Heat pump water heater control method and device and heat pump water heater
By predicting and controlling the water tank temperature of the heat pump water heater, the problem of energy waste and water demand matching of heat pump water heater is solved, and the dual satisfaction of energy conservation and water demand is achieved.
Patent Information
- Application Number
- CN202310554109.9
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2023-05-16
- Publication Date
- 2024-11-22
- Estimated Expiration
- 2043-05-16
AI Technical Summary
The heat pump water heater has problems such as waste of energy and inability to meet users' water needs, especially due to the excessive temperature limit setting and the thermal inertia of the heat storage water tank, which makes it impossible to accurately match the user's water use habits.
By obtaining the water tank temperature demand value for the next water use plan, using the water tank temperature prediction model to predict the temperature of the heat storage water tank, and controlling the start and stop of the heat pump unit based on the predicted value and the current start and stop state, ensuring that the water tank temperature at the water use time meets the demand. Avoid heating ahead of time.
It achieves the ability to save energy while meeting users' water needs, avoid energy waste, and ensures that the water tank temperature just meets the needs at the moment of water use.
Smart Images

Figure CN118999002A_ABST
Abstract
Description
Technical Field
[0001] The present invention belongs to the technical field of water heaters, and in particular relates to a heat pump water heater control method, device and heat pump water heater. Background Art
[0002] As energy prices rise, heat pump water heaters have higher energy efficiency requirements. Most users purchase heat pump water heaters for energy consumption considerations, so they pay special attention to energy-saving related functions.
[0003] Heat pump water heaters generally control the start and stop of the heat pump unit based on an upper temperature limit and a lower temperature limit, thereby passively running a fixed logic to make the water tank temperature fluctuate within a preset range. In order to meet the user's water demand, the upper temperature limit needs to be raised as much as possible. However, if the upper temperature limit is set too high, there is a defect of energy waste. In addition, due to the thermal inertia of the hot water storage tank, the delay is large and cannot match the user's usage habits well, resulting in the inability to meet the user's water demand. Summary of the invention
[0004] In view of the technical problems that heat pump water heaters in related technologies waste energy and cannot meet the water needs of users, the embodiments of the present invention provide a heat pump water heater control method, device and heat pump water heater, which can save energy while meeting the water needs of users.
[0005] In a first aspect, an embodiment of the present invention provides a heat pump water heater control method, wherein the heat pump water heater comprises a heat pump unit and a hot water storage tank, and the method comprises: obtaining a water tank temperature requirement value for a next water use plan; in response to the next water use plan, obtaining input parameters, and inputting the input parameters into a water tank temperature prediction model for prediction, to obtain a water tank temperature prediction value of the hot water storage tank at the water use time of the next water use plan, wherein the input parameters comprise current environmental parameters, current time parameters and current operating parameters of the heat pump water heater; comparing the water tank temperature prediction value with the water tank temperature requirement value, and controlling the start and stop of the heat pump unit according to the comparison result and the current start and stop state of the heat pump unit, so that at the water use time of the next water use plan, the actual water tank temperature of the hot water storage tank meets the water tank temperature requirement value.
[0006] In combination with the first aspect, in some implementations, comparing the predicted value of the water tank temperature with the required value of the water tank temperature, and controlling the start and stop of the heat pump unit according to the comparison result and the current start and stop state of the heat pump unit, includes:
[0007] If the heat pump unit is currently in a shutdown state, determine whether the water tank temperature prediction value is greater than a first reference temperature, wherein the first reference temperature is determined based on the water tank temperature demand value and a first preset threshold value; if so, control the heat pump unit to remain in a shutdown state before the water use time of the next water use plan; if not, determine the required operating time of the heat pump unit based on the water tank temperature demand value, and control the next startup time of the heat pump unit based on the required operating time, so that by the water use time of the next water use plan, the actual water tank temperature of the hot water storage tank meets the water tank temperature demand value.
[0008] In combination with the first aspect, in some embodiments, the comparison of the water tank temperature prediction value and the water tank temperature demand value, and the control of the start and stop of the heat pump unit before the next water use according to the comparison result, also includes: if the heat pump unit is currently in a startup state, determining whether the water tank temperature prediction value is less than a second reference temperature, the second reference temperature being determined based on the water tank temperature demand value and a second preset threshold value; if so, controlling the heat pump unit to remain in a startup state before the water use time of the next water use plan; if not, controlling the heat pump unit to shut down, and determining the required operating time of the heat pump unit according to the water tank temperature demand value, and controlling the next startup time of the heat pump unit according to the required operating time, so that at the water use time of the next water use plan, the actual water tank temperature of the hot water storage tank meets the water tank temperature demand value.
