Cast-in-place box girder flange plate cantilever supporting frame construction method

By hardening the foundation and building the lower clasp frame, steel pipe diagonal brace and prestressed steel strand, the problem of high cost when traditional construction methods approaches unremovable obstacles such as railways and cables is solved, and the construction is improved Safety and quality, suitable for the construction of cast-in-place box beams in complex environments.

CN118979442APending Publication Date: 2024-11-19XINJIANG CONSTR ENG GRP
View PDF 0 Cites 1 Cited by

Patent Information

Application Number
CN202411163594.8
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-08-23
Publication Date
2024-11-19

AI Technical Summary

Technical Problem

In urban viaduct construction, the traditional prestressed concrete cast-in-place box girder construction method is relatively expensive and difficult to meet construction conditions when it is close to unremovable obstacles such as railways and cables, which affects construction safety and efficiency.

Method used

The construction method of cast-in-place box beam cantilever support frame is adopted. By hardening and waterproofing the foundation, the lower buckle frame and steel pipe oblique brace are built, prestressed steel strands are installed and tensioned, combined with the buckle plates are combined. Supports and I-steel are gradually completed to pour concrete and build and dismantle support frames.

Benefits of technology

It reduces construction costs, improves construction safety and stability, ensures the construction quality of cast-in-place box beams, enhances the overall load-bearing capacity and crack resistance, and is suitable for complex construction environments.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118979442A_ABST
    Figure CN118979442A_ABST
Patent Text Reader

Abstract

The invention relates to a construction method of an overhanging supporting frame, and aims to solve the technical problem that the construction cost is high when non-detachable obstacles such as near railways and cables exist in an existing construction method. The invention provides a cast-in-place box girder flange plate cantilever supporting frame construction method. Comprising the following steps of frame body foundation treatment, lower part disc buckle frame building, steel pipe inclined strut building, I-shaped steel mounting, flange plate disc buckle support building, flange plate and box girder bottom plate formwork building, first-time concrete pouring, cantilever I-shaped steel prestressed steel strand mounting and tensioning, adjusting of jacking at the upper end of a vertical rod of a lower part disc buckle support. Inclined strut jacking supports are arranged on the tops of the steel pipe inclined struts, flange plate disc buckle supports are adjusted, concrete is poured, and a frame body is dismantled; according to the construction method, the construction problem caused when the construction method is close to non-detachable obstacles such as railways and cables is solved, the construction quality of the cast-in-place box girder can be ensured through the use of the prestressed steel strands, and the construction safety is ensured.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to a cantilever support frame construction method, and in particular to a cantilever support frame construction method for a cast-in-place box beam flange plate. Background Art

[0002] With the rapid development of urbanization, the construction of urban viaducts is increasing day by day. These viaducts often need to cross complex environments such as subways, railways, cables, etc. In these construction environments, the construction conditions are subject to various constraints, making it difficult to apply traditional construction methods. Prestressed concrete cast-in-place box girders have been widely used in urban viaduct construction due to their beautiful appearance, large span, and relatively low cost.

[0003] However, the traditional construction method of prestressed concrete cast-in-place box beam, such as the full-span support method, has high requirements for the foundation and site. When the viaduct crosses (is close to) an obstacle and the obstacle cannot be removed, the construction conditions are difficult to meet. In addition, although the construction method of steel pipe column Bailey beam passing through the door opening can be used when it is orthogonal or oblique, it cannot be used effectively when there is an obstacle parallel to the bridge on the side of the cast-in-place box beam, and this method is expensive.

[0004] Therefore, in complex construction environments, especially when the viaduct is close to non-removable obstacles such as railways and cables, an innovative construction method is urgently needed to ensure construction safety and efficiency. Summary of the invention

[0005] The purpose of the present invention is to solve the technical problem of high construction cost in existing construction methods when there are non-removable obstacles such as adjacent railways and cables, and to provide a construction method for a cantilever support frame of a cast-in-place box girder flange plate.

