A Temporary Reinforcement Method for Independent Tube Structures in Super High-Rise Climbing Formwork Construction
By setting up climbing formwork, outer frame steel beams, and C-shaped channel steel supports in super high-rise buildings to form a frame structure, the problem of insufficient stability of the core tube structure in high-rise construction is solved, enabling rapid construction and safe staggered synchronous construction, avoiding idle work on the outer frame, and shortening the construction period.
Patent Information
- Application Number
- CN202411259602.9
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2024-09-10
- Publication Date
- 2026-11-17
- Estimated Expiration
- 2044-09-10
AI Technical Summary
In the construction of super high-rise buildings, the stiffness and stability of the core tube structure decrease as the height increases, which leads to an increase in the load at the attachment support of the climbing formwork, posing safety hazards such as cracking and overturning instability, and making it difficult to achieve the height requirement of independent construction of the core tube.
The system employs components such as climbing formwork inner frame, climbing formwork outer frame, outer frame steel beams, outer frame steel columns, C-channel steel supports, support node plates, and attachment supports to form an overall frame structure. The C-channel steel supports are connected to the outer frame steel beams to increase the stability and wind pressure resistance of the core tube, and can be reused to accelerate the construction progress.
It enables rapid construction of the core tube and forms a staggered synchronous construction of multiple working surfaces of the outer frame, avoiding idle work on the outer frame, shortening the construction period, and making the construction environmentally friendly and reusable.
Smart Images

Figure CN118979616B_ABST
Abstract
Description
Technical Field
[0001] This invention relates to the field of building protective frame construction technology, specifically to a temporary reinforcement method for independent cylindrical structures in ultra-high-rise climbing formwork construction. Background Technology
[0002] In the construction of buildings with a core tube-steel frame structure and a total height exceeding 100 meters, the general principle for this type of construction is a construction sequence of "core tube first, outer frame structure following". During construction, the core tube structure must be constructed quickly and prioritized to provide working surfaces for subsequent installation of the outer frame steel structure and construction of the outer frame floor slab structure. Therefore, the safety protection of such projects generally adopts hydraulic climbing formwork construction technology to ensure that the core tube and outer frame structure are constructed independently first, thereby forming a favorable working condition of "staggered synchronous construction" of the three working layers of "core tube - steel frame outer frame - outer frame floor slab". The key to achieving the "staggered synchronous construction" mode lies in increasing the construction speed of the core tube structure and creating a difference of at least six stories between it and the outer frame structure. However, the difficulty in forming this operation mode lies in the following: As the core tube structure of the super high-rise building is constructed upwards, after it exceeds a certain height: the thickness of the shear walls in the core tube structure decreases, and the walls become thinner; all elevators in the middle and low zones of the core tube reach the top, and some internal horizontal connecting beams and shear wall structures are eliminated, resulting in fewer connecting components between walls and a simpler structural form; the wind load at the top of the building increases, causing the horizontal load at the attachment support of the climbing formwork to also increase. The changes have led to a decrease in the stiffness and overall stability of the core tube structure. As a result, the height of the core tube structure can be independently constructed, which is constrained. If the expected design and construction height is not reached, there will be quality and safety hazards such as cracking or even overturning and instability within the structure. To address this, the applicant has proposed a temporary reinforcement method for independent tube structures in ultra-high-rise climbing formwork construction, based on the characteristics of this type of building construction. This method effectively solves the above problems, enables rapid construction of the core tube, and creates a favorable working condition of "staggered synchronous construction" of multiple working surfaces of the outer frame. This avoids the occurrence of idle work on the outer frame and greatly shortens the construction period. Summary of the Invention
[0003] To address the aforementioned technical problems, this invention proposes a temporary reinforcement method for independent core tube structures in ultra-high-rise climbing formwork construction. The method involves setting up an inner and outer climbing formwork frame, outer frame steel beams, outer frame steel, attachment supports, C-channel steel supports, support node plates, connecting plates, and material discharge ports. The construction method involves installing the inner and outer climbing formwork frames on the core tube, installing the outer frame on the outer main structure plate of the core tube, optimizing the C-channel steel support layout on the outer frame, reserving material discharge ports, welding support node plates onto the outer frame steel beams and columns on the same floor, and placing the C-channel steel supports flat on the support node plates and fixing them with bolts. This connects the core tube structure, C-channel steel supports, outer frame steel beams, and outer frame steel columns into a whole, providing bracing-tension constraints to the thin core tube wall. Multiple layers of outer frame steel beams and C-channel steel supports are simultaneously installed according to the actual required floor difference between the core tube and the outer frame. These supports are removed after the outer frame main structure is completed and can be reused, accelerating construction.
