Clamping system for external prestressing single-end tensioning of concrete structure
By designing a clamping system for external prestressed single-ended tensioning of concrete structures, the problems of complex operation and poor adaptability of traditional clamps are solved, and efficient and safe prestress application is achieved, suitable for high-performance concrete and complex structures.
Patent Information
- Application Number
- CN202411196025.3
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-29
- Publication Date
- 2024-11-22
AI Technical Summary
Traditional concrete prestressed fixtures are complex in operation, frequent maintenance, and poor adaptability, which are difficult to meet the engineering needs of high-performance concrete and complex structures, and may lead to concentrated stress damage.
A clamping system for external prestressed single-ended tensioning of concrete structures is designed, including anchor clamps, tension clamps and connectors. Multi-angle and graded components are achieved through anchoring load-bearing plates, tension bearing plates, suspenders and other components. Compound loading, using connectors and screws to improve the stability and flexibility of the fixture.
It improves the flexibility and safety of construction and testing, ensures the stability and controllability of prestress application, adapts to different structural needs, reduces transportation and maintenance costs, and avoids concentrated stress damage.
Smart Images

Figure CN118997496A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of external prestressing reinforcement of concrete structures, and more particularly to a clamping system for single-end tensioning of external prestressing of concrete structures. Background Art
[0002] External prestressing is one of the important branches of post-tensioned prestressed structural system. It is a kind of prestressing that arranges the prestressing lock outside the concrete section.
[0003] Prestressed concrete clamps are devices used to apply and maintain prestress in concrete members. Prestressed concrete technology is a method of introducing stress (usually tensile stress) into concrete in advance to increase its bearing capacity and durability. This technology is widely used in the construction of bridges, floors, beams, reservoirs and other structures. Prestressing can be achieved by tensioning steel bars, strands or other reinforcing materials, and prestressed concrete clamps play a key role in this process.
[0004] The main functions of the concrete prestressing clamp are:
[0005] 1. Tensioning reinforcement materials: Clamps are used to tension steel bars or strands in concrete to apply prestress. This process usually involves the use of hydraulic or mechanical devices to stretch the reinforcement material and hold it in place at the appropriate tension.
[0006] 2. Fixing and anchoring: After the reinforcement is stretched, the clamps help hold it in place, ensuring that the reinforcement maintains the required tension as the concrete hardens and forms. Anchors are an important part of this process, ensuring that the tensioning force is effectively transferred to the concrete.
[0007] 3. Adjust and control prestress: By adjusting the clamps and anchors, the amount of prestress applied to the concrete can be precisely controlled to suit different design requirements and specifications.
[0008] The type and specific design of concrete prestressing clamps may vary depending on the specific needs of the application, including the type of reinforcement material used, the amount of prestressing force, and the shape and size of the member. Proper selection and use of prestressing clamps is critical to ensuring the performance and safety of the structure.
[0009] Although traditional prestressed clamps have been widely used in the field of concrete construction, they have significant limitations in many aspects, which not only affect the performance and economy of the construction, but also may reduce the efficiency of the construction process. First, the operation process of these clamps is usually very complicated, and it is necessary to rely on experienced technicians to complete the tensioning and anchoring work, which not only increases the labor cost of the project, but also makes the construction period have to be extended. Secondly, traditional clamps are prone to wear and damage after long-term use, and require frequent maintenance and replacement of parts, which undoubtedly increases the long-term cost of the project.
[0010] In addition, the design of traditional prestressed clamps may be too limited in some cases and cannot adapt to all types of prestressed concrete structures, especially those with complex or non-standard shapes, which often require customized solutions. This not only increases costs, but may also extend the implementation time of the project. At the same time, these clamps are usually heavy and bulky, which not only increases transportation costs but also brings difficulties to on-site operations. Another key issue is stress concentration, which may cause local damage to concrete members or reinforcement materials, thereby reducing the overall performance of the structure.
[0011] As construction technology advances and design requirements change, the adaptability of traditional prestressed clamps becomes more apparent. They may not be able to meet new engineering needs, especially in projects involving high-performance concrete and complex structural designs.
[0012] Therefore, how to provide a multifunctional clamping system that can be used for single-end tensioning of external prestressed concrete structures with composite loading, which can apply prestress in a multi-level composite manner at multiple angles, with different methods and at different force application stages, and prevent imperfect stress application due to external factors during the prestressing process, is a problem that technical personnel in this field urgently need to solve. Summary of the invention
[0013] In view of this, the present invention provides a clamping system for external prestressed single-end tensioning of concrete structures, aiming to solve the above technical problems.
[0014] In order to achieve the above object, the present invention adopts the following technical solution:
[0015] A clamping system for external prestressed single-end tensioning of a concrete structure, comprising an anchoring clamp, a tensioning clamp, and a connector connecting the anchoring clamp and the tensioning clamp;
[0016] The anchoring fixture comprises an anchoring bearing plate, an anchoring cover plate and an anchoring clamping plate; the anchoring cover plate covers the top surface of the anchoring bearing plate to clamp one end of the steel fiber bundle, and the anchoring clamping plate is arranged parallel to the lower side of the anchoring bearing plate and clamped relative to one end of the structure;
[0017] The tensioning fixture comprises a tensioning bearing plate, a tensioning cover plate, a tensioning clamp and a sling, wherein the tensioning cover plate covers the top surface of the tensioning bearing plate to clamp the other end of the steel fiber bundle, and the tensioning clamp is arranged parallel to the bottom of the tensioning bearing plate and clamped relative to the other end of the structure; the sling is annular and is sleeved on the outer periphery of the tensioning fixture close to the anchoring fixture to change the inclination angle of the steel fiber bundle;
[0018] Wherein, connecting rods are fixed to both end surfaces of the anchoring bearing plate and the tensioning bearing plate that are opposite to each other, and both ends of the connector are bolted to the two connecting rods respectively.
