Node structure of comprehensive pipe gallery
By designing the prefabricated comprehensive pipeline node structure, including work wells, wellbores and water collection pits, the problems of low construction efficiency and drainage are solved, and rapid construction and safe comprehensive pipeline construction are achieved.
Patent Information
- Application Number
- CN202411209678.0
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Priority Date
- 2024-06-27
- Filing Date
- 2024-08-30
- Publication Date
- 2024-11-22
- Estimated Expiration
- Not applicable · inactive patent
AI Technical Summary
In the construction of comprehensive pipeline corridors, the existing technology is difficult to effectively solve the problems of low construction efficiency and drainage in node areas, resulting in extended construction period, low quality and safety hazards.
A prefabricated integrated pipeline node structure is designed, including a working well, a wellbore and a water collection pit. The working well can be detached and connected. The wellbore is a hollow structure. The water collection pit can be fixed or detachable and connected, and is set in the standard section. The room is used to collect accumulated water and facilitate maintenance.
It realizes rapid prefabricated assembly of node structures, saves construction time, ensures the normal operation of the drainage system, reduces safety hazards, and improves construction efficiency and quality.
Smart Images

Figure CN118997218A_ABST
Abstract
Description
Technical Field
[0001] The present application relates to the field of integrated pipe corridor construction, and specifically to a node structure of an integrated pipe corridor. Background Art
[0002] A comprehensive pipeline corridor is a tunnel space underground in the city, which integrates various engineering pipelines such as electricity, communications, gas, heating, water supply and drainage, and is equipped with special inspection openings, lifting openings and monitoring systems. It is an important infrastructure and "lifeline" to ensure the operation of the city.
[0003] The prefabrication and assembly technology of the integrated pipe corridor refers to a fast and green construction technology that prefabricates the main structure of the integrated pipe corridor in blocks or segments in the factory under construction conditions such as open excavation, dark excavation or cover excavation, and then transports it to the site for assembly. The advantages of the prefabrication and assembly technology of the integrated pipe corridor are that it can greatly improve construction efficiency, shorten construction period, reduce the impact of construction on the environment, and improve construction quality. In addition, this technology also helps to achieve the standardization and modularization of the integrated pipe corridor, reduce construction costs, and promote the promotion and application of prefabrication and assembly technology. Usually, prefabrication and assembly technology is only used for prefabrication of standard sections, and cast-in-place is required in the node area. For small integrated pipe corridors, on the one hand, they are usually located in areas with relatively dense land services. Only prefabrication of standard sections and cast-in-place nodes have limited effects on reducing construction period and improving construction quality; on the other hand, the integrated pipe corridor also needs to consider drainage issues to avoid water accumulation causing failures of the integrated pipe corridor or safety hazards. Usually, the drainage of the integrated pipe corridor is set in the standard section area, which is not convenient for maintenance and cleaning.
[0004] Therefore, it is necessary to provide a prefabricated node structure with a drainage structure for the field of comprehensive pipeline corridor construction. Summary of the invention
[0005] In view of this, the present application proposes a node structure of an integrated pipeline corridor, which is a prefabricated structure. The node structure of the integrated pipeline corridor includes: a working well: the working well is integrated and arranged between the standard sections of two sections of the integrated pipeline corridor; a wellbore: arranged at the top of the working well, coordinated with the working well, and used for personnel maintenance; a sump: arranged at the bottom of the working well.
[0006] Specifically, the top and bottom of the working well are respectively provided with openings for communicating with the wellbore and the sump, and the wellbore is detachably connected to the working well.
[0007] Specifically, the shaft is a hollow structure with upper and lower openings, and the bottom opening of the shaft is communicated with the top opening of the working well.
[0008] Specifically, the top opening of the working well is a concave opening, the inner diameter of the concave opening is the same as the outer diameter of the wellbore, and is used to place the wellbore. The concave opening is provided with a hole with the same inner diameter as the wellbore.
[0009] Specifically, the wellbore extends longitudinally to the ground, and the top opening of the wellbore is connected to the outside.