[0006] To solve the above technical problems, the technical solutions provided by the present invention are as follows:

[0007] A construction method for a cast-in-place box beam flange plate cantilever support frame comprises the following steps:

[0008] S1. Determine the construction scope of the cantilever support frame, extend the construction scope of the cantilever support frame outward by 2m on all sides, and use it as the foundation for building the cantilever beam support frame; harden and waterproof the foundation;

[0009] S2, determining the construction step distance of the lower buckle frame, constructing the lower buckle frame on the foundation within the construction range of the cantilever support frame according to the construction step distance of the lower buckle frame, and installing a top support at the upper end of the vertical pole of the lower buckle frame and a bottom support at the lower end of the vertical pole;

[0010] S3, determining the construction pitch of the steel pipe horizontal rods, and sequentially installing a plurality of steel pipe horizontal rods on the vertical rods of the lower buckle frame from top to bottom according to the construction pitch of the steel pipe horizontal rods; at the same time, making the plurality of steel pipe horizontal rods extend to the outside of the lower buckle frame, and the plurality of steel pipe horizontal rods extending to the outside of the lower buckle frame are distributed in an inverted trapezoidal shape;

[0011] Multiple groups of parallel steel pipe braces are sequentially installed on multiple steel pipe horizontal rods, and brace top supports are arranged on the tops of the steel pipe braces;

[0012] S4. Adjust the top support of the steel pipe brace and the top support of the upper end of the lower plate buckle frame upright to make them at the same height;

[0013] Install the I-beam on the top support of the lower buckle frame upright and the top support of the diagonal brace at the top of the steel pipe diagonal brace, and build the flange plate buckle bracket above the I-beam;

[0014] S5. Install the cast-in-place box girder bottom plate and flange plate formwork above the flange plate buckle bracket and above the lower buckle bracket;

[0015] Combine the cast-in-place box girder bottom plate, flange plate formwork and web plate formwork to carry out the first concrete pouring, and pre-embed sleeves on the inclined web and middle web of the cast-in-place box girder, and pre-embed prestressed tension anchors on the middle web;

[0016] S6. After the concrete strength reaches 90% of the design strength and the concrete age exceeds 7 days, install the prestressed steel strand, connect one end of the prestressed steel strand to the cantilever end of the I-beam, and pass the other end through the inclined web and the middle web, and tension the prestressed steel strand through the prestressed tensioning anchor;

[0017] S7. After the prestressed steel strands are tensioned, adjust the top support of the upper end of the vertical pole of the lower buckle bracket under the I-beam and the top support of the diagonal brace at the top of the steel pipe diagonal brace, so that the top support of the diagonal brace at the top of the steel pipe diagonal brace and the top support of the upper end of the vertical pole of the lower buckle bracket fit the I-beam;

[0018] S8. Adjust the top support at the upper end of the neutral rod of the flange plate buckle bracket to make it fit with the flange plate template, and then combine the flange plate template and the bottom box template to perform the second concrete pouring and flange plate pouring;

[0019] S9. After the concrete strength reaches 90% of the design strength and the concrete age exceeds 7 days, the construction of the cantilever support frame of the cast-in-place box girder flange plate can be completed after removing the lower disc frame, flange plate disc bracket, flange plate formwork, cast-in-place box girder bottom plate and prestressed steel strands.

[0020] Furthermore, in step S1, the specific method of hardening and waterproofing the foundation is:

[0021] Excavate the humus and garbage soil on the surface of the foundation, and use a 22t roller to compact it to make the foundation bearing capacity greater than 200Kpa;

[0022] A 30cm thick Panax notoginseng lime soil base layer is laid on the compacted foundation and compacted to a degree of more than 95%; the bearing capacity of the compacted Panax notoginseng lime soil base layer is greater than 300kpa;

[0023] Lay 20cm thick concrete on the compacted Sanqi lime soil base, and ensure that the concrete within the cantilever support frame has a horizontal slope of 1.5%, completing the hardening treatment of the foundation;

[0024] Drainage ditches are set up on both sides of the foundation to complete the waterproofing of the foundation.

[0025] Further, in step S2, the step distance of the construction of the lower buckle frame includes: the step distance between two adjacent vertical poles along the bridge direction is 0.6m, the step distance between two adjacent vertical poles along the bridge transverse direction is 0.6m; the step distance between two adjacent horizontal poles is 1.5m, and the step distance between two adjacent horizontal poles at the top of the lower buckle frame is 1m;

[0026] A channel steel is provided between the base support at the lower end of the vertical pole and the concrete.