[0019] The beneficial effect of the above technical solution is that the tensioning clamp and the anchoring clamp are respectively clamped at the two ends of the structure and connected through a connector, the steel fiber bundle is passed from the tensioning clamp to the anchoring clamp, and the steel fiber bundle is pressed against the bearing plate through the cover plate. The sling provides a clamping force at the end of the tensioning clamp to change the inclination angle of the steel fiber bundle at the other end of the tensioning clamp, and the tensioning equipment can perform composite loading on the steel fiber bundle at multiple angles and levels.
[0020] Preferably, the tensioning fixture further comprises a first pressing plate, and both ends of the top surface of the tensioning bearing plate are fixed with a restrainer for passing the steel fiber bundle, and the tensioning bearing plate is fixed with a plurality of first sawtooth blocks on the top surface of the two restrainers, and the bottom surface of the first pressing plate is provided with a first sawtooth groove adapted to the first sawtooth block, and the first pressing plate is buckled with the first sawtooth block and embedded between the tensioning cover plate and the tensioning bearing plate. The steel fiber bundle passes through the tensioning fixture from the restrainer, and the steel fiber bundle is placed between the first sawtooth block and the first sawtooth groove, and the steel fiber bundle is pressed by the first pressing plate, and the first sawtooth block is used to provide friction and restraint for the steel fiber bundle, so as to prevent the steel fiber bundle from being unable to be tightened or sliding during the tensioning process and affecting the tensioning effect.
[0021] Preferably, it also includes a support plate and a jack, a plurality of guide rails perpendicular to the panel are fixed in an array on one side of the bottom surface of the tensioning splint, the support plate is arranged parallel to the tensioning splint and slidably connected to the guide rail, the jack is supported between the support plate and the tensioning splint, the sling is connected end to end and fixed into a ring shape by a fixing member, and the sling is sleeved on the outer periphery of the tensioning cover plate and the support plate to limit the sliding of the support plate. On the one hand, the sling can provide a pre-tightening force so that the tensioning splint abuts against the structure, which facilitates the clamping and fixing of the structure by the tensioning clamp, and on the other hand, the sling provides a clamping force. When the steel fiber bundle is fixed, the sling is tightened under the operation of the jack. After the tensioning clamp is stressed at one end, the steel fiber bundle at the other end will rise due to its own characteristics. By changing the lifting distance of the jack to adjust the tightness of the sling, the angle of the steel fiber bundle at the tensioning clamp can be changed, so as to achieve graded tensioning of the angle.
[0022] Preferably, an annular boss is fixed on the top surface of the support plate, and an annular groove is formed on the bottom surface of the tensioning clamp relative to the annular boss. The lifting end of the jack extends into the inner cavity of the annular boss and abuts against the top surface of the support plate, and the fixed end is embedded in the annular groove. The jack can be clamped between the support plate and the tensioning clamp through the annular boss and the annular groove, ensuring that the axis of the jack is always perpendicular to the tensioning clamp and the support plate, thereby preventing the tensioning clamp from becoming unstable due to the tilting force of the jack.
[0023] The bottom surface of the support plate is provided with a receiving groove along its length direction, and the tensioning cover plate is fixed with limiting rings at both ends of the top surface corresponding to the receiving groove, and the bottom end of the sling is sleeved in the receiving groove and the top end is inserted in the limiting ring to limit the displacement of the sling. The displacement of the sling is limited by the limiting ring and the receiving groove to prevent the sling from slipping off the tensioning clamp after being tightened, thereby affecting the normal tensioning operation.
[0024] Preferably, the anchoring fixture further comprises a second pressing plate, a second sawtooth block is fixed to the middle of the top surface of the anchoring bearing plate, a second sawtooth groove adapted to the second sawtooth block is provided on the bottom surface of the second pressing plate, the second pressing plate is buckled in the second sawtooth groove and is embedded between the anchoring cover plate and the anchoring bearing plate. The second pressing plate presses the steel fiber bundle tightly against the second sawtooth block, and the friction and restraint force provided by the second sawtooth block are used to tightly fix one end of the steel fiber bundle on the anchoring fixture.
[0025] Preferably, it further comprises a plurality of third pressing plates, a plurality of sawtooth modules are fixed to the top end of the anchor bearing plate away from the connecting rod, a rectangular groove is provided on the top surface of the anchor cover plate relative to the plurality of sawtooth modules, a third sawtooth groove corresponding to the plurality of sawtooth modules is provided on the bottom surface of the plurality of third pressing plates, and the plurality of third pressing plates cover the plurality of sawtooth modules one by one and are placed in the rectangular groove. The cooperation between the third pressing plates and the sawtooth modules is used to increase the restraint force and friction force of the anchor clamp on the steel fiber bundle, thereby preventing the steel fiber bundle from being broken.
