Construction method of high-pressure jet grouting column groove in treatment process of underground drainage pipe network

Through the combination of vibration pile driver and drilling rig, the high-pressure rotary spray parameters are controlled, which solves the problems of long construction cycles and large equipment investment in the existing technology, and realizes efficient and stable high-pressure rotary spray column groove construction, improving construction quality and environmental impact.

CN118997166APending Publication Date: 2024-11-22THE 5TH ENGINEERING CO LTD OF CHINA RAILWAY CONSTRUCTION BRIDGE ENGINEERING BUREAU GROUP +2
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411422237.9
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-10-12
Publication Date
2024-11-22

AI Technical Summary

Technical Problem

The existing high-pressure rotary spray column groove construction technology has problems such as long construction cycle, large equipment investment, prone to failure and great impact on the environment.

Method used

Vibration pile driver is used to drive the casing, place the drilling rig and slow winch into the rotary nozzle, connect the high-pressure pipe and the cement slurry pipe, control the pressure, flow and air volume, ensure the precise adjustment of the rotary nozzle parameters, and level the site before and after construction. and equipment positioning to monitor changes in nearby structures.

Benefits of technology

It improves the efficiency and quality of construction, reduces labor costs, ensures the stability and controllability of the construction process, and enhances the stability and compressive resistance of the pile foundation.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118997166A_ABST
    Figure CN118997166A_ABST
Patent Text Reader

Abstract

The invention relates to the technical field of high-pressure jet grouting column groove construction, and discloses a construction method of a high-pressure jet grouting column groove in the treatment process of an underground drainage pipe network, a sleeve with a movable pile shoe is driven into soil by using a vibratory pile driver, and a part of the sleeve is pulled out to be higher than the ground; a drilling machine and a low-speed winch are placed, and the rotary spraying pipe is inserted into the hole through a drilling machine disc; connecting a high-pressure pipe and a cement slurry pipe, starting a high-pressure pump, a slurry pump and a rotary drilling machine to perform rotary spraying, and controlling pressure, flow and air quantity; after the preset parameters are reached, starting to lift the rotary spraying pipe until the rotary spraying height is reached; the rotary spraying pipe and the sleeve are pulled out, and the pipeline is washed with clear water, so that the punching time is saved, and the labor cost is reduced; by arranging the drilling machine and the low-speed winch and inserting the rotary spraying pipe into the hole through the drilling machine disc, the accuracy and stability of the construction process can be ensured, and therefore the engineering quality is improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of high-pressure rotary jet column trench construction, in particular to a method for constructing a high-pressure rotary jet column trench in the process of underground drainage pipe network management. Background Art

[0002] High-pressure rotary jet piles are widely used in comprehensive drainage network management projects to reinforce soil, foundations and pipeline trenches to prevent groundwater infiltration and soil sliding. The piles formed by high-pressure water jets and rotary jet technology provide stable support and waterproofing effects. During the construction process, they can be used as temporary supports to ensure construction safety.

[0003] The Chinese invention patent with announcement number CN110172969B in the prior art book provides a quadruple-tube high-pressure jet grouting pile construction method, including preparatory work before construction, determining the drilling position, using a drilling rig to drill, installing the jet pipe, performing jet grouting, cleaning the equipment and moving to the next pile construction position. The invention improves the bending strength of the formed pile by adding steel bars in the formed pile.

[0004] The existing technology has a long construction period, high technical requirements, large equipment investment, is prone to failure, and has a great impact on the environment. Summary of the invention

[0005] The purpose of the present invention is to provide a method for constructing a high-pressure rotary jet column trench in the process of underground drainage pipe network management to achieve a high-efficiency rotary jet function.

[0006] The present invention is implemented by the following technical scheme: A method for constructing a high-pressure rotary jet column trench in the process of underground drainage pipe network management, comprising the following steps: Step S1: Use a vibrating pile driver to drive a casing with a movable pile shoe into the soil, and pull out a portion of it to raise it above the ground.

[0007] Step S2: placing the drilling rig and the slow winch, and inserting the rotary nozzle into the hole through the drilling rig disc.

[0008] Step S3: Connect the high-pressure pipe and the cement slurry pipe, start the high-pressure pump, the mud pump and the rotary drill to perform rotary spraying, and control the pressure, flow and air volume at the same time.

[0009] Step S4: After reaching the predetermined parameters, the rotary spraying pipe begins to be lifted until the rotary spraying height is reached.

[0010] Step S5: Pull out the rotary spray pipe and sleeve, and flush the pipeline with clean water.

[0011] In order to better realize the present invention, further, the depth of the vibrating pile driver when driving into the casing is greater than the height of the quasi-rotational grouting.

[0012] In order to better realize the present invention, further, before the rotary grouting process starts, an instrument is used to accurately control the grouting pressure to be no less than 25 MPa.