[0027] Furthermore, in step S3, the construction pitch of the steel pipe horizontal bars is the distance between two adjacent steel pipe horizontal bars, which is 1.5 m;

[0028] The bottom of the steel pipe diagonal brace is erected on the channel steel.

[0029] Furthermore, in step S3, the steel pipe horizontal rod and the steel pipe diagonal brace are connected by fasteners.

[0030] Furthermore, in steps S5 and S8, after the concrete pouring is completed, the concrete is sprinkled with water for curing.

[0031] Further, in step S6, the prestressed tensioning anchor is a digital display prestressed tensioning anchor; the specific method of tensioning the prestressed steel strand by the prestressed tensioning anchor is:

[0032] Set the controlled tension stress of the prestressed steel strand;

[0033] The prestressed steel strands are tensioned with 0.1 times of controlled tensioning stress, 0.2 times of controlled tensioning stress, and 100% of controlled tensioning stress in sequence through prestressed tensioning anchors, and tensioned for 5 minutes under 100% controlled tensioning stress. After the tensioning is completed, the prestressed steel strands are anchored with prestressed tensioning anchors.

[0034] Furthermore, in step S6, when the prestressed steel strand is tensioned by the prestressed tensioning anchor, the error range between the actual tensioning elongation value of the prestressed steel strand and the theoretical tensioning elongation value is -6% to 6%; and the retraction amount at both ends of the prestressed steel strand is less than 6mm.

[0035] Compared with the prior art, the present invention has the following beneficial effects:

[0036] The method for constructing a cast-in-place box girder flange plate cantilever support frame provided by the present invention ensures safety and stability during the construction process by hardening and waterproofing the foundation; through the lower buckle frame, the flange plate buckle bracket, the prestressed steel strands and the I-beams, the problem of high construction cost when adjacent to non-detachable obstacles such as railways and cables is overcome; and through the tensioning and anchoring of the prestressed steel strands, the construction quality of the cast-in-place box girder can be ensured, and the overall bearing capacity and crack resistance can be improved. BRIEF DESCRIPTION OF THE DRAWINGS

[0037] Figure 1 It is a construction flow chart of the cantilever support frame of the cast-in-place box beam flange plate in the embodiment of the present invention;

[0038] Figure 2 This is a schematic structural diagram of a cantilever support frame for a cast-in-place box girder flange plate according to an embodiment of the present invention;

[0039] Figure 3 It is a schematic diagram of the arrangement structure of the flange plate buckle bracket and the lower buckle bracket in an embodiment of the present invention.

[0040] Explanation of the reference numerals in the accompanying drawings: Area I - cantilever area of ​​the support frame; Area II - encrypted arrangement area of ​​the support frame; Area III - normal arrangement area of ​​the support frame; 101, channel steel; 102, wedge-shaped wooden block support; 103, lower buckle frame; 104, horizontal steel pipe rod; 105, steel pipe diagonal brace; 106, fastener tensioning; 107, anti-skid wooden wedge; 108, anti-skid steel bar; 201, I-beam; 202, anti-skid steel bar; 203, flange plate buckle bracket; 204, steel pipe tensioning; 205, steel pedal; 206, flange plate formwork; 301, embedded sleeve; 302, prestressed steel strand; 303, prestressed tensioning anchor; 401, first concrete pouring; 402, second concrete pouring; 403, flange plate; 5, cantilever area; 6, encrypted arrangement area; 7, normal arrangement area. DETAILED DESCRIPTION

[0041] The technical solutions in the present invention will be described clearly and completely below in conjunction with the accompanying drawings. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0042] Embodiment 1

[0043] like Figure 1 As shown, a construction method for a cast-in-place box girder flange plate cantilever support frame, the specific steps are:

[0044] 1) Treat the foundation of the cantilever support frame

[0045] Determine the construction range of the cantilever support frame, extend the construction range of the cantilever support frame outward by 2m on all sides, and use it as the foundation for building the cantilever beam support frame;

[0046] Excavate the humus and garbage soil on the surface of the foundation, and use a 22t roller to compact it to make the foundation bearing capacity greater than 200Kpa;

[0047] A 30cm thick Panax notoginseng lime soil base layer is laid on the compacted foundation and compacted to a degree of more than 95%; the bearing capacity of the compacted Panax notoginseng lime soil base layer is greater than 300kpa;

[0048] A 20cm thick concrete is laid on top of the compacted 37 lime soil base, and the concrete within the cantilever support frame construction range has a horizontal slope of 1.5% to complete the hardening of the foundation; drainage ditches are set on both sides of the foundation to complete the waterproofing of the foundation. The drainage ditch and the 1.5% horizontal slope facilitate drainage of the foundation.