[0026] Preferably, the connector includes a connecting rod, the end of which is provided with a first mortise and tenon groove, and a first tenon rod adapted to the first mortise and tenon groove is fixed to the end of the connecting rod; the connecting rods are multiple and face each other end to end, the first tenon rod of one of the connecting rods is inserted into the first tenon groove of the connecting rod adjacent to it and fastened by bolts; the connecting rod is inserted into the first tenon groove of the connecting rod corresponding to it and fastened by bolts. By utilizing the characteristics of the mortise and tenon connection, connecting rods of different lengths can be selected according to the length of the structure to connect the clamp, thereby improving the flexibility of the use of the clamp.
[0027] Preferably, it also includes a steering rod, the steering rod includes a first steering rod and a second steering rod, one end of the first steering rod is hinged to one end of the second steering rod, the ends of the first steering rod and the second steering rod facing away from each other are provided with a second tenon matched with the first tenon rod, and the corresponding ends are fixed with a second tenon matched with the first tenon rod, the steering rod is arranged between two adjacent connecting rods, the second tenon rod is inserted into the adjacent first tenon rod, and the corresponding first tenon rod is inserted into the second tenon rod and fastened by bolts. The steering rod can make the tensioning clamp turn between the anchoring clamps, meet the requirements of applying prestress outside the complex structure, avoid damage to the structure, and improve the flexibility of the clamping system.
[0028] Preferably, it further comprises a rotating shaft, the connector is provided with two, the two connectors are symmetrically arranged, the rotating shaft passes through the two opposite ends of the two first steering rods and the second steering rods so that the two first steering rods and the two second steering rods can rotate relative to the rotating shaft. The two connectors can improve the firmness of the tensioning clamp and the anchoring clamp after being connected, and the steering rod realizes the steering function by using the rotating shaft.
[0029] Preferably, the tensioning clamp further includes a first screw, and the anchoring clamp further includes a second screw; the first screw is arranged perpendicular to the tensioning cover plate, and its threaded end sequentially passes through the tensioning cover plate, the tensioning bearing plate, the structure and the tensioning clamp, and the first screw is fastened to the bottom surface of the tensioning clamp by a first nut to fix the tensioning clamp to the structure;
[0030] The second screw is arranged perpendicular to the anchor cover plate and its threaded end passes through the anchor cover plate, the anchor bearing plate, the structure and the anchor clamp in sequence. The second screw is fastened to the bottom surface of the anchor clamp by a second nut to fix the anchor clamp to the structure.
[0031] The beneficial effect of the above technical solution is that after the clamp clamps the structure, the clamp and the structure can be anchored into a whole by passing a screw through the anchor hole on the structure, thereby improving the installation effect of the clamp and preventing the clamp from moving during the tensioning process and affecting the tensioning effect and causing damage to the structure.
[0032] It can be seen from the above technical solutions that, compared with the prior art, the present invention discloses a clamping system for external prestressed single-end tensioning of concrete structures, which has the following beneficial effects:
[0033] 1. Before applying prestress to actual engineering components and laboratory test beams, plates and other structural components, the fixtures in the clamping system can be placed in a fixture storage box, which is convenient for carrying and storage; its detachable and reassembled design features provide greater flexibility and convenience for construction and testing. At the same time, the reasonable structural design of the fixture ensures the stability and safety of the components during the prestressing process, thereby ensuring the smooth progress of construction and testing, providing more options and convenience for engineering construction and experiments, and meeting the needs of different scenarios;
[0034] 2. In traditional concrete prestressed fixtures, dangerous situations often occur due to problems with the loading method. The present invention uses a semi-mechanized form for loading, which significantly improves safety and reliability.
[0035] 3. In traditional concrete prestressing fixtures, the prestress is often difficult to control and not intuitive. The present invention calculates the prestress by using trigonometric functions and the elastic modulus of materials such as fibers and steel strands, making the specific numerical value of the applied prestress more controllable; the different angle graded loading system makes the loading method more intuitive and flexible. In the actual loading process, the loading order of the prestress can be determined according to the needs of different structural components. BRIEF DESCRIPTION OF THE DRAWINGS
[0036] In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are only embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on the provided drawings without paying creative work.
[0037] Figure 1 A schematic diagram of the structure of the clamping system provided by the present invention;
[0038] Figure 2 A schematic diagram of the tensioning fixture structure provided by the present invention;
[0039] Figure 3 An exploded schematic diagram of the tensioning fixture provided by the present invention;
[0040] Figure 4 A schematic diagram of the tension bearing plate structure provided by the present invention;
[0041] Figure 5 A schematic diagram of the structure of the anchoring clamp provided by the present invention;
[0042] Figure 6 An exploded schematic diagram of the anchoring clamp provided by the present invention;
[0043] Figure 7A schematic diagram of the connecting rod structure provided by the present invention;
[0044] Figure 8 This is a schematic diagram of the steering rod structure provided by the present invention.
