Flood drainage structure for underneath pass of immovable cultural relics

By adopting underground drainage channels and non-excavation methods to penetrate immovable cultural relics under the coastal plains, the damage to cultural relics and land occupation by drainage projects is solved, efficient drainage and cultural relics protection is achieved, and the difficulty of disposal of abandoned soil is reduced and the project is reduced. invest.

CN118997294APending Publication Date: 2024-11-22ZHEJIANG DESIGN INST OF WATER CONSERVANCY & HYDROELECTRIC POWER
View PDF 0 Cites 1 Cited by

Patent Information

Application Number
CN202411348839.4
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-09-26
Publication Date
2024-11-22

AI Technical Summary

Technical Problem

In drainage projects in coastal plains, it is difficult to damage cultural relics, land occupation and policy handling when crossing immovable cultural relics, and the problems of abandoned soil disposal caused by open digging of rivers are complex, affecting the protection of environmental and historical cultural relics.

Method used

The underground drainage channel is designed to penetrate the immovable cultural relics through non-excavation methods such as shield structure, top pipe or shallow burial and hidden excavation to reduce the impact on cultural relics. It is designed through the outlet pressure box culvert, open water inlet and water outlet. Water pump stations and diversion piers achieve drainage, reducing the difficulty of land occupation and disposal of abandoned soil.

Benefits of technology

It effectively reduces the impact on immovable cultural relics, reduces the difficulty of land occupation and policy processing, reduces the amount of soil abandoned, controls project investment, and improves drainage efficiency and environmental protection effect.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118997294A_ABST
    Figure CN118997294A_ABST
Patent Text Reader

Abstract

According to the flood drainage structure, an underground flood drainage channel is adopted for underneath penetrating the immovable cultural relics, and a flood drainage pump station, a water outlet pressure box culvert, an open type water inlet, the underground flood drainage channel and a water outlet are sequentially arranged in the flood drainage water flow direction; the upstream of the pump station is connected with the built river channel, and the downstream is connected into the open water inlet through the water outlet pressure box culvert. The open type water inlet is reconstructed from an underground drainage channel construction vertical shaft and also serves as a system surge shaft. The top elevation of the underground drainage channel needs to be lower than the lowest elevation of cultural relics. The water outlet is provided with a drainage check gate capable of being remotely and automatically controlled, and a submersible sewage pump is arranged for discharging silt and emptying a flood drainage channel for overhauling. The drainage channel is located underground and has no influence on cultural relics; the floor area is small, and the influence on traffic, electric power and other infrastructures along the line is small; compared with a conventional open-cut river channel, the pressure drainage section is small in section, little in spoil and low in spoil disposal difficulty; and non-excavation equipment in the existing traffic field is utilized, so that the investment is controllable.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to a waterlogging drainage structure in a water conservancy project, in particular to a waterlogging drainage structure passing under immovable cultural relics. Background Art

[0002] Economically developed coastal plains often suffer from floods due to their low terrain and poor drainage. The rapid expansion of cities has led to a reduction in the area of ​​regulated waters and farmland, further increasing the pressure of drainage. The path for flood water to be discharged into the sea is long, and due to the support of the offshore tide, the self-drainage potential of flood water is insufficient, so new forced drainage pumping stations and supporting drainage channels are needed.

[0003] In order to prevent the invasion of storm surges, seawalls were artificially built in coastal areas in history. In recent years, many ancient seawalls have been identified as immovable cultural relics, and drainage channels must pass through seawalls to discharge water into the sea, which puts forward requirements for the crossing method.

[0004] Flood control and drainage projects in coastal plain areas usually adopt the scheme of "open excavation of river channels + breaking the seawall at the end to build a new forced drainage pump station". The pump station is connected to the seawall using a connecting wall to form a closed flood control system. Such schemes often involve farmland, residential buildings, cultural relics, factories, and infrastructure such as transportation, electricity, and communications. The amount of land and various types of demolitions involved is large, the cost is high, the disposal of cultural relics is difficult, and the open excavation of river channels will produce a large amount of abandoned soil, which has a great impact on the environment.