[0010] Specifically, the sump is fixedly connected to the working well, the top of the sump is flush with the bottom of the working well, and the bottom of the sump is lower than the bottom of the working well; or the sump is detachably connected to the working well, the top of the sump is flush with the bottom of the working well, and the bottom of the sump is lower than the bottom of the working well.
[0011] Specifically, the sump is a concave structure with at least an opening on the top surface, and is used to collect the accumulated water in the working well.
[0012] Specifically, the working shaft has at least two openings in the horizontal direction for connecting with the standard section of the integrated pipeline corridor.
[0013] Specifically, the top of the working pit is provided with lifting points for lifting, and the number of the lifting points is at least 4, preferably 6.
[0014] Specifically, an outward expansion section is arranged in the horizontal direction of the working well to provide space for pipelines.
[0015] The node structure of the integrated pipeline corridor proposed in this application is a prefabricated structure. During the construction of the integrated pipeline corridor, the node structure can be directly connected to the two standard sections, saving construction time and improving construction efficiency. In addition, a sump is set at the bottom of the node structure to collect accumulated water or seepage in the integrated pipeline corridor in time, and it is also convenient for personnel to inspect and deal with dirt in the sump, avoid blockage, and ensure the normal operation of the sump, thereby ensuring the normal use and safety of the integrated pipeline corridor.
[0016] Other features and advantages of the present application will be described in detail in the subsequent detailed description. BRIEF DESCRIPTION OF THE DRAWINGS
[0017] The accompanying drawings constituting a part of the present application are used to provide a further understanding of the present application, and the schematic implementation modes and descriptions of the present application are used to explain the present application. In the accompanying drawings:
[0018] Figure 1 It is a schematic diagram of the front view and section of the node structure of the integrated pipeline corridor according to the preferred embodiment of the present application.
[0019] Figure 2 It is a schematic diagram of a top view of the node structure of an integrated pipeline corridor according to a preferred embodiment of the present application.
[0020] Figure 3 It is a schematic diagram of the side section of the node structure of the integrated pipeline corridor according to the preferred embodiment of the present application.
[0021] Figure 4 This is a schematic diagram of the hanging point of the preferred embodiment of the present application.
[0022] Figure 5 This is a schematic diagram of the tongue-and-groove connection of the preferred embodiment of the present application.
[0023] Explanation of the numbers in the attached drawings: 1-working well; 2-standard section; 3-wellbore; 4-sump; 5-concave opening; 6-hanging point; 7-extension section; 8-ladder; 9-well cover; 10-sleeve bolt; 11-sealing and waterproofing part; 12-ground; 13-sump cover; 14-water stop. DETAILED DESCRIPTION
[0024] The technical solution of the present application will be described in detail below with reference to the accompanying drawings and in combination with the implementation modes.
[0025] During the construction of urban integrated pipeline corridors, it is usually necessary to cast the node structure on site, which results in a long construction period and seriously affects the construction efficiency. In addition, integrated pipeline corridors are usually located underground, and water generated by underground humidity or damage to water supply and drainage pipelines may cause water accumulation inside the integrated pipeline corridor, which may affect the failure of the integrated pipeline corridor or pose a safety hazard. Integrated pipeline corridors are usually located between standard sections, which makes maintenance difficult.
[0026] Therefore, if Figure 1 As shown, the present application proposes a node structure of an integrated pipe corridor, and the node structure of the integrated pipe corridor is a prefabricated structure, and the node structure of the integrated pipe corridor includes: a working shaft 1: the working shaft 1 is an integrated rectangular structure, which is arranged between two standard sections 2 of the integrated pipe corridor; a shaft 3: arranged at the top of the working shaft 1, and cooperates with the working shaft 1 for personnel maintenance; a sump 4: arranged at the bottom of the working shaft 1.
[0027] The above-mentioned working well 1 is arranged in an integrated manner, so that it is avoided that the upper opening needs to be covered and sealed after the working well 1 is installed, and it is also avoided that water seeps into the working well 1 from this opening after the construction is completed.