[0045] in,
[0046] 100-tensioning fixture; 110-tensioning cover plate; 1101-limiting ring; 120-tensioning bearing plate; 1201-constraint; 1202-first sawtooth block; 130-tensioning clamp; 1301-guide rail; 140-jack; 150-support plate; 1501-annular boss; 160-sling; 1601-fixing piece; 170-first screw rod; 180-first pressing plate;
[0047] 200-anchoring fixture; 210-anchoring cover plate; 220-anchoring bearing plate; 2201-second sawtooth block; 2202-sawtooth module; 230-anchoring clamp; 240-second screw rod; 250-second pressing plate; 260-third pressing plate;
[0048] 300-connector; 310-connecting rod; 3101-first tenon groove; 3102-second tenon groove; 320-steering rod; 3201-first steering rod; 3202-second steering rod; 3203-second tenon groove; 3204-second tenon rod; 330-rotating axis;
[0049] 400-Connecting rod. DETAILED DESCRIPTION
[0050] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0051] In the description of the present invention, it should be understood that the terms "up", "down", "front", "back", "left", "right", "vertical", "horizontal", "top", "bottom", "inside" and "outside" etc., indicating orientations or positional relationships, are based on the orientations or positional relationships shown in the accompanying drawings, and are only for the convenience of describing the present invention and simplifying the description, rather than indicating or implying that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore should not be understood as a limitation on the present invention.
[0052] In the description of the present invention, “plurality” means two or more than two, unless otherwise clearly and specifically defined.
[0053] In the present invention, unless otherwise clearly specified and limited, the terms "installed", "connected", "connected", "fixed" and the like should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or a welding connection; it can be a direct connection or an indirect connection through an intermediate medium, it can be the internal connection of two elements or the interaction relationship between two elements. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.
[0054] In the present invention, unless otherwise clearly specified and limited, a first feature being "above" or "below" a second feature may include that the first and second features are in direct contact, or may include that the first and second features are not in direct contact but are in contact through another feature between them. Moreover, a first feature being "above", "above" and "above" a second feature includes that the first feature is directly above and obliquely above the second feature, or simply indicates that the first feature is higher in level than the second feature. A first feature being "below", "below" and "below" a second feature includes that the first feature is directly below and obliquely below the second feature, or simply indicates that the first feature is lower in level than the second feature.
[0055] See attached Figures 1 to 8 The embodiment of the present invention discloses a clamping system for single-end tensioning of external prestressing of concrete structures, including an anchoring clamp 200 clamped at both ends of the structure, a tensioning clamp 100, and a connector 300 connecting the anchoring clamp 200 and the tensioning clamp 100; the clamping system adopts bolt connection, and the detachable and assembling characteristics improve the flexibility of use and storage of the clamping system, provide more choices and convenience for engineering construction and experiments, and can meet the needs of different scenarios;
[0056] The anchoring fixture 200 includes an anchoring bearing plate 220, an anchoring cover plate 210 and an anchoring clamp plate 230; the anchoring cover plate 210 covers the top surface of the anchoring bearing plate 220 to clamp one end of the steel fiber bundle, and the anchoring clamp plate 230 is arranged parallel to the lower side of the anchoring bearing plate 220 and clamped relative to one end of the structure;
[0057] The tensioning fixture 100 includes a tensioning bearing plate 120, a tensioning cover plate 110, a tensioning clamp plate 130 and a sling 160. The tensioning cover plate 110 covers the top surface of the tensioning bearing plate 120 to clamp the other end of the steel fiber bundle. The tensioning clamp plate 130 is arranged parallel to the tensioning bearing plate 120 and clamped relative to the other end of the structure. The sling 160 is annular and is sleeved on the outer periphery of the tensioning fixture 100 close to the anchoring fixture 200 to change the inclination angle of the steel fiber bundle.
[0058] The two opposite end surfaces of the anchoring bearing plate 220 and the tensioning bearing plate 120 are both fixed with connecting rods 400 , and the two ends of the connector 300 are bolted to the two connecting rods 400 , respectively.
[0059] like Figure 1 , 2 As shown in , 5, the tensioning fastening bolts penetrate the panels of the tensioning bearing plate and the tensioning cover plate from bottom to top to connect the two, and the anchoring fastening bolts penetrate the panels of the anchoring bearing plate and the anchoring cover plate from bottom to top to connect the two; the steel fiber bundle is passed from the tensioning clamp to the anchoring clamp for fixation, and the end of the steel fiber bundle relative to the tensioning clamp is the tensioning end, and the end relative to the anchoring clamp is the fixed end. When the sling is put on one end of the tensioning clamp, the steel fiber bundle at the other end will be tilted at a certain angle. By adjusting the tightness of the sling, the tilting angle of the steel fiber bundle can be changed, thereby realizing the composite loading of multi-angle graded in vitro prestressing.
[0060] In this embodiment, the tensioning clamp 100 also includes a first pressure plate 180, and both ends of the top surface of the tensioning bearing plate 120 are fixed with restraints 1201 for passing steel fiber bundles. A plurality of first serrated blocks 1202 are fixed on the top surface of the tensioning bearing plate 120 relative to the two restraints 1201. The bottom surface of the first pressure plate 180 is provided with a first serrated groove adapted to the first serrated block 1202. The first pressure plate 180 is buckled with the first serrated block 1202 and is embedded between the tensioning cover plate 110 and the tensioning bearing plate 120.