[0005] The scheme of "open-cut river channel + terminal forced drainage pump station + siphon water outlet channel across the seawall" adopted to reduce damage to immovable cultural relics has major defects in vibration impact on immovable cultural relics, land occupation, policy handling, and waste soil disposal. Against the backdrop of strengthening the protection of historical relics and strictly protecting cultivated land, the disadvantages of this scheme are further highlighted. Summary of the invention

[0006] The purpose of the present invention is to overcome the impact of drainage projects on immovable cultural relics when they pass through them, while reducing land occupation and lowering the difficulty of policy processing, waste soil disposal, etc.

[0007] The technical solution adopted by the present invention is:

[0008] A drainage structure that passes under immovable cultural relics, which adopts an underground drainage channel to pass under the immovable cultural relics, and a drainage pump station, a water outlet pressure box culvert, an open water inlet, an underground drainage channel, and a water outlet are arranged in sequence along the flow direction of the drainage water; the drainage pump station is connected to an existing river channel upstream, and is connected to the open water inlet downstream through the water outlet pressure box culvert; the water outlet pressure box culvert connects the drainage pump station and the open water inlet to play a diversion role, and is provided with a diversion pier inside; the underground drainage channel is constructed by non-excavation methods such as shield, jacking pipe or shallow buried excavation; the open water inlet is located at the head end of the underground drainage channel; the water outlet is located at the end of the underground drainage channel, on the outer sea side that receives the flood water.

[0009] Furthermore, the drainage pump station is provided with an inlet pool, an inlet section, a pump room section, and an outlet section in sequence along the water flow direction. The inlet section is provided with a maintenance gate, and the outlet section is provided with a fast working gate and a fast emergency gate, and the fast emergency gate is provided downstream of the fast working gate. The pump head is determined based on the water level of the built river channel and the water level of the outlet, taking into account the head loss of the drainage channel; the pump type and number are determined based on factors such as drainage flow, head and head amplitude, operation and scheduling requirements, installation and maintenance, investment and land occupation.

[0010] Furthermore, in order to save land, the top covering soil is restored to its original state after the construction of the water outlet pressure box culvert is completed.

[0011] Furthermore, during the construction period, the open water inlet is a construction shaft for non-excavation equipment such as shield machines and pipe jacking machines, and serves as a starting well and a channel for slag discharge, ventilation, and drainage during the construction of the underground drainage channel. After the construction of the underground drainage channel is completed, the top of the open water inlet is raised to serve as the water inlet of the underground drainage channel, and also as a system pressure regulating well to cope with the system hydraulic agitation when the pump is started or stopped.

[0012] Furthermore, the size of the underground drainage channel is determined by comprehensively considering the non-scouring and non-silting flow rate, project investment and operating energy consumption, and the size of existing non-excavation equipment. The underground drainage channel is sloped toward the downstream side to facilitate the displacement and exhaust of suspended matter in the water body to the outlet side after sedimentation. In order to avoid construction disturbance of immovable cultural relics, the top elevation of the underground drainage channel must be lower than the lowest elevation of the immovable cultural relics, including the lowest elevation of the cultural relics foundation, anti-scouring structure, etc.

[0013] Furthermore, the water outlet is used as a receiving well for non-excavation equipment such as shield machines, pipe jacking machines, etc. during the construction period, and is transformed into a water outlet after the construction of the underground drainage channel is completed.

[0014] Furthermore, the offshore distance of the outlet should be such that the outlet scouring pit is outside the existing seawall protection range to prevent outlet scouring from affecting seawall safety.

[0015] Furthermore, the water outlet is provided with a drainage regulating gate which can be remotely and automatically controlled, and a maintenance gate slot is provided on the outside of the regulating gate. When the regulating gate and its opening and closing equipment need to be repaired, the maintenance gate is hoisted into the opening by a ship crane to block water.