[0028] The working well 1 of the node structure of the integrated pipe gallery proposed in this application is an integrated type, and during construction, it can be directly placed between the standard sections 2, saving on-site construction time. In addition, a sump 4 is set at the bottom of the node structure, which can facilitate maintenance personnel to inspect and handle dirt in the sump 4 to avoid blockage, and can also promptly discover problems with the sump 4 and solve them in a timely manner, thereby ensuring the normal and safe use of the integrated pipe gallery and reducing safety hazards.
[0029] In order to inspect the working well 1 and collect water leakage or seepage in the working well 1 and the integrated pipe gallery, specifically, the top and bottom of the working well 1 can be respectively provided with openings for connecting with the wellbore 3 and the sump 4. The wellbore 3 and the working well 1 can be connected in an appropriate manner, for example, they can be fixedly connected. Preferably, the wellbore 3 and the working well 1 are detachably connected. The wellbore 3 and the working well 1 are separately arranged and detachably connected. On the one hand, it is convenient for the prefabrication of the working well 1 and improves the prefabrication efficiency of the working well 1. On the other hand, it is also convenient for transportation.
[0030] In order to inspect the working well 1, specifically, the wellbore 3 can be a hollow structure with upper and lower openings, and the bottom opening of the wellbore 3 is connected to the top opening of the working well 1. Specifically, the top opening of the working well 1 is a concave opening 5, and the inner diameter of the concave opening 5 is the same as the outer diameter of the wellbore 3, which is used to place the wellbore 3. The concave opening 5 is provided with a hole with the same inner diameter as the wellbore 3. After the wellbore 3 is prefabricated, it can be directly placed at the concave opening 5. In order to prevent the upper water from entering the working well 1 from the gap between the concave opening 5 and the wellbore 3, a water stop 14 is also provided at the connection between the concave opening 5 and the wellbore 3. The above-mentioned water stop 14 can be made of appropriate materials, such as rubber. The rubber material can have a good water stop effect, can be in close contact with the contact surface, and play a good waterproof effect; the above-mentioned water stop 14 can be in an appropriate form, such as a rubber water stop strip, preferably a water-swelling water stop strip, which can be easily installed during use to improve work efficiency. The shaft 3 and the concave opening 5 can be circular or square. A continuous ladder 8 is arranged on the inner wall of the shaft 3 and the working shaft 1 to facilitate maintenance personnel to enter and exit the working shaft 1. The ladder 8 is a 90° steel ladder, which can save space in the working shaft 1 and has a certain load-bearing capacity to prevent safety accidents caused by insufficient load-bearing capacity of the ladder 8.
[0031] In order to facilitate maintenance personnel to quickly find the top opening of the well shaft 3 and inspect the working well 1, specifically, the well shaft 3 can extend longitudinally to the ground 12, and the top opening of the well shaft 3 is connected to the outside world. A manhole cover 9 is provided on the top opening of the well shaft 3 to prevent people, animals or debris from falling into the working well 1.
[0032] like Figure 1 and Figure 3As shown, in order to facilitate personnel to inspect the sump 4, specifically, the sump 4 can be fixedly connected to the working well 1, the top of the sump 4 can be flush with the bottom of the working well 1, and the bottom of the sump 4 can be lower than the bottom of the working well 1; or the sump 4 can be detachably connected to the working well 1, the top of the sump 4 can be flush with the bottom of the working well 1, and the bottom of the sump 4 can be lower than the bottom of the working well 1. In the present application, the sump 4 is detachably connected to the working well 1 by a sleeve bolt 10. In order to better fix the sump 4, 2 D20 sleeve bolts are set in each of the 4 directions, and a sealing waterproof part 11 is pre-embedded at the connection to prevent water from passing through the gap into the sump 4 or water in the sump 4 from flowing out. The sealing waterproof part 11 can be made of an appropriate material, such as silicone and PVC, preferably rubber. The sealing waterproof part 11 made of rubber has a stronger deformation ability and a better waterproof effect. The above-mentioned sump adopts a detachable connection method, which can facilitate the prefabrication of the sump 4 and the working well 1 on the one hand, and facilitate transportation on the other hand, avoiding damage to the sump 4 structure during transportation, causing the entire working well 1 to be damaged and unusable.
