Method for reinforcing tunnel by adopting prefabricated composite boards connected by inserting board edges into interfaces
The prefabricated composite panel reinforcement method connected through the plate edge insertion interface, combined with high ductility concrete and FRP grid, solves the problem of reinforcement of the negative bending moment zone at the waist of the tunnel, realizes efficient and convenient tunnel reinforcement effect, and enhances the bearing capacity and integrity , reducing water leakage problems.
Patent Information
- Application Number
- CN202411346437.0
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-09-25
- Publication Date
- 2024-11-22
AI Technical Summary
In the existing tunnel reinforcement technology, FRP materials can only be used for reinforcement of positive bending moment zones and cannot be used for negative bending moment zones. The reinforcement is poor in integrity and difficult to construct, and poor economicality. It is urgently needed to apply to the waist of the tunnel. Efficient reinforcement method for negative bending moment zone.
The prefabricated composite plate reinforcement method is adopted to connect the plate edge insertion interface. The arc mold is manufactured through measurement design and design, and the cast high-ductility concrete is combined with the FRP grid to form the prefabricated composite plate, which is installed on site and fixed by chemical anchor bolts and connecting bolts. , providing annular stiffness and reinforcement effect.
It realizes efficient reinforcement of the negative bending moment zone of the tunnel waist, improves the bearing capacity and stiffness, simplifies the installation process, reduces water leakage problems, and enhances the integrity and economical reinforcement.
Smart Images

Figure CN118997788A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of tunnel reinforcement, in particular to a method for reinforcing a tunnel by using a prefabricated composite plate connected by inserting a plate edge into an interface. Background Art
[0002] With the continuous acceleration of urbanization, the urban underground space is constantly being developed and utilized. As the main structural form of urban rail transit, the buried depth, length and cross-sectional area of tunnels are constantly increasing. With the increase of operating years, some tunnel structures have gradually exposed problems such as water leakage, cracks, missing corners, joint opening, tunnel segment displacement, tunnel segment deformation, etc. Some of the problems have affected the normal operation of the tunnel, and if they continue to develop, they may affect normal driving safety.
[0003] FRP (fiber reinforced composite material) and steel plate are two commonly used reinforcement components for shield tunnel reinforcement. However, FRP can only withstand tension, so it is usually only used to reinforce the positive bending moment area near the tunnel vault, and cannot be used to reinforce the negative bending moment area near the waist of the tunnel; although steel plates are suitable for reinforcement of both positive and negative bending moment areas, the reinforcement has good integrity and high rigidity, but there are many welds, the construction quality is not easy to control, and the amount of steel used is large, and the economy is difficult to guarantee.
[0004] Therefore, there is an urgent need for a method of reinforcing tunnels using prefabricated composite panels connected by panel edge insertion interfaces to solve the above problems. Summary of the invention
[0005] The purpose of the embodiments of the present invention is to provide a method for reinforcing a tunnel by using prefabricated composite panels connected by panel edge insertion interfaces, so as to solve the problems raised in the above-mentioned background technology.
[0006] To achieve the above object, the present invention provides the following technical solutions:
[0007] A method for reinforcing a tunnel using a prefabricated composite plate connected by plate edge insertion interfaces, comprising the following steps:
[0008] S1: Measure the geometric dimensions of the tunnel body and the reinforcement parts according to the design requirements, ensure the accuracy of the dimensions of the composite plate edge insertion interface, and manufacture the arc plate mold and FRP grid;
[0009] S2: Mix high-ductility concrete, pour it into a curved plate-shaped mold, prefabricate the FRP-ECC composite board, place the FRP grid in the mold during the pouring process, and after the pouring is completed, perform room temperature moisture maintenance on the FRP-ECC composite board;
[0010] S3: Clean and roughen the surface of the tunnel lining structure to be reinforced to expose the aggregate, and drill holes at the marked positions;
[0011] S4: Mix and stir the epoxy resin and hardener in the prescribed proportion, and evenly apply the mixed epoxy resin on the concrete surface to ensure that the epoxy resin covers the entire reinforcement area and forms a uniform film;
[0012] S5: The first FRP-ECC prefabricated composite panel is placed close to the tunnel surface and fixed with chemical anchor bolts;
[0013] S6: Install the second FRP-ECC prefabricated composite panel along the panel edge insertion interface of the first FRP-ECC prefabricated composite panel to ensure the fit. The panel edge insertion interfaces of two adjacent prefabricated composite panels in the transverse direction are fixed by using inter-ring panel edge connection bolts, and the panel edge insertion interfaces of two adjacent prefabricated composite panels in the longitudinal direction are fixed by using annular panel edge connection bolts.
[0014] S7: Repeat steps S5-S6 to completely reinforce the tunnel.
[0015] As a further solution of the present invention: the connection interface of the prefabricated composite board adopts a board edge insertion interface.