[0016] Furthermore, arc-shaped guide piers are arranged on both sides of the water outlet to guide the open sea water; an equipment access hole is arranged above the arc-shaped guide pier for equipment hoisting and personnel passage, and is waterproof and sealed at normal times; and an air vent is also arranged on the arc-shaped guide pier, and the elevation of the highest point of the air vent needs to be higher than the highest water level in the open sea.

[0017] Furthermore, the water outlet is provided with an operating platform, an opening and closing platform, an electrical equipment room, etc. as required. The water outlet is provided with a submersible sewage pump, which is used for two purposes, to discharge silt and empty the underground drainage channel for maintenance. The top of the water collection well where the submersible sewage pump is located is sealed with a waterproof cover plate, and a plurality of silt suction and water suction flower pipes are dispersedly arranged around it to collect muddy water. The silt discharge pipe after the submersible sewage pump is buried in the water outlet, and the outlet of the silt discharge pipe is located outside the maintenance door slot of the water outlet.

[0018] Furthermore, a sea bank is provided around the water outlet to prevent erosion.

[0019] The working principle of the present invention is: when the water level of the upstream river reaches the drainage level of the pump station, the water pump, the rapid working gate, and the drainage control gate are opened, and the pump station starts to drain; when the water level of the upstream river reaches the drainage stop level of the pump station, the water pump and the rapid working gate are closed, and the drainage control gate is closed after the hydraulic agitation of the drainage channel basically stops. In order to prevent accidents caused by the failure of the rapid working gate to close, a rapid emergency gate is set downstream of the rapid working gate. When the water pump and the water inlet and outlet flow channel of the water pump need to be repaired, the maintenance gate is closed to drain the water in the flow channel for maintenance.

[0020] When designing the underground drainage channel, the drainage flow rate has been considered to be kept between the flow rate of no flushing and no silting, and the amount of siltation in the channel can be controlled; the small amount of siltation that may exist can be discharged by turning on the submersible sewage pump. During the non-drainage period, the underground drainage channel can be emptied, and mechanical equipment can be hoisted from the open water inlet to inspect and repair the underground drainage channel.

[0021] The flow rate of a single submersible sewage pump and the number of pumps are determined by comprehensively considering the amount of siltation, the emptying time of the underground drainage channel, the outlet layout, etc.

[0022] Immovable cultural relics may be located anywhere along the underground drainage channel.

[0023] The beneficial effects of the present invention are:

[0024] 1. No impact on immovable cultural relics. During the construction period, the settlement of cultural relics can be strictly controlled through grouting, controlling soil loss rate, and adopting the mud-reduction method; there is no impact on cultural relics during the operation period.

[0025] 2. Less land is occupied. The drainage channel is mainly located underground, the permanent land acquisition area is small, the corresponding costs and policy handling difficulties are reduced, and there is basically no impact on the transportation, electricity, communication and other infrastructure along the line.

[0026] 3. Small amount of abandoned earth and low difficulty in disposal. The underground drainage channel is a pressurized drainage channel, which is pressurized by the upstream pump station to provide kinetic energy and increase the flow rate. It is different from the water flow in the conventional open-cut river channel that only consumes its own potential energy and kinetic energy. The cross-section of the underground drainage channel is smaller than that of the conventional open-cut river channel, and the corresponding amount of abandoned earth is small, and the difficulty and cost of abandoned earth disposal are low.

[0027] 4. Project investment is controllable. At present, trenchless construction methods are increasingly used in the field of urban transportation. Using existing trenchless equipment can reduce equipment amortization and effectively control project investment. BRIEF DESCRIPTION OF THE DRAWINGS

[0028] Figure 1 is a plan view of an embodiment of the present invention;

[0029] Figure 2 yes Figure 1 AA longitudinal section of

[0030] Figure 3 yes Figure 2 BB cross-section diagram;

[0031] Figure 4 1 is a plan view of a water outlet according to an embodiment of the present invention.