[0004] To achieve the above objectives, the technical solution adopted by the present invention is as follows: A temporary reinforcement method for an independent core tube structure constructed using climbing formwork in ultra-high-rise buildings includes an inner climbing formwork frame, an outer climbing formwork frame, an outer frame, outer frame steel columns, outer frame steel beams, C-channel steel supports, a material discharge port, support node plates, connecting plates, and attachment supports. The method is characterized by the following: the inner climbing formwork frame, the outer climbing formwork frame, and the outer frame are installed on the core tube; the outer frame is installed on the main structural slab outside the core tube; the inner climbing formwork frame and the outer climbing formwork frame are installed on the core tube via attachment supports; the attachment supports and connecting plates are pre-embedded in the core tube wall. Structurally, the outer frame is provided with outer frame steel columns and outer frame steel beams, which are bolted together. The outer frame steel columns are installed on the main structural plate. The outer frame steel columns and outer frame steel beams are supported by C-shaped channel steel to form a space frame structure. The C-shaped channel steel supports have a pre-reserved material outlet in the middle of the space frame. Support node plates are provided on the outer frame steel columns and outer frame steel beams. The C-shaped channel steel supports are connected to the outer frame steel columns and outer frame steel beams through the support node plates. The connection between the C-shaped channel steel supports and the core tube is connected through support node plates and connecting plates. The support node plates are welded to the connecting plates. Multiple sets of outer frame steel beams are provided between the outer frame steel columns and the core tube as needed.
[0005] Furthermore, the outer side of the core tube of the temporary reinforcement and construction method of the independent tube structure for the super high-rise climbing formwork construction is connected to the C-shaped channel steel support, the outer frame steel column and the outer frame steel beam, and the C-shaped channel steel support, the outer frame steel column and the outer frame steel beam form a frame support for the core tube.
[0006] Furthermore, the temporary reinforcement of the independent cylindrical structure in the super high-rise climbing formwork construction and the C-shaped channel steel support connection set by the construction method form a triangular mesh structure, which has strong stability.
[0007] Furthermore, the construction method for temporary reinforcement of the independent cylindrical structure in the super high-rise climbing formwork construction includes the following specific construction steps: Step 1: Based on the dimensions of the building's core tube and the external main structure, prepare the frame layout drawing and construction plan for the climbing formwork, verify its safety performance to ensure it meets safety protection and construction requirements, and obtain expert approval; fabricate and optimize the C-shaped channel steel support layout in the construction plan, and reserve a sufficiently large material discharge port. Step 2: Based on the scaffolding layout drawing and construction plan, fabricate the inner scaffolding, outer scaffolding, outer frame steel beams, outer frame steel columns, and C-shaped channel steel supports of the climbing formwork. After completion, organize acceptance. Step 3: During the construction of the building core tube and external main structure, embed attachment supports and connecting plates in the core tube wall and main structure slab; Step 4: After reaching the installation height of the inner climbing formwork, outer climbing formwork, and outer frame, simultaneously install the inner climbing formwork, outer climbing formwork, outer frame steel columns, outer frame steel beams, and C-channel steel supports. Step 5: After the inner frame, outer frame and outer frame of the climbing formwork are raised to a certain height, the outer frame is connected to the outside of the core tube by C-shaped channel steel support, so as to form an integral frame structure. The outer frame provides a certain support to the outside of the core tube, which can increase the construction height of the core tube and make the core tube have a strong wind pressure resistance. Step 6: Based on the number of floors between the building's core tube and the external frame structure, set up multi-level, multi-channel outer frame steel beams and C-shaped channel steel supports to form a zoned, continuous operation surface; Step 7: As the building height increases, the inner climbing formwork, outer climbing formwork, and outer frame are used in a cyclical climbing process until the building is topped out, thus accelerating the construction progress and ensuring construction safety.