[0009] In combination with the first aspect, in some embodiments, controlling the next startup time of the heat pump unit according to the required operating time includes: inputting the water tank temperature demand value into the water tank temperature prediction model for prediction to obtain the required operating time of the heat pump unit; when the time difference between the current moment and the water use time of the next water use plan is reduced to the required operating time, starting the heat pump unit to heat the water in the hot water storage tank.
[0010] In combination with the first aspect, in some embodiments, the input parameters are obtained and input into a water tank temperature prediction model for prediction to obtain a predicted value of the water tank temperature of the hot water storage tank at the time of water use in the next water use plan, including: using the current environmental parameters and the current operating parameters to correct the water tank temperature prediction model; initializing the corrected water tank temperature prediction model with a given initial water tank temperature value to obtain a target prediction model adapted to the current environment and the current operating state of the heat pump water heater; inputting the current time parameters into the target prediction model to predict the change of the water tank temperature of the hot water storage tank to obtain a predicted value of the water tank temperature of the hot water storage tank at the time of water use in the next water use plan.
[0011] In combination with the first aspect, in some implementations, the obtaining of input parameters includes: collecting the current time, current environmental parameters, and current operating parameters of the heat pump water heater; obtaining the next water use time from the next water use plan; and obtaining the current time parameters based on the time difference between the current time and the next water use time.
[0012] In combination with the first aspect, in some embodiments, it also includes: executing the step of obtaining the input parameters multiple times according to a preset step size; after each acquisition of the input parameters, triggering the input of the currently acquired input parameters into the water tank temperature prediction model to re-execute the prediction to update the water tank temperature prediction value.
[0013] In combination with the first aspect, in some embodiments, obtaining the water tank temperature requirement value for the next water use plan includes: obtaining the next water use plan, wherein the next water use plan is generated based on a user setting operation, or is predicted by a machine learning model based on the user's historical water use data; obtaining the next water use set temperature and the next water use duration from the next water use plan; and determining the water tank temperature requirement value based on the next water use set temperature and the next water use duration.
[0014] In a second aspect, a heat pump water heater control device is provided, characterized in that the heat pump water heater comprises a heat pump unit and a hot water storage tank, and the device comprises: a demand acquisition unit, used to acquire a water tank temperature demand value for a next water use plan; an input prediction unit, used to acquire input parameters in response to the next water use plan, and input the input parameters into a water tank temperature prediction model for prediction, so as to obtain a water tank temperature prediction value of the hot water storage tank at the water use time of the next water use plan, wherein the input parameters comprise current environmental parameters, current time parameters and current operating parameters of the heat pump water heater; a comparison control unit, used to compare the water tank temperature prediction value with the water tank temperature demand value, and control the start and stop of the heat pump unit according to the comparison result and the current start and stop state of the heat pump unit, so that at the water use time of the next water use plan, the actual water tank temperature of the hot water storage tank meets the water tank temperature demand value.
[0015] In a third aspect, an embodiment of the present invention provides a heat pump water heater, comprising a memory, a processor, and a computer program stored in the memory and executable on the processor, wherein the processor implements the method described in any one of the embodiments of the first aspect when executing the program.
[0016] One or more technical solutions provided by the embodiments of the present invention achieve at least the following technical effects or advantages:
[0017] The technical solution provided by the embodiment of the present invention obtains the required value of the water tank temperature for the next water use plan; in response to the next water use plan, input parameters are obtained and input into the water tank temperature prediction model for prediction, so as to obtain the predicted value of the water tank temperature of the hot water storage tank at the water use time of the next water use plan; the predicted value of the water tank temperature is compared with the required value of the water tank temperature, and the start and stop of the heat pump unit is controlled according to the comparison result and the current start and stop state of the heat pump unit. By actively predicting the water tank temperature, the start and stop of the heat pump unit is accurately controlled in combination with the current start and stop state of the heat pump unit and the required value of the water tank temperature for the next water use plan of the user, so as to ensure that at the water use time of the next water use plan, the actual water tank temperature of the hot water storage tank just meets the user's next water use demand, and will not be heated for a long time in advance. Therefore, while meeting the user's needs, it can also avoid wasting energy. BRIEF DESCRIPTION OF THE DRAWINGS
[0018] In order to more clearly illustrate the technical solutions in the embodiments of the present invention, the following briefly introduces the drawings required for use in the description of the embodiments. Obviously, the drawings described below are some embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without creative work.