[0049] 2) Build the lower plate buckle frame 103

[0050] Determine the construction pitch of the lower buckle frame 103, that is, the pitch between two adjacent vertical poles along the bridge direction is 0.6m, and the pitch between two adjacent vertical poles along the bridge transverse direction is 0.6m; the pitch between two adjacent horizontal bars (the spacing along the vertical pole height direction of the lower buckle frame 103) is 1.5m, and the pitch between two adjacent horizontal bars at the top of the lower buckle frame 103 is 1m;

[0051] On the foundation within the construction range of the cantilever support frame, build the lower buckle frame 103 according to the construction step of the lower buckle frame 103, and install a top support on the upper end of the vertical pole of the lower buckle frame 103, and install a bottom support on the lower end of the vertical pole;

[0052] In order to enhance the integrity of the lower plate-hook frame 103, multiple rows of channel steels 101 are arranged along the transverse direction of the bridge, and the channel steels 101 are located between the bottom support at the lower end of the vertical pole and the concrete.

[0053] 3) Build steel pipe diagonal brace 105

[0054] Determine the construction pitch of the steel pipe horizontal rods 104, that is, the distance between two adjacent steel pipe horizontal rods 104, which is 1.5m;

[0055] Multiple steel pipe horizontal rods 104 are sequentially installed on the vertical rods of the lower buckle frame 103 from top to bottom according to the construction pitch of the steel pipe horizontal rods 104; at the same time, the multiple steel pipe horizontal rods 104 are extended to the outside of the lower buckle frame 103, and the multiple steel pipe horizontal rods 104 extended to the outside of the lower buckle frame 103 are distributed in an inverted trapezoidal shape;

[0056] On the plurality of steel pipe horizontal rods 104, a plurality of parallelly distributed steel pipe diagonal braces 105 are sequentially connected by fasteners 106, and a diagonal brace top support is provided on the top of the steel pipe diagonal brace 105;

[0057] The bottom of the steel pipe brace 105 is erected on the channel steel 101. In order to ensure the stability of the steel pipe brace 105 on the channel steel 101, a wedge-shaped wooden block support 102 is arranged between the bottom of the steel pipe brace 105 and the channel steel 101, and the anti-slip steel bars 202108 of the steel pipe brace 105 are welded on the channel steel 101 to fix the wedge-shaped wooden block support 102.

[0058] 4) Install I-beam 201

[0059] Adjust the top support of the steel pipe brace 105 and the top support of the upper end of the lower plate buckle frame 103 so that they are at the same height; install the I-beam 201 on the top support of the lower plate buckle frame 103 and the top support of the steel pipe brace 105, with the cantilevered end of the I-beam 201 extending out of the edge of the box beam structure, and the other end serving as the main keel of the box beam bottom plate;

[0060] The top support of the steel pipe brace 105 is located on the same axis as the steel pipe brace 105 , an anti-skid wooden wedge 107 is arranged between the top support and the I-beam 201 , and anti-skid steel bars 202108 for fixing the anti-skid wooden wedge 107 are welded.

[0061] 5) Build flange plate buckle bracket 203

[0062] A flange plate buckle bracket 203 is built above the I-beam 201; the vertical poles of the flange plate buckle bracket 203 are arranged at a spacing of 0.6m along the bridge direction, and the spacing along the transverse direction of the bridge increases from 0.6m to 0.9m from the center line of the bridge outward; the step distance of the cross bar along the height direction is 1m.

