Movable tower crane section foundation and construction method thereof
By designing a detachable mobile tower crane section foundation, the problem of long construction period and inability to move the tower crane foundation is solved, rapid construction and efficient utilization of resources are achieved, and it is suitable for large-span steel structure roof construction.
Patent Information
- Application Number
- CN202411333501.1
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-09-24
- Publication Date
- 2024-11-26
AI Technical Summary
The existing tower crane foundation has a long construction cycle, slows down the construction period, and cannot move, resulting in waste of resources.
A mobile tower crane joint foundation including a roadbed box and a removable connector is designed. The roadbed box is welded into a tic-tac support frame by H-shaped steel. The connectors include support plates, vertical plates, open-hole plates, pins and vertical pins. , can be customized according to the size of the tower crane section, so as to achieve flexible connection and disassembly between the tower crane section and the foundation.
It significantly reduces the construction time of tower crane foundation, realizes the mobility of the foundation, reduces resource waste, and improves the construction speed of steel structures, and is suitable for the turnover and use of multiple projects.
Smart Images

Figure CN119021262A_ABST
Abstract
Description
Technical Field
[0001] The invention belongs to steel structure installation construction in construction engineering, and specifically relates to a movable foundation of a temporary supporting structure of a tower crane section and a construction method thereof. Background Art
[0002] The installation of steel structures is a key line in steel structure projects, which directly affects the construction progress and quality of the main structure of the project. During the construction of large-span steel structure roofs, due to factors such as large volume and small site, it is impossible to lift or hoist the entire structure. In order to ensure the safety and quality of the structure during construction, temporary supports need to be set up under the large-span roof. At present, during the construction of large-span steel structure roofs, the components have large spans, large weights, and small slenderness ratios, which lead to deformation and instability after the components are hoisted to the existing positions. The existing practice is to set up temporary supports for tower crane sections in advance under the steel structure roof components. The temporary supports for tower crane sections have good stress conditions, can resist deformation of steel components, and prevent instability of the structure. This leads to a large amount of temporary supports for tower crane sections. During the regional construction process, the use of temporary supports for tower crane sections continues to increase.
[0003] The existing temporary support of the tower crane section requires setting up a concrete foundation on the ground in advance and pre-embedded tower crane section connectors. Since the concrete and tower crane section embedded parts have a long construction period, they cannot be reused and their positions cannot be flexibly adjusted, resulting in a waste of resources on site and slowing down the overall construction progress. Summary of the invention
[0004] The technical problem to be solved by the present invention is that the existing tower crane foundation has a long construction period, which slows down the construction period, and cannot be moved, resulting in a waste of resources.
[0005] The present invention solves the above-mentioned problem by adopting the following technical solution: A mobile tower crane section foundation comprises a roadbed box fixed to the ground, a connecting piece connected to the tower crane section is arranged on the top of the roadbed box, the roadbed box comprises an upper cover plate, a lower cover plate and an intermediate support beam, the upper cover plate and the lower cover plate are customized according to the cross-sectional size of the tower crane section, the intermediate support beam is welded by H-shaped steel into a criss-cross support frame, and the intermediate support beam is welded to the upper cover plate and the lower cover plate; the connecting piece is positioned on the upper cover plate corresponding to the tower crane section column, the bottom of the connecting piece is welded and fixed to the upper cover plate, and the top is detachably connected to the lower end of the column of the tower crane section.
[0006] Compared with the prior art, the present invention adopting the above structure has the following beneficial effects: The present invention provides a steel structure tower crane foundation, which has a fast steel structure construction speed and can effectively reduce the construction time of the tower crane foundation, thereby saving construction period; the steel structure tower crane foundation provided by the present invention makes the tower crane foundation a movable structure relative to the ground, so that it can be turned around in multiple projects; the invention designs a detachable connection structure between the foundation and the tower crane column, so that the foundation is a structure relative to the tower crane that can be used in conjunction with multiple tower cranes, thereby reducing resource waste.
[0007] As a preferred embodiment, a further technical solution of the above structure is: The connecting parts include a supporting plate, a vertical plate, a perforated plate, a pin shaft and a vertical pin. The supporting plate is a flat steel plate fixedly welded to the top surface of the upper cover plate; the vertical plate is an angle steel with an L-shaped cross-section, and the lower end is vertically welded to the top surface of the supporting plate; the perforated plate is composed of a first orifice plate and a second orifice plate, and the first orifice plate and the second orifice plate are respectively fixedly welded to the top of the two side plates of the vertical plate, and the upper ends of the first orifice plate and the second orifice plate are both provided with axial holes, and the elevation of the axial hole of the first orifice plate is located above the axial hole of the second orifice plate; the pin shaft penetrates the axial holes of the first orifice plate and the second orifice plate from the outside, respectively, and the tail ends of the two pin shafts are arranged crosswise; the vertical pin is arranged at the intersection of the two pin shafts and penetrates the two pin shafts.