[0013] In order to better implement the present invention, further, the water-cement ratio of the cement slurry is between 0.9 and 1.1.

[0014] In order to better realize the present invention, further, the lifting speed of the rotary spray pipe is 20cm / min.

[0015] In order to better implement the present invention, further, the step of cleaning the grouting pipe during the pulling out process uses clean water.

[0016] In order to better realize the present invention, further, before the construction process begins, the site is leveled, and slurry drainage ditches and drilling rig positioning are set to ensure that the drilling rig remains horizontal and the drill rod is vertical, and the inclination shall not be greater than 1%.

[0017] In order to better implement the present invention, further, during the construction process, nearby structures or buildings are monitored, and the construction is suspended when the elevation change of the nearby structures or buildings is greater than 10 mm.

[0018] Compared with the prior art, the present invention has the following advantages and beneficial effects: (1) The present invention uses a vibrating pile driver to drive the casing into the soil and then pulls out a portion of it to raise it above the ground, thereby saving drilling time and reducing labor costs; by placing a drilling rig and a slow winch and using a drilling rig disc to insert the rotary jet pipe into the hole, the accuracy and stability of the construction process can be ensured, thereby improving the quality of the project.

[0019] (2) The present invention connects a high-pressure pipe and a cement slurry pipe, and starts a high-pressure pump, a mud pump and a rotary drill to perform rotary spraying, while controlling the pressure, flow rate and air volume, thereby achieving precise adjustment of construction parameters and ensuring stability and controllability during the construction process.

[0020] (3) The present invention uses a vibrating pile driver to drive the casing into a depth greater than the height of the quasi-rotational grouting, which can ensure the stability and compressive strength of the pile foundation, thereby enhancing the bearing capacity and seismic resistance of the pile foundation. BRIEF DESCRIPTION OF THE DRAWINGS

[0021] Other features, objects and advantages of the present invention will become more apparent from the detailed description of non-limiting embodiments with reference to the following drawings: Figure 1 It is a schematic diagram of the construction process of the present invention. DETAILED DESCRIPTION

[0022] Embodiments of the present invention are described in detail below, examples of which are shown in the accompanying drawings, wherein the same or similar reference numerals throughout represent the same or similar elements or elements having the same or similar functions. The embodiments described below with reference to the accompanying drawings are exemplary and are only used to explain the present invention, and cannot be understood as limiting the present invention.

[0023] Embodiment 1: This embodiment provides a method for constructing a high-pressure jet spray column trench in the process of underground drainage pipe network management, comprising the following steps: Step S1: Use a vibrating pile driver to drive a casing with a movable pile shoe into the soil, and pull out a portion of it to raise it above the ground.

[0024] Step S2: placing the drilling rig and the slow winch, and inserting the rotary nozzle into the hole through the drilling rig disc.

[0025] Step S3: Connect the high-pressure pipe and the cement slurry pipe, start the high-pressure pump, the mud pump and the rotary drill to perform rotary spraying, and control the pressure, flow and air volume at the same time.

[0026] Step S4: After reaching the predetermined parameters, the rotary spraying pipe begins to be lifted until the rotary spraying height is reached.

[0027] Step S5: Pull out the rotary spray pipe and sleeve, and flush the pipeline with clean water.

[0028] The depth of the vibrating pile driver when driving into the casing is greater than the height of the planned jet grouting. Before the jet grouting process begins, the instrument is used to accurately control the grouting pressure to be no less than 25 MPa, the water-cement ratio of the cement slurry is between 0.9 and 1.1, the jet grouting tube lifting speed is 20 cm / min, and the grouting tube is cleaned with clean water during the extraction process. Before the construction process begins, the site is leveled, and the grouting ditch and drilling rig positioning are set to ensure that the drilling rig remains horizontal and the drill rod is vertical, with an inclination of no more than 1%. During the construction process, monitor nearby structures or buildings, and suspend construction when the elevation change of nearby structures or buildings is greater than 10 mm.

[0029] Embodiment 2: This embodiment further defines a method for constructing a high-pressure jet spray column trench in an underground drainage network treatment process based on the embodiment 1, comprising the following steps: Step S1: Use a vibrating pile driver to drive a casing with a movable pile shoe into the soil, and pull out a part of it to make it higher than the ground; before the construction begins, first select a casing of appropriate specifications and length, and the diameter, wall thickness and material of the casing need to be selected according to the engineering design and geological conditions; the movable pile shoe is a device installed at the bottom of the casing, which can be opened and closed during the piling and pulling out process. The pile shoe is designed to be closed when driven into the soil to prevent soil from entering the casing, and open when pulling out the pile to facilitate the separation of soil and casing; connect the vibrating pile driver to the casing; fix the clamping device of the vibrating pile driver to the top of the casing; start vibrating piling The vibrating pile driver is used to drive the casing slowly and evenly into the soil. The vibration rearranges the soil particles, thereby reducing the soil's resistance to the casing. During construction, the entry speed and direction of the casing are monitored to ensure that the casing sinks vertically to prevent deviation. After the casing is driven to the predetermined depth, the vibration is stopped and the position and verticality of the casing are checked. If necessary, adjustments are made to ensure the accuracy of the pile foundation and the safety of the structure. The vibrating pile driver is restarted to gradually pull out the casing. At this time, the active pile shoe will open and close according to the design to help separate the casing from the soil. The degree of pulling out is determined according to actual needs. Usually the casing needs to be above the ground by a certain length to facilitate subsequent construction operations.