[0061] In order to further optimize the above technical solution, Figure 4 As shown, the restraint is symmetrically arranged, including a fixed block and a sleeve. The fixed block is fixed at both ends of the top surface of the tensioning bearing plate. One end of the multiple sleeves is arranged perpendicular to the end surface of the fixed block, and the other end extends toward the direction of the first serrated block. The steel fiber bundle is passed through the sleeves at both ends. After the first pressing plate is pressed and fastened with the first serrated block, the steel fiber bundle will be pressed on the bearing plate in a curve; the bearing plate, the first pressing plate and the tensioning cover plate are locked by tensioning fastening bolts, and the first serrated block is used to provide restraint and friction for the fixation of the steel fiber bundle and press it.
[0062] In order to further optimize the above technical solution, an auxiliary bolt hole is opened on the top surface of the tensioning bearing plate near one end of the connector, and the auxiliary pressure plate can be fastened to the tensioning bearing plate by the auxiliary bolts. The auxiliary pressure plate is utilized to further improve the fixing ability of the steel fiber bundle, provide tensioning pre-tightening force, ensure that the steel fiber bundle can be tightened during the tensioning process, and ensure the effective and complete implementation of the tensioning.
[0063] In order to further optimize the above technical solution, it also includes a support plate 150 and a jack 140. A plurality of guide rails 1301 perpendicular to the panel are fixed in an array on one side of the bottom surface of the tensioning splint 130. The support plate 150 is arranged parallel to the tensioning splint 130 and is slidably connected to the guide rail 1301. The jack 140 is supported between the support plate 150 and the tensioning splint 130. The sling 160 is connected end to end and fixed into a ring shape by a fixing member 1601. The sling 160 is sleeved on the outer periphery of the tensioning cover plate 110 and the support plate 150 to limit the sliding of the support plate 150.
[0064] The tensioning clamp can be fixed to the structure by a jack, and the jack can be removed after being tightened by a nut; the jack is supported between the support plate and the tensioning clamp, and when the jack is lifted, the sling will tighten to provide clamping force to change the inclination angle of the steel fiber bundle at the tensioning end.
[0065] In this embodiment, if Figure 3 As shown, the sling is a high-strength polyester sling, and a plurality of bolt holes are opened at one end of the fixing piece, and a protective copper ring is arranged in the bolt hole, and three pressure columns are fixed at the other end. A plurality of triangular bolt holes are opened at one end of the sling, and according to the actual size, the bolt holes at different positions of the sling are selected and fastened with bolts to the bolt holes on the fixing piece, and the other end of the sling is reversed and fixed between the middle pressure column and the pressure columns at both ends in turn and fastened by rivets. In this way, under the action of external force, not only the protective copper ring can be stressed, but also the sling can be subjected to frictional stress under the action of the three pressure columns of the fixing piece, thereby increasing the service life of the sling and making the sling more stably fixed; in the design of the triangular holes of the sling, the force mode is designed according to the optimal triangular force mode, so that the sling can be subjected to more uniform force under the action of left and right pulling forces, and the lateral tensile resistance can be increased.
[0066] In order to further optimize the above technical solution, ensure the degree of freedom of the jack, and prevent instability due to tilted lifting, an annular boss 1501 is fixed on the top surface of the support plate 150, and an annular groove is opened on the bottom surface of the tension clamp 130 relative to the annular boss 1501. The lifting end of the jack 140 extends into the inner cavity of the annular boss 1501 and abuts against the top surface of the support plate 150, and the fixed end is embedded in the annular groove;
[0067] In order to further optimize the above technical solution and prevent the sling from slipping on the tensioning clamp after being tightened and causing the jack to tip over or become unstable, a receiving groove is opened on the bottom surface of the support plate 150 along its length direction, and limiting rings 1101 are fixed at both ends of the top surface of the receiving groove corresponding to the tensioning cover plate 110. The bottom end of the sling 160 is sleeved in the receiving groove and the top end is passed through the limiting ring 1101 to limit the displacement of the sling 160.
[0068] In this embodiment, if Figure 5 and6 As shown, the anchoring clamp 200 also includes a second pressure plate 250, a second serrated block 2201 is fixed to the middle of the top surface of the anchoring bearing plate 220, and a second serrated groove adapted to the second serrated block 2201 is opened on the bottom surface of the second pressure plate 250. The second pressure plate 250 is snapped into the second serrated groove and embedded between the anchoring cover plate 210 and the anchoring bearing plate 220.
[0069] The fixed end of the steel fiber bundle is pressed between the second serrated block and the second serrated groove by the second pressing plate on the top surface of the anchor bearing plate, and the steel fiber bundle is fixed by the second pressing plate; the anchor fastening bolts penetrate the anchor bearing plate, the second pressing plate and the anchor cover plate from bottom to bottom in sequence to fasten the three.
[0070] In order to further optimize the above technical solution and improve the fixing effect of the steel fiber bundle, it also includes a plurality of third pressing plates 260, a plurality of sawtooth modules 2202 are fixed on the top end of the anchor bearing plate 220 away from the connecting rod 400, the anchor cover plate 210 is provided with a rectangular groove on the top surface relative to the plurality of sawtooth modules 2202, and the bottom surfaces of the plurality of third pressing plates 260 are provided with third sawtooth grooves corresponding to the plurality of sawtooth modules 2202, and the plurality of third pressing plates 260 cover the plurality of sawtooth modules 2202 one by one and are placed in the rectangular grooves.