[0008] The beneficial effects obtained by the above features are as follows: the four connection points of the connector are customized according to the size of the standard section of the tower crane, ensuring the adaptability of the connection with the standard section; each column foot of the standard section is locked by a two-way pin to ensure the stability of the node, and this connector is very convenient for connecting or folding the connection node.
[0009] The first orifice plate and the second orifice plate are both composed of two layers of steel plates, the upper ends of the two layers of steel plates are welded together, and the lower ends are separated to form a slot, the slot is buckled on the upper end of the vertical plate, and the welding of the slot and the vertical plate is a full welding of the edge of the structural seam.
[0010] Beneficial effects obtained by the above features: In this solution, the perforated plate contacts the vertical plate in the form of double-sided wrapping, so that both sides can withstand stress and avoid cracking of the welding surface.
[0011] The pin shaft consists of a shaft rod and an end cap. The end cap is fitted to the outer wall of the perforated plate. A pin hole is provided at the tail end of the shaft rod. The distance between the pin hole and the inner wall of the perforated plate is adapted to the thickness of the tower crane section column. The tower crane section column is an L-shaped steel.
[0012] The beneficial effects obtained by the above features are as follows: the structural parts of this implementation are compactly combined, the components of the connection node are restrained to ensure the stability of the node, and the end caps and the vertical pins can prevent them from falling off.
[0013] The present invention also provides a construction method for the mobile tower crane section foundation. The first step is to select steel sections of the same size and specification as the tower crane section as the main material for the tooling; The second step is to cut and weld the tooling materials for the roadbed box and the connectors; The third step is to drill holes in the perforated plate to form shaft holes according to the size of the tower crane section connection position used on site; The fourth step is to weld the hole reinforcement plate at the shaft hole position; The fifth step is to weld the connector to the upper cover plate of the roadbed box, and the fixing position of the connector corresponds to the internal support beam of the roadbed box; Step 6: After the connection parts are welded, stiffening ribs are welded around their roots; Step 7: When it is necessary to connect and use, insert the tower crane section column into the inner side of the vertical plate and fit it with the first hole plate and the second hole plate, then take two pins and penetrate the first hole plate, the second hole plate and the tower crane section column from the outside respectively. When the tail ends of the two pins are staggered and the pin holes are coaxial, install the vertical pins. After all the columns and connectors are connected, the tower crane section is fixed to the foundation; Step 8. When dismantling is required, install the lifting tool on the tower crane section, lift the vertical pin, and then pull out the pin shaft, and the tower crane section can be removed. BRIEF DESCRIPTION OF THE DRAWINGS
[0014] Figure 1 It is the overall schematic diagram of the roadbed box and the connecting parts assembly; Figure 2 It is a three-dimensional structural diagram of the connecting piece of the present invention; In the figure: 1, roadbed box; 101, upper cover plate; 102, support beam; 103, lower cover plate; 2, supporting plate; 3, vertical plate; 4, first hole plate; 5, second hole plate; 6, stiffening rib; 7, pin shaft; 8, vertical pin. DETAILED DESCRIPTION
[0015] The present invention will be further described below in conjunction with embodiments, the purpose of which is only to provide a better understanding of the content of the present invention. Therefore, the examples given do not limit the protection scope of the present invention.
[0016] See also Figure 1 and Figure 2 As shown, a mobile tower crane section foundation comprises a roadbed box 1 fixed to the ground, and a connecting piece connected to the tower crane section is arranged on the top of the roadbed box 1. The roadbed box 1 includes an upper cover plate 101, a lower cover plate 103 and an intermediate support beam 102. The upper cover plate 101 and the lower cover plate 103 are customized according to the cross-sectional size of the tower crane section. The intermediate support beam 102 is welded from H-shaped steel into a tic-tac-toe support frame. The intermediate support beam 102 is welded to the upper cover plate 101 and the lower cover plate 103; The connecting piece is positioned on the upper cover plate 101 corresponding to the tower crane section columns. The bottom of the connecting piece is welded and fixed to the upper cover plate 101, and the top is detachably connected to the lower end of the column of the tower crane section.
[0017] According to the project, the fixed position of the connector is determined by laying out on the upper cover plate 101 of the roadbed box 1. Each connector is used to be connected to a column of the tower crane section. The connector support plate 2 is welded to the roadbed box 1, and the tower crane is fixed to the upper end of the connector, so that the tower crane section and the roadbed box 1 form a whole.