[0030] Step S2: Place the drill and slow winch, insert the jet pipe into the hole through the drill disc; select a suitable drill and winch, the drill should have enough torque and power to handle the predetermined depth and soil type; the winch should be able to control the speed of the jet pipe in and out. When installing the drill and winch, it is necessary to ensure that the equipment is stable and safe, the operating platform is level, and it is correctly positioned according to the instructions of the construction drawings. The jet pipe is a long pipe with a nozzle for spraying cement slurry or other reinforcement materials. According to the project requirements, select the appropriate pipe and nozzle and check whether the jet pipe is intact, ensure that the nozzle is not blocked, use the winch to slowly lower the jet pipe to the predetermined hole position, and control the lowering speed through the winch to ensure the stability of the operation. After the jet pipe reaches the specified depth, start spraying cement slurry or other stabilized materials through the pipeline. The flow rate and pressure of the material should be adjusted according to the soil conditions and design requirements. As the material is sprayed, slowly pull the jet pipe to ensure that the reinforcement material is evenly distributed and form a jet pile of the required diameter. During the whole process, the position, depth and injection parameters of the jetting pipe are continuously monitored, and the verticality and position of the jetting pipe are monitored using ground instruments such as total stations; the settings of the drill rig and winch are adjusted according to the monitoring results to ensure that the construction quality meets the design specifications. The drill rig disc plays the role of rotating the jetting pipe, making it rotate in the soil to better penetrate the soil layer and mix the soil and reinforcement materials. When the jetting pile reaches the designed depth and the jetting is completed, the jetting pipe is thoroughly cleaned and the equipment is checked to prepare for the construction of the next jetting point.

[0031] Step S3: Connect the high-pressure pipe and cement slurry pipe, start the high-pressure pump, mud pump and rotary drill for rotary spraying, and control the pressure, flow and air volume at the same time; ensure that all pipelines are clean and undamaged, use suitable joints and fasteners to connect the high-pressure pipe to the high-pressure pump, and the cement slurry pipe to the mud pump. Before starting the pump, perform a preliminary inspection to confirm that all safety measures are in place, check the oil level of the pump and whether there are any obstructions in the pipeline; before starting the pump, ensure that all operators stay away from dangerous parts of the machine, first start the mud pump to start the cement slurry flowing, then start the high-pressure pump, start injecting high-pressure air or water into the rotary spray pipe, start the rotary drill, and ensure that the drill and winch work synchronously to control the lowering speed and rotation speed of the rotary spray pipe. During the entire rotary spraying process, the dashboard in the control room is monitored and Adjust the flow rate, pressure and air volume of the cement slurry and high-pressure air. The control of pressure and flow rate is crucial to ensure that the material can be evenly mixed with the soil while avoiding blockage of the pipe or nozzle. The control of air volume affects the dilution and spread range of the material. Appropriate air volume can help the material penetrate the soil better and form a more uniform and stable jet grouting pile. Use flow meters and pressure gauges to monitor the pressure and flow of cement slurry and high-pressure air in real time, adjust parameters according to geological conditions and construction requirements, observe the formation of jet grouting piles, and adjust the pulling speed and rotation speed of the jet grouting pipe when necessary to ensure construction quality. After the jet grouting pile construction reaches the predetermined depth and completes the injection of the material, stop the pump and rotary drill, slowly lift the jet grouting pipe, and thoroughly clean the pump and pipe after the construction is completed to prevent the hardened cement slurry from clogging the equipment.

[0032] Step S4: After reaching the predetermined parameters, the rotary jet pipe is lifted until the rotary jet height is reached; after the rotary jet reaches the predetermined depth, the winch or other lifting equipment is operated to slowly lift the rotary jet pipe, ensuring that the lifting equipment runs smoothly and avoiding any sudden pulling or pause. The control of the lifting speed is crucial. Too fast speed will lead to insufficient mixing of cement slurry and soil, while too slow speed will lead to excessive dilution or uneven distribution of cement slurry. Generally, the lifting speed should be set according to the construction specifications and geological conditions. The common speed range is 20 to 30 cm per minute, but it should be adjusted according to the specific situation; in the process of lifting the rotary jet pipe, continue to monitor the flow rate and pressure of the cement slurry to ensure that they remain within the set range, and adjust the output of the pump when necessary to maintain stable pressure and flow. The rotation speed should also be adjusted during the lifting process to adapt to different soil layers and construction depths. A higher rotation speed helps to improve the mixing effect of cement slurry and soil.