[0063] An anti-slip steel bar 202108 is provided between the lower end of the vertical rod of the flange plate buckle bracket 203 and the I-beam 201;

[0064] The height of the outermost row of vertical poles of the flange plate buckle bracket 203 along the horizontal direction of the bridge exceeds the structural surface of the flange plate 403 by 1.5m, and two cross bars are set at the height of 0.5m and 1m of the outermost row of vertical poles, and the inner side between the two cross bars is fully hung with a dense mesh safety net.

[0065] A 0.9m wide construction platform is arranged between the two outermost rows of vertical poles of the flange plate buckle bracket 203 along the horizontal direction of the bridge, and the construction platform is fully paved with steel pedals 205 matching the buckle frame, and footboards with a height of not less than 18cm are arranged around the steel pedals 205.

[0066] 6) Build flange plate formwork 206 and cast-in-place box beam bottom plate

[0067] Install the cast-in-place box beam bottom plate and flange plate formwork 206 above the flange plate buckle bracket 203 and above the lower buckle bracket;

[0068] Installation of longitudinally distributed square timber: After the installation of I-beam 201 is completed, the installation of the bottom plate secondary ribs is carried out. Install 100×100mm wooden secondary ribs along the bridge direction, with a spacing of 200mm in the side web area, 300mm in the empty box room area, and 200mm in the middle web area. The laying spacing must be strictly in accordance with the design, and the pre-camber of the box beam must be reserved. Use a level to check the elevation. After it is correct, the bottom formwork can be assembled.

[0069] Installation of bottom formwork: After the secondary ribs are installed, the formwork is laid. The formwork uses 15mm bamboo plywood. When laying the bottom formwork of the beam, the top adjustable support should be adjusted to the predetermined elevation first, and the wire should be pulled to level it. The secondary ribs should be placed smoothly. After the flatness requirements are met, the bottom formwork is laid, and the bottom formwork and the secondary ribs are fixed by nailing. When laying, the long side of the formwork is laid along the bridge to ensure that the board seams are aligned in the horizontal and vertical directions. To prevent leakage, the joints of the formwork are first hammered tight, and then double-sided tape is applied, and the bottom formwork is nailed to the square wood with iron nails to reduce the gap between the square wood and the formwork. The stability of the bracket system and the close connection between the components ensure the integrity of the bottom formwork system of the box beam.

[0070] The main keel of the outer side form of flange plate 403 adopts double-piece φ48×2.7mm steel pipes, and each side form diagonal brace is fastened with 4 fasteners to the vertical pole or horizontal pole of the buckle frame; the secondary ribs adopt 100×100mm wooden beams, which are arranged along the direction of the bridge with a spacing of 250mm.

[0071] The outer formwork of the inclined web is made of 15mm bamboo plywood. The edge line of the bottom plate of the box beam is determined according to the measurement and setting out. The ink line is drawn on the bottom template, and then the side template is installed. Ensure that the plate seams are aligned in the horizontal and vertical directions. To prevent leakage, double-sided tape is pasted between the template joints, and the bottom template is nailed to the square wood with iron nails to reduce the gap between the square wood and the template. The rounded chamfer of the lower part of the web is made of 1.5mm thick customized galvanized steel plate, which is nailed to the bottom template and side template with carpentry nails. When installing the outer template of the inclined web, reserve the steel strand bundle hole at the corresponding position of 16# I-beam 201.

[0072] 7) Concrete pouring construction

[0073] The box beam bottom plate and web steel bars are centrally cut and processed in the steel bar processing yard and transported to the site for installation. The steel bar installation construction sequence is: first layer bottom plate steel bars → cross beam steel bars → web steel bars → second layer bottom plate steel bars → chamfered steel bars between bottom plate and web plates. The installation of prestressed corrugated pipes and the threading of prestressed steel strands 302 are carried out in parallel with the installation of steel bars.

[0074] During the construction process, if reserved holes or the steel bars collide with the prestressed pipes, prestressed bars should be used as the main reinforcement and the position of ordinary steel bars should be adjusted appropriately.

[0075] The vertical concrete of the box girder is poured in two times, first pouring the web and bottom plate, and then pouring the top plate. The vertical concrete pouring sequence is: the first pouring of box girder concrete 401: unloading from the web, pouring to the chamfer of the web → unloading from the inner box, pouring the bottom plate → unloading from the web, pouring the web concrete. The second pouring of box girder concrete 402: pouring of top plate concrete.

