Fabricated subway tunnel construction method in high-water-level area
By using prefabricated culverts, prefabricated support and transfer transportation channels in high water levels, sealed water stop of underwater spliced subway tunnels is achieved, and the problem of difficult sealed water stop in traditional enclosure structures in high water levels is solved. Provides an economical, efficient, safe and controllable construction technology.
Patent Information
- Application Number
- CN202411516026.1
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-10-29
- Publication Date
- 2024-11-26
- Estimated Expiration
- Not applicable · inactive patent
AI Technical Summary
In high water levels, it is difficult to achieve sealing and water stop in the foundation pit in traditional enclosure structures, resulting in poor underwater sealing effect during subway tunnel construction.
The methods of prefabricated box culverts, prefabricated support and transport channels are adopted to form a sealed box through pile foundation construction, underwater foundation trough construction, prefabricated support installation, underwater foundation trough treatment, prefabricated box culvert sinking and underwater docking. The end-sealed door structure realizes underwater splicing subway tunnel construction, and uses prestressed concrete structure and water pressure for precise docking and sealing.
Underwater sealed water stop during subway tunnel construction in high water levels is achieved, forming economical, efficient, highly adaptable, safe and controllable construction quality construction technology, solving the problem of poor water stopping effect in traditional methods.
Smart Images

Figure CN119021275A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of construction engineering, and in particular to a method for constructing an assembled subway tunnel in a high water level area. Background Art
[0002] Conventional subway tunnel construction process: 1. Construction of retaining structure: According to the buried depth of the tunnel and the geological conditions on site, reasonable foundation pit support forms are adopted to maintain soil stability, prevent soil collapse and cut off groundwater.
[0003] 2. Foundation pit dewatering: Before excavating the soil layer, the groundwater level in the foundation pit needs to be lowered.
[0004] 3. Earth excavation: After the retaining structure and foundation pit dewatering measures are completed, earth excavation begins. The earth excavation needs to be carried out in layers, sections and blocks. During the excavation process, supports need to be installed in time to maintain the stability of the soil.
[0005] 4. Construction of cushion layer and main structure: After excavating the earth to the bottom of the foundation pit, a cushion layer should be laid to prevent soil collapse and facilitate construction; after the cushion layer construction is completed, the main structure construction (either cast-in-place reinforced concrete structure or prefabricated reinforced concrete structure) and the waterproof layer construction should be carried out at the same time.
[0006] 5. Backfill and level the site.
[0007] The use of traditional retaining structures in highly permeable strata in high water level areas has the problem of poor sealing and water-stopping effects in the foundation pit. Summary of the invention
[0008] The purpose of the present invention is to provide a method for constructing an assembled subway tunnel in a high water level area, aiming to realize a method for constructing a subway tunnel that can ensure that prefabricated box culverts are connected to form a sealed and water-stopping structure during underwater construction.
[0009] The technical solution of the present invention is: a method for constructing an assembled subway tunnel in a high water level area, comprising a prefabricated box culvert, a prefabricated cap and a transfer and transportation channel, wherein the prefabricated box culvert has an end sealing door structure for forming a seal, and also comprises an underwater operation area, wherein the construction steps are as follows: S1. Pile foundation construction, which is the installation of sinking reduction piles at required locations within the underwater operation area; S2, underwater foundation trench construction, the underwater foundation trench construction is to excavate a foundation trench at the underwater position corresponding to the sinking reduction pile and form a water area transportation channel foundation trench, the water area transportation channel foundation trench is connected to the transfer transportation channel and is used to transport the prefabricated box culvert and the prefabricated cap; S3, installation and construction of prefabricated caps, wherein the prefabricated caps are installed on the corresponding subsidence reducing piles after the foundation trench of the water transport channel and the transfer transport channel are transported underwater together; S4, underwater foundation trench treatment, the underwater foundation trench treatment is to level the underwater foundation trench so that it is flush with the top surface of the prefabricated foundation; S5, sinking the prefabricated box culvert, wherein the prefabricated box culvert is to transport the prefabricated box culvert together with the base trench of the water transport channel and the transfer transport channel and install them on the corresponding prefabricated caps respectively; S6. Underwater docking of prefabricated box culverts. The underwater docking of the prefabricated box culverts is achieved by controlling the state of the prefabricated box culverts in water and making the interfaces of two adjacent prefabricated box culverts achieve precise docking. After the adjacent prefabricated box culverts are docked and sealed, the corresponding end sealing doors are removed respectively and then connected to form a subway tunnel.