[0033] In order to collect the accumulated water from the integrated pipe gallery, specifically, the sump 4 can be a concave structure with at least an opening on the top surface, which is used to collect the accumulated water in the working shaft 1. The side of the sump 4 can also be provided with an opening, which is connected to the sewer through a pipe to discharge the accumulated water in the sump 4 in time. The sump 4 and the opening of the shaft 3 can be set to be aligned up and down. In the present application, the sump 4 and the shaft 3 opening can be staggered to prevent debris from falling into the sump 4 when the manhole cover 9 is opened. When personnel need to enter the bottom of the working shaft 1, the staggered setting is safer. In order to further prevent debris from entering the interior of the sump 4, a sump cover 12 is provided on the top of the sump. The sump cover 12 can be made of a suitable material that can achieve a water leakage function, such as a galvanized steel grating. The galvanized steel grating has a strong load-bearing capacity, is easy to install, has good corrosion resistance, and can be in a humid environment for a long time.
[0034] In order to connect the working well 1 with the standard section 2, specifically, the working well 1 has at least two openings in the horizontal direction for connecting with the standard section 2 of the integrated pipe gallery. The positions and numbers of the openings of the working well 1 and the standard section 2 can be set according to actual construction needs. The bottom of the working well 1 is flush with the bottom of the standard section 2.
[0035] In order to quickly install the working well 1, the cross section of the working well 1 is the same as the cross section of the standard section 2, and can be quickly installed on site. The interface between the working well 1 and the cross section of the standard brick section can be in an appropriate form, such as a bottle mouth, a socket joint, preferably a tongue-and-groove, and the outer side of the tongue-and-groove is smooth. The connection between the working well 1 and the standard section 2 can achieve uniform settlement, avoiding the situation where the height of the working well 1 and the standard section 2 is inconsistent due to uneven settlement. Figure 5 As shown, in order to ensure the waterproof performance of the interface between the standard section 2 and the working well 1, an elastic sealing pad 11 is used at the level of the tongue-and-groove connection. The material of the elastic sealing pad 11 can be a suitable material, such as rubber. Sealant is used at the longitudinal connection of the tongue-and-groove connection to prevent water from entering through the tongue-and-groove connection. In order to better fix the standard section 2 and the working well 1, a grouting pipe that runs through the upper and lower parts can also be provided at the level of the tongue-and-groove connection of the standard section 2. Grouting material is poured into the tongue-and-groove connection through the grouting pipe to increase the strength and sealing of the tongue-and-groove connection. The grouting material can be a cement-based grouting material or an epoxy resin grouting material, and the grouting pipe can be a steel pipe.
[0036] like Figure 1-Figure 3 As shown, in order to transport or place the working well 1 at a location where it needs to be installed, specifically, the top of the working well 1 can be provided with a lifting point 6 for lifting, and the number of the lifting points 6 is at least 4, preferably 6. Figure 4 As shown, the lifting point can be a round steel lifting ring, which is integrally tied to the steel cage of the working shaft 1 during prefabrication. After the working shaft 1 is prefabricated, it is heavy and cannot be transported or moved manually, and requires the aid of machinery. In order to reduce the weight of each lifting point 6, the number of the lifting points 6 can be set to 6, which are symmetrically arranged at both ends and the middle of the working shaft 1.
[0037] like Figure 1 and Figure 2 As shown, in order to meet the needs of pipeline conversion and maintenance space, specifically, the working shaft 1 is provided with an expansion section 7 in the horizontal direction to provide space for the turning of the pipeline. A raised section is also provided on the top of the working shaft 1 to provide conversion space and maintenance space for the pipeline.