[0018] Specifically, the connecting member includes a supporting plate 2, a vertical plate 3, a perforated plate, a pin shaft 7 and a vertical pin 8. The supporting plate 2 is a flat steel plate fixedly welded to the top surface of the upper cover plate 101; The vertical plate 3 is an angle steel with an L-shaped cross section, and the lower end is vertically welded to the top surface of the supporting plate 2; The perforated plate is composed of a first perforated plate 4 and a second perforated plate 5. The first perforated plate 4 and the second perforated plate 5 are respectively fixedly welded to the top of the two side plates of the vertical plate 3. The upper ends of the first perforated plate 4 and the second perforated plate 5 are both provided with axial holes. The elevation of the axial hole of the first perforated plate 4 is located above the axial hole of the second perforated plate 5. The pin shaft 7 penetrates the shaft holes of the first orifice plate 4 and the second orifice plate 5 from the outside, respectively, and the tail ends of the two pin shafts 7 are arranged to cross each other; The vertical pin 8 is arranged at the intersection of the two pin shafts 7 and passes through the two pin shafts 7 .
[0019] If the temporary support of the tower crane section is used in the existing position and needs to be adjusted to a new position, the pin shaft 7 and the vertical pin 8 can be removed to separate the tower crane section from the foundation, and the steel structure foundation composed of the roadbed box 1 and the connecting piece can be adjusted in position, and then the tower crane section and the present invention are reconnected through the pin shaft 7 and the vertical pin 8, and then put into use again. In this embodiment, the four connection points of the connecting piece are customized according to the size of the tower crane standard section, ensuring the adaptability of the connection with the standard section; each column foot of the standard section is locked by a two-way pin shaft 7 to ensure the stability of the node, and this connecting piece is very convenient for connecting or folding the connection node.
[0020] Optionally, the first orifice plate 4 and the second orifice plate 5 are both composed of two layers of steel plates, which are welded together at the upper ends and separated at the lower ends to form a slot, which is buckled at the upper end of the vertical plate 3. The welding of the slot and the vertical plate 3 is a full weld of the edge of the structural seam, and the perforated plate is in contact with the vertical plate 3 in the form of double-sided wrapping, so that both sides can withstand stress and avoid cracking of the welding surface.
[0021] Optionally, the pin shaft 7 is composed of a shaft rod and an end cap, the end cap is fitted to the outer wall of the perforated plate, and a pin hole is provided at the tail end of the shaft rod. The distance between the pin hole and the inner wall of the perforated plate is adapted to the thickness of the tower crane section column plate. The tower crane section column is L-shaped steel. This implementation has a compact combination of structural parts, and the components of the connecting node are restricted to ensure the stability of the node. The end cap and the pin 8 can both prevent falling off.
[0022] The construction method of the above-mentioned mobile tower crane section foundation is carried out according to the following steps: The first step is to select steel sections of the same size and specification as the tower crane section as the main material for the tooling; The second step is to cut the tooling materials of the roadbed box 1 and the connecting parts and perform welding; The third step is to drill holes in the perforated plate to form shaft holes according to the size of the tower crane section connection position used on site; The fourth step is to weld the hole reinforcement plate at the shaft hole position; Step 5: Weld the connector to the upper cover plate 101 of the roadbed box 1, and the fixing position of the connector corresponds to the internal support beam 102 of the roadbed box 1; Step 6: After the connection is welded, a stiffening rib 6 is welded around the root of the connection; Step 7: When it is necessary to connect and use, insert the tower crane section column into the inner side of the vertical plate 3 and fit it with the first hole plate 4 and the second hole plate 5, then take two pins 7 and penetrate the first hole plate 4, the second hole plate 5 and the tower crane section column from the outside respectively. When the tail ends of the two pins 7 are staggered and the pin holes are coaxial, install the vertical pin 8. After all the columns and connectors are connected, the tower crane section is fixed to the foundation; Step 8. When dismantling is required, install the lifting tool on the tower crane section, lift the vertical pin 8, and then pull out the pin shaft 7, and the tower crane section can be removed.
[0023] The movable tower crane section steel structure foundation designed by the present invention adopts a detachable device, which can be immediately dismantled after the temporary support of the tower crane section is used, and reused to the next use position, under the premise of limited site for the construction of large-span steel structure roof. The temporary support position of the tower crane section can be flexibly adjusted, which can perfectly cooperate with the construction of different areas, and all materials can be used in a turnover manner. The solution designed by the present invention does not require earth excavation, steel bar binding, embedded parts installation, foundation pouring and other processes, and the temporary support erection and installation of the tower crane section can be carried out conveniently and quickly. The present invention also avoids the previous waiting time for the strength of the foundation concrete, speeds up the construction progress of the steel structure roof, reduces the labor intensity of the operators, and reduces the construction danger of the operators.
[0024] The steel structure foundation provided by the present invention can be moved on the ground, which solves the problems of small and limited construction sites for existing large-span steel structure roofs and slow and dangerous installation processes. The movable tower crane section steel structure foundation provided by the present invention will not damage the tower crane section even if it is used multiple times, and does not need to be repaired, which does not affect the construction quality. At the same time, it solves the problem of small construction sites for large-span steel structure roofs, limited sites, and the need for a large number of temporary supports for tower crane sections to be erected in different areas, which makes it impossible to turn around.