[0019] Figure 1 The flow chart of the heat pump water heater control method provided by the embodiment of the present invention is shown;
[0020] Figure 2 An example of control logic of a heat pump water heater control method according to an embodiment of the present invention is shown;
[0021] Figure 3 The functional modules of the heat pump water heater control device in the embodiment of the present invention are shown;
[0022] Figure 4 A schematic structural diagram of a heat pump water heater in an embodiment of the present invention is shown. DETAILED DESCRIPTION
[0023] In order to make the purpose, technical solution and advantages of the present invention clearer, the technical solution in the embodiment of the present invention will be clearly and completely described below in conjunction with the drawings in the embodiment of the present invention. Obviously, the described embodiment is only a part of the embodiment of the present invention, not all the embodiments. Based on the embodiment of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0024] It should be noted that the terms "first", "second", etc. in the specification and claims of the present invention and the above-mentioned drawings are used to distinguish similar objects, and are not necessarily used to describe a specific order or sequence. It should be understood that the data used in this way can be interchanged where appropriate, so that the embodiments of the present invention described herein can be implemented in an order other than those illustrated or described herein. In addition, the terms "including" and "having" and any variations thereof are intended to cover non-exclusive inclusions, for example, a process, method, system, product or device that includes a series of steps or units is not necessarily limited to those steps or units that are clearly listed, but may include other steps or units that are not clearly listed or inherent to these processes, methods, products or devices.
[0025] The embodiment of the present invention provides a heat pump water heater control method, which is applied to a heat pump water heater including a heat pump unit and a heat storage tank. Figure 1 As shown, the heat pump water heater control method comprises the following steps:
[0026] S101, obtaining the required water tank temperature value for the next water use plan.
[0027] It should be noted that the next water use plan is relative to the current moment or the user's current water use. The next water use plan can be generated based on the user's setting operation, or predicted by the machine learning model based on the user's historical water use data. Among them, the next water use plan includes: the time of the next water use (i.e., the next water use time), the next water use duration, and the next water use set temperature. For example, the next water use plan is: the water use time is at 9 o'clock in the evening, the set temperature is 45°C, and the water use duration is 1 hour. If the next water use plan is generated based on the user's setting operation, the user can set the next water use plan at any time; if the next water use plan is predicted, the next water use plan can be predicted by the machine learning model based on the user's historical water use data after the user's current water use ends.
[0028] S102. In response to the next water use plan, obtain input parameters and input the input parameters into a water tank temperature prediction model for prediction, to obtain a predicted value of the water tank temperature of the heat storage tank at the time of the next water use plan, wherein the input parameters include current environmental parameters, current time parameters and current operating parameters of the heat pump water heater.
[0029] It should be noted that the water tank temperature prediction model in this article is mainly used to predict the change of the water tank temperature of the hot water storage tank under different operating control conditions of the heat pump unit, so as to obtain the predicted value of the water tank temperature of the hot water storage tank at the time of the next water use plan.
[0030] It should be noted that the current environmental parameters include the current ambient temperature and ambient humidity; the current operating parameters of the heat pump water heater include the current inlet water temperature and actual water tank temperature, and the current start / stop state of the heat pump unit. In order to obtain the above parameters, several temperature sensors are arranged on the heat pump water heater to detect the ambient temperature, inlet water temperature, and water tank temperature during the operation of the heat pump unit, and the controller of the heat pump water heater is provided with a clock.
[0031] Below, an example of a water tank temperature prediction model is given as follows:
[0032] According to the energy balance equation of the heat pump water heater tank, that is, the change of the water tank temperature in the heat pump water heater is determined by the heat added by the heat pump unit, the energy difference between the cold water inflow and the hot water outflow, and the heat loss to the environment, the energy balance equation is combined and converted to obtain a standard equation (Formula 1 below) and its general solution (Formula 2 below):
[0033]
[0034]
[0035] in,
[0036] in,
[0037] It should be noted that T t is the predicted value of the water tank temperature at the time of the next water use plan, in K; M is the mass of water, in kg; Cp is the specific heat capacity of water, which is regarded as a constant, in J / kg; Tin is the inlet temperature of the hot water storage tank, in K; Td is the ambient temperature, in K, which can be the ambient dry bulb temperature; The heat provided by the heat pump unit, in W; is the heat lost to the environment, unit is W; is the nominal heating capacity of the heat pump unit, in W; m is the water flow rate, kg / s; T t ′ is the actual water tank temperature at the current moment; UA loss is the total heat transfer coefficient of heat loss, unit is W / K; τ – current time parameter, unit is s; a, b, C, k are coefficients.
[0038] Among them, k is the correction coefficient, which is a correlation formula related to the water tank temperature and the ambient temperature and humidity. It is fitted according to the product performance characteristics of the heat pump water heater and built into the controller of the heat pump water heater for use in calculations.
[0039] It should be understood that the water tank temperature prediction model in this article is not limited to the above examples, but can also be in other forms, such as a digital twin model built on platforms such as MATLAB, Modelica or Trnsys.
[0040] It should be understood that S102 may include the following steps S1021 to S1023 that are performed in sequence:
[0041] S1021: The water tank temperature prediction model is corrected using the current environmental parameters and the current operating parameters to calibrate some model parameters of the water tank temperature prediction model.