[0008] The benefits of this application are: 1. The temporary reinforcement and construction method of independent core tube structure in the construction of climbing formwork for super high-rise buildings effectively solves the problem of safe and stable independent construction of the core tube structure under the action of climbing formwork attachment support and wind load after the building height increases and the structure changes abruptly. 2. The temporary reinforcement and construction method of the independent tube structure in the climbing formwork construction of super high-rise buildings enabled the rapid construction of the core tube and formed a favorable working condition of "staggered synchronous construction" of multiple working surfaces of the outer frame, avoiding the occurrence of idle work of the outer frame and greatly shortening the construction period. 3. Temporary reinforcement and construction methods for independent tube structures in ultra-high-rise climbing formwork construction: The form and arrangement of steel supports on the outer side of the core tube and the outer frame do not affect the construction of other disciplines, and can be reused and eventually recycled, making the construction green and environmentally friendly. Attached Figure Description
[0009] Figure 1 This is a schematic diagram of the overall structure of the present invention; Figure 2 This is a partial structural diagram of the present invention. Figure 1 ; Figure 3 This is a partial structural diagram of the present invention. Figure 2 ; Figure 4 This is a partial structural diagram of the present invention. Figure 3 .
[0010] The markings in the diagram are as follows: 1. Core tube; 1-1. Climbing formwork inner frame; 1-2. Climbing formwork outer frame; 2. Outer frame; 3. Outer frame steel column; 4. Outer frame steel beam; 5. C-shaped channel steel support; 6. Discharge port; 7. Support node plate; 8. Connecting plate; 9. Attachment support. Detailed Implementation
[0011] The present invention will be further described in detail below with reference to the accompanying drawings and specific embodiments: like Figure 1-4 As shown, this is a temporary reinforcement method for an independent cylindrical structure in a high-rise climbing formwork construction project, including an inner climbing formwork 1-1, an outer climbing formwork 1-2, an outer frame 2, outer frame steel columns 3, outer frame steel beams 4, C-shaped channel steel supports 5, a material discharge port 6, support node plates 7, connecting plates 8, and attachment supports 9. Figure 1 As shown, the temporary reinforcement and construction method for the independent tube structure in the super high-rise climbing formwork construction includes an inner climbing formwork frame 1-1, an outer climbing formwork frame 1-2, and an outer frame 2. The inner climbing formwork frame 1-1, the outer climbing formwork frame 1-2, and the outer frame 2 are fabricated from prefabricated climbing formwork frames. The outer frame 2 is installed on the main structural plate outside the core tube 1. Figure 2 As shown, the inner frame 1-1 and outer frame 1-2 of the climbing formwork are installed on the core tube 1 via attachment supports 9. The attachment supports 9 are pre-embedded in the core tube wall structure, with some parts installed by welding. The outer frame 2 is equipped with outer frame steel columns 3 and outer frame steel beams 4, which are bolted together. C-shaped channel steel supports 5 form a grid structure between the outer frame steel columns 3 and outer frame steel beams 4. The C-shaped channel steel supports 5 are connected to form a triangular mesh structure, providing strong stability. A material discharge port 6 is reserved in the middle of the C-shaped channel steel support 5 grid structure. Figure 3As shown, support node plates 7 are installed on the outer frame steel columns 3 and outer frame steel beams 4. C-shaped channel steel supports 5 are connected to the outer frame steel columns 3 and outer frame steel beams 4 through the support node plates 7. Multiple sets of outer frame steel beams 4 are provided between the outer frame steel columns 3 and the core tube 1 as required; Figure 2 The outer side of the core tube 1 is connected to the C-shaped channel steel support 5, the outer frame steel column 3, and the outer frame steel beam 4, forming an integral frame structure. The outer frame 2 provides some support to the outer side of the core tube 1, which can increase the construction height of the core tube and give it strong wind pressure resistance. Figure 4 As shown, the C-shaped channel steel support 5 is connected to the core tube 1 through a support node plate 7 and a connecting plate 8. The support node plate 7 is welded to the connecting plate 8. The C-shaped channel steel support 5, the outer frame steel column 3 and the outer frame steel beam 4 form a frame structure support for the climbing formwork outer frame 1-2 and the core tube 1.
