Split type ascending type movable formwork
By setting up a steel bar binding trench and a lifting trolley behind the upward moving mold frame, the steel bar cage is fully lifted into the mold, and combined with the casting, health and tensioning processes, the problems of low construction efficiency and high cost in the existing technology are solved. Improve construction efficiency and beam quality.
Patent Information
- Application Number
- CN202411081790.0
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-08
- Publication Date
- 2024-11-26
AI Technical Summary
The existing upstream mobile formwork frames are inefficient in construction of high-speed rail, insufficient labor utilization, long construction cycle, low craft efficiency and high cost, especially in mountainous areas when construction conditions are harsh.
A split-type upstream mobile mold frame is designed, using the steel bar tying tread behind the mold frame for the overall steel cage binding, and equipped with a door machine and a lifting truck to realize the overall lifting of the steel cage into the mold, combining concrete pouring and health care. , the tensioning process is carried out to simplify the construction process.
It improves construction efficiency, shortens construction period, reduces labor intensity and construction costs, and achieves beam-making quality similar to cast-in-place beam factory.
Smart Images

Figure CN119021097A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of upward movable mold frames, and in particular to a split upward movable mold frame. Background Art
[0002] Bridges are an important part of high-speed rail lines, accounting for more than 50%. How to quickly make and erect beams is the key to ensuring the construction period. The mobile formwork bridge-building machine is a construction machine that comes with its own formwork and uses abutments or piers as supports to cast bridges on site. Among them, the upward mobile formwork is not restricted by the clearance under the bridge during construction and has been widely used in bridge construction.
[0003] At present, the steel cages of the upward mobile formwork are pre-tied in the beam yard and then transported to the bridge construction site. As the high-speed rail construction advances towards the mountainous areas, the construction of the beam yard is becoming more and more difficult; and for construction projects with less than 150 beam holes, the construction of the beam yard is not economical. In addition, the existing mobile formwork bridge-building machine must carry out several construction processes in sequence for the in-situ cast-in-place construction of a single-hole bridge. Different types of work have a long waiting time, the labor force is not fully utilized, the construction period is long, the work efficiency is low, and the construction cost is high. Summary of the invention
[0004] The present invention provides a split upward mobile formwork, which is used to tie the steel cage as a whole on a steel cage tying platform behind the mobile formwork, and is equipped with a gantry crane to cooperate with the lifting trolley on the mobile formwork to hoist the steel cage as a whole into the mold, so that the tying of the steel cage as a whole and the pouring, curing and tensioning processes of the concrete bridge are carried out simultaneously, with high construction efficiency and short construction period.
[0005] The technical solution adopted to achieve the above-mentioned purpose of the present invention is:
[0006] A split upward movable formwork, at least comprising an upward movable formwork body, a steel bar binding platform is arranged on the bridge behind the upward movable formwork body, the steel bar binding platform comprises a platform body, a platform running mechanism and a gantry, the platform body comprises a bottom mold frame, a side mold frame and an inner mold frame for supporting the bridge deck steel bars, the inner mold frame is fixedly connected to the bottom mold frame, two side mold frames are arranged and symmetrically connected to the two sides of the bottom mold frame, the structure of the platform body is adapted to the structure of a section of the bridge box girder, so that the steel bar cage is tied as a whole on the platform body; the platform running mechanism is installed at the bottom of the bottom mold frame, and is driven by the platform running mechanism The gantry body runs on the bridge, and the gantry crane is installed on the side mold frame and runs longitudinally along the side mold frame; the bottom mold frame is connected to the outside of the outer mold frame with a longitudinal support box beam for supporting the outer mold frame, and a plurality of frame diagonal support cylinders are distributed and connected between the longitudinal support box beam and the outer mold frame; a plurality of spiral column feet with adjustable lengths and a plurality of gantry lifting cylinders are distributed at the bottom of the bottom mold frame; the front lifting trolley and the rear lifting trolley are installed on the rear guide beam and the main beam, and the front lifting trolley and the rear lifting trolley run longitudinally on the rear guide beam and the main beam, and the front lifting trolley and the rear lifting trolley are detachably connected with lifting equipment to cooperate with the gantry crane to lift the entire steel cage into the mold.
[0007] The cross section of the longitudinal support box beam is a right-angle trapezoid, and the oblique side of the longitudinal support box beam is supported on the outer side of the inner mold frame.
[0008] Two gantry cranes are movably installed on the side formwork frame, one of which is a 70t gantry crane for assisting in lifting the entire steel cage, and the other is a 10t gantry crane for assisting in lifting the tied steel bars.
[0009] An opening for parking a steel bar transport vehicle is reserved at the rear end of the bottom mold frame.
[0010] The hoisting device includes a main hanger, hanging points distributedly connected to the front and rear ends of the main hanger for connecting with the front lifting trolley, the rear lifting trolley and the gantry crane, and hangings distributedly connected under the lifting frame; the hanging points are connected to the main hanger through pins, and the hangings are integrally connected to the steel cage, so that the steel cage is hoisted as a whole to the outer mold hanging assembly.
[0011] The upward movable formwork body includes a leg assembly, which is installed at the bottom of the main beam assembly and supported on the bridge and the pier. The leg assembly includes a front leg, a middle leg, a rear main leg and a rear auxiliary leg. The four legs are installed at the front end of the main beam, the middle of the main beam, the rear end of the main beam and the front end of the rear guide beam in sequence.
[0012] The front leg comprises an upper roller running mechanism, an upper cross beam of the front leg, a front leg column, a front leg lifting cylinder, a lower cross beam of the front leg, a front leg transverse cylinder, a front leg transverse beam and a front leg fixed cross beam connected in sequence, the upper roller running mechanism is connected to the front leg running track and the front leg hanging wheel track provided on the main beam assembly, and drives the mobile mold frame to move forward as a whole; the front leg column comprises an upper column of the front leg and a lower column of the front leg, and the upper column of the front leg and the lower column of the front leg are connected by a pin shaft and a cotter pin; the front leg lifting cylinder passes through the lower cross beam of the front leg and is connected to the front leg The lower cross beam is fixedly connected, and the two ends of the front outrigger lifting cylinder are respectively fixedly connected to the front outrigger column and the front outrigger transverse beam; the front outrigger transverse beam is slidably connected to the front outrigger fixed cross beam, and the two ends of the front outrigger transverse cylinder are respectively connected to the front outrigger transverse beam and the front outrigger fixed cross beam, and the front outrigger transverse cylinder is extended and retracted to drive the front outrigger transverse beam to move laterally along the front outrigger fixed cross beam, and the front outrigger fixed cross beam is detachably anchored to the bridge pier through the front outrigger anchor rod; the upper cross beam of the front outrigger is longitudinally extended and connected to a support beam, and a front outrigger diagonal support cylinder is connected between the support beam and the front outrigger column;
[0013] The middle outrigger comprises a middle outrigger hinge seat, a middle outrigger lifting column, a middle outrigger transverse beam, a middle outrigger transverse track and a middle outrigger rotating cylinder, wherein a hydraulic outrigger is installed in the middle outrigger lifting column, the middle outrigger lifting column is connected to the lower part of the main beam through the middle outrigger hinge seat, the two ends of the middle outrigger rotating cylinder are respectively connected to the main beam and the middle outrigger lifting column through the middle outrigger upper hinge seat and the middle outrigger lower hinge seat, the middle outrigger rotating cylinder is extended and retracted, driving the middle outrigger to rotate around the main beam; the middle outrigger transverse beam is fixedly connected to the bottom of the middle outrigger lifting column, the middle outrigger transverse beam is slidably connected to the middle outrigger transverse track, and the middle outrigger transverse cylinder is connected between the two, the middle outrigger transverse cylinder is extended and retracted, driving the middle outrigger transverse beam to move transversely along the middle outrigger transverse track;
[0014] The rear main leg comprises a rear main leg hinge seat, a rear main leg column, a rear main leg lifting cylinder, a rear main leg pad and a rear main leg rotating cylinder, wherein the rear main leg column is connected to the lower part of the main beam through the rear main leg hinge seat, and the two ends of the rear main leg rotating cylinder are respectively connected to the main beam and the rear main leg column through the rear main leg upper hinge seat and the rear main leg lower hinge seat, and the rear main leg rotating cylinder is extended and retracted to drive the rear main leg to rotate around the main beam; the rear main leg lifting cylinder is connected to the bottom of the rear main leg column, and the rear main leg pad is connected to the bottom of the rear main leg lifting cylinder through a fine-tuning screw;
[0015] The rear auxiliary outrigger has an O-shaped structure as a whole, including C-shaped outrigger columns symmetrically connected to both sides of the rear guide beam, a rear auxiliary outrigger lifting cylinder, a rear auxiliary outrigger running mechanism, and a rear auxiliary outrigger running track, wherein the C-shaped outrigger column is composed of multiple sections of columns connected by pins and cotter pins, the top of the C-shaped outrigger column is fixedly connected to the main beam, the rear auxiliary outrigger running track is installed on the bridge beam surface, the rear auxiliary outrigger lifting cylinder and the rear auxiliary outrigger running mechanism are connected to the bottom of the C-shaped outrigger column in sequence, the rear auxiliary outrigger running mechanism is installed on the rear auxiliary outrigger running track, and the rear auxiliary outrigger running mechanism is driven by a reducer to move the rear auxiliary outrigger running mechanism along the rear auxiliary outrigger running track.