[0010] Optionally, prestressed steel cables are symmetrically arranged on the top plate, bottom plate and side wall of the prefabricated box culvert, so as to increase the bearing capacity of the prefabricated box culvert; Temporary prestressed cables are built into the cavity of the prefabricated box culvert, so that the prefabricated box culvert structure is subjected to compressive stress, thereby causing it to produce a certain deformation, namely, an arching effect, to cope with the load borne by the prefabricated box culvert structure itself. When the temporary prestressed cables are installed in the prefabricated box culvert and the backfilling construction process, as the water and soil pressures increase, the arching effect comes into play, so that the prefabricated box culvert can gradually unload the stress in the temporary prestressed cables to improve the bearing capacity of the prefabricated box culvert.
[0011] Optionally, the transfer transport channel includes a land transport channel and a water transport channel which are connected in sequence, and the water transport channel is connected to the water transport channel base trench.
[0012] Optionally, the water transport channel has a transport channel with an inclined slope, a slide is provided on the transport channel, a transport vehicle for transporting prefabricated caps or prefabricated box culverts runs on the slide, and the transport vehicle is driven by a traction device to reciprocate along the slide; A prefabricated box culvert concrete bottom form is provided in the prefabrication area of the prefabricated box culvert, sleepers and transport airbags are provided on the prefabricated box culvert concrete bottom form, the prefabricated box culvert is transferred from the prefabricated box culvert concrete bottom form to a transport vehicle by using the traction equipment and rolling of the transport airbag, and the transport vehicle moves the prefabricated box culvert from the land transport channel to the water transport channel under the drive of the traction equipment; As the transport vehicle is transporting, the prefabricated box culvert gradually separates from the transport vehicle and completely floats on the water surface, that is, the prefabricated box culvert enters the foundation trench of the water area transport channel.
[0013] Optionally, the water transport channel foundation trench is provided with ground anchors on opposite sides of the settlement reduction piles, and the two adjacent ground anchors on the same side are arranged at intervals; After the prefabricated cap and the prefabricated box culvert are transported into the foundation trench of the water transport channel respectively by the transport vehicle, the prefabricated cap is installed on the settlement reduction pile after passing through the anchor fixing position, and then the prefabricated box culvert is placed on the prefabricated cap after passing through the anchor fixing position.
[0014] Optionally, after the plurality of prefabricated box culverts are placed one by one on the prefabricated foundation, the prefabricated box culverts that are opposite to each other can be accurately docked with each other by utilizing the combined action of water pressure and a pulling jack.
[0015] Optionally, a ballast water tank is installed in the closed compartment formed by the end sealing door of each prefabricated box culvert, which can be used to remotely control the negative buoyancy and posture of the prefabricated box culvert in the water, and at the same time assist in the precise docking of the prefabricated box culverts.
[0016] Optionally, the prefabricated box culvert has a ballast bin, which is backfilled with plain concrete or graded sand and gravel.
[0017] Optionally, the construction step further includes backfilling, and the backfilling includes a graded crushed stone layer, a backfill crushed stone layer and a top soil layer of the prefabricated box culvert that are backfilled in sequence from bottom to top.
[0018] Optionally, the end sealing door of the prefabricated box culvert is in the form of a concrete end sealing door, a steel structure end sealing door or an assembled end sealing door.