[0032] In the figure: 1-drainage pump station; 11-water inlet pool; 12-inlet section; 13-pump room section; 14-outlet section; 15-water pump; 16-maintenance gate; 17-fast working gate; 18-fast emergency gate; 2-outlet pressure box culvert; 21-diversion pier; 22-top cover; 3-open water inlet; 4-underground drainage channel; 41-prefabricated reinforced concrete segments; 42-bolts; 43-cast-in-place reinforced concrete lining; 5-outlet; 51-drainage control gate; 52-maintenance door slot; 53-arc diversion pier; 54-equipment manhole; 55-vent; 56-submersible sewage pump; 57-sewage suction pipe; 58-sewage drainage pipe; 59-sea floodplain; 6-built river channel; 7-immovable cultural relics. DETAILED DESCRIPTION

[0033] The present invention will be further described in detail below in conjunction with the accompanying drawings and embodiments.

[0034] like Figure 1 to Figure 4As shown, the present invention is a drainage structure for passing under an immovable cultural relic, using an underground drainage channel 4 to pass under an immovable cultural relic 7, and a drainage pump station 1, a water outlet pressure box culvert 2, an open water inlet 3, an underground drainage channel 4, and a water outlet 5 are sequentially arranged along the drainage water flow direction. The underground drainage channel 4 of this embodiment is constructed by a trenchless shield method.

[0035] The upstream of the drainage pump station 1 is connected to the built river channel 6, and the downstream is connected to the open water inlet 3 through the outlet pressure box culvert 2. The drainage pump station 1 is provided with an inlet pool 11, an inlet section 12, a pump room section 13, and an outlet section 14 in the direction of the water flow. The inlet section 12 is provided with a maintenance gate 16, and the outlet section 14 is provided with a fast working gate 17 and a fast emergency gate 18. According to the water level of the built river channel 6 and the water level of the outlet 5, the head loss of the drainage channel is considered to determine the head of the water pump 15; according to the drainage flow, head and head amplitude, operation and scheduling requirements, installation and maintenance, investment and land occupation and other factors, the pump type and number of water pumps 15 are determined.

[0036] The outlet pressure box culvert 2 connects the drainage pump station 1 and the open water inlet 3, plays a diversion role, and is internally provided with a diversion pier 21. In order to save land, after the construction of the outlet pressure box culvert 2 is completed, the top is covered with soil 22 to restore the original state.

[0037] The open water inlet 3 is located at the head end of the underground drainage channel 4. During the construction period, it is the construction shaft of the trenchless equipment shield machine, which serves as the starting well and the channel for slag discharge, ventilation and drainage of the underground drainage channel 4. After the construction of the underground drainage channel 4 is completed, the top of the open water inlet 3 is raised to serve as the water inlet of the underground drainage channel 4. It also serves as a system pressure-regulating well to cope with the system hydraulic agitation when starting and stopping the pump.

[0038] The size of the underground drainage channel 4 is determined by comprehensively considering the non-scouring and non-silting flow rate, project investment and operating energy consumption, and the size of existing non-excavation equipment. The underground drainage channel 4 is sloped toward the downstream side to facilitate the displacement and exhaust of suspended matter in the water body toward the outlet 5 after sedimentation. In order to avoid construction disturbance of the immovable cultural relics 7, the top elevation of the underground drainage channel 4 must be lower than the lowest elevation of the immovable cultural relics 7, including the lowest elevation of the cultural relics foundation, anti-scouring structure, etc.