[0025] The above description is only a preferred feasible embodiment of the present invention, and does not limit the scope of rights of the present invention. All equivalent changes made using the contents of the present specification and its drawings are included in the scope of rights of the present invention.
Claims
1. A mobile tower crane section foundation, characterized in that: It comprises a roadbed box (1) fixed to the ground, wherein a connecting piece connected to a tower crane section is arranged on the top of the roadbed box (1). The roadbed box (1) comprises an upper cover plate (101), a lower cover plate (103) and an intermediate support beam (102); the upper cover plate (101) and the lower cover plate (103) are customized according to the cross-sectional dimensions of the tower crane section; the intermediate support beam (102) is welded from H-shaped steel into a crisscross support frame; the intermediate support beam (102) is welded to the upper cover plate (101) and the lower cover plate (103); The connecting piece is positioned on the upper cover plate (101) corresponding to the tower crane section columns respectively. The bottom of the connecting piece is welded and fixed to the upper cover plate (101), and the top is detachably connected to the lower end of the tower crane section column.
2. The mobile tower crane section foundation according to claim 1, characterized in that: The connecting member comprises a supporting plate (2), a vertical plate (3), a perforated plate, a pin shaft (7) and a vertical pin (8). The supporting plate (2) is a flat steel plate fixedly welded to the top surface of the upper cover plate (101); The vertical plate (3) is an angle steel with an L-shaped cross section, and the lower end is vertically welded to the top surface of the supporting plate (2); The perforated plate is composed of a first perforated plate (4) and a second perforated plate (5), wherein the first perforated plate (4) and the second perforated plate (5) are respectively fixedly welded to the top of the two side plates of the vertical plate (3), and the upper ends of the first perforated plate (4) and the second perforated plate (5) are both provided with axial holes, and the elevation of the axial hole of the first perforated plate (4) is located above the axial hole of the second perforated plate (5); The pin shafts (7) are respectively passed through the shaft holes of the first orifice plate (4) and the second orifice plate (5) from the outside, and the tail ends of the two pin shafts (7) are arranged to cross each other; The vertical pin (8) is arranged at the intersection of the two pin shafts (7) and passes through the two pin shafts (7).
3. The mobile tower crane section foundation according to claim 2 is characterized in that: The first orifice plate (4) and the second orifice plate (5) are both composed of two layers of steel plates, the upper ends of the two layers of steel plates are welded together, and the lower ends are separated to form a slot, the slot is buckled on the upper end of the vertical plate (3), and the welding between the slot and the vertical plate (3) is a full welding of the structural seam edge.
4. The mobile tower crane section foundation according to claim 2, characterized in that: A stiffening rib (6) is provided on the outer side of the vertical plate (3); the vertical side edge of the stiffening rib (6) is welded to the vertical plate (3), and the bottom edge is welded to the supporting plate (2).
5. The mobile tower crane section foundation according to claim 2, characterized in that: The pin shaft (7) is composed of a shaft and an end cap, the end cap is fitted to the outer wall of the perforated plate, a pin hole is provided at the tail end of the shaft, the spacing between the pin hole and the inner wall of the perforated plate is adapted to the plate thickness of the tower crane section column, and the tower crane section column is an L-shaped steel.
6. The construction method of a mobile tower crane section foundation according to any one of claim 2, characterized in that: The first step is to select steel sections of the same size and specification as the tower crane section as the main material for the tooling; The second step is to cut and weld the tooling materials of the roadbed box (1) and the connecting parts; The third step is to drill holes in the perforated plate to form shaft holes according to the size of the tower crane section connection position used on site; The fourth step is to weld the hole reinforcement plate at the shaft hole position; Step 5: welding the connecting piece to the upper cover plate (101) of the roadbed box (1), wherein the fixing position of the connecting piece corresponds to the internal support beam (102) of the roadbed box (1); Step 6: After the connection is welded, a stiffening rib (6) is welded around the root of the connection; Step 7: When it is necessary to connect and use, the tower crane section column is inserted into the inner side of the vertical plate (3) and fits with the first hole plate (4) and the second hole plate (5), and then two pins (7) are taken to penetrate the first hole plate (4), the second hole plate (5) and the tower crane section column from the outside respectively. When the tail ends of the two pins (7) are staggered and the pin holes are coaxial, the vertical pins (8) are installed. After all the columns and the connecting parts are connected, the tower crane section is fixed to the foundation; Step 8: When dismantling is required, install the lifting tool on the tower crane section, lift the vertical pin (8), and then pull out the pin shaft (7), and the tower crane section can be removed.