside the prompt tube 62 under the force of the gas pressure. As the second piston 63 moves, the arc block 67 above the second piston 63 moves synchronously. When the arc block 67 moves to contact the concave block 68, due to the structural characteristics of the concave block 68, the arc block 67 moves along the concave surface when rising. When the arc block 67 enters the concave surface of the concave block 68, the elastic squeezing force of the squeezing spring 65 causes the arc block 67 to hit the arc copper sheet 69 to make a "click" sound, providing a prompt sound, thereby conveniently reminding the installation staff that there is no need to continue tightening. Tight operation, through this design scheme, the technical difficulty of accessory installation is simplified, the installation and fixing methods of high-altitude installed connectors are unified, and the installation personnel in the prior art avoid inconsistent tightness of the bolt structure installation, which causes the structure to be overloaded and deformed or easy to loosen, thereby improving the safety performance of the transmission tower and reducing maintenance costs. At the same time, the top side of the movable plate 66 is always in contact with one side of the concave block 68 in the initial stage. When the arc block 67 contacts the concave block 68, the top of the movable plate 66 extends out of the extension port 691 to squeeze the shunt pipe 51 above, limit the backflow of the internal airflow, and improve the stability of the structure of the limit component 5, so that the prompt component 6 has a prompting function and a flow limiting function.

[0042] The above description is only a preferred specific implementation manner of the present invention, but the protection scope of the present invention is not limited thereto. Any technician familiar with the technical field can make equivalent replacements or changes according to the technical scheme and inventive concept of the present invention within the technical scope disclosed by the present invention, which should be covered by the protection scope of the present invention.

Claims

1. A transmission tower installation assembly, comprising a component a (1) and a component b (2), wherein a screw rod (31) is inserted into the component a (1) and the component b (2), a nut (3) is fixed to one end of the screw rod (31), and a nut (32) matching the screw rod (31) is provided at the threaded end of the screw rod (31), for installing and fixing the component a (1) and the component b (2), characterized in that: A sealing assembly (4) disposed on the nut (3), symmetrically mounted on both sides of the screw rod (31), and used to seal and protect the contact portion between the nut (3) and the component a (1) when the component a (1) and the component b (2) are installed; A limit assembly (5) is arranged in the screw rod (31), one end of which extends to the outside and is connected to the sealing assembly (4). When the sealing assembly (4) is in operation, the limit assembly (5) is driven to move, and is used to limit the screw rod (31) and the components a (1) and b (2) to prevent loosening; A prompting component (6) is mounted on the sealing component (4) and is used to prompt the tightness of the installation of the component a (1) and the component b (2) when the sealing component (4) is in operation; The sealing assembly (4) comprises a sliding groove (41) formed on the bottom surface of the nut (3); a sliding block (42) is slidably connected in the sliding groove (41); a lifting rod (43) is fixed to the bottom of the sliding block (42); a first piston (45) is fixed to the bottom of the lifting rod (43); the first piston (45) is slidably connected in a connecting tube (44); the connecting tube (44) is mounted on the surface of a cushion block (46); the cushion block (46) is slidably connected to the surface of the screw rod (31); and a protective member is connected to one end of the connecting tube (44); The protective member comprises an air delivery pipe (47) connected to one end of the connecting tube (44); one end of the air delivery pipe (47) passes through the cushion block (46) and is connected to a first air bag (48); the first air bag (48) is arranged in a limiting ring (49); the limiting ring (49) is mounted on the top surface of the cushion block (46); and a concave ring (491) is fixed to the bottom of the nut (3); The limiting assembly (5) comprises a shunt pipe (51) fixed to the end of the connecting tube (44), the shunt pipe (51) being fixed to a fixing plate (52), the fixing plate (52) being fixed to the screw rod (31), one end of the shunt pipe (51) passing through the screw rod (31) and extending to the inside where a second airbag (53) is fixed, the second airbag (53) being arranged in a cavity (54), the cavity (54) being opened in the screw rod (31), the surface of the screw rod (31) being opened with symmetrically distributed notches (55), the notches (55) being connected to the cavity (54).

2. A transmission tower installation assembly according to claim 1, characterized in that: The prompt component (6) includes a communicating pipe (61) fixed to one end of the connecting cylinder (44). One end of the communicating pipe (61) penetrates through the cushion block (46) and is fixed with a prompt cylinder (62). The prompt cylinder (62) is installed on the cushion block (46). A second piston (63) is slidably connected inside the prompt cylinder (62), and a moving member is arranged on the top of the second piston (63).

3. A transmission tower installation assembly according to claim 2, characterized in that: The moving member includes a movable plate (66) slidably connected to the surface of the second piston (63). An arc-shaped block (67) is fixed to one side surface of the movable plate (66), and a compression spring (65) is fixed to the other side surface of the movable plate (66). The end of the compression spring (65) is fixed with a fixed block (64), and the fixed block (64) is fixed on the surface of the second piston (63). A sounding member is arranged inside the prompt cylinder (62).

4. A transmission tower installation assembly according to claim 3, characterized in that: The sounding member includes a concave block (68) fixed inside the prompt cylinder (62). The concave block (68) is in the shape of a concave character, and an arc-shaped copper sheet (69) is installed on the concave surface of the concave block (68). An extension opening (691) is formed on the top surface of the prompt cylinder (62).

5. A transmission tower installation assembly according to claim 1, characterized in that: The peripheral surface of the nut (3) is an inclined surface (7), and the nut (3) is in a trapezoidal structure.

6. A transmission tower installation assembly according to claim 1, characterized in that: The side surface of the cushion block (46) is inclined, and a rubber cover (8) is fixed to the bottom surface of the nut (3).

7. The transmission tower installation assembly according to claim 1, characterized in that: A protective layer is sleeved on the surface of the shunt pipe (51) at the fixing plate (52). The protective layer is made of wear-resistant rubber material.