[0039] The outlet 5 is located at the end of the underground drainage channel 4 and the outer sea side that receives the flood water. During the construction period, it serves as a receiving well for the shield machine of the trenchless equipment. After the construction of the underground drainage channel 4 is completed, it will be transformed into the outlet 5. The offshore distance of the outlet 5 should make the range of the outlet scouring pit outside the existing seawall protection range to prevent the outlet scouring from affecting the safety of the seawall. The outlet 5 is provided with a drainage control gate 51 that can be remotely and automatically controlled. A maintenance gate groove 52 is provided on the outside of the control gate. When the control gate and its opening and closing equipment need to be repaired, the maintenance gate is hoisted into the hole by a ship crane to block water. Arc-shaped diversion piers 53 are provided on both sides of the outlet 5 to guide the offshore water flow. An equipment access hole 54 is provided above the arc-shaped diversion pier 53 for equipment hoisting and personnel passage, and is usually waterproof and sealed. A vent 55 is also provided on the arc-shaped diversion pier 53, and the highest point elevation of the vent 55 must be higher than the highest water level in the open sea. An operating platform, an opening and closing platform, an electrical equipment room, etc. are provided inside the water outlet 5. A submersible sewage pump 56 is provided at the water outlet 5, which is used for two purposes, to discharge silt and empty the underground drainage channel 4 for maintenance. The top of the water collection well where the submersible sewage pump 56 is located is sealed with a waterproof cover plate, and a plurality of silt suction and water suction flower pipes 57 are dispersedly arranged around it to collect muddy water. After the submersible sewage pump 56 pumps, a silt discharge pipe 58 is buried in the water outlet 5, and the outlet of the silt discharge pipe 58 is located outside the water outlet maintenance door slot 52. A sea cover 59 is provided around the water outlet 5 for anti-scouring.

[0040] When the water level of the built river channel 6 upstream reaches the drainage level of the drainage pump station 1, the water pump 15, the fast working gate 17, and the drainage control gate 51 are opened, and the pump station starts to drain; when the water level of the built river channel 6 upstream reaches the drainage level of the drainage pump station 1, the water pump 15 and the fast working gate 17 are closed, and the drainage control gate 51 is closed after the hydraulic agitation of the drainage channel basically stops. In order to prevent accidents caused by the failure of the fast working gate 17 to close, a fast emergency gate 18 is set downstream of the fast working gate 17. When the water pump 15 and its inlet and outlet water flow channel need to be repaired, the maintenance gate 16 is closed to drain the water in the flow channel for maintenance.

[0041] When designing the underground drainage channel 4, it has been considered that the drainage flow rate is kept between the flow rate of no flushing and no silting, and the siltation in the channel is controllable; the small amount of siltation that may exist can be discharged by turning on the submersible sewage pump 56. During the non-drainage period, the underground drainage channel 4 can be emptied, and mechanical equipment can be hoisted from the open water inlet 3 to inspect and repair the underground drainage channel 4.

[0042] In this embodiment, the underground drainage channel 4 adopts a shield tunnel. The shield tunnel is assembled by prefabricated reinforced concrete segments 41, and the segments are connected by bolts 42. According to the drainage pressure, tunnel burial depth and geological conditions, the shield tunnel can choose to adopt a single-layer lining, that is, assembling prefabricated reinforced concrete segments 41 or a double-layer lining, that is, a cast-in-place reinforced concrete lining 43 is set inside the prefabricated reinforced concrete segments 41. The number of blocks of the prefabricated reinforced concrete segments 41 is determined by comprehensively considering the diameter of the shield tunnel, the construction hoisting capacity, the construction progress requirements, etc. In this embodiment, 8 blocks are used, including 1 capping block, 2 adjacent blocks and 5 standard blocks.

[0043] The single pump flow rate and number of submersible sewage pumps 56 are determined by comprehensively considering the amount of siltation, the emptying time of the underground drainage channel 4, the layout of the outlet 5, etc.

[0044] The immovable cultural relics 7 may be located at any position along the underground drainage channel 4.

[0045] The above-mentioned embodiments describe the present invention in conjunction with the accompanying drawings, but this should not be understood as limiting the scope of protection of the present invention. It should be pointed out that for ordinary technicians in this field, without departing from the concept of the present invention, the technical solutions obtained by equivalent replacement or equivalent transformation methods all belong to the scope of protection of the present invention.