[0042] Referring to the above formulas, the current ambient temperature, ambient humidity, water inlet temperature and actual water tank temperature are used to calibrate some model parameters of the water tank temperature prediction model. For example, These model parameters are calibrated, while other model parameters: M, Cp are constants; It is pre-determined and built into the controller of the heat pump water heater for use in calculations. However, for heat pump water heaters with adjustable water flow, the water flow It is also a variable parameter, which is set by user needs or obtained by machine learning.
[0043] An example of a water tank temperature prediction model. The values of coefficients a and b in the water tank temperature prediction model can be determined by calibrating some model parameters.
[0044] S1022: Initializing the modified water tank temperature prediction model by giving an initial value of the water tank temperature, and obtaining a target prediction model adapted to the current environment and the current operating state of the heat pump water heater.
[0045] After completing the correction of the water tank temperature prediction model, the coefficient C of the water tank temperature prediction model can be determined by giving the initial value of the water tank temperature. Therefore, the temperature change trend of the water tank at different times can be obtained through the target prediction model obtained after correction and initialization.
[0046] S1023: Input the current time parameter into the target prediction model to predict the change of the water tank temperature of the hot water storage tank, and obtain the predicted value of the water tank temperature of the hot water storage tank at the water use time of the next water use plan.
[0047] It should be noted that the predicted value of the water tank temperature refers to the value that the water tank temperature of the heat storage tank may reach at the time of the next water use plan according to the current environment and the current operating state of the heat pump water heater.
[0048] It should be understood that in order to obtain the input parameters, it includes: collecting the current time, current environmental parameters, and current operating parameters of the heat pump water heater; obtaining the next water use time from the next water use plan; and obtaining the current time parameter according to the time difference between the current time and the next water use time. Specifically, the current time parameter is equal to the difference between the next water use time and the current time.
[0049] It should be understood that it is possible to trigger the acquisition of input parameters once when the next water use plan is obtained, and input the input parameters into the water tank temperature prediction model for a prediction, so as to obtain the predicted value of the water tank temperature of the hot water storage tank at the water use time of the next water use plan. For example, the next water use plan is obtained at 7:00: the water use time is 9:00 pm, the set temperature is 45°C, and the water use time is 1 hour. The input parameters triggered at 7:00 are specifically: the environmental parameters and the operating parameters of the heat pump water heater at 7:00, and the current time parameter obtained is 2 hours.
[0050] Since the ambient temperature and humidity may change at any time, the actual operating state of the heat pump water heater will also change with the environment, resulting in that over time, the predicted value of the water tank temperature obtained based on the input parameters obtained at the time of the next water use plan may be inaccurate. If the start and stop of the heat pump unit is always controlled based on the predicted value of the water tank temperature, the accuracy will be low. In order to improve the accuracy of controlling the start and stop of the heat pump unit, before reaching the water use time of the next water use plan, it can also include: executing the step of obtaining the input parameters multiple times according to the preset step length, for example: executing the step of obtaining the input parameters once every 10 minutes; after each time the input parameters are obtained, trigger the input of the current input parameters to the water tank temperature prediction model to re-execute the prediction to update the predicted value of the water tank temperature. For example, taking the preset step length of 10 minutes as an example, the input parameters at the time will be obtained once at 7:00, 7:20, 7:30..., and a prediction will be performed based on the input parameters at the time to continuously update the predicted value of the water tank temperature.
[0051] It should be noted that, in order to improve the accuracy of the input parameters, each time the input parameters are obtained, the various current environmental parameters and various current operating parameters obtained may be the average of multiple sampling values of the sensor.
[0052] S103, comparing the predicted water tank temperature value with the water tank temperature requirement value, and controlling the start and stop of the heat pump unit according to the comparison result and the current start and stop state of the heat pump unit, so that at the time of the next water use plan, the actual water tank temperature of the hot water storage tank meets the water tank temperature requirement value.
[0053] The current start / stop state of the heat pump unit indicates whether the heat pump unit is currently in the shutdown state or the startup state. According to the different current start / stop states of the heat pump unit, the logic for controlling the start / stop of the heat pump unit is also different accordingly:
[0054] If the heat pump unit is currently in a shutdown state, that is, the water in the hot water storage tank is in a naturally static state, determine whether the predicted value of the water tank temperature is greater than the first reference temperature, which is determined based on the water tank temperature demand value and the first preset threshold value; if yes, control the heat pump unit to remain in a shutdown state before the water use time of the next water use plan; if no, determine the required operating time of the heat pump unit based on the water tank temperature demand value, and control the next start-up time of the heat pump unit based on the required operating time, so that at the water use time of the next water use plan, the actual water tank temperature of the hot water storage tank meets the water tank temperature demand value. Thus, by controlling the heat pump unit to start the next operation at a reasonable time point, the water in the hot water storage tank is heated to meet the water tank temperature demand value just at the water use time of the next water use plan.