[0016] The upward movable formwork body includes an outer formwork hanging assembly, on which an outer formwork is installed. The outer formwork hanging assembly is hung below the cantilever beams on both sides of the main beam, so that the outer formwork is hung below the main beam; the outer formwork hanging assembly includes multiple groups of C-type hangings distributed on the main beam, wherein the number of groups of C-type hangings corresponds to the number of groups of cantilever beams, and each group of C-type hangings includes two C-type hangings, and the two C-type hangings are respectively installed on the cantilever beams through a transverse movement mechanism and open and close relatively; the outer formwork is connected to the C-type hanging through a support assembly, and the outer formwork is spliced by a left outer formwork and a right outer formwork, and the left outer formwork and the right outer formwork are respectively connected to all left C-type hangings and right C-type hangings through the support assembly, and the C-type hanging opens and closes, driving the left outer formwork and the right outer formwork to open and close; a C-type hanging hanger is detachably connected between the cantilever beam and the bottom of the C-type hanging.
[0017] The upward movable formwork body also includes an attached vibrator, a concrete hydraulic placing machine, a tensioning auxiliary tooling and an electric push-pull canopy, and a ladder platform is installed on the steel bar binding stand and the upward movable formwork body.
[0018] The upward movable formwork body also includes a spray curing assembly, which includes a spray curing system for formed box beams and a spray curing system for cast-in-place beam surfaces.
[0019] The upward movable formwork body comprises a main beam assembly, which comprises a front guide beam, a main beam and a rear guide beam, and the main beam assembly adopts a double longitudinal beam structure.
[0020] Compared with the prior art, the technical solution provided by the present invention has the following advantages: (1) In the present invention, the steel cage is tied as a whole on the steel cage tying platform behind the mobile formwork, and a gantry crane is equipped to cooperate with the lifting trolley on the mobile formwork to lift the steel cage as a whole into the mold, so that the tying of the steel cage as a whole and the pouring, curing and tensioning processes of the concrete bridge are carried out simultaneously, with high construction efficiency and short construction period.
[0021] (2) In the present invention, the front outrigger running mechanism adopts the form of an upper roller, and the front outrigger running mechanism and the rear auxiliary outrigger running mechanism both adopt a reducer-driven roller structure, so that each outrigger can be installed by itself through a hole, which reduces the investment in auxiliary equipment and reduces labor intensity; the front outrigger column can be extended and retracted by the front outrigger lifting cylinder, which can lower (raise) the height of the whole machine, making it convenient for the equipment to make the beam at the end span; the middle outrigger and the rear main outrigger are hydraulically rotated, which is convenient for the entire steel cage to pass through the mold; the front outrigger and the middle outrigger can be moved laterally by the cylinder, which is convenient for the mold frame to pass through small curves on the plane; the C-type suspension is opened and closed by the hydraulic lateral movement cylinder, which is simple to operate; the lifting and lowering, lateral movement of the whole machine and the opening and closing of the C-type suspension are all hydraulically controlled, and the movement is smooth, safe and reliable.
[0022] (3) In the present invention, tensioning auxiliary tooling is provided on the front legs and the middle legs, and auxiliary lifting tooling for the reverse transportation of the inner mold is also provided on the front legs. In addition, the C-type hanging hanger is a through-cylinder stretching hanger, which can quickly adjust the posture of the entire mold bed, greatly reducing the labor intensity of the mobile mold frame; by integrating the spray maintenance assembly, concrete hydraulic placing machine, attached vibrator and electric push-pull canopy, the quality of the mobile mold frame beam manufacturing reaches the effect of a prefabricated beam factory. BRIEF DESCRIPTION OF THE DRAWINGS
[0023] Figure 1 It is an overall side view of the split upward movable mold frame of the present invention;
[0024] Figure 2 It is a side view of the steel bar binding stand in the present invention;
[0025] Figure 3 This is a front view of the steel bar binding stand in the present invention;
[0026] Figure 4 It is a top view of the steel bar binding stand in the present invention;
[0027] Figure 5 Schematic diagram of the structure of the upward movable mold frame in the present invention, (a) is a side view, (b) is a top view;
[0028] Figure 6 Schematic diagram of the structure of the main beam assembly in the present invention, (a) is a side view, (b) is a top view;
[0029] Figure 7 Schematic diagram of the structure of the front support leg in the present invention, (a) is a side view, (b) is a top view;
[0030] Figure 8 The front view of the front leg in the present invention when it is in the final stride position
[0031] Fig. 9 A side view of the middle leg of the present invention being lowered and retracted;
[0032] Fig.10 It is a front view of the present invention when the middle leg is lowered;
[0033] Fig.11 It is a side view of the rear main support leg of the present invention being lowered and retracted;
[0034] Fig.12 This is a front view of the present invention when the rear main support leg is lowered;
[0035] Fig.13 is a side view of the rear auxiliary support leg of the present invention;
[0036] Fig.14 It is a front view of the rear auxiliary supporting leg in the present invention;
[0037] Fig.15 It is a side view of the outer mold hanging assembly of the present invention;
[0038] Fig.16 It is a front view of the outer mold hanging assembly in the mold opening and through-hole state of the present invention;
[0039] Fig.17 It is a front view of the outer mold hanging assembly in the mold closing casting state in the present invention;
[0040] Fig.18 This is a front view of the connection of the front lifting trolley, the sling and the steel cage in the present invention;
[0041] Fig.19 Schematic diagram of the structure of the sling in the present invention, (a) is a side view, (b) is a top view;
[0042] Fig. 20 It is a schematic diagram of the arrangement of the water tank in the spray curing assembly of the present invention;
[0043] Fig.21 Schematic diagram of the arrangement of the spray head B and the spray head C in the spray curing assembly of the present invention;
[0044] Fig. 22 This is a front view of the arrangement of the cast-in-place beam surface spraying and curing system of the present invention;
[0045] Fig.23 It is a front view of the arrangement of the spray curing system for the formed box beam in the present invention;
[0046] Fig.24 The construction diagram of the split upward movable formwork in the present invention is shown in FIG. Figure 1 ;
[0047] Fig.25 The construction diagram of the split upward movable formwork in the present invention is shown in FIG. Figure 2 ;