[0019] By adopting the above technical solution, the beneficial effects of the present invention are: Since the construction method of prefabricated subway tunnel in high water level area includes prefabricated box culvert, prefabricated pedestal and transfer transportation channel, the prefabricated box culvert has end sealing door structure to form a seal, and the specific construction steps include pile foundation construction, underwater foundation trench construction, prefabricated pedestal installation construction, underwater foundation trench treatment, prefabricated box culvert sinking and underwater prefabricated box culvert docking. After the construction in the underwater operation area according to the above main steps, a sealed cavity can be formed to achieve underwater splicing prefabricated tunnel to stop water, which solves the problem that it is difficult to achieve sealing and water stopping in the foundation pit using traditional retaining structure in the highly permeable stratum in the reclamation area. The method of assembling prefabricated box culvert with water is adopted to form a set of economic, efficient, adaptable, safe and quality-controlled construction technology, which can be widely used in the later stage. BRIEF DESCRIPTION OF THE DRAWINGS
[0020] Figure 1 It is the overall flow chart of the operation construction technology of the present invention; Figure 2 It is a general plan layout diagram of the land and underwater operation areas in the construction technology in the embodiment of the present invention; Figure 3 It is a schematic diagram of the transportation of prefabricated box culvert or prefabricated cap in the construction technology in the embodiment of the present invention; Figure 4 It is a schematic diagram of the floating installation of a prefabricated box culvert in the construction technology in an embodiment of the present invention; Figure 5 A cross-sectional view of a subway tunnel in the construction technology in an embodiment of the present invention (a schematic diagram of backfilling); Figure 6 It is a schematic diagram of underwater connection of a prefabricated box culvert in the construction technology in an embodiment of the present invention; Figure 7 It is a cross-sectional view of a prefabricated box culvert using a prestressed concrete structure in the construction technology in an embodiment of the present invention; Figure 8 It is a structural schematic diagram of the butt joint end and sealing structure of the prefabricated box culvert in an embodiment of the present invention; Fig. 9 for Figure 8 AA section view.
[0021] As shown in the figure: ; DETAILED DESCRIPTION
[0022] In order to make the purpose, technical solutions and advantages of the present invention more clearly understood, the present invention is further described in detail below in conjunction with the accompanying drawings and embodiments.
[0023] like Figure 1 and Fig. 9 As shown in the figure, a method for constructing an assembled subway tunnel in a high water level area includes a prefabricated box culvert, a prefabricated cap and a transfer and transportation channel. The prefabricated box culvert has an end sealing door structure to form a seal, and also includes an underwater operation area, wherein the construction steps are as follows: S1. Pile foundation construction: Pile foundation construction is the installation of settlement reduction piles at the required locations within the underwater operation area; S2, underwater foundation trench construction, the underwater foundation trench construction is to excavate the foundation trench at the underwater position corresponding to the settlement reduction pile and form a water area transportation channel foundation trench, the water area transportation channel foundation trench is connected with the transfer transportation channel and is used to transport the prefabricated box culvert and the prefabricated cap; S3, installation and construction of prefabricated caps, the installation and construction of prefabricated caps is to install the caps that are transported underwater together with the water transport channel foundation trench and the transfer transport channel respectively on top of the corresponding settlement reduction piles; S4, underwater foundation trench treatment, the underwater foundation trench treatment is to level the underwater foundation trench so that it is flush with the top surface of the prefabricated foundation; S5. Prefabricated box culvert sinking: the prefabricated box culvert sinking is to transport the water transport channel foundation trench and the transfer transport channel together to the underwater prefabricated box culvert and install them on the corresponding caps respectively; S6. Underwater docking of prefabricated box culverts. Underwater docking of prefabricated box culverts is to control the state of the prefabricated box culverts in the water and make the interfaces of two adjacent prefabricated box culverts achieve precise docking. After the adjacent prefabricated box culverts are docked and sealed, the corresponding end sealing doors are removed respectively and then connected to form an underwater subway tunnel. The end sealing doors of the above-mentioned prefabricated box culverts are in the form of concrete end sealing doors, steel structure end sealing doors or assembled end sealing doors.
[0024] like Figure 1 As shown in , the main method steps of the present invention include pile foundation construction, underwater foundation trench construction, prefabricated pedestal installation construction, underwater foundation trench treatment, prefabricated box culvert sinking and underwater prefabricated box culvert docking. After the construction in the underwater operation area according to the above steps, a sealed cavity can be formed to achieve water-stopping underwater prefabricated subway tunnel, which solves the problem that it is difficult to achieve sealing and water-stopping in the foundation pit using traditional retaining structures in highly permeable strata in reclamation areas. The method of assembling prefabricated box culverts with water is adopted to form a set of economic, efficient, adaptable, safe and quality-controlled construction technology, which can be widely used in the future.
[0025] like Figure 2 and Figure 3 As shown in , in a preferred embodiment, the above-mentioned transfer and transportation channel 4 preferably includes a land transportation channel 40 and a water transportation channel 41 which are connected in sequence, and the water transportation channel 41 is connected to the water transportation channel base trench 3.
[0026] like Figure 2 As shown in , the present invention also includes a land operation area 1, which includes a material and equipment yard 10, a box culvert and foundation prefabrication yard 11 and a land transportation channel 40.