[0055] If the heat pump unit is currently in the startup state, that is, the water in the hot water storage tank is in the state of being heated, it is determined whether the predicted value of the water tank temperature is less than the second reference temperature, and the second reference temperature is determined according to the water tank temperature demand value and the second preset threshold value; if it is, the heat pump unit is controlled to remain in the startup state before the water use time of the next water use plan; if not, the heat pump unit is controlled to stop, and the required operating time for starting the heat pump unit is determined according to the water tank temperature demand value, and the time point of the next startup of the heat pump unit is controlled according to the required operating time, so that at the water use time of the next water use plan, the actual water tank temperature of the hot water storage tank meets the water tank temperature demand value. Thus, by controlling the heat pump unit to restart at a reasonable time point, the water in the hot water storage tank is heated to meet the water tank temperature demand value just at the water use time of the next water use plan.
[0056] It should be noted that the actual water tank temperature of the hot water tank meets the water tank temperature requirement value, which may mean that the difference between the actual water tank temperature at the next water use time and the water tank temperature requirement value is less than the preset difference threshold, or the actual water tank temperature at the next water use time is equal to the water tank temperature requirement value, or is slightly greater than the water tank temperature requirement value.
[0057] In the specific implementation process, the first reference temperature is the sum of the water tank temperature requirement value and the first preset threshold, and the second reference temperature is the sum of the water tank temperature requirement value and the second preset threshold, wherein the first preset threshold and the second preset threshold can be the same or different values.
[0058] The next start-up time of the heat pump unit is controlled according to the required operating time, including: inputting the water tank temperature demand value into the water tank temperature prediction model for prediction to obtain the required operating time of the heat pump unit; when the time difference between the current moment and the water use time is reduced to the required operating time, starting the heat pump unit to heat the water in the hot water storage tank, so that from the current moment to the water use time of the next water use plan (that is, the next water use time), the actual water tank temperature of the hot water storage tank meets the water tank temperature demand value.
[0059] Refer to the above formula (2), for example: the first reference temperature is expressed as T_req+δ1, and the second reference temperature is expressed as T_req+δ2. T_req is the required value of the water tank temperature, and δ1 and δ2 are the first preset threshold and the second preset threshold, respectively. Then, if the heat pump unit is currently in the shutdown state, let Tt=T_req+δ1 and then substitute it into formula (2); if the heat pump unit is currently in the startup state, let Tt=T_req+δ2 and then substitute it into formula (2), and the required operating time Δτ of the heat pump unit in the current start-stop state can be obtained, wherein the required operating time Δτ refers to: in order to make the actual water tank temperature at the next water use time equal to the water tank temperature demand value, the total operating time of the heat pump unit needs to be operated. As the current time changes, the time difference τ2-τ1 between the current time τ1 and the next water use time τ2 will continue to decrease. When the time difference decreases to τ1-τ2=Δτ, the heat pump unit is started to heat the water in the hot water storage tank. Otherwise, the heat pump unit is kept in a shutdown state. In this way, the heat pump water heater can meet the user's next water demand without wasting energy.
[0060] In order to facilitate those skilled in the art to understand the technical solution provided by the embodiment of the present invention, taking the first reference temperature as T_req+δ1 and the second reference temperature as T_req+δ2 as an example, Figure 2 A control logic of the heat pump water heater control method in an embodiment of the present invention is given:
[0061] Step S1: Read the next user plan: the next water use time, the next water use duration, and the next water use set temperature;
[0062] Step S2: obtaining the current time and various sensor parameters at the current time, such as: ambient temperature, ambient humidity, actual water tank temperature and inlet water temperature;
[0063] Step S3: using various sensing parameters at the current moment to correct some model parameters of the water tank temperature prediction model, and initializing the corrected water tank temperature prediction model based on the initial value of the water tank temperature, to obtain a target prediction model adapted to the current environment and the current operating state of the heat pump water heater;
[0064] Step S4: taking the time difference between the next water use time and the time when the next user plan is read as the current time parameter;
[0065] Step S5: Determine whether the heat pump unit is currently in the startup state or the shutdown state; if the heat pump unit is currently in the shutdown state, proceed to steps S6 to S7; if the heat pump unit is currently in the startup state, jump to steps S9 to S10;
[0066] Step S6: input the current time parameter into the target prediction model, and obtain the predicted value of the water tank temperature at the next water use time T_pred_off through the target prediction model;
[0067] Step S7: Determine whether T_pred_off>T_req+δ1 is satisfied. If so, proceed to step S8. If not, jump to steps S12-S13.