[0033] Step S5: Pull out the jet pipe and casing, and flush the pipeline with clean water; before starting to pull out the pipe, ensure that all grouting operations have been completely stopped and the pressure has been completely released, use the lifting equipment to slowly pull the jet pipe and casing out of the ground, and continue to observe the reaction of the surrounding soil and the condition of the jet pipe during the pipe pulling process, so as to promptly discover and solve any possible problems. After the pipe pulling is completed, immediately use clean water to clean the jet pipe and casing to remove the residual cement slurry inside and outside the pipeline to prevent hardening. Use a high-pressure water pump to transport a large amount of clean water through the jet pipe and casing to thoroughly flush the pipeline, ensuring that the water flow is sufficient to completely flush away the residual cement slurry in the pipe; continue flushing until the discharged water becomes clear. After flushing, perform visual inspections and necessary functional tests to ensure that there is no blockage in the pipeline; compressed air can also be used to assist in cleaning, especially for longer or narrower pipelines. After cleaning, perform necessary maintenance and inspection on the lifting and pipe pulling equipment to ensure that the equipment is in good condition when used next time. After completing the cleaning and maintenance work, record all relevant information in detail.

[0034] The depth of the vibrating pile driver when driving into the casing is greater than the height of the planned jet grouting. Before the jet grouting process begins, the instrument is used to accurately control the grouting pressure to be no less than 25 MPa, the water-cement ratio of the cement slurry is between 0.9 and 1.1, the jet grouting tube lifting speed is 20 cm / min, and the grouting tube is cleaned with clean water during the extraction process. Before the construction process begins, the site is leveled, and the grouting ditch and drilling rig positioning are set to ensure that the drilling rig remains horizontal and the drill rod is vertical, with an inclination of no more than 1%. During the construction process, monitor nearby structures or buildings, and suspend construction when the elevation change of nearby structures or buildings is greater than 10 mm.

[0035] Although the embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that various changes, modifications, substitutions and variations may be made to the embodiments without departing from the principles and spirit of the present invention, and that the scope of the present invention is defined by the claims and their equivalents.

Claims

1. A method for constructing a high-pressure jet spray column trench in the process of underground drainage network management, characterized in that: The following steps are involved: Step S1: using a vibrating pile driver to drive a casing with a movable pile shoe into the soil, and pulling out a portion of it to make it higher than the ground; Step S2: placing a drilling rig and a slow winch, and inserting the rotary nozzle into the hole through the drilling rig disc; Step S3: Connect the high-pressure pipe and the cement slurry pipe, start the high-pressure pump, the mud pump and the rotary drill to perform rotary grouting, and control the pressure, flow rate and air volume at the same time; Step S4: after reaching the predetermined parameters, the rotary spraying pipe begins to be lifted until the rotary spraying height is reached; Step S5: Pull out the rotary spray pipe and sleeve, and flush the pipeline with clean water.

2. The method for constructing a high-pressure jet spray column trench in the process of underground drainage pipe network management according to claim 1, characterized in that: The depth of the vibrating pile driver when driving into the casing is greater than the height of the quasi-rotational grouting.

3. The method for constructing a high-pressure jet spray column trench in the process of underground drainage pipe network management according to claim 2, characterized in that: Before the jet grouting process begins, an instrument is used to accurately control the grouting pressure to no less than 25 MPa.

4. The method for constructing a high-pressure jet spray column trench in the process of underground drainage pipe network management according to claim 3, characterized in that: The water-cement ratio of the cement slurry is between 0.9 and 1.

1.

5. The method for constructing a high-pressure jet spray column trench in the process of underground drainage pipe network management according to claim 4, characterized in that: The lifting speed of the rotary spray pipe is 20cm / min.

6. The method for constructing a high-pressure jet spray column trench in the process of underground drainage pipe network management according to claim 5, characterized in that: The step of cleaning the grouting pipe during the pulling out process uses clean water.

7. The method for constructing a high-pressure jet spray column trench in the process of underground drainage pipe network management according to claim 6, characterized in that: Before the construction process begins, the site is leveled, and slurry drainage ditches and drilling rig positioning are set up to ensure that the drilling rig remains horizontal and the drill rod is vertical, with an inclination of no more than 1%.

8. The method for constructing a high-pressure jet spray column trench in the process of underground drainage pipe network management according to claim 7, characterized in that: During the construction process, nearby structures or buildings are monitored, and construction is suspended when the elevation change of the nearby structures or buildings is greater than 10 mm.