[0027] The foundation treatment of land operation area 1 includes the use of dynamic compaction replacement method in high fill areas and the use of vibration compaction method in low-lying areas.
[0028] In this embodiment, Figure 7 As shown in the figure, the top plate and the bottom plate of the prefabricated box culvert 5 are symmetrically arranged with prestressed steel cables 51, and the side walls on both sides of the prefabricated box culvert 5 are also symmetrically arranged with prestressed steel cables 51, so as to increase the bearing capacity of the prefabricated box culvert 5; The temporary prestressed cable 52 is built into the cavity of the prefabricated box culvert 5, which makes the prefabricated box culvert structure bear compressive stress, thereby causing it to produce a certain deformation, namely, an arching effect, to cope with the load on the prefabricated box culvert structure itself. When the temporary prestressed cable 52 is installed during the prefabricated box culvert 5 and the backfilling construction process, as the water and soil pressure increases, the arching effect comes into play, so that the prefabricated box culvert can gradually unload the stress in the temporary prestressed cable to improve the bearing capacity of the prefabricated box culvert.
[0029] like Figure 3 As shown in , specifically, in this embodiment, the water transport channel 41 has a transport channel 410 with an inclined slope of 1:10, a slideway (using a steel rail slideway 411, etc.) is arranged on the transport channel 410, and a transport vehicle 412 for transporting the prefabricated cap 6 or the prefabricated box culvert 5 runs on the slideway, and the transport vehicle 412 is driven by a traction device 413 to reciprocate along the slideway; A prefabricated box culvert concrete bottom form 12 is provided in the prefabrication area of the prefabricated box culvert 5, and sleepers 13 and transport airbags 14 are provided on the prefabricated box culvert concrete bottom form 12. The prefabricated box culvert 5 is transferred from the prefabricated box culvert concrete bottom form 12 to the transport vehicle 412 by using the traction equipment 413 and the rolling of the transport airbag 14. The transport vehicle 412 moves the prefabricated box culvert 5 from the land transport channel 40 to the water transport channel 41 under the drive of the traction equipment 413. As the transport vehicle 412 is transported, the prefabricated box culvert 5 gradually separates from the transport vehicle 412 and completely floats on the water surface (e.g. Figure 3 As shown in II, the prefabricated box culvert 5 floats beyond the water level A, that is, the prefabricated box culvert 5 enters the foundation trench 3 of the water transport channel. At this time, the floating transportation of the prefabricated box culvert 5 can be realized. The floating transportation process of the present invention can be fully realized through calculation and analysis. The specific analysis is: suppose the height of the prefabricated box culvert pipe section exposed above the water surface during the floating transportation is h, the pipe section height is H, the pipe section width is B, the pipe section length is L, and the water gravity is γ w , the total weight of the pipe section is G, the deadweight of the end sealing door is Q, and the anti-floating safety factor is K; prefabricated box culvert K = (B × L × (Hh) × γ w ) / (G+Q)>1, that is, the prefabricated box culvert pipe section has the conditions for floating.
[0030] like Figure 4 As shown in the figure, the water transport channel foundation trench 3 is provided with ground anchors 8 on opposite sides of the settlement reduction piles 7, and two adjacent ground anchors 8 on the same side are arranged at intervals; After the prefabricated cap 6 and the prefabricated box culvert 5 are transported into the water transport channel foundation trench 3 respectively by the above-mentioned transport vehicle 412, the prefabricated cap 6 is installed on the settlement reduction pile 7 after being locked in position by the ground anchor 8, and then the prefabricated box culvert 5 is placed on the prefabricated cap 6 after being locked in position by the ground anchor 8.
[0031] like Figure 6As shown in the figure, after a plurality of prefabricated box culverts 5 are placed one by one on the corresponding prefabricated caps 6, the water pressure and the pulling jacks 9 are used together to enable the relative prefabricated box culverts 5 to be accurately docked.
[0032] The closed compartment formed by the end sealing door of each prefabricated box culvert 5 is equipped with a ballast water tank 53. The ballast water tank is a conventional technology and can be used to remotely control the negative buoyancy and posture of the prefabricated box culvert in the water, and at the same time assist in the precise docking of the prefabricated box culverts 5.