[0071] There are different types of sawtooth modules. The diameter of the steel fiber bundle is taken into consideration when designing the sawtooth module. In order to prevent the steel fiber bundle from generating excessive tangential stress during the constraint process, a fiber buffer area is added to each set of wavy teeth, so that the steel fiber bundle is not easily broken under the action of the anchoring clamp. The sawtooth module is inspired by the pattern of car tires. Such a spiral pattern can increase the constraint and friction of the anchoring clamp on the steel fiber bundle in the overall structure. The structure can adopt a graded loading method. According to different forces, sawtooth modules can be added to the anchor bearing plate in an unfixed order and fixed by bolts and nuts. Finally, the anchoring clamp can be fixed as a whole by the anchor cover plate.
[0072] In order to further optimize the above technical solution, a secondary bolt hole is opened on the panel of the anchor bearing plate corresponding to the second serrated block, and bolts are passed through the secondary bolt holes from bottom to top to fasten them to the second pressure plate and the anchor cover plate. The secondary bolt holes can increase the clamping force between the second pressure plate and the anchor bearing plate to ensure that the steel fiber bundle is completely fixed in the anchor clamp without loosening, so that the steel fiber bundle is fully tightened.
[0073] In order to further optimize the above technical solution, the connector 300 includes a connecting rod 310, the end of which is provided with a first tenon groove 3101, and the end of which is fixed with a first tenon rod 3102 adapted to the first tenon groove 3101; there are multiple connecting rods 310 and the end thereof is opposite to each other, and the first tenon rod 3102 of one connecting rod 310 is inserted into the first tenon groove 3101 of the adjacent connecting rod 310 and fastened by bolts; the connecting rod 400 is inserted into the first tenon groove 3101 of the corresponding connecting rod 310 and fastened by bolts.
[0074] See attached Figure 7 The connecting rods can be engaged with each other through the mortise and tenon connecting rods and the mortise and tenon connecting grooves, and connected by bolts and nuts of the same size, where the elongation of the tenon rod is smaller than the length of the tenon groove, which can leave enough length for buffering under stress and prevent structural wear and damage. There are long bolt fixing holes at different positions on the connecting rod, which can adapt to different prestressed anchor holes and structures for anchoring.
[0075] In order to further optimize the above technical solution, improve the flexibility of the clamping system, and be able to apply external prestress to non-planar structures, it also includes a steering rod 320, the steering rod 320 includes a first steering rod 3201 and a second steering rod 3202, one end of the first steering rod 3201 and one end of the second steering rod 3202 are hinged to each other, the ends of the first steering rod 3201 and the second steering rod 3202 that are away from each other are provided with a second tenon groove 3203 that is adapted to the first tenon rod 3102, and the corresponding end is fixed with a second tenon rod 3204 that is adapted to the first tenon groove 3101, the steering rod 320 is arranged between two adjacent connecting rods 310, its second tenon rod 3204 is inserted into the adjacent first tenon groove 3101, and the corresponding first tenon rod 3102 is inserted into the second tenon groove 3203 and fastened by bolts.
[0076] like Figure 8 As shown, the connection between the steering rod and the connecting rod is the same as the connection between the connecting rods, and the two opposite ends of the first steering rod and the second steering rod are hinged by a pin. When the structure is non-planar or has a certain angle and curvature, the hinge between the first steering rod and the second steering rod can be used to change the angle of the connection line between the tensioning clamp and the anchoring clamp, so that the connection line between them is not a straight line, but a broken line that adapts to the shape of the structure. In this way, the non-planar structure can be prestressed in vitro without destroying the existing shape of the structure, thereby improving the flexibility and versatility of the clamping system.
[0077] In order to further optimize the above technical solution, improve the connection effect between the tensioning clamp and the anchoring clamp, and ensure reliable and stable connection, the device further includes a rotating shaft 330, two connectors 300 are provided, and the two connectors 300 are symmetrically arranged. The rotating shaft 330 passes through the two opposite ends of the two first steering rods 3201 and the second steering rods 3202 so that the two first steering rods 3201 and the two second steering rods 3202 can rotate relative to the rotating shaft 330. The rotating column is used to replace the pin shaft, and the rotating shaft connects the two symmetrically arranged steering rods. The tensioning clamp and the anchoring clamp are connected through two sets of connectors. Both sets of connectors can be fastened to the structure through the holes on the connecting rod using long bolts, which ensures the fixing effect between the tensioning clamp and the anchoring clamp and the structure, so that the clamping system and the structure form an overall stable tensioning system.
[0078] In some other specific embodiments, the tensioning clamp 100 further includes a first screw 170, and the anchoring clamp 200 further includes a second screw 240; the first screw 170 is arranged vertically on the tensioning cover plate 110, and its threaded end sequentially penetrates the tensioning cover plate 110, the tensioning bearing plate 120, the structure and the tensioning clamp 130, and the first screw 170 is fastened to the bottom surface of the tensioning clamp 130 by a first nut to fix the tensioning clamp 100 to the structure;
[0079] The second screw 240 is arranged perpendicular to the anchor cover plate 210 and its threaded end passes through the anchor cover plate 210, the anchor bearing plate 220, the structure and the anchor clamp 230 in sequence. The second screw 240 and the bottom surface of the anchor clamp 230 are fastened by a second nut to fix the anchor clamp 200 to the structure.