[0048] Fig.26 The construction diagram of the split upward movable formwork in the present invention is shown in FIG. Figure 3 ;
[0049] Fig. 27 The construction diagram of the split upward movable formwork in the present invention is shown in FIG. Figure 4 ;
[0050] Fig.28 The construction diagram of the split upward movable formwork in the present invention is shown in FIG. Figure 5 ;
[0051] Fig.29 The construction diagram of the split upward movable formwork in the present invention is shown in FIG. Figure 6 ;
[0052] Fig.30 The construction diagram of the split upward movable formwork in the present invention is shown in FIG. Figure 7 ;
[0053] Fig.31 It is a schematic diagram of the reverse transportation construction of the inner formwork in the present invention;
[0054] Fig.32 The construction diagram of the split upward movable formwork in the present invention is shown in FIG. Figure 8 ;
[0055] Fig.33 The construction diagram of the split upward movable formwork in the present invention is shown in FIG. Figure 9 ;
[0056] Fig.34 The construction diagram of the split upward movable formwork in the present invention is shown in FIG. Figure 10 ;
[0057] Fig.35 The construction diagram of the split upward movable formwork in the present invention is shown in FIG. Figure 10 one;
[0058] Fig.36 It is the first span station diagram of the split upward movable formwork in the present invention;
[0059] Fig.37 It is a side view of the temporary support of the first hole in the present invention;
[0060] Fig.38 This is a front view of the temporary support for the first hole in the present invention;
[0061] Fig.39 A top view of the temporary support for the first hole in the present invention;
[0062] In the figure: 100-bridge, 1001-just cast box girder, 200-bridge pier, 2001-1# pier, 2002-2# pier, 300-external formwork, 3001-left external formwork, 3002-right external formwork, 400-inner formwork, 500-reinforcement cage, 5001-reinforcement cage bottom plate and side plates, 5002-reinforcement cage top plate;
[0063] 11- platform body, 111- bottom mold frame, 112- side mold frame, 113- inner mold frame, 12- platform running mechanism, 121- platform running track, 13- gantry, 131- front gantry, 1311- gantry running mechanism, 1312- gantry longitudinal running track, 1313- reinforced longitudinal beam, 132- rear gantry, 14- longitudinal supporting box beam, 15- frame diagonal support cylinder, 16- spiral column foot, 17- platform lifting cylinder;
[0064] 2-main beam assembly, 21-front guide beam, 22-main beam, 221-main cross beam, 23-rear guide beam, 231-rear cross beam, 24-main cantilever beam, 25-front outrigger running track, 26-front outrigger hanging wheel track, 27-hoisting track;
[0065] 31-front outrigger, 311-front outrigger running mechanism, 312-front outrigger upper crossbeam, 313-front outrigger column, 3131-front outrigger upper column, 3132-front outrigger lower column, 3133-split pin, 314-front outrigger lifting cylinder, 315-front outrigger lower crossbeam, 316-front outrigger transverse cylinder, 317-front outrigger transverse beam, 318-front outrigger fixed crossbeam, 319-front outrigger diagonal support cylinder;
[0066] 32-middle outrigger, 321-middle outrigger hinge seat, 322-middle outrigger lifting column, 323-middle outrigger transverse beam, 324-middle outrigger transverse track, 325-middle outrigger rotating cylinder, 326-middle outrigger upper hinge seat, 327-middle outrigger lower hinge seat, 328-middle outrigger transverse cylinder;
[0067] 33-rear main outrigger, 331-rear main outrigger hinge seat, 332-rear main outrigger column, 333-rear main outrigger lifting cylinder, 334-rear main outrigger pad, 335-rear main outrigger rotating cylinder, 336-rear main outrigger upper hinge seat, 337-rear main outrigger lower hinge seat, 238-fine-tuning screw;
[0068] 34-rear auxiliary outrigger, 341-C-type outrigger column, 342-rear auxiliary outrigger lifting cylinder, 343-rear auxiliary outrigger running mechanism, 344-rear auxiliary outrigger running track;
[0069] 4-external mold hanging assembly, 41-C type hanging, 42-C type hanging suspension rod, 43-formwork supporting cylinder;
[0070] 51-front lifting trolley, 52-rear lifting trolley, 53-auxiliary lifting tooling;
[0071] 6- sling, 61- main sling, 62- sling point, 63- sling;
[0072] 71-Attached vibrator, 72-Electric push-pull canopy, 73-Hydraulic concrete placing machine, 74-Ladder platform, 75-Tensioning auxiliary tooling;
[0073] 8-spray maintenance assembly, 81-spray head A, 82-spray head B, 83-spray head C, 84-water tank;
[0074] 9-temporary support for the first hole, 91-upper platform, 92-middle column, 93-lower platform, 94-lower column, 95-supplementary railing, 96-lower entrance, 97-ladder. DETAILED DESCRIPTION
[0075] The present invention is described in detail below with reference to the accompanying drawings and specific embodiments.
[0076] The structure of the split upward movable mold frame provided by the present invention is as follows Figure 1 As shown, the split upward movable formwork mainly includes an upward movable formwork body and a bridge upper reinforcement binding stand 1 located behind the upward movable formwork body.
[0077] Here we first describe the steel bar binding stand. The structure of the steel bar binding stand is as follows: Figure 2 to Figure 4 As shown, the steel bar binding stand includes a stand body 11, a stand traveling mechanism 12 and a gantry machine 13.
[0078] The gantry body includes a bottom mold frame 111, a side mold frame 112 and an inner mold frame 113 for supporting the bridge deck steel bars, wherein the inner mold frame is fixedly connected to the bottom mold frame, two side mold frames are provided and symmetrically connected to both sides of the bottom mold frame, and the structure of the gantry body is adapted to the structure of a section of the bridge box girder, so that the steel cage as a whole is tied to the gantry body. The steel cage as a whole described in this embodiment includes an inner mold 400, a steel cage 500, an end mold 600 and a prestressed steel pipe. Specifically, the bottom of the inner mold frame is connected to the bottom mold frame through a support beam, the bottom of the support beam is fixedly connected to the bottom mold frame, the top of the support beam is connected to a longitudinal slideway, the bottom of the inner mold frame is provided with an inner mold frame roller, and the inner mold frame roller is installed on the longitudinal slideway, which is convenient for the push-pull positioning and installation of the inner mold frame. In this embodiment, the side mold frame is a square tube that is bent or welded according to the shape of the concrete box girder, and short steel bars for tying and positioning the steel bars are welded on the side mold frame.
[0079] In this embodiment, a longitudinal support box beam 14 for supporting the outer mold frame is connected to the outer side of the outer mold frame on the bottom mold frame, and a plurality of tire frame diagonal support cylinders 15 are distributed and connected between the longitudinal support box beam and the outer mold frame; in this embodiment, the cross-section of the longitudinal support box beam is a right-angle trapezoid, and the oblique side of the longitudinal support box beam is supported on the outer side of the inner mold frame, so as to better bear the force.