[0068] Step S8: Before the next water use time, the heat pump water heater remains in the shutdown state;
[0069] Step S9: input the current time parameter into the target prediction model, and obtain the predicted value of the water tank temperature at the next water use time T_pred_on through the target prediction model;
[0070] Step S10: Determine whether T_pred_on<T_req+δ2 is satisfied, if so, proceed to step S11, if not, jump to steps S12-S13;
[0071] Step S11: before the next water use time, the heat pump water heater remains in the start-up state;
[0072] Step S12: Let Tt=T_req+δ (specifically δ1 or δ2) to obtain the required operating time Δτ of the heat pump unit;
[0073] Step S13: Determine whether the time difference τ2-τ1 between the current time τ1 and the next water use time τ2 is reduced to τ2-τ1=Δτ. If so, proceed to step S14: restart the heat pump unit and continue to run for the required operating time Δτ, otherwise keep the heat pump off.
[0074] Based on the same inventive concept, an embodiment of the present invention provides a heat pump water heater control device, the heat pump water heater includes a heat pump unit and a hot water storage tank, Figure 3 As shown, the heat pump water heater control device includes:
[0075] The demand acquisition unit 301 is used to obtain the water tank temperature demand value of the next water use plan;
[0076] An input prediction unit 302 is used to obtain input parameters in response to the next water use plan, and input the input parameters into a water tank temperature prediction model for prediction, to obtain a predicted value of the water tank temperature of the hot water storage tank at the water use time of the next water use plan, wherein the input parameters include current environmental parameters, current time parameters and current operating parameters of the heat pump water heater;
[0077] The comparison control unit 303 is used to compare the predicted water tank temperature value with the water tank temperature requirement value, and control the start and stop of the heat pump unit according to the comparison result and the current start and stop status of the heat pump unit, so that at the time of the next water use plan, the actual water tank temperature of the hot water storage tank meets the water tank temperature requirement value.
[0078] It can be understood that the comparison control unit 303 includes:
[0079] A first judgment subunit is used to judge whether the predicted value of the water tank temperature is greater than a first reference temperature if the heat pump unit is currently in a shutdown state, wherein the first reference temperature is determined according to the required value of the water tank temperature and a first preset threshold value;
[0080] A shutdown holding subunit, for controlling the heat pump unit to remain in a shutdown state before the water use time of the next water use plan if yes;
[0081] The start-stop control subunit is used to determine the required operating time of the heat pump unit according to the water tank temperature requirement value if not, and control the time point of the next start-up of the heat pump unit according to the required operating time, so that at the time of the next water use plan, the actual water tank temperature of the hot water storage tank meets the water tank temperature requirement value.
[0082] It can be understood that the comparison control unit 303 also includes:
[0083] A second judgment subunit is used to judge whether the predicted value of the water tank temperature is less than a second reference temperature if the heat pump unit is currently in a startup state, wherein the second reference temperature is determined according to the required value of the water tank temperature and a second preset threshold value;
[0084] a start-up and maintenance subunit, for controlling the heat pump unit to remain in a start-up state before the water use time of the next water use plan if yes;
[0085] The start-stop control subunit is also used to control the heat pump unit to shut down if no, and determine the required operating time of the heat pump unit according to the water tank temperature requirement value, and control the time point of the next start-up of the heat pump unit according to the required operating time, so that at the time of the next water use plan, the actual water tank temperature of the hot water storage tank meets the water tank temperature requirement value.
[0086] It can be understood that the start-stop control subunit is specifically used to: input the water tank temperature demand value into the water tank temperature prediction model for prediction, so as to obtain the required operating time of the heat pump unit; when the time difference between the current moment and the water use time of the next water use plan is reduced to the required operating time, start the heat pump unit to heat the water in the hot water storage tank.
[0087] It can be understood that the input prediction unit 302 includes:
[0088] A correction subunit, used to correct the water tank temperature prediction model using the current environmental parameters and the current operating parameters;
[0089] An initialization subunit, used to initialize the modified water tank temperature prediction model by giving an initial value of the water tank temperature, so as to obtain a target prediction model adapted to the current environment and the current operating state of the heat pump water heater;
[0090] The prediction subunit is used to input the current time parameter into the target prediction model to predict the change of the water tank temperature of the hot water storage tank, and obtain the predicted value of the water tank temperature of the hot water storage tank at the water use time of the next water use plan.
[0091] It can be understood that the input subunit of the input prediction unit 302 is specifically used to: collect the current time, current environmental parameters, and current operating parameters of the heat pump water heater; obtain the next water use time from the next water use plan; and obtain the current time parameter based on the time difference between the current time and the next water use time.
[0092] It can be understood that the device also includes an updating unit, which is used to: execute the step of obtaining the input parameters multiple times according to a preset step size; after each acquisition of the input parameters, trigger the input of the currently acquired input parameters into the water tank temperature prediction model to re-execute the prediction to update the water tank temperature prediction value.