[0016] Compared with the prior art, the present invention has the following beneficial effects:
[0017] According to the measurement of geometric parameters of the on-site reinforcement position, a mold with a plate edge insertion interface is made. After pouring high-performance concrete, the FRP grid is placed in the mold in the middle of pouring so that it is located in the center of the prefabricated panel to form a prefabricated composite panel. According to different reinforcement requirements, the size of the mold can be adjusted to adapt to the on-site conditions; and according to different reinforcement requirements, different FRP grid thicknesses and layers can be used to parameterize the reinforcement bearing capacity and stiffness; the combination of high-ductility concrete and FRP grid has higher bearing capacity and stiffness; prefabricated panels are used for on-site installation, and the plate edge insertion interface makes installation more convenient; the plate edge insertion interface can provide a certain circumferential stiffness, and the interface is further reinforced with connecting bolts, which has a stronger reinforcement effect. BRIEF DESCRIPTION OF THE DRAWINGS
[0018] Figure 1 It is a three-dimensional structural schematic diagram of a method for reinforcing a tunnel using prefabricated composite panels connected by panel edge insertion interfaces in an embodiment of the present invention.
[0019] Figure 2 It is a front view of a method for reinforcing a tunnel using prefabricated composite panels connected by panel edge insertion interfaces in an embodiment of the present invention.
[0020] Figure 3 It is a schematic diagram of the three-dimensional structure of the prefabricated composite panel in an embodiment of the present invention.
[0021] In the figure: 1. Tunnel body; 2. Prefabricated composite panel; 3. Chemical anchor bolts; 4. Inter-ring panel edge connecting bolts; 5. Annular panel edge connecting bolts. DETAILED DESCRIPTION
[0022] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0023] In the embodiment of the present invention, please refer to Figures 1 to 3 , a method for strengthening a tunnel using a prefabricated composite plate connected by a plate edge insertion interface, comprising the following steps:
[0024] S1: Measure the geometric dimensions of the tunnel body 1 and the reinforcement parts according to the design requirements, ensure the accuracy of the dimensions of the composite plate connection interface, and manufacture the arc plate mold and FRP grid;
[0025] S2: Mix high ductility concrete (ECC), pour it into a curved plate-shaped mold, prefabricate the FRP-ECC composite plate 2, place the FRP grid in the mold during the pouring, and after the pouring is completed, perform room temperature moisture maintenance on the FRP-ECC composite plate 2;
[0026] S3: Clean and roughen the surface of the tunnel lining structure to be reinforced to expose the aggregate, and drill holes at the marked positions;
[0027] S4: Mix and stir the epoxy resin and hardener in the prescribed proportion, and evenly apply the mixed epoxy resin on the concrete surface to ensure that the epoxy resin covers the entire reinforcement area and forms a uniform film;
[0028] S5: placing the first FRP-ECC prefabricated composite panel 2 close to the tunnel surface and fixing it with chemical anchor bolts 3;
[0029] S6: Install the second FRP-ECC prefabricated composite panel 2 along the connection interface of the first FRP-ECC prefabricated composite panel 2 to ensure fit. The connection interfaces of two adjacent prefabricated composite panels 2 in the transverse direction are fixed with annular plate edge connection bolts 4, and the connection interfaces of two adjacent prefabricated composite panels 2 in the longitudinal direction are fixed with annular plate edge connection bolts 5;
[0030] S7: Repeat steps S5-S6 to completely reinforce the tunnel.
[0031] The connection interface of the prefabricated composite board adopts a board edge insertion interface.
[0032] The present invention combines high ductility concrete (ECC) and FRP grid, so that the prepared composite board has stronger bearing capacity and rigidity, and also has high strength, light weight and excellent fatigue performance; the present invention adopts prefabricated panels for on-site installation, and various properties of the prefabricated panels can be parameterized and controlled according to reinforcement requirements, and the connection interface adopts the form of a plate edge insertion interface, which makes the installation more convenient; secondly, the plate edge insertion interface can provide a certain circumferential stiffness, and the interface is further reinforced by connecting bolts, so the reinforcement effect is stronger, and the dripping of leakage water after reinforcement can also be reduced.
[0033] In this embodiment, the thickness of the board edge insertion interface on the prefabricated composite panel 2 is half the thickness of the prefabricated composite panel 2, and the board edge insertion interface on one prefabricated composite panel 2 matches the board edge insertion interface on an adjacent prefabricated composite panel 2, so that the two prefabricated composite panels 2 can be connected together.
[0034] In this embodiment, the thickness of the FRP mesh is 1 to 5 mm, and the mesh spacing of the FRP mesh is 50 to 100 mm. A spacer is used to control the minimum spacing between the FRP mesh and the inner surface of the tunnel lining structure to 2 to 3 mm. The coating thickness of the epoxy resin glue is 0.1 to 0.5 mm, and the thickness of the high-ductility concrete protective layer of the FRP mesh is 12 to 20 mm.
[0035] As an embodiment of the present invention, the material of the FRP mesh in step S1 is aramid fiber, carbon fiber, glass fiber or basalt fiber.