[0080] The gantry running mechanism is installed at the bottom of the bottom mold frame, and the gantry body is driven to run on the bridge through the gantry running mechanism. Specifically, a gantry running track 121 is provided on the bridge, and the gantry running mechanism is a supporting wheel group, which is driven by a reducer to run.
[0081] The gantry crane is installed on the side form frame and moves longitudinally along the side form frame. Specifically, two gantry cranes are installed on the side form frame, one of which is a front gantry crane 131 for assisting the lifting of the entire steel cage, and the other is a rear gantry crane 132 for assisting the lifting of the tied steel bars. In this embodiment, the front gantry crane is a 70t gantry crane, and the rear gantry crane is a 10t gantry crane. The mechanisms of the two gantry cranes are basically the same. In this embodiment, taking the structure of the front gantry crane as an example, a gantry crane running mechanism 1311 is provided at the bottom of the front gantry crane, and a gantry crane longitudinal running track 1312 is installed on the top of the side form frame near the outside. The gantry crane running mechanism drives the gantry crane to move on the longitudinal running track. Specifically, in order to increase the bending strength, a reinforced longitudinal beam 1313 is welded between the gantry crane longitudinal running track and the side form frame, and the distance between the two gantry crane longitudinal running tracks is 13m. The two gantry cranes share the gantry crane longitudinal running track, and the front gantry crane is located in front of the rear gantry crane.
[0082] The bottom of the bottom mold frame is distributed with multiple spiral column feet 16 with adjustable lengths and multiple platform lifting cylinders 17. When the steel cage is tied as a whole, the spiral column feet are supported on the bridge. At this time, the platform lifting cylinder is supported on the bridge, which provides temporary support for taking steel bars at the tail of the gantry crane and for the gantry crane to lift and feed the steel bars forward, thereby increasing the stability of the mechanism. Specifically, the tops of the spiral column feet are fixed to the bottom mold frame by bolts, and the bottoms of the spiral column feet are configured as a triangular support base structure. In order to provide walking power and hydraulic pump station power, the steel bar tying platform is equipped with a gasoline generator. In order to allow the steel bar transport vehicle to enter under the gantry crane and facilitate the gantry crane to lift the steel bars, an opening of about 11m is left at the rear end of the bottom mold frame in this embodiment without a cross connection. Figure 4 , the rebar transfer vehicle can be placed within the lifting range of the gantry crane. In addition, in order for the front end of the rebar tying platform to be able to transport the rebar cage as a whole to the rear auxiliary support legs of the upward mobile formwork, the front end of the rebar tying platform adopts a variable cross-section structure with a length of about 2.6m. This rebar tying platform can tie both 32m prefabricated box girder rebars and 24m prefabricated box girder rebars. In order to facilitate the transfer of the rebar cage as a whole to the mobile formwork, the range of tying the rebar cage should be as close as possible to the tail of the mobile formwork (i.e. the front end of the rebar tying platform).
[0083] The main body of the upward movable mold frame includes a main beam assembly 2, a leg assembly, an outer mold hanging assembly 4, a front lifting trolley 51, a rear lifting trolley 52 and a sling 6 as well as an electrical assembly, a hydraulic assembly and other auxiliary facilities. Figure 1 and Figure 5 .
[0084] In this embodiment, the main beam assembly adopts a three-span structure, including a front guide beam 21, a main beam 22 and a rear guide beam 23 connected in sequence. Figure 6 As shown. The main beam assembly adopts a double longitudinal beam structure with good lateral stability and strong wind resistance. In this embodiment, each longitudinal beam of the main beam is connected by three sections of load-bearing steel box beams, each longitudinal beam of the front guide beam is connected by two sections of long hollow box beams, and each longitudinal beam of the rear guide beam is connected by one section of load-bearing steel box beam. A rear cross-beam 231 is connected between the two longitudinal beams at the rear end of the rear guide beam, and a plurality of main cross-beams 221 are distributed and connected between the two longitudinal beams of the main beam. The structural design of the main beam assembly in this embodiment allows a stop and travel space for the steel bar binding stand to be reserved on the rear end bridge of the split upward mobile formwork. At the same time, the front guide beam assists the whole machine in passing through the hole, and the structural setting of the front guide beam makes the whole machine anti-tilting safety good. In this embodiment, a plurality of groups of main cantilever beams 24 are symmetrically connected to the two outer sides of the main beam. In this embodiment, five groups of main cantilever beams are arranged. The main cantilever beam is a truss structure with a right-angled trapezoidal cross-section. The main cantilever beam is fixed against the outer side of the main beam, such as Fig.15 As shown, the main cantilever beam is used for hanging the outer mold hanging assembly. In this embodiment, both sides of the bottom of the front guide beam and the two longitudinal beams of the main beam are provided with front outrigger running tracks 25, the bottom of the two outer sides of the two longitudinal beams of the front guide beam and the main beam (i.e., the outer sides of the two longitudinal beams) are provided with front outrigger hanging wheel tracks 26, and the two inner sides of the main beam and the rear guide beam (i.e., the inner sides of the two longitudinal beams) are provided with hoisting tracks 27 for the running of the hoisting assembly.
[0085] Furthermore, in this embodiment, the main beam and the outer formwork hanging assembly are designed to be symmetrical in the transverse direction. Only by replacing the front guide beam, the rear guide beam and the supporting legs, a quick turnaround and bidirectional construction can be achieved, thereby reducing the difficulty and cost of equipment transfer.
[0086] The leg assembly is installed at the bottom of the main beam assembly and supported on the bridge 100 and the pier 200, so that the entire main beam assembly is placed above the bridge deck. The leg assembly includes a front leg 31, a middle leg 32, a rear main leg 33 and a rear auxiliary leg 34. The four legs are installed at the front end of the main beam, the middle of the main beam, the rear end of the main beam and the front end of the rear guide beam in sequence.
[0087] Front outrigger structure Figure 7The front outrigger includes a front outrigger running mechanism 311, a front outrigger upper crossbeam 312, a front outrigger column 313, a front outrigger lifting cylinder 314, a front outrigger lower crossbeam 315, a front outrigger transverse cylinder 316, a front outrigger transverse beam 317 and a front outrigger fixed crossbeam 318. The front outrigger running mechanism includes a front supporting wheel group, a rear supporting wheel group, a hanging wheel group and a horizontal wheel group. The front outrigger running mechanism is driven by a reducer. The front outrigger running mechanism is connected to the front outrigger running track and the front outrigger hanging wheel track provided on the main beam assembly. The reducer is used to drive the front outrigger running mechanism, so that the mobile formwork moves forward as a whole. During the through-hole operation, the initially tensioned beam body is not subjected to the heavy load of the bridge-building machine, so that the construction period requirements of rapid beam manufacturing are met. The upper roller assembly is fixed to the top of the upper crossbeam of the front leg, and the front leg column is fixed to the bottom of the upper crossbeam of the front leg. The front leg column includes an upper column 3131 of the front leg and a lower column 3132 of the front leg. The upper column of the front leg and the lower column of the front leg are connected by a pin shaft and a cotter pin 3133. When the front leg is in the last span, the lower column of the front leg can be disassembled to reduce the height of the front leg, which is suitable for the last span erection working condition, such as Figure 8 As shown. The front outrigger lifting cylinder passes through the front outrigger lower cross beam and is fixedly connected to the front outrigger lower cross beam. The two ends of the front outrigger lifting cylinder are respectively fixedly connected to the front outrigger column and the front outrigger transverse beam. The front outrigger lifting cylinder telescopes to adjust the height of the front outrigger. The front outrigger transverse beam is slidably connected to the front outrigger fixed cross beam. The two ends of the front outrigger transverse cylinder are respectively connected to the front outrigger transverse beam and the front outrigger fixed cross beam. The front outrigger transverse cylinder telescopes to drive the front outrigger transverse beam to move laterally along the front outrigger fixed cross beam. The front outrigger fixed cross beam is detachably anchored to the bridge pier through the front outrigger anchor rod. The front outrigger is an inverted triangle anti-overturning device. The upper edge of the front outrigger upper cross beam is longitudinally extended and connected to a support beam. The front outrigger diagonal support cylinder 319 is connected between the support beam and the front outrigger column.
