Prefabricated tubular pile pre-grouting core structure and grouting method thereof

By filling the core before the pipe piles are pressed into the ground and compacting the core material with compaction plates, the problems of low soil cleaning efficiency and difficult to ensure core filling density in the prior art are solved, and efficient core filling density is achieved ensure.

CN119041399AActive Publication Date: 2024-11-29CHINA CONSTR EIGHTH ENG BUREAU TECH CONSTR CO LTD
View PDF 7 Cites 0 Cited by

Patent Information

Application Number
CN202411416058.4
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-10-11
Publication Date
2024-11-29
Estimated Expiration
2044-10-11

AI Technical Summary

Technical Problem

In the prior art, the efficiency of cleaning soil after being pressed into the ground is low, and the compactness of the core when placed horizontally on the ground is difficult to ensure.

Method used

The core is poured before the pipe pile is pressed into the ground, and the core filling material is compacted using compact plates to drain air, forming an adjustable pouring space through the seal plate and compact plate to ensure compaction.

Benefits of technology

It realizes efficient core filling before the pipe piles are pressed into the ground, ensuring the compactness of the core filling and reducing the inefficiency problem during subsequent cleaning.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119041399A_ABST
    Figure CN119041399A_ABST
Patent Text Reader

Abstract

The invention relates to a prefabricated pipe pile pre-grouting core structure and a grouting method thereof.The prefabricated pipe pile pre-grouting