[0012] The construction method for temporary reinforcement of independent cylindrical structures in ultra-high-rise climbing formwork construction, as shown, includes the following specific construction steps: Step 1: Based on the dimensions of the building's core tube and the external main structure, prepare the frame layout drawing and construction plan for the climbing formwork, verify its safety performance to ensure it meets safety protection and construction requirements, and obtain expert approval; fabricate and optimize the C-shaped channel steel support layout in the construction plan, and reserve a sufficiently large material discharge port. Step 2: Based on the scaffolding layout drawing and construction plan, fabricate the inner scaffolding, outer scaffolding, outer frame steel beams, outer frame steel columns, and C-channel steel supports of the climbing formwork. After completion, organize acceptance testing. Prefabrication and modular installation accelerate construction efficiency. Joint acceptance testing ensures safety. Step 3: During the construction of the building core tube and external main structure, pre-embed attachment supports and connecting plates in the core tube wall and main structure slab; the use of pre-embedded connecting plates ensures a stable connection node during the installation and welding of the outer frame steel beams, and guarantees the maximum height of the steel support to the upper flange of the steel beam, which helps to facilitate the continuous arrangement of the main steel pipe ribs and secondary timber ribs at the bottom of the slab during the construction of the outer frame concrete floor slab formwork. Step 4: After reaching the installation height of the inner climbing formwork, outer climbing formwork, and outer frame, install the inner climbing formwork, outer climbing formwork, outer frame steel columns, outer frame steel beams, and C-shaped channel steel supports. The simultaneous installation ensures the movement and use of long materials such as steel pipes and reinforcing bars or large equipment such as concrete placing booms during the construction of the outer frame, thus ensuring the smooth operation of the outer frame construction. Step 5: After the climbing formwork inner frame, climbing formwork outer frame, and outer frame are raised to a certain height, the outer frame is connected to the outside of the core tube through C-shaped channel steel supports, forming an integral frame structure. The outer frame provides certain support to the outside of the core tube, which can increase the construction height of the climbing formwork inner frame and climbing formwork outer frame, giving the core tube a stronger wind pressure resistance; it also allows the horizontal load of the climbing formwork support to be effectively transferred to the steel components of the outer frame, thereby reducing the independent height of the tube structure and increasing its overall stability. Step Six: Based on the difference in height between the building's core tube and the external frame structure, set up multi-level, multi-channel outer frame steel beams and C-shaped channel steel supports to form zoned, continuous operation surfaces; increase the number of construction surfaces and stagger construction to ensure construction safety; Step 7: As the building height increases, the inner climbing formwork, outer climbing formwork, and outer frame are used in a cyclical climbing process until the building is topped out, thus accelerating the construction progress and ensuring construction safety.
[0013] The above description is merely a preferred embodiment of the present invention and is not intended to limit the present invention in any other way. Any modifications or equivalent changes made based on the technical essence of the present invention shall still fall within the scope of protection claimed by the present invention.