[0033] like Figure 1 and Figure 5 As shown in , the construction steps also include backfilling, which includes a graded crushed stone layer 30, a backfill crushed stone layer 31 and a top soil layer 32 of the prefabricated box culvert, which are backfilled in sequence from bottom to top.
[0034] To facilitate understanding of the overall concept of the invention, the working principle of the invention is described below by way of example: like Figure 1 As shown in the example, firstly, according to the layout path of the subway tunnel, a nearby site is selected as the land operation area 1, which includes a material and equipment yard 10, a box culvert and abutment prefabrication site 11, and a land transportation channel 40; the land operation area 1 adopts a strong tamping replacement method in high fill areas and a vibro-compaction method in low-lying areas to carry out foundation treatment within the range; then, the construction of the settlement reduction piles 7 and the underwater foundation trench excavation are carried out in the direction of the layout path of the subway tunnel. In this example, the construction of the land operation area 1 is carried out simultaneously, which basically includes the prefabrication of the prefabricated box culvert 5 and the prefabricated abutment 6; then, the submerged piles 7 and the underwater foundation trench excavation are carried out in the direction of the layout path of the subway tunnel. The construction of the lower foundation trench forms a foundation trench 3 for the water transport channel, which is connected to the transfer transport channel 4 and is used to transport the prefabricated box culvert 5 and the prefabricated cap 6. The specific transportation process is to use the rail slide 411 and the traction equipment 413 to move the prefabricated cap 6 and the prefabricated box culvert 5 from the land operation area 1 to the deep water area of the underwater operation area 2 through the land transport channel 40 and the water transport channel 41, and then use the anchor 8 and the traction equipment 413 to move the prefabricated box culvert 5 and the prefabricated cap 6 to the shallow water area, that is, the designated position within the layout path of the subway tunnel for underwater installation and connection.
[0035] like Figure 3 As shown in the figure, the specific transportation method is to install the assembled end sealing door 50 before the prefabricated box culvert 5 is floated, so that each prefabricated box culvert 5 forms a closed structure, and during construction, the top of the prefabricated box culvert concrete bottom mold 12 is composed of sleepers 13 and transport air bags 14, and the prefabricated box culvert 5 is moved to the transport vehicle 412 by the rolling of the transport air bag 14 using the traction equipment 413.
[0036] After the prefabricated box culvert 5 is moved to the top of the transport vehicle 412, the transport vehicle 412 is moved from the land transport channel 40 to the water transport channel 41 through the rail slide 411 by the traction device 413 (winch), and the water transport channel 41 has a slope; when the transport vehicle 412 moves to the deep water area of the underwater operation area 2, the prefabricated box culvert 5 gradually separates from the transport vehicle 412 and completely floats on the water surface. The transport vehicle 412 in the deep water area is pulled back to the land transport channel 40 by the rail slide 411 using the traction device 413, and is ready for the next transportation.
[0037] like Figure 4 As shown in the figure, settlement reducing piles 7 are constructed within the scope of the subway tunnel layout path, and they are constructed synchronously with the land operation area 1. At the same time, underwater foundation trench is excavated within the scope of the subway tunnel layout path to form a water transport channel foundation trench 3. A group of ground anchors 8 are installed at intervals on opposite sides of the foundation trench corresponding to the positions of the settlement reducing piles 7. The prefabricated cap 6 is transported to the water transport channel foundation trench 3 by the above method. The prefabricated cap 6 is installed in place by using the traction equipment 413 and the ground anchors 8, so that an effective connection is formed between the settlement reducing piles 7 and the prefabricated cap 6. The installation of the prefabricated cap 6 is a prior art in the field and will not be described in detail here.
[0038] like Figure 6 As shown in the figure, in the above-mentioned water transport channel foundation trench 3, the prefabricated box culvert 5 is installed in place by using the traction equipment 413 and the anchor 8 by using the above-mentioned method, and the negative buoyancy and posture of the prefabricated box culvert 5 in the water can be remotely controlled by using the ballast water tank device 53 in the closed compartment of the prefabricated box culvert 5. After the water between the end sealing doors 50 is removed, the water pressure and the pulling jack 9 are used to make it possible to dock accurately; In order to ensure the overall sealing and waterproofness of the subway tunnel, Figure 8 and Fig. 9 As shown in the figure, the outer peripheral wall of the prefabricated box culvert interface 57 is annularly arranged with a GINA rubber water stop 55 as the first water stop line, and the OMEGA rubber water stop 56 is close to it as the second water stop line; after the prefabricated box culvert 5 is installed and spliced, the assembled end sealing door 50 is removed, so that each prefabricated box culvert 5 forms an integrally connected and sealed subway tunnel. This sealing technology is a prior art in this field and will not be described one by one.