[0088] The structure of the middle leg is as follows Fig. 9 and Fig.10As shown, it includes a middle leg hinge seat 321, a middle leg lifting column 322, a middle leg transverse beam 323, a middle leg transverse track 324 and a middle leg rotating cylinder 325, wherein a hydraulic lifting cylinder is installed in the middle leg lifting column, and the extension and retraction of the hydraulic lifting cylinder drives the middle leg lifting column to extend and retract. The middle leg lifting column is connected to the lower part of the main beam through the middle leg hinge seat, and the two ends of the middle leg rotating cylinder are connected to the main beam and the middle leg lifting column through the middle leg upper hinge seat 326 and the middle leg lower hinge seat 327 respectively. The middle leg rotating cylinder is extended and retracted to drive the middle leg to rotate around the main beam. During the through-hole process, the middle leg lifting column is controlled to extend so that the middle leg is supported on the bridge beam surface; during the casting process, the integral steel cage needs to pass through the mold, at this time, the middle leg lifting column is controlled to shrink, and then the middle leg rotating cylinder is controlled to retract the middle leg to the bottom of the main beam. The middle leg transverse beam is fixedly connected to the bottom of the middle leg lifting column, and the middle leg transverse beam is slidably connected to the middle leg transverse track, and a middle leg transverse oil cylinder 328 is connected between the two. The middle leg transverse oil cylinder is extended and retracted to drive the middle leg transverse beam to move laterally along the middle leg transverse track. When the middle leg is turned over and retracted, the middle leg transverse beam and the middle leg transverse track are turned over and retracted together with the middle leg lifting column. The front and middle legs of the mobile mold frame can be moved laterally by the cylinder, which is convenient for the mobile mold frame to pass through a small curve on the plane.
[0089] The structure of the rear main support leg is as follows Fig.11 and Fig.12 As shown, the upper structure of the rear main leg is the same as that of the middle leg, and the rear main leg includes a rear main leg hinge seat 331, a rear main leg column 332, a rear main leg lifting cylinder 333, a rear main leg pad 334 and a rear main leg rotating cylinder 335, wherein the rear main leg column is connected to the bottom of the main beam through the rear main leg hinge seat, and the two ends of the rear main leg rotating cylinder are respectively connected to the main beam and the rear main leg column through the rear main leg upper hinge seat 336 and the rear main leg lower hinge seat 337. The rear main leg rotating cylinder is extended and retracted to drive the rear main leg to rotate around the main beam. The rear main leg lifting cylinder is connected to the bottom of the rear main leg column, and the rear main leg pad is connected to the bottom of the rear main leg lifting cylinder through the fine-tuning screw 338. During the through-hole process, the rear main leg lifting cylinder is controlled to extend so that the rear main leg is supported on the bridge beam surface; during the pouring process, the overall steel cage needs to pass through the mold. At this time, the telescopic column of the rear main leg is controlled to shrink, and then the rear main leg lifting cylinder is controlled to shrink so that the rear main leg is retracted to the bottom of the main beam.
[0090] The structure of the rear auxiliary outrigger is as follows: Fig.13 and Fig.14As shown, the rear auxiliary leg is an O-shaped structure as a whole, which is convenient for the overall steel cage to pass through the mold. The rear auxiliary leg includes a C-type leg column 341 symmetrically connected to both sides of the rear guide beam, a rear auxiliary leg lifting cylinder 342, a rear auxiliary leg running mechanism 343, and a rear auxiliary leg running track 344. The C-type leg column is composed of multiple sections of columns connected by a pin shaft and a cotter pin, and the height is adjustable. The top of the C-type leg column is fixedly connected to the main beam, and the rear auxiliary leg running track is installed on the bridge beam surface. The rear auxiliary leg lifting cylinder and the rear auxiliary leg running mechanism are connected to the bottom of the C-type leg column in sequence. The rear auxiliary leg running mechanism is installed on the rear auxiliary leg running track. The rear auxiliary leg running mechanism is a supporting wheel group, and the rear auxiliary leg running mechanism is driven by a reducer to move the rear auxiliary leg running mechanism along the rear auxiliary leg running track. The rear auxiliary outrigger lifting cylinder is extended and retracted, so that the rear auxiliary outrigger running mechanism is supported on or detached from the rear auxiliary outrigger running track.
[0091] The structure of the outer mold hanging assembly is as follows Figure 15 to Figure 17 As shown, it includes multiple groups of C-type hangers 41 distributed on the main beam, wherein the number of groups of C-type hangers corresponds to the number of groups of main cantilever beams. In this embodiment, the number of groups of C-type hangers is five, and each group of C-type hangers includes two C-type hangers, which are respectively installed on the main cantilever beams through hydraulic transverse movement mechanisms and are relatively opened and closed. The hydraulic transverse movement mechanism is a conventional technical means in the field and will not be described in detail here. In this embodiment, the outer formwork 300 is connected to the C-type suspension through a supporting assembly. The outer formwork is spliced by a left outer formwork 3001 and a right outer formwork 3002. The left outer formwork and the right outer formwork are respectively connected to all left-side C-type suspensions and right-side C-type suspensions through a formwork supporting cylinder 43. The opening and closing of the C-type suspension drives the opening and closing of the left outer formwork and the right outer formwork. The formwork supporting cylinders are distributed on the outer formwork and the side and the bottom. The formwork supporting cylinders on the side of the outer formwork are hingedly connected to the outer formwork and the C-type suspension. After the left outer formwork and the right outer formwork are molded, the formwork supporting cylinders are used to adjust the posture of the left outer formwork and the right outer formwork and the beam elevation position to form a precise outer formwork space. In the mold-closing casting state, the C-type suspension is closed, and the bottoms of each group of two C-type suspensions are connected as a whole through connecting bolts, and the left outer formwork and the right outer formwork are connected as a whole. When the steel cage is put into the mold as a whole, the C-type suspension hanger 42 can be detachably connected between the main cantilever beam and the bottom of the C-type suspension to transfer the concrete load to the main beam. Moreover, the C-type suspension hanger is a through-cylinder tension hanger, which can quickly adjust the posture of the installed inner formwork. In the mold opening and through-hole state, the connection between each group of two C-type suspensions is released, the connection between the left outer formwork and the right outer formwork is released, and the C-type suspension hanger is removed to avoid affecting the overall mold entry of the steel cage.
[0092] The front hoisting trolley and the rear hoisting trolley are installed on the hoisting track of the main beam assembly and move along the hoisting track. The installation diagram is shown in the figure. Fig.18As shown. The front hoisting trolley and the rear hoisting trolley each have independent lifting mechanism, longitudinal movement and transverse movement mechanism, with three-dimensional movement and micro-motion function, which can ensure the accurate alignment and installation of the steel cage. The longitudinal movement of the front hoisting trolley and the rear hoisting trolley is chain-driven, and they run forward and backward on the hoisting track of the main beam assembly; the fixed pulley group can be synchronously moved horizontally left and right through the extension of the oil cylinder to meet the needs of transverse fine-tuning of the beam body and curved beam erection. Specifically, two winches are set at the rear end of the main beam, and two winches are set at the front end of the main beam. The four winches are grouped in twos, and they are connected to the front hoisting trolley and the rear hoisting trolley through the guide winding system, and pass through the fixed pulley group on the trolley and the movable pulley group on the sling to form a lifting system. The steel wire ropes of the two winches of the front hoisting trolley are connected, so that the two lifting points of the sling are balanced to form one lifting point, thereby realizing four-point beam lifting and three-point balance.