[0076] After the concrete is poured, it is watered and cured. Geotextile is laid on the bottom plate and watered for curing. Plastic film is pasted on the belly plate to play a moisturizing role.

[0077] 8) Installation and tensioning of cantilever I-beam 201 prestressed steel strand 302:

[0078] Before pouring the box girder web, a steel strand bundle sleeve is pre-buried at the corresponding position of the same cross section of each cantilevered I-beam 201. After the web concrete is poured, the steel strand bundle is passed through, and a hole is drilled at the cantilevered end of the I-beam 201 and fixed with a steel plate + anchor as the anchor end of the steel strand.

[0079] When the concrete strength and elastic modulus of the web reach 90% of the design and the concrete age is greater than 7 days, a steel plate and a prestressed tensioning anchor 303 are installed at the tensioning end of the prestressed steel strand 302 inside the web.

[0080] The prestressed tension anchor 303 is a digital display prestressed tension anchor 303;

[0081] Set the controlled tensioning stress of the prestressed steel strand 302; tension the prestressed steel strand 302 with 0.1 times the controlled tensioning stress, 0.2 times the controlled tensioning stress, and 100% of the controlled tensioning stress in sequence through the prestressed tensioning anchor 303, and tension it for 5 minutes under the controlled tensioning stress of 100%. After the tensioning is completed, use the prestressed tensioning anchor 303 to anchor the prestressed steel strand 302.

[0082] When the prestressed steel strand 302 is tensioned by the prestressed tensioning anchor 303, the error range between the actual tensioning elongation value of the prestressed steel strand 302 and the theoretical tensioning elongation value is -6% to 6%; and the retraction amount at both ends of the prestressed steel strand 302 is less than 6mm; no broken wires of the steel strand shall occur during the tensioning construction process.

[0083] 9) Adjust the top support of the upper end of the vertical rod of the lower buckle bracket and the top support of the diagonal brace 105 at the top of the steel pipe diagonal brace

[0084] After the prestressed steel strand 302 is tensioned, adjust the top support of the upper end of the vertical rod of the lower buckle bracket below the I-beam 201 and the top support of the diagonal brace at the top of the steel pipe diagonal brace 105 so that the top support of the diagonal brace at the top of the steel pipe diagonal brace 105 and the top support of the upper end of the vertical rod of the lower buckle bracket 103 are in contact with the I-beam 201.

[0085] 10) Adjust the flange plate buckle bracket 203

[0086] Adjust the top support of the upper end of the middle rod of the flange plate buckle bracket 203 to make it fit with the flange plate template 206, and then combine the flange plate template 206 and the web template to perform concrete pouring construction;

[0087] The construction steps for pouring flange plate 403 are: installation of top plate reinforcement and prestressing → pouring and curing of top plate concrete.

[0088] 11) Dismantle the frame

[0089] When the measured cubic strength and elastic modulus of the cast-in-place prestressed box girder concrete reach 90% of the design value and the age reaches 7 days, the frame is dismantled;

[0090] The cast-in-place box beam bottom plate, flange plate formwork 206 and web plate formwork are removed when the concrete strength can ensure that there is no block drop and crack on the surface of the components and holes. Generally, the compressive strength of concrete should reach 2.5Mpa. The side formwork of the web plate formwork and flange plate formwork 206 is removed when the concrete strength reaches 75% of the design strength.

[0091] The lower buckle frame 103 and the flange plate buckle bracket 203 can only be removed when the concrete strength reaches more than 95% of the standard value and the curing time is not less than 7 days and the elastic modulus reaches 100%; before the lower buckle frame 103 and the flange plate buckle bracket 203 are removed, all prestressed steel strands 302 should have been tensioned and grouted, and the grouting strength should have reached more than 90% of the design value.

[0092] The dismantling procedure for cast-in-place box girders should start from the support node where the mid-span deflection is the largest, and gradually remove the adjacent nodes on both sides. It is required to be carried out symmetrically, evenly and in sequence. At the same time, each node should be removed in multiple times so that the settlement curve of the beam can be gradually increased.