Claims

1. A drainage structure passing under an immovable cultural relic, characterized in that: An underground drainage channel is used to pass under the immovable cultural relics, and a drainage pump station, a water outlet pressure box culvert, an open water inlet, an underground drainage channel and a water outlet are arranged in sequence along the flow direction of the drainage water; the drainage pump station is connected to the existing river channel upstream, and is connected to the open water inlet downstream through the water outlet pressure box culvert; the water outlet pressure box culvert connects the drainage pump station and the open water inlet to divert the flow, and is provided with a diversion pier inside; the underground drainage channel is constructed by trenchless methods such as shield, jacking pipe or shallow buried excavation; the open water inlet is located at the head end of the underground drainage channel; the water outlet is located at the end of the underground drainage channel, on the outer sea side that receives the flood water.

2. The drainage structure for passing under immovable cultural relics according to claim 1, characterized in that: The drainage pump station is provided with an inlet pool, an inlet section, a pump room section and an outlet section in sequence along the direction of water flow. The inlet section is provided with a maintenance gate, and the outlet section is provided with a fast working gate and a fast emergency gate. The fast emergency gate is provided downstream of the fast working gate.

3. The drainage structure for passing under immovable cultural relics according to claim 1, characterized in that: The top of the water outlet pressure box culvert is covered with a soil layer after the construction is completed.

4. The drainage structure for passing under immovable cultural relics according to claim 1, characterized in that: The open water inlet is a construction shaft of trenchless equipment during the construction period, serving as a starting well and a channel for slag discharge, ventilation and drainage during the construction of the underground drainage channel. After the construction of the underground drainage channel is completed, the top of the open water inlet is raised to serve as the water inlet of the underground drainage channel, and also as a system pressure regulating well.

5. The drainage structure for passing under immovable cultural relics according to claim 1, characterized in that: The underground drainage channel is sloped toward the downstream side to facilitate the displacement of suspended matter in the water body toward the outlet side and exhaust after deposition; the top elevation of the underground drainage channel is lower than the lowest elevation of the immovable cultural relics to avoid disturbance of the immovable cultural relics during construction.

6. The drainage structure for passing under immovable cultural relics according to claim 1, characterized in that: The water outlet is used as a receiving well for trenchless equipment during the construction period, and is transformed into a water outlet after the construction of the underground drainage channel is completed.

7. The drainage structure for passing under immovable cultural relics according to claim 1, characterized in that: The offshore distance of the outlet is set so that the outlet scouring pit is outside the existing seawall protection range to prevent outlet scouring from affecting the safety of the seawall.

8. The drainage structure for passing under immovable cultural relics according to claim 1, characterized in that: The outlet is provided with a drainage control gate capable of remote automatic control, and an inspection gate slot is provided on the outer side of the control gate. When the control gate and its opening and closing equipment need to be inspected, the inspection gate is hoisted into the orifice by a ship crane to block water.

9. The drainage structure for passing under immovable cultural relics according to claim 1, characterized in that: Arc-shaped guide piers are arranged on both sides of the water outlet, an equipment access hole is arranged above the arc-shaped guide piers, and air vents are arranged on the arc-shaped guide piers, and the highest point elevation of the air vents is higher than the highest water level in the open sea.

10. The drainage structure for passing under immovable cultural relics according to claim 8, characterized in that: An operating platform, an opening and closing platform, and an electrical equipment room are arranged inside the water outlet; a submersible sewage pump is provided at the water outlet for draining silt and emptying the underground drainage channel for maintenance; the top of the water collection well where the submersible sewage pump is located is sealed with a waterproof cover plate, and a plurality of silt and water suction flower pipes are dispersedly arranged around it for collecting muddy water, and a silt discharge pipe after the submersible sewage pump is buried in the water outlet, and the outlet of the silt discharge pipe is located outside the maintenance door groove of the water outlet.

Citation Information

Cited By

  • Urban deep-tunnel arrangement structure capable of forward drainage and reverse water replenishment, and operating method

    WO2026118988A1