[0093] The sling includes a main sling 61, sling points 62 connected to the front and rear ends of the main sling for connecting with the front lifting trolley, the rear lifting trolley and the 70t gantry crane, and a sling 63 connected to the bottom of the sling frame. Fig.18 and 19 As shown, specifically, the hanging point is connected to the main hanger through a pin shaft, and the hanger is integrally connected to the steel cage, and the steel cage is hoisted as a whole to the outer mold hanging assembly. Each hanging point is composed of two horizontal hanging beams.
[0094] In this embodiment, attached vibrators 71 are installed on both sides of the outer template. Figure 1 and Figure 5 , the vibration force is transmitted to the concrete through the outer formwork, so that the overall molding quality of the concrete is better. The attached vibrator adopts a high-frequency vibrator, and 15 2.2kW high-frequency vibrators are evenly arranged on one side of the outer formwork. The high-frequency vibrator adopts a matching high-frequency control cabinet to realize centralized activation and stopping, time setting and other functions.
[0095] Electric push-pull canopies 72 are installed above the steel bar binding stand, main beam and rear guide beam, which can provide shade, rain protection, folding and anti-floating, prevent the outside weather from affecting the pouring of concrete and the binding of steel cages, realize all-weather construction, improve the overall working efficiency of the bridge construction machine, and ensure the requirements of the total construction period. Each electric push-pull canopy is 36m long when unfolded and 6-7m long when retracted. The H-shaped steel on the main beam assembly and the outer formwork frame is installed in reverse to prevent overturning. When there is a strong wind and typhoon warning, the electric push-pull canopy and the bolting points set on the main beam assembly and the outer formwork frame should be bolted. The electric push-pull canopy adopts the Bayer sun panel system, which is arranged orthogonally with the main beam upper chord channel steel through special curling channel steel, with a spacing of 1400mm, and 5 upstream and downstream. Square steel pipes are laid on the top of the curling channel steel at a longitudinal spacing of 1060mm, and the sun panel is fixed on the square steel pipe through a special aluminum profile pressure plate. Special sealing strips are installed between the upper and lower parts of the sun panel and the pressure plate and square steel pipe to achieve the effect of rainproof sealing. The sun panel adopts double-layer 10mm thick shaped plate, the standard block size is 6000×2100mm, the long side is installed in the horizontal direction, and the longitudinal joint is provided with a 20mm gap. Special aluminum profile pressure plate is used to fix the sun panel at the joint of the sun panel, so the longitudinal spacing of the pressure plate is 2120mm. In addition, a negative pressure reinforcement belt is set between the two pressure plates, and the spacing is also 2120mm, which is arranged at intervals from the pressure plate.
[0096] A concrete hydraulic placing machine 73 is fixedly connected to the main beam. After the steel cage and the inner formwork are integrally placed in the mold, concrete is poured by the concrete hydraulic placing machine. The concrete hydraulic placing machine is arranged at the front and rear ends of the main beam to meet the needs of rapid placing construction in the entire pouring area. A ladder platform 74 is installed on the steel bar binding stand and the upper movable formwork body to facilitate workers to enter the construction. In this embodiment, a tensioning auxiliary tool 75 is installed on the front leg and the rear main leg. Figure 7 and Fig.11 When the concrete strength of the beam reaches 80% of the design value, loosen the inner formwork, remove the end formwork and then start the initial tensioning. When the concrete strength and elastic modulus of the beam reach the design value, the final tensioning is carried out when the age is not less than 7 days.
[0097] In this embodiment, the upward movable formwork also includes a spray curing assembly 8, which includes a spray curing system for the formed box beam and a spray curing system for the cast-in-place beam surface. The spray curing system for the formed box beam includes a spray head A81 distributed in the box beam hole and a spray head B82 distributed at the bottom of the steel cage binding stand. Fig. 22 The cast-in-place beam surface spray curing system includes a spray head C83 distributed on the outer formwork hanging assembly (located above the outer formwork on the C-type hanging), as shown in FIG. Fig.23The spray curing system for the formed box beam and the spray curing system for the cast-in-place beam surface are each equipped with a water tank 84 and a pump control system. The two water tanks and pump control systems are respectively installed on both sides of the rear end of the main beam and are respectively connected to the corresponding spray heads, so as to spray and cure the cast-in-place beam surface and the formed box beam respectively. Fig. 20 and Fig.21 The spray heads are all rotating spray heads, and 8 spray heads A are individually connected in series in a single water pipe in the beam to meet the requirements of spray curing in the formed box beam.
[0098] The construction method of the split upward movable formwork provided by the present invention comprises the following steps: (1) the split upward movable formwork is positioned on the bridge through a hole, the initial state of the whole machine is prepared, the front lifting trolley and the rear lifting trolley on the movable formwork body are positioned on the rear guide beam, and the Fig.24 As shown; at the same time, the steel cage is tied up on the steel bar tying stand behind the whole machine;
[0099] The initial state of the whole machine is: the front outrigger is supported on the front end of the main beam and 1# pier 2001, the rear main outrigger is supported on the rear end of the main beam and the front end beam surface of the newly cast box beam 1001, the rear auxiliary outrigger is supported on the front end of the rear guide beam and the beam surface of the newly cast box beam, the middle outrigger is turned over and retracted, the C-type hanging suspends the outer formwork at the box beam to be cast, and the C-type hanging and the outer formwork are in a mold-closed connection state;
[0100] In this embodiment, after the whole machine is through-hole positioned, the formed box beam spray curing system is used to spray the beam body of the newly cast box beam, including spray curing inside the box beam hole and on the beam surface.