[0093] It can be understood that the demand acquisition unit 301 is specifically used to: obtain the next water use plan, which is generated based on the user's setting operation, or predicted by the machine learning model based on the user's historical water use data; obtain the next water use set temperature and the next water use duration from the next water use plan; determine the water tank temperature requirement value based on the next water use set temperature and the next water use duration.
[0094] The above-mentioned heat pump water heater control device is a device for implementing the above-mentioned heat pump water heater control method. For more implementation details, please refer to the description in the above-mentioned heat pump water heater control method embodiment. For the sake of brevity of the specification, they will not be repeated here.
[0095] Based on the same inventive concept, the embodiment of the present invention provides a heat pump water heater, referring to Figure 4 As shown, the heat pump water heater control includes: a memory 404, a processor 402, and a computer program stored in the memory 404 and executable on the processor 402. When the processor 402 executes the program, any implementation method of the heat pump water heater control method is implemented.
[0096] Among them, Figure 4 In the embodiment of the present invention, a bus architecture (represented by bus 400) is shown, which may include any number of interconnected buses and bridges, and bus 400 links various circuits including one or more processors represented by processor 402 and memory represented by memory 404. Bus 400 may also link various other circuits such as peripherals, voltage regulators, and power management circuits, which are well known in the art and are therefore not further described herein. Bus interface 405 provides an interface between bus 400 and receiver 401 and transmitter 403. Receiver 401 and transmitter 403 may be the same element, namely a transceiver, providing a unit for communicating with various other devices over a transmission medium. Processor 402 is responsible for managing bus 400 and general processing, while memory 404 may be used to store data used by processor 402 when performing operations.
[0097] The functions described herein may be implemented in hardware, software executed by a processor, firmware, or any combination thereof. If implemented in software executed by a processor, the functions may be stored as one or more instructions or codes on a computer-readable medium or transmitted via a computer-readable medium. Other examples and implementations are within the scope and spirit of the present invention and the appended claims. For example, due to the nature of software, the functions described above may be implemented using software executed by a processor, hardware, firmware, hard wiring, or a combination of any of these. In addition, each functional unit may be integrated into a processing unit, each unit may exist physically separately, or two or more units may be integrated into one unit.
[0098] In the several embodiments provided in this application, it should be understood that the disclosed technical content can be implemented in other ways. Among them, the device embodiments described above are only schematic. For example, the division of the units can be a logical function division. There may be other division methods in actual implementation. For example, multiple units or components can be combined or integrated into another system, or some features can be ignored or not executed. Another point is that the mutual coupling or direct coupling or communication connection shown or discussed can be through some interfaces, indirect coupling or communication connection of units or modules, which can be electrical or other forms.
[0099] The units described as separate components may or may not be physically separated, and the components of the control device may or may not be physical units, that is, they may be located in one place or distributed in multiple units. Some or all of the units may be selected according to actual needs to achieve the purpose of the present embodiment.
[0100] If the integrated unit is implemented in the form of a software functional unit and sold or used as an independent product, it can be stored in a computer-readable storage medium. Based on this understanding, the technical solution of the present invention, in essence, or the part that contributes to the prior art, or all or part of the technical solution can be embodied in the form of a software product, and the computer software product is stored in a storage medium, including a number of instructions for a computer device (which can be a personal computer, a server or a network device, etc.) to perform all or part of the steps of the method described in each embodiment of the present invention. The aforementioned storage medium includes: U disk, read-only memory (ROM, Read-Only Memory), random access memory (RAM, Random Access Memory), mobile hard disk, magnetic disk or optical disk and other media that can store program codes.
[0101] The above description is only an embodiment of the present invention and is not intended to limit the present invention. For those skilled in the art, the present invention may have various modifications and variations. Any modification, equivalent substitution, improvement, etc. made within the spirit and principle of the present invention shall be included in the scope of the claims of the present invention.
Claims
1. A heat pump water heater control method, characterized in that: The heat pump water heater comprises a heat pump unit and a hot water storage tank, and the method comprises: Get the required water tank temperature value for the next water use plan; In response to the next water use plan, input parameters are obtained, and the input parameters are input into a water tank temperature prediction model for prediction, so as to obtain a predicted value of the water tank temperature of the heat storage tank at the water use time of the next water use plan, wherein the input parameters include current environmental parameters, current time parameters and current operating parameters of the heat pump water heater; The predicted water tank temperature value is compared with the required water tank temperature value, and the start and stop of the heat pump unit is controlled according to the comparison result and the current start and stop status of the heat pump unit, so that at the time of the next water use plan, the actual water tank temperature of the hot water storage tank meets the required water tank temperature value.