Claims
1. A construction method for temporary reinforcement of an independent tube structure in a super high-rise climbing formwork construction, comprising an inner climbing formwork frame (1-1), an outer climbing formwork frame (1-2), an outer frame (2), outer frame steel columns (3), outer frame steel beams (4), C-shaped channel steel supports (5), a material outlet (6), support node plates (7), connecting plates (8), and attachment supports (9). The inner climbing formwork frame (1-1) and the outer climbing formwork frame (1-2) are installed on the core tube (1). The outer frame (2) is installed on the main structural plate outside the core tube (1). The inner climbing formwork frame (1-1) and the outer climbing formwork frame (1-2) are installed on the core tube (1) through attachment supports (9). The attachment supports (9) and the connecting plates (8) are pre-embedded on the wall structure of the core tube (1). The outer frame (2) is provided with outer frame steel columns (3) and outer frame steel beams (4). The outer frame steel columns (3) and outer frame steel beams (4) are bolted together. The outer frame steel columns (3) are installed on the main structure plate. The outer frame steel columns (3) and outer frame steel beams (4) are connected by C-shaped channel steel supports (5) to form a grid structure. The C-shaped channel steel supports (5) have a pre-reserved discharge port (6) in the middle of the grid. Support node plates (7) are provided on the outer frame steel columns (3) and outer frame steel beams (4). The C-shaped channel steel supports (5) are connected to the outer frame steel columns (3) and outer frame steel beams (4) through the support node plates (7). The C-shaped channel steel supports (5) are connected to the core tube (1) through the support node plates (7) and the connecting plate (8). The support node plates (7) are welded to the connecting plate (8). Multiple sets of outer frame steel beams (4) are provided between the outer frame steel columns (3) and the core tube as required. The specific construction steps are as follows: Step 1: Based on the dimensions of the building's core tube and the external main structure, prepare the frame layout drawing and construction plan for the climbing formwork, verify its safety performance to ensure it meets safety protection and construction requirements, and obtain expert approval; fabricate and optimize the C-shaped channel steel support layout in the construction plan, and reserve a sufficiently large material discharge port. Step 2: Based on the scaffolding layout drawing and construction plan, fabricate the inner scaffolding, outer scaffolding, outer frame steel beams, outer frame steel columns, and C-shaped channel steel supports of the climbing formwork. After completion, organize acceptance. Step 3: During the construction of the building core tube and external main structural slab, embed attachment supports and connecting plates in the core tube wall and the main structural slab; Step 4: After reaching the installation height of the inner climbing formwork, outer climbing formwork, and outer frame, simultaneously install the inner climbing formwork, outer climbing formwork, outer frame steel columns, outer frame steel beams, and C-channel steel supports. Step 5: After the inner frame, outer frame and outer frame of the climbing formwork are raised to a certain height, the outer frame is connected to the outside of the core tube through C-shaped channel steel support, so as to form an integral frame structure. The outer frame provides a certain support for the core tube, which can increase the construction height of the core tube and make the core tube have a strong wind pressure resistance. Step 6: Based on the number of floors between the building's core tube and the external frame structure, set up multi-level, multi-channel outer frame steel beams and C-shaped channel steel supports to form a zoned, continuous operation surface; Step 7: As the building height increases, the inner climbing formwork, outer climbing formwork, and outer frame are used in a cyclical climbing process until the building is topped out, thus accelerating the construction progress and ensuring construction safety.
2. The construction method for temporary reinforcement of an independent cylindrical structure in ultra-high-rise climbing formwork construction according to claim 1, characterized in that: The C-shaped channel steel supports (5) are connected to form a triangular mesh structure.
Citation Information
Patent Citations
Core tube crisscross structure synchronous construction structure and construction method thereof
CN107246073A
Ultra-high special-shaped outer-frame steel structure construction method