[0101] (2) The steel cage is put into the mold as a whole, and the outer formwork is polished and the mold release agent is applied. Figure 25 to Figure 28 As shown;
[0102] The specific steps of placing the steel cage into the mold are as follows: (2.1) Connect the tied steel cage to the hoist, move the steel bar binding platform forward to the rear auxiliary support leg, connect the front lifting trolley to the first lifting point at the front end of the hoist, and connect the front gantry crane to the second lifting point at the rear end of the hoist; at the same time, turn over and retract the rear main support leg. Fig.25 As shown;
[0103] (2.2) The front hoisting trolley and the front gantry crane move forward at the same time until the front gantry crane approaches the rear hoisting trolley. The rear hoisting trolley is connected to the third lifting point at the rear end of the spreader. The connection between the front gantry crane and the second lifting point is released. Fig.26 and Fig. 27 As shown;
[0104] (2.3) The front and rear lifting trolleys move forward to hoist the steel cage as a whole to the top of the outer formwork. Fig.28As shown, after adjusting the position, the steel cage is lowered as a whole, the connection between the hanger and the steel cage as a whole is released, and the steel cage as a whole is put into the mold;
[0105] (3) Simultaneously carry out the construction of the pouring area below the main beam and the construction of the steel cage binding area on the steel binding platform, such as Figure 29 to Figure 31 As shown;
[0106] The construction steps of the pouring area are as follows: (3.11) the front lifting trolley and the rear lifting trolley move backward, the front gantry crane connects to the second lifting point, the connection between the rear lifting trolley and the third lifting point is released, the front gantry crane and the front lifting trolley move backward together, so that the lifting device is located above the steel bar binding platform, the lifting device is lowered, and the connection between the front gantry crane, the front lifting trolley and the lifting device is released;
[0107] (3.12) Lower the rear main legs and support them on the bridge deck of the cast bridge. Put on the C-type hanging rod and adjust the elevation of the entire mold bed. Fig.29 As shown;
[0108] (3.13) The concrete hydraulic placing machine is working to pour concrete, and the vibrating assembly is started to assist in vibrating. Specifically, when pouring concrete, the pouring construction is carried out in longitudinal sections and oblique (horizontal) layers. After the concrete pouring is completed, the bridge deck is leveled;
[0109] (3.14) After the initial setting of the concrete, the beam surface is sprayed and cured; in this embodiment, the spray curing is performed by the spray heads C distributed on both sides of the outer formwork hanging assembly in the cast-in-place beam surface spray curing system;
[0110] (3.15) When the concrete strength of the beam reaches 80% of the design value, loosen the inner formwork, remove the end formwork and start the initial tensioning. Fig.30 As shown;
[0111] (3.16) Remove the inner formwork, and use the front lifting trolley, rear lifting trolley and auxiliary lifting tooling 53 installed at the front outrigger to transport the inner formwork and end formwork to the reinforcement cage binding area. Fig.31 As shown in the figure, after the reverse transportation is completed, the front lifting trolley and the rear lifting trolley are moved to the rear guide beam to stay; at the same time, when the concrete strength and elastic modulus of the beam body reach the design value, the final tensioning is carried out when the age is not less than 7 days;
[0112] The construction steps of the reinforcement cage binding area are as follows: (3.21) Adjust the length of the spiral column foot so that the spiral column foot at the bottom of the reinforcement binding gantry is supported on the beam surface of the cast bridge;
[0113] (3.22) The rebar transporter transports the materials required for the entire rebar cage to the bottom of the front door machine and the rear door machine on the rebar tying platform, and uses the front door machine and the rear door machine to assist in tying the entire rebar cage on the rebar tying platform; when tying the rebar cage, first tie the bottom plate and side plates of the rebar cage, and when the inner formwork and the end formwork are transported to the rebar cage tying area in step (3.16), install the inner formwork, tie the top plate of the rebar cage, and install the end formwork, and install the prestressed rebar pipe when tying the bottom plate, side plate and top plate of the rebar cage;
[0114] (4) Demolding and preparation of the whole machine for via hole status, such as Fig.32 As shown;
[0115] (4.1) After the final tensioning is completed, the longitudinal, vertical and transverse constraints of the external formwork are released;
[0116] (4.2) The lifting cylinders of the front outrigger, rear main outrigger and rear auxiliary outrigger are unloaded at the same time, so that the whole machine is lowered 15cm to be demoulded. Fig.37 ;
[0117] (4.3) Remove the C-type hanging rod, release the center seam connection between the outer formwork and the C-type hanging, and open the mold of the C-type hanging and the outer formwork;
[0118] (5) The whole machine is in place through the holes, such as Figure 33 to Figure 35 As shown;
[0119] (5.1) After starting the auxiliary outrigger travel mechanism, the whole machine moves forward until the middle outrigger is above the front end beam surface of the newly cast box girder. Fig.33 At this time, the front outrigger is anchored on the 1# pier through the front outrigger anchor rod. The front outrigger, rear main outrigger and rear auxiliary outrigger support the whole machine. After the rear auxiliary outrigger running mechanism starts to move forward, the main beam moves along the front outrigger running mechanism.
[0120] (5.2) The middle outrigger is rotated and lowered to support on the beam surface, and the middle outrigger supports the force. In this embodiment, the lifting cylinders of the middle outrigger, rear auxiliary outrigger and rear main outrigger are all lifted up by 40cm, so that the front outrigger is free; at this time, the anchor rod of the front outrigger is removed to separate the front outrigger from the 1# pier, and the middle outrigger, rear main outrigger and rear auxiliary outrigger support the whole machine;
[0121] (5.3) The front outrigger moves forward to the 2# pier and is in position. Fig.34 As shown, the front outrigger supports the force, and the middle outrigger rotates and retracts; at this time, the front outrigger is anchored on the 2# pier;
[0122] (5.4) Start the rear auxiliary outrigger travel mechanism, and the whole machine moves forward until the front end of the main beam is located at the front outrigger. The lifting cylinders of the front outrigger, rear main outrigger and rear auxiliary outrigger work synchronously to lift the whole machine 15cm into place. The whole machine is in place after passing through the hole. Fig.35 As shown;
[0123] (6) The C-type hanging and the inner formwork are molded together, and the outer formwork and the center seam on the C-type hanging are connected to start the next construction cycle.
[0124] The mobile formwork in this embodiment is also suitable for the construction of 24m standard beams and 30m and 27.2m non-standard beams.
[0125] When the whole machine passes the continuous beam, it only needs to convert the front support leg to the last span support state, and then open the C-type suspension to a certain width and lock it, and the whole machine and the template can pass the continuous beam smoothly.
[0126] In this embodiment, the position diagram of the upward movable formwork when the first span of 32m is stationed is as follows Fig.36 As shown, a temporary support 9 for the first hole is installed on the pier. The temporary support for the first hole includes an upper platform 91, a middle column 92, a lower platform 93 and a lower column 94 connected in sequence. The structure of the temporary support for the first hole is shown in the figure. The main material of the upper platform is 40b I-beam with a size of 12200×4840. Except for the main structure, the rest are paved with steel plate mesh, as shown in the figure. Fig.39 As shown in the figure, the rear auxiliary outrigger and the rear main outrigger are in the first span position on the upper platform, and there is enough space on the upper platform to meet the needs of construction workers to walk and operate. The middle column and the lower column are both φ800 steel pipes, with flanges welded at both ends, and connected to the upper platform and the lower platform through flanges. The lower platform is also welded from 40b I-beams, with a size of 8058×4840. The lower platform is supported on the piers, and a gap is opened at the pad stone of the pier to allow it to leak out. An auxiliary railing 95 is set on the upper platform, and a lower entrance 96 is also set on the upper platform. A ladder 97 is set between the lower entrance and the lower platform to facilitate construction.
Claims
1. A split upward movable mold frame, comprising at least an upward movable mold frame body, characterized in that: A steel bar binding platform is arranged on the bridge behind the upward movable formwork body, and the steel bar binding platform includes a platform body, a platform running mechanism and a gantry crane. The platform body includes a bottom mold frame, a side mold frame and an inner mold frame for supporting the bridge deck steel bars, the inner mold frame is fixedly connected to the bottom mold frame, two side mold frames are arranged and symmetrically connected to the two sides of the bottom mold frame, the structure of the platform body is adapted to the structure of a section of the bridge box girder, so that the steel bar cage is tied as a whole on the platform body; the platform running mechanism is installed at the bottom of the bottom mold frame, and the platform body is driven to travel on the bridge by the platform running mechanism, and the gantry crane It is installed on the side mold frame and moves longitudinally along the side mold frame; the bottom mold frame is connected to the outer side of the outer mold frame with a longitudinal support box beam for supporting the outer mold frame, and a plurality of frame diagonal support cylinders are distributed and connected between the longitudinal support box beam and the outer mold frame; a plurality of spiral column feet with adjustable lengths and a plurality of platform lifting cylinders are distributed at the bottom of the bottom mold frame; the front lifting trolley and the rear lifting trolley are installed on the rear guide beam and the main beam, and the front lifting trolley and the rear lifting trolley move longitudinally on the rear guide beam and the main beam, and the front lifting trolley and the rear lifting trolley are detachably connected with lifting equipment, which cooperates with the gantry crane to lift the entire steel cage into the mold.