2. The method according to claim 1, characterized in that The step of comparing the predicted water tank temperature value with the required water tank temperature value, and controlling the start and stop of the heat pump unit according to the comparison result and the current start and stop state of the heat pump unit, includes: If the heat pump unit is currently in a shutdown state, determining whether the predicted value of the water tank temperature is greater than a first reference temperature, wherein the first reference temperature is determined based on the required value of the water tank temperature and a first preset threshold value; If yes, controlling the heat pump unit to remain in a shutdown state before the water use time of the next water use plan; If not, the required operating time of the heat pump unit is determined according to the water tank temperature requirement value, and the time point of the next startup of the heat pump unit is controlled according to the required operating time, so that at the time of the next water use plan, the actual water tank temperature of the hot water storage tank meets the water tank temperature requirement value.
3. The method according to claim 2, characterized in that The step of comparing the predicted value of the water tank temperature with the required value of the water tank temperature and controlling the start and stop of the heat pump unit before the next water use according to the comparison result further includes: If the heat pump unit is currently in a startup state, determining whether the predicted value of the water tank temperature is less than a second reference temperature, where the second reference temperature is determined based on the required value of the water tank temperature and a second preset threshold value; If yes, controlling the heat pump unit to remain in a startup state before the water use time of the next water use plan; If not, the heat pump unit is controlled to shut down, and the required operating time of the heat pump unit is determined according to the water tank temperature requirement value, and the next startup time of the heat pump unit is controlled according to the required operating time, so that at the time of the next water use plan, the actual water tank temperature of the hot water storage tank meets the water tank temperature requirement value.
4. The method according to claim 2 or 3, characterized in that The step of controlling the time point of the next startup of the heat pump unit according to the required operating time includes: Inputting the water tank temperature demand value into the water tank temperature prediction model for prediction to obtain the required operating time of the heat pump unit; When the time difference between the current time and the water use time of the next water use plan is reduced to the required operating time, the heat pump unit is started to heat the water in the hot water storage tank.
5. The method according to claim 1, characterized in that The step of obtaining input parameters and inputting the input parameters into a water tank temperature prediction model for prediction to obtain a predicted value of the water tank temperature of the hot water storage tank at the water use time of the next water use plan includes: Using the current environmental parameters and the current operating parameters to modify the water tank temperature prediction model; Initializing the modified water tank temperature prediction model by giving an initial value of the water tank temperature, and obtaining a target prediction model adapted to the current environment and the current operating state of the heat pump water heater; The current time parameter is input into the target prediction model to predict the change of the water tank temperature of the hot water storage tank, and obtain the predicted value of the water tank temperature of the hot water storage tank at the water use time of the next water use plan.
6. The method according to claim 5, characterized in that The obtaining of input parameters includes: Collecting the current time, current environmental parameters, and current operating parameters of the heat pump water heater; Obtaining the next water use time from the next water use plan; The current time parameter is obtained according to the time difference between the current time and the next water use time.
7. The method according to claim 1, characterized in that Also includes: Execute the step of obtaining the input parameters multiple times according to a preset step length; After each acquisition of input parameters, the input parameters currently acquired are input into the water tank temperature prediction model to re-execute the prediction to update the water tank temperature prediction value.
8. The method according to claim 1, characterized in that The step of obtaining the required water tank temperature value for the next water use plan includes: Obtaining a next water use plan, where the next water use plan is generated based on a user setting operation or is predicted by a machine learning model based on the user's historical water use data; Obtaining the next water use set temperature and the next water use duration from the next water use plan; The water tank temperature requirement value is determined according to the next water use set temperature and the next water use duration.
9. A heat pump water heater control device, characterized in that: The heat pump water heater comprises a heat pump unit and a hot water storage tank, and the device comprises: A demand acquisition unit, used to obtain the water tank temperature demand value for the next water use plan; An input prediction unit is used to obtain input parameters in response to the next water use plan, and input the input parameters into a water tank temperature prediction model for prediction, so as to obtain a predicted value of the water tank temperature of the hot water storage tank at the water use time of the next water use plan, wherein the input parameters include current environmental parameters, current time parameters and current operating parameters of the heat pump water heater; A comparison control unit is used to compare the water tank temperature prediction value with the water tank temperature requirement value, and control the start and stop of the heat pump unit according to the comparison result and the current start and stop state of the heat pump unit, so that at the time of the next water use plan, the actual water tank temperature of the hot water storage tank meets the water tank temperature requirement value.
10. A heat pump water heater, characterized in that: The method comprises a memory, a processor and a computer program stored in the memory and executable on the processor, wherein the processor implements the method according to any one of claims 1 to 8 when executing the program.
Citation Information
Patent Citations
Control method and device of heat pump water heater and heat pump water heater
CN104896733A
Automatic control method for air energy water heater
CN105371498A
Solar energy heat gain estimation and control method for heat pump and solar water heater combined system
CN106123360A
Control method and device used for water heater as well as water heater
CN111473523A
Heat pump type hot water supply system
JP2015010773A