[0093] When dismantling the prestressed cantilever support frame system, first release the prestressed steel strand 302. After the prestressed steel strand 302 is relaxed, remove the flange plate buckle bracket 203 above the I-beam 201. After the cast-in-place box girder bottom plate is removed, remove the I-beam 201, and finally remove the lower buckle bracket 103 and steel pipe diagonal brace 105 below the I-beam 201.

[0094] Embodiment 2

[0095] Compared with the first embodiment, the difference is that after the foundation treatment is completed, the cantilever support frame can be arranged according to the on-site construction conditions so that it can be reasonably supported; in this embodiment, Figure 2 and Figure 3 As shown, the cantilever support frame is divided into three support areas, namely cantilever area 5, dense layout area 6, and normal layout area 7; cantilever area 5 corresponds to the flange plate buckle bracket 203; the dense layout area 6 and the normal layout area 7 correspond to the lower buckle frame 103, and the difference between the dense layout area 6 and the normal layout area 7 is that the step distance of the lower buckle frame 103 in the two areas is different. The step distance of the lower buckle frame 103 in the normal layout area 7 is: the step distance of two adjacent vertical poles along the bridge direction is 0.9m, and the step distance of two adjacent vertical poles along the horizontal direction of the bridge is 0.9m; the step distance between two adjacent cross bars (the distance along the height direction of the vertical poles of the lower buckle frame 103) is 1.5m, and the step distance between two adjacent cross bars at the top of the lower buckle frame 103 is 1m.

[0096] The above is only a specific embodiment of the present invention, but the protection scope of the present invention is not limited thereto. Any changes or substitutions within the technical scope disclosed by the present invention should be included in the protection scope of the present invention. Therefore, the protection scope of the present invention should be based on the protection scope recorded in the claims.

Claims

1. A construction method for a cast-in-place box beam flange plate cantilever support frame, characterized in that: The steps include: S1. Determine the construction scope of the cantilever support frame, extend the construction scope of the cantilever support frame outward by 2m on all sides, and use it as the foundation for building the cantilever beam support frame; harden and waterproof the foundation; S2, determining the construction step distance of the lower buckle frame (103), constructing the lower buckle frame (103) on the foundation within the construction range of the cantilever support frame according to the construction step distance of the lower buckle frame (103), and installing a top support on the upper end of the vertical pole of the lower buckle frame (103) and a bottom support on the lower end of the vertical pole; S3, determining the construction pitch of the steel pipe horizontal rod (104), and sequentially installing a plurality of steel pipe horizontal rods (104) on the vertical rods of the lower buckle frame (103) from top to bottom according to the construction pitch of the steel pipe horizontal rod (104); at the same time, making the plurality of steel pipe horizontal rods (104) extend to the outside of the lower buckle frame (103), and the plurality of steel pipe horizontal rods (104) extending to the outside of the lower buckle frame (103) are distributed in an inverted trapezoidal shape; A plurality of sets of parallel steel pipe diagonal braces (105) are sequentially installed on a plurality of steel pipe horizontal rods (104), and a diagonal brace top support is arranged on the top of the steel pipe diagonal braces (105); S4, adjusting the top support of the steel pipe brace (105) and the top support of the upper end of the vertical rod of the lower plate buckle frame (103) so that the two are at the same height; Install the I-beam (201) on the top support of the vertical pole of the lower buckle frame (103) and the top support of the diagonal brace on the top of the steel pipe diagonal brace (105), and build a flange plate buckle bracket (203) above the I-beam (201); S5, installing the cast-in-place box beam bottom plate and flange plate formwork (206) above the flange plate buckle bracket (203) and above the lower buckle bracket; Combine the cast-in-place box girder bottom plate, flange plate formwork (206) and web plate formwork to perform the first concrete pouring 401, and pre-embed sleeves (301) on the inclined web and middle web of the cast-in-place box girder, and pre-embed prestressed tension anchors (303) on the middle web; S6. After the concrete strength reaches 90% of the design strength and the concrete age exceeds 7 days, the prestressed steel strand (302) is installed, one end of the prestressed steel strand (302) is connected to the cantilevered end of the I-beam (201), and the other end passes through the inclined web and the middle web, and the prestressed steel strand (302) is tensioned by a prestressed tensioning anchor (303); S7, after the prestressed steel strand (302) is tensioned, the top support of the upper end of the vertical rod of the lower buckle bracket below the I-beam (201) and the top support of the diagonal brace at the top of the steel pipe diagonal brace (105) are adjusted to make the top support of the diagonal brace at the top of the steel pipe diagonal brace (105) and the top support of the upper end of the vertical rod of the lower buckle bracket (103) fit the I-beam (201); S8, adjusting the top support of the upper end of the middle rod of the flange plate buckle bracket (203) to make it fit with the flange plate template (206), and then combining the flange plate template (206) and the inner box template to perform the second concrete pouring 402 and the flange plate 403 pouring; S9. After the concrete strength reaches 90% of the design strength and the concrete age exceeds 7 days, the lower buckle frame (103), the flange plate buckle bracket (203), the flange plate formwork (206), the cast-in-place box beam bottom plate and the prestressed steel strand (302) are removed, and the cantilever support frame construction of the cast-in-place box beam flange plate is completed.