2. The split upward movable mold frame according to claim 1 is characterized in that: The cross section of the longitudinal support box beam is a right-angle trapezoid, and the oblique side of the longitudinal support box beam is supported on the outer side of the inner mold frame.
3. The split upward movable mold frame according to claim 1 is characterized in that: Two gantry cranes are movably installed on the side formwork frame, one of which is a 70t gantry crane for assisting in lifting the entire steel cage, and the other is a 10t gantry crane for assisting in lifting the tied steel bars.
4. The split upward movable mold frame according to claim 1 is characterized in that: An opening for parking a steel bar transport vehicle is reserved at the rear end of the bottom mold frame.
5. The split upward movable mold frame according to claim 1 is characterized in that: The hoisting device includes a main hanger, hanging points distributedly connected to the front and rear ends of the main hanger for connecting with the front lifting trolley, the rear lifting trolley and the gantry crane, and hangings distributedly connected under the lifting frame; the hanging points are connected to the main hanger through pins, and the hangings are integrally connected to the steel cage, so that the steel cage is hoisted as a whole to the outer mold hanging assembly.
6. The split upward movable mold frame according to claim 1, characterized in that: The upward movable formwork body includes a leg assembly, which is installed at the bottom of the main beam assembly and supported on the bridge and the pier. The leg assembly includes a front leg, a middle leg, a rear main leg and a rear auxiliary leg. The four legs are installed at the front end of the main beam, the middle of the main beam, the rear end of the main beam and the front end of the rear guide beam in sequence. The front leg comprises an upper roller running mechanism, an upper cross beam of the front leg, a front leg column, a front leg lifting cylinder, a lower cross beam of the front leg, a front leg transverse cylinder, a front leg transverse beam and a front leg fixed cross beam connected in sequence, the upper roller running mechanism is connected to the front leg running track and the front leg hanging wheel track provided on the main beam assembly, and drives the mobile mold frame to move forward as a whole; the front leg column comprises an upper column of the front leg and a lower column of the front leg, and the upper column of the front leg and the lower column of the front leg are connected by a pin shaft and a cotter pin; the front leg lifting cylinder passes through the lower cross beam of the front leg and is connected to the front leg The lower cross beam is fixedly connected, and the two ends of the front outrigger lifting cylinder are respectively fixedly connected to the front outrigger column and the front outrigger transverse beam; the front outrigger transverse beam is slidably connected to the front outrigger fixed cross beam, and the two ends of the front outrigger transverse cylinder are respectively connected to the front outrigger transverse beam and the front outrigger fixed cross beam, and the front outrigger transverse cylinder is extended and retracted to drive the front outrigger transverse beam to move laterally along the front outrigger fixed cross beam, and the front outrigger fixed cross beam is detachably anchored to the bridge pier through the front outrigger anchor rod; the upper cross beam of the front outrigger is longitudinally extended and connected to a support beam, and a front outrigger diagonal support cylinder is connected between the support beam and the front outrigger column; The middle outrigger comprises a middle outrigger hinge seat, a middle outrigger lifting column, a middle outrigger transverse beam, a middle outrigger transverse track and a middle outrigger rotating cylinder, wherein a hydraulic outrigger is installed in the middle outrigger lifting column, the middle outrigger lifting column is connected to the lower part of the main beam through the middle outrigger hinge seat, the two ends of the middle outrigger rotating cylinder are respectively connected to the main beam and the middle outrigger lifting column through the middle outrigger upper hinge seat and the middle outrigger lower hinge seat, the middle outrigger rotating cylinder is extended and retracted, driving the middle outrigger to rotate around the main beam; the middle outrigger transverse beam is fixedly connected to the bottom of the middle outrigger lifting column, the middle outrigger transverse beam is slidably connected to the middle outrigger transverse track, and the middle outrigger transverse cylinder is connected between the two, the middle outrigger transverse cylinder is extended and retracted, driving the middle outrigger transverse beam to move transversely along the middle outrigger transverse track; The rear main leg comprises a rear main leg hinge seat, a rear main leg column, a rear main leg lifting cylinder, a rear main leg pad and a rear main leg rotating cylinder, wherein the rear main leg column is connected to the lower part of the main beam through the rear main leg hinge seat, and the two ends of the rear main leg rotating cylinder are respectively connected to the main beam and the rear main leg column through the rear main leg upper hinge seat and the rear main leg lower hinge seat, and the rear main leg rotating cylinder is extended and retracted to drive the rear main leg to rotate around the main beam; the rear main leg lifting cylinder is connected to the bottom of the rear main leg column, and the rear main leg pad is connected to the bottom of the rear main leg lifting cylinder through a fine-tuning screw; The rear auxiliary outrigger has an O-shaped structure as a whole, including C-shaped outrigger columns symmetrically connected to both sides of the rear guide beam, a rear auxiliary outrigger lifting cylinder, a rear auxiliary outrigger running mechanism, and a rear auxiliary outrigger running track, wherein the C-shaped outrigger column is composed of multiple sections of columns connected by pins and cotter pins, the top of the C-shaped outrigger column is fixedly connected to the main beam, the rear auxiliary outrigger running track is installed on the bridge beam surface, the rear auxiliary outrigger lifting cylinder and the rear auxiliary outrigger running mechanism are connected to the bottom of the C-shaped outrigger column in sequence, the rear auxiliary outrigger running mechanism is installed on the rear auxiliary outrigger running track, and the rear auxiliary outrigger running mechanism is driven by a reducer to move the rear auxiliary outrigger running mechanism along the rear auxiliary outrigger running track.
7. The split upward movable mold frame according to claim 1, characterized in that: The upward movable formwork body includes an outer formwork hanging assembly, on which an outer formwork is installed. The outer formwork hanging assembly is hung below the cantilever beams on both sides of the main beam, so that the outer formwork is hung below the main beam; the outer formwork hanging assembly includes multiple groups of C-type hangings distributed on the main beam, wherein the number of groups of C-type hangings corresponds to the number of groups of cantilever beams, and each group of C-type hangings includes two C-type hangings, and the two C-type hangings are respectively installed on the cantilever beams through a transverse movement mechanism and open and close relatively; the outer formwork is connected to the C-type hanging through a support assembly, and the outer formwork is spliced by a left outer formwork and a right outer formwork, and the left outer formwork and the right outer formwork are respectively connected to all left C-type hangings and right C-type hangings through the support assembly, and the C-type hanging opens and closes, driving the left outer formwork and the right outer formwork to open and close; a C-type hanging hanger is detachably connected between the cantilever beam and the bottom of the C-type hanging.
8. The split upward movable mold frame according to claim 1, characterized in that: The upward movable formwork body also includes an attached vibrator, a concrete hydraulic placing machine, a tensioning auxiliary tooling and an electric push-pull canopy, and a ladder platform is installed on the steel bar binding stand and the upward movable formwork body.
9. The split upward movable mold frame according to claim 1, characterized in that: The upward movable formwork body also includes a spray curing assembly, which includes a spray curing system for formed box beams and a spray curing system for cast-in-place beam surfaces.
10. The split upward movable mold frame according to claim 1, characterized in that: The upward movable formwork body comprises a main beam assembly, which comprises a front guide beam, a main beam and a rear guide beam, and the main beam assembly adopts a double longitudinal beam structure.