[0039] like Figure 5 and Figure 1 As shown in , the construction steps finally include backfilling, which includes backfilling the graded crushed stone layer 30, the backfill crushed stone layer 31 and the top soil layer 32 of the subway tunnel in sequence from bottom to top of the water transport channel foundation trench 3.
[0040] Expanded explanation: The first treatment method for the foundation trench of the water transport channel is the first paving method. First, the foundation trench is leveled, and graded crushed stones 30 are first laid between the prefabricated caps, flush with the top surface of the prefabricated cap 6, and the vibratory compaction method is used to make the filling material dense; then fill with sand for leveling to ensure the overall flatness of the foundation trench. Make full use of the crushed stones excavated from the foundation trench, and cooperate with the advanced first paving method construction technology to backfill the crushed stone layer 31, flush with the top surface of the prefabricated box culvert 5, meet the stress performance requirements of the base bed while reducing the environmental damage caused by crushed stone mining, and then cover the top of the prefabricated box culvert 5 with soil.
[0041] like Figure 7 As shown in , this embodiment uses prestressed reinforced concrete prefabricated box culverts to assemble subway tunnels. Prestressed steel cables 51 are symmetrically arranged on both sides of the top and bottom plates of the prefabricated concrete box culvert 5, and their function is to increase the shear resistance of the top and bottom plates of the box culvert. Temporary prestressed cables 52 are set in the prefabricated box culvert 5. During the installation of the prestressed concrete prefabricated box culvert and the backfilling construction process, as the water and soil pressure increases, the stress in the temporary prestressed cables is gradually unloaded. The application of prestressed steel bars and cables can not only improve the bearing capacity of the concrete prefabricated box culvert, but also improve the anti-seepage performance of concrete.
[0042] In order to meet the anti-floating requirements during the construction phase, the prefabricated box culvert 5 is also designed with a counterweight bin 54, which is backfilled with plain concrete or graded sand and gravel. The anti-floating coefficient of the subway tunnel during the use phase must meet the requirements of the current national standards, and the counterweight of the plain concrete or graded sand and gravel backfilled in the counterweight bin is determined according to calculations.
[0043] The above description is only a preferred specific implementation manner of the present invention, but the present invention is not limited thereto. All technicians familiar with the technical field within the technical scope disclosed in the present invention and based on the technical scheme of the present invention and the concept of the present invention are within the protection scope of the present invention.
Claims
1. A method for constructing an assembled subway tunnel in a high-water area, comprising a prefabricated box culvert, a prefabricated cap and a transfer and transportation channel, wherein the prefabricated box culvert has an end sealing door structure to form a seal, It is characterized in that It also includes underwater operation areas, where the construction steps are as follows: S1. Pile foundation construction, which is the installation of sinking reduction piles at required locations within the underwater operation area; S2, underwater foundation trench construction, the underwater foundation trench construction is to excavate a foundation trench at the underwater position corresponding to the sinking reduction pile and form a water area transportation channel foundation trench, the water area transportation channel foundation trench is connected to the transfer transportation channel and is used to transport the prefabricated box culvert and the prefabricated cap; S3, installation and construction of prefabricated caps, wherein the prefabricated caps are installed on the corresponding subsidence reducing piles after the foundation trench of the water transport channel and the transfer transport channel are transported underwater together; S4, underwater foundation trench treatment, the underwater foundation trench treatment is to level the underwater foundation trench so that it is flush with the top surface of the prefabricated foundation; S5, sinking the prefabricated box culvert, wherein the prefabricated box culvert is to transport the prefabricated box culvert together with the base trench of the water transport channel and the transfer transport channel and install them on corresponding caps respectively; S6. Underwater docking of prefabricated box culverts. The underwater docking of the prefabricated box culverts is achieved by controlling the state of the prefabricated box culverts in water and making the interfaces of two adjacent prefabricated box culverts achieve precise docking. After the adjacent prefabricated box culverts are docked and sealed, the corresponding end sealing doors are removed respectively and then connected to form a subway tunnel.