[0080] Both the tensioning clamp and the anchoring clamp are fastened to the structure by screws to ensure the effective installation of the clamp. At the same time, in order to improve the installation effect of the clamp, a pre-tightening bolt hole is opened on the panel of the tensioning clamp. The threaded end of the pre-tightening bolt passes through the pre-tightening bolt hole from bottom to top and abuts against the surface of the structure. The actual pre-tightening force between the tensioning clamp and the structure is ensured by the pre-tightening bolt. During the tensioning operation, there is no need for pre-tensioning but the steel fiber bundle is tightened, which saves the operation process.
[0081] When applying external prestress, the tensioning clamp and the anchoring clamp can be adapted to most structural members with prestressed anchor points already punched; first, the anchoring clamp is fixed at the prestressed anchor point using a long rod bolt and a long rod nut, and then connecting rods and steering rods of different lengths are connected in sequence from right to left. The number of connecting rods can be freely determined according to the length of the specific member and the effective length of the prestressed force; the fiber bundle is placed in the sleeve of the tensioning bearing plate restraint and the tensioning bearing plate, the first pressure plate and the tensioning cover plate are fixed by bolts, so that the steel fiber can be completely fixed.
[0082] When the steel fiber bundle is initially fixed to the anchoring clamp, the tensioning clamp and the structure are in a non-parallel relationship. The anchoring clamp is connected to the support plate of the jack by a sling, and the jack is used to fix it in between. At this time, the steel fiber bundle and the anchoring clamp are initially fixed, and prestress can be applied in layers through sawtooth molds of different specifications, and fixed by bolts and nuts. When the tensioning clamp and the anchoring clamp are fixed separately, most of the steel fiber bundles should be in a taut state. The specific height of the tensioning clamp when prestressing is applied can be calculated through the elastic modulus, trigonometric function and deformation through mathematical calculation formulas, and the tensioning clamp is fixed to the structure through the jack. After this step, the tensioning clamp is fixed with the first screw and nut and the jack can be removed.
[0083] In some other specific embodiments, the steel fiber bundles may be replaced by steel wires or prestressed steel strands.
[0084] In this specification, each embodiment is described in a progressive manner, and each embodiment focuses on the differences from other embodiments. The same or similar parts between the embodiments can be referred to each other. For the device disclosed in the embodiment, since it corresponds to the method disclosed in the embodiment, the description is relatively simple, and the relevant parts can be referred to the method part.
[0085] The above description of the disclosed embodiments enables one skilled in the art to implement or use the present invention. Various modifications to these embodiments will be apparent to one skilled in the art, and the general principles defined herein may be implemented in other embodiments without departing from the spirit or scope of the present invention. Therefore, the present invention will not be limited to the embodiments shown herein, but rather to the widest scope consistent with the principles and novel features disclosed herein.
Claims
1. A clamping system for external prestressing of concrete structures at one end. It is characterized in that It comprises an anchoring clamp (200), a tensioning clamp (100), and a connector (300) connecting the anchoring clamp (200) and the tensioning clamp (100); The anchoring clamp (200) comprises an anchoring bearing plate (220), an anchoring cover plate (210) and an anchoring clamp plate (230); the anchoring cover plate (210) covers the top surface of the anchoring bearing plate (220) to clamp one end of the steel fiber bundle, and the anchoring clamp plate (230) is arranged parallel to the bottom of the anchoring bearing plate (220) and is arranged to clamp one end of the structure; The tensioning clamp (100) comprises a tensioning bearing plate (120), a tensioning cover plate (110), a tensioning clamp (130) and a sling (160); the tensioning cover plate (110) covers the top surface of the tensioning bearing plate (120) to clamp the other end of the steel fiber bundle; the tensioning clamp (130) is arranged in parallel below the tensioning bearing plate (120) and is arranged to clamp the other end of the structure; the sling (160) is annular and is sleeved on the outer periphery of the tensioning clamp (100) close to the anchoring clamp (200) to change the inclination angle of the steel fiber bundle; Wherein, connecting rods (400) are fixed to both opposite end surfaces of the anchoring bearing plate (220) and the tensioning bearing plate (120), and both ends of the connector (300) are bolted to the two connecting rods (400) respectively.
2. A clamping system for external prestressing single-end tensioning of concrete structures according to claim 1, It is characterized in that The tensioning clamp (100) also includes a first pressure plate (180), and both ends of the top surface of the tensioning bearing plate (120) are fixed with restraints (1201) for passing the steel fiber bundles. The tensioning bearing plate (120) is fixed with a plurality of first sawtooth blocks (1202) on the top surfaces of the two restraints (1201). The bottom surface of the first pressure plate (180) is provided with a first sawtooth groove adapted to the first sawtooth block (1202), and the first pressure plate (180) is buckled with the first sawtooth block (1202) and is embedded between the tensioning cover plate (110) and the tensioning bearing plate (120).