2. The construction method of the cast-in-place box girder flange plate cantilever support frame according to claim 1 is characterized in that: In step S1, the specific method of hardening and waterproofing the foundation is: Excavate the humus and garbage soil on the surface of the foundation, and use a 22t roller to compact it to make the foundation bearing capacity greater than 200Kpa; A 30cm thick Panax notoginseng lime soil base layer is laid on the compacted foundation and compacted to a degree of more than 95%; the bearing capacity of the compacted Panax notoginseng lime soil base layer is greater than 300kpa; Lay 20cm thick concrete on the compacted Sanqi lime soil base, and ensure that the concrete within the cantilever support frame has a horizontal slope of 1.5%, completing the hardening treatment of the foundation; Drainage ditches are set up on both sides of the foundation to complete the waterproofing of the foundation.

3. The construction method of cast-in-place box girder flange plate cantilever support frame according to claim 1, characterized in that: In step S2, the construction pitch of the lower buckle frame (103) includes: the pitch of two adjacent vertical poles along the bridge direction is 0.6m, the pitch of two adjacent vertical poles along the bridge transverse direction is 0.6m; the pitch between two adjacent horizontal poles is 1.5m, and the pitch between two adjacent horizontal poles at the top of the lower buckle frame (103) is 1m; A channel steel (101) is arranged between the bottom bracket at the lower end of the vertical pole and the concrete.

4. The construction method of the cast-in-place box girder flange plate cantilever support frame according to claim 1, characterized in that: In step S3, the construction pitch of the steel pipe horizontal rods (104) is the distance between two adjacent steel pipe horizontal rods (104) above and below, which is 1.5 m; The bottom of the steel pipe diagonal brace (105) is placed on the channel steel (101).

5. The construction method of cast-in-place box girder flange plate cantilever support frame according to claim 1, characterized in that: In step S3, the steel pipe horizontal rod (104) and the steel pipe diagonal brace (105) are connected by fasteners (106).

6. The construction method of cast-in-place box girder flange plate cantilever support frame according to claim 1, characterized in that: In steps S5 and S8, after the concrete pouring is completed, the concrete is sprinkled with water for curing.

7. The construction method of cast-in-situ box girder flange plate cantilever support frame according to claim 1, characterized in that: In step S6, the prestressed tension anchor (303) is a digital display prestressed tension anchor (303); the specific method of tensioning the prestressed steel strand (302) by the prestressed tension anchor (303) is: Setting the controlled tension stress of the prestressed steel strand (302); The prestressed steel strand (302) is tensioned by a prestressed tensioning anchor (303) at 0.1 times of controlled tensioning stress, 0.2 times of controlled tensioning stress, and 100% of controlled tensioning stress in sequence, and tensioned for 5 minutes at 100% of controlled tensioning stress. After tensioning is completed, the prestressed steel strand (302) is anchored by the prestressed tensioning anchor (303).

8. The construction method of the cast-in-situ box girder flange plate cantilever support frame according to claim 7, characterized in that: In step S6, when the prestressed steel strand (302) is tensioned by the prestressed tensioning anchor (303), the error range between the actual tensioning elongation value of the prestressed steel strand (302) and the theoretical tensioning elongation value is -6% to 6%; and the retraction amount at both ends of the prestressed steel strand (302) is less than 6mm.