[0038] The node structure of the integrated pipeline corridor proposed in this application is a prefabricated structure. During the construction of the integrated pipeline corridor, the node structure can be directly connected to the two standard sections, saving construction time and improving construction efficiency. In addition, a sump is set at the bottom of the node structure to collect accumulated water or seepage in the integrated pipeline corridor in time, and it is also convenient for personnel to inspect and deal with dirt in the sump, avoid blockage, and ensure the normal operation of the sump, thereby ensuring the normal use and safety of the integrated pipeline corridor.
[0039] The preferred embodiments of the present application are described in detail above; however, the present application is not limited to the specific details in the above embodiments. Within the technical concept of the present application, a variety of simple modifications can be made to the technical solution of the present application, and these simple modifications all fall within the protection scope of the present application.
[0040] It should also be noted that the various specific technical features described in the above specific embodiments can be combined in any suitable manner without contradiction. In order to avoid unnecessary repetition, this application will not further describe various possible combinations.
[0041] In addition, the various implementation modes of the present application may be arbitrarily combined, and as long as they do not violate the concept of the present application, they should also be regarded as the contents disclosed by the present invention.
Claims
1. The node structure of the integrated pipe gallery is characterized by: The node structure of the integrated pipe gallery is a prefabricated structure, and the node structure of the integrated pipe gallery includes: Working well (1): the working well (1) is an integrated type and is arranged between the standard sections (2) of two sections of the integrated pipe gallery; Shaft (3): arranged at the top of the working shaft (1), coordinated with the working shaft (1) for personnel maintenance; Sump (4): arranged at the bottom of the working well (1).
2. The node structure of the integrated pipe gallery according to claim 1 is characterized in that: The top and bottom of the working well (1) are respectively provided with openings for communicating with the wellbore (3) and the sump (4); the wellbore (3) and the working well (1) are detachably connected.
3. The node structure of the integrated pipe gallery according to claim 1 or 2, characterized in that: The shaft (3) is a hollow structure with upper and lower openings, and the bottom opening of the shaft (3) is in communication with the top opening of the working shaft (1).
4. The node structure of the integrated pipe gallery according to claim 2 is characterized in that: The top opening of the working well (1) is a concave opening (5), the inner diameter of the concave opening (5) is the same as the outer diameter of the wellbore (3), and is used to place the wellbore (3). The concave opening (5) is provided with a hole with the same inner diameter as the wellbore (3).
5. The node structure of the integrated pipe gallery according to claim 3 is characterized in that: The shaft (3) extends longitudinally to the ground, and the top opening of the shaft (3) is in communication with the outside.
6. The node structure of the integrated pipe gallery according to claim 1 or 2, characterized in that: The sump (4) is fixedly connected to the working well (1), the top of the sump (4) is flush with the bottom of the working well (1), and the bottom of the sump (4) is lower than the bottom of the working well (1); or The sump (4) is detachably connected to the working well (1); the top of the sump (4) is flush with the bottom of the working well (1); and the bottom of the sump (4) is lower than the bottom of the working well (1).
7. The node structure of the integrated pipe gallery according to claim 6 is characterized in that: The water collection pit (4) is a concave structure with at least an opening on the top surface, and is used to collect the accumulated water in the working well (1).
8. The node structure of the integrated pipe gallery according to any one of claim 1, characterized in that: The working shaft (1) has at least two openings in the horizontal direction, which are used to communicate with the standard section (2) of the integrated pipe gallery.
9. The node structure of the integrated pipe gallery according to claim 1 is characterized in that: The top of the working shaft (1) is provided with lifting points (6) for lifting, and the number of the lifting points is at least 4, preferably 6.
10. The node structure of the integrated pipe gallery according to claim 1, characterized in that: The working well (1) is provided with an outward expansion section (7) in the horizontal direction, which is used to provide space for pipelines.
Citation Information
Patent Citations
Prefabricated combined joint suitable for rapid construction of small comprehensive pipe gallery
CN115748809A
Supporting prefabricated type reinforced concrete sump pit of benzvalene form interface of utility tunnel
CN208121807U
Cited By
Municipal pipeline integrated structure for narrow street of historical and cultural block
CN120867336A