[0036] As an embodiment of the present invention, in step S2, the number of FRP mesh layers can be adjusted according to the reinforcement requirements and mechanical performance requirements.
[0037] As an embodiment of the present invention, in step S4, a brush or a roller brush may be used to apply the epoxy resin.
[0038] As an embodiment of the present invention, step S4 can be omitted according to the tunnel reinforcement requirements.
[0039] As an embodiment of the present invention, in step S6, according to the tunnel reinforcement requirements, a layer of epoxy resin can be evenly applied to the connection interface of the prefabricated composite panel.
[0040] The epoxy resin can improve the bonding strength between the prefabricated composite panel 2 and another prefabricated composite panel 2 and between the prefabricated composite panel 2 and the tunnel body 1, thereby improving the durability thereof.
[0041] The working principle of the present invention is as follows: the present invention uses polymers such as carbon fiber (CFRP), glass fiber (GFRP), basalt fiber (BFRP) to reinforce high ductility concrete (ECC), and the two are combined to form a high-performance composite material to reinforce the tunnel structure; the geometric parameters are measured according to the on-site reinforcement position, and a prefabricated composite board with a plate edge insertion interface is manufactured, and the ratio of the fiber layer number and the cement base can be flexibly adjusted to form reinforcement materials with different mechanical properties. During on-site construction, the prefabricated composite board is spliced along the plate edge interface and fixed with chemical anchor bolts, connecting bolts, etc., so as to reinforce the tunnel structure.
[0042] It will be apparent to those skilled in the art that the invention is not limited to the details of the exemplary embodiments described above and that the invention can be implemented in other specific forms without departing from the spirit or essential features of the invention. Therefore, the embodiments should be considered exemplary and non-limiting in all respects, and the scope of the invention is defined by the appended claims rather than the foregoing description, and it is intended that all variations falling within the meaning and scope of the equivalent elements of the claims be included in the invention. Any reference numeral in a claim should not be considered as limiting the claim to which it relates.
[0043] In addition, it should be understood that although the present specification is described according to implementation modes, not every implementation mode contains only one independent technical solution. This description of the specification is only for the sake of clarity. Those skilled in the art should regard the specification as a whole. The technical solutions in each embodiment may also be appropriately combined to form other implementation modes that can be understood by those skilled in the art.
Claims
1. A method for reinforcing a tunnel using prefabricated composite panels connected by panel edge insertion interfaces, characterized in that: The following steps are involved: S1: Measure the geometric dimensions of the tunnel body and the reinforcement parts according to the design requirements, ensure the accuracy of the dimensions of the composite plate edge insertion interface, and manufacture the arc plate mold and FRP grid; S2: Mix high-ductility concrete, pour it into a curved plate-shaped mold, prefabricate the FRP-ECC composite board, place the FRP grid in the mold during the pouring process, and after the pouring is completed, perform room temperature moisture maintenance on the FRP-ECC composite board; S3: Clean and roughen the surface of the tunnel lining structure to be reinforced to expose the aggregate, and drill holes at the marked positions; S4: Mix and stir the epoxy resin and hardener in the prescribed proportion, and evenly apply the mixed epoxy resin on the concrete surface to ensure that the epoxy resin covers the entire reinforcement area and forms a uniform film; S5: The first FRP-ECC prefabricated composite panel is placed close to the tunnel surface and fixed with chemical anchor bolts; S6: Install the second FRP-ECC prefabricated composite panel along the panel edge insertion interface of the first FRP-ECC prefabricated composite panel to ensure the fit. The panel edge insertion interfaces of two adjacent prefabricated composite panels in the transverse direction are fixed by using inter-ring panel edge connection bolts, and the panel edge insertion interfaces of two adjacent prefabricated composite panels in the longitudinal direction are fixed by using annular panel edge connection bolts. S7: Repeat steps S5-S6 to completely reinforce the tunnel.
2. A method for reinforcing a tunnel using prefabricated composite panels connected by panel edge insertion interfaces according to claim 1, characterized in that: The material of the FRP mesh in step S1 is aramid fiber, carbon fiber, glass fiber or basalt fiber.
3. The method for reinforcing a tunnel using a prefabricated composite plate connected by plate edge insertion interface according to claim 1, characterized in that: In step S2, the number of FRP mesh layers can be adjusted according to the reinforcement requirements and mechanical performance requirements.
4. A method for reinforcing a tunnel using prefabricated composite panels connected by panel edge insertion interfaces according to claim 1, characterized in that: In step S4, the epoxy resin may be applied using a brush or a roller brush.
5. The method for reinforcing a tunnel using a prefabricated composite plate connected by inserting a plate edge into an interface according to claim 1, characterized in that: Step S4 can be omitted according to the tunnel reinforcement requirements.
6. The method for reinforcing a tunnel using a prefabricated composite plate connected by plate edge insertion interface according to claim 1, characterized in that: In step S6, according to the tunnel reinforcement requirements, a layer of epoxy resin can be evenly applied to the edge insertion interface of the prefabricated composite panel.