2. The method for constructing an assembled subway tunnel in a high water level area according to claim 1, It is characterized in that The prestressed steel cables are symmetrically arranged on the top plate, bottom plate and side wall of the prefabricated box culvert, so as to increase the bearing capacity of the prefabricated box culvert; Temporary prestressed cables are built into the cavity of the prefabricated box culvert, so that the prefabricated box culvert structure is subjected to compressive stress, thereby causing it to produce a certain deformation, namely, an arching effect, to cope with the load borne by the prefabricated box culvert structure itself. When the temporary prestressed cables are installed in the prefabricated box culvert and the backfilling construction process, as the water and soil pressures increase, the arching effect comes into play, so that the prefabricated box culvert can gradually unload the stress in the temporary prestressed cables to improve the bearing capacity of the prefabricated box culvert.
3. The method for constructing an assembled subway tunnel in a high water level area according to claim 1, It is characterized in that The transfer transport channel includes a land transport channel and a water transport channel which are connected in sequence, and the water transport channel is connected to the water transport channel base trench.
4. A method for constructing an assembled subway tunnel in a high water level area according to claim 3, It is characterized in that The water transport channel has a transport channel with an inclined slope, a slide is arranged on the transport channel, a transport vehicle for transporting prefabricated caps or prefabricated box culverts runs on the slide, and the transport vehicle is driven by a traction device to reciprocate along the slide; A prefabricated box culvert concrete bottom form is provided in the prefabrication area of the prefabricated box culvert, sleepers and transport airbags are provided on the prefabricated box culvert concrete bottom form, the prefabricated box culvert is transferred from the prefabricated box culvert concrete bottom form to a transport vehicle by using the traction equipment and rolling of the transport airbag, and the transport vehicle moves the prefabricated box culvert from the land transport channel to the water transport channel under the drive of the traction equipment; As the transport vehicle is transporting, the prefabricated box culvert gradually separates from the transport vehicle and completely floats on the water surface, that is, the prefabricated box culvert enters the foundation trench of the water area transport channel.
5. The method for constructing an assembled subway tunnel in a high water level area according to claim 4, It is characterized in that The water area transport channel foundation trench is provided with ground anchors on opposite sides of the settlement reduction piles, and the two adjacent ground anchors on the same side are arranged at intervals; After the prefabricated cap and the prefabricated box culvert are transported into the foundation trench of the water transport channel respectively by the above-mentioned transport vehicle, the prefabricated cap is installed on the settlement reduction pile after passing through the anchor fixing position, and then the prefabricated box culvert is placed on the prefabricated cap after passing through the anchor fixing position.
6. The method for constructing an assembled subway tunnel in a high water level area according to claim 5, It is characterized in that After the multiple prefabricated box culverts are placed one by one on the prefabricated foundation, the prefabricated box culverts that are opposite to each other can be accurately docked under the combined action of water pressure and the pulling jack.
7. The method for constructing an assembled subway tunnel in a high water level area according to claim 6, It is characterized in that The closed compartment formed by the end sealing door of each prefabricated box culvert is equipped with a ballast water tank, which can be used to remotely control the negative buoyancy and posture of the prefabricated box culvert in the water, and at the same time assist in the precise docking of the prefabricated box culverts.
8. The method for constructing an assembled subway tunnel in a high water level area according to claim 1, It is characterized in that The prefabricated box culvert has a counterweight bin, and the counterweight bin is backfilled with plain concrete or graded sand and gravel.
9. The method for constructing an assembled subway tunnel in a high water level area according to claim 1, It is characterized in that The construction steps also include backfilling, which includes backfilling the graded crushed stone layer, the backfill crushed stone layer and the top soil layer of the prefabricated box culvert in sequence from bottom to top of the foundation trench of the water transport channel.
10. The method for constructing an assembled subway tunnel in a high water level area according to any one of claims 1 to 9, It is characterized in that The end sealing door of the prefabricated box culvert is in the form of a concrete end sealing door, a steel structure end sealing door or an assembled end sealing door.
Citation Information
Patent Citations
Prestressed application method in concrete frame box culvert construction
CN103485287A
Stayed cable beam end fixing device for central cable plane cable-stayed bridge concrete box beam
CN103643635A
Launching floating transportation and underwater assembly process of fabricated comprehensive pipe gallery
CN108252328A
Dry-dock-free underwater shallow-buried open-cut large channel basic structure unit and construction method