3. A clamping system for external prestressing single-end tensioning of concrete structure according to claim 2, It is characterized in that It also includes a support plate (150) and a jack (140); a plurality of guide rails (1301) perpendicular to the panel are fixed in an array on one side of the bottom surface of the tensioning splint (130); the support plate (150) is arranged parallel to the tensioning splint (130) and is slidably connected to the guide rails (1301); the jack (140) is supported between the support plate (150) and the tensioning splint (130); the sling (160) is connected end to end and fixed into a ring shape by a fixing member (1601); the sling (160) is sleeved on the outer periphery of the tensioning cover plate (110) and the support plate (150) to limit the sliding of the support plate (150).
4. A clamping system for external prestressing single-end tensioning of concrete structures according to claim 3, It is characterized in that An annular boss (1501) is fixed on the top surface of the support plate (150), an annular groove is formed on the bottom surface of the tensioning clamp (130) relative to the annular boss (1501), the lifting end of the jack (140) extends into the inner cavity of the annular boss (1501) and abuts against the top surface of the support plate (150), and the fixed end is embedded in the annular groove; The bottom surface of the support plate (150) is provided with a receiving groove along its length direction, and the tension cover plate (110) is fixed with limiting rings (1101) at both ends of the top surface corresponding to the receiving groove, and the bottom end of the sling (160) is sleeved in the receiving groove and the top end is passed through the limiting ring (1101) to limit the displacement of the sling (160).
5. A clamping system for external prestressing single-end tensioning of concrete structure according to claim 1, It is characterized in that The anchoring clamp (200) further comprises a second pressing plate (250), a second sawtooth block (2201) being fixed in the middle of the top surface of the anchoring bearing plate (220), a second sawtooth groove matching the second sawtooth block (2201) being provided on the bottom surface of the second pressing plate (250), and the second pressing plate (250) being snap-fitted into the second sawtooth groove and embedded between the anchoring cover plate (210) and the anchoring bearing plate (220).
6. A clamping system for external prestressing single-end tensioning of concrete structure according to claim 5, It is characterized in that It also includes a plurality of third pressure plates (260), a plurality of sawtooth modules (2202) are fixed to the top end of the anchoring bearing plate (220) away from the connecting rod (400), the anchoring cover plate (210) is provided with a rectangular groove on the top surface relative to the plurality of sawtooth modules (2202), the bottom surfaces of the plurality of third pressure plates (260) are provided with third sawtooth grooves corresponding to the plurality of sawtooth modules (2202), and the plurality of third pressure plates (260) cover the plurality of sawtooth modules (2202) one by one and are placed in the rectangular grooves.
7. A clamping system for external prestressing single-end tensioning of concrete structure according to claim 1, It is characterized in that The connector (300) comprises a connecting rod (310), the end of which is provided with a first tenon groove (3101), and the end of which is fixed with a first tenon rod (3102) adapted to the first tenon groove (3101); the connecting rod (310) is multiple in number and is opposite in end to end, wherein the first tenon rod (3102) of one of the connecting rods (310) is inserted into the first tenon groove (3101) of the adjacent connecting rod (310) and is fastened by bolts; the connecting rod (400) is inserted into the first tenon groove (3101) of the corresponding connecting rod (310) and is fastened by bolts.
8. A clamping system for external prestressing single-end tensioning of concrete structures according to claim 7, It is characterized in that It also includes a steering rod (320), the steering rod (320) includes a first steering rod (3201) and a second steering rod (3202), one end of the first steering rod (3201) and one end of the second steering rod (3202) are hinged to each other, the ends of the first steering rod (3201) and the second steering rod (3202) that are away from each other are provided with a second tenon groove (3203) adapted to the first tenon rod (3102), and the corresponding end is fixed with a second tenon rod (3204) adapted to the first tenon groove (3101), the steering rod (320) is arranged between two adjacent connecting rods (310), its second tenon rod (3204) is inserted into the first tenon groove (3101) adjacent to it, and the corresponding first tenon rod (3102) is inserted into the second tenon groove (3203) and fastened by bolts.
9. A clamping system for external prestressing single-end tensioning of concrete structures according to claim 8, It is characterized in that It also includes a rotating shaft (330), two connectors (300) are provided, and the two connectors (300) are symmetrically arranged. The rotating shaft (330) passes through the two opposite ends of the two first steering rods (3201) and the two second steering rods (3202) so that the two first steering rods (3201) and the two second steering rods (3202) can rotate relative to the rotating shaft (330).
10. A clamping system for external prestressing single-end tensioning of concrete structure according to claim 1, It is characterized in that The tensioning clamp (100) further includes a first screw rod (170), and the anchoring clamp (200) further includes a second screw rod (240); the first screw rod (170) is arranged perpendicular to the tensioning cover plate (110), and its threaded end sequentially passes through the tensioning cover plate (110), the tensioning bearing plate (120), the structure and the tensioning clamp (130); the first screw rod (170) and the bottom surface of the tensioning clamp (130) are fastened by a first nut to fix the tensioning clamp (100) to the structure; The second screw rod (240) is arranged perpendicular to the anchor cover plate (210) and its threaded end sequentially passes through the anchor cover plate (210), the anchor bearing plate (220), the structure and the anchor clamp (230); the second screw rod (240) and the bottom surface of the anchor clamp (230) are fastened by a second nut so that the anchor clamp (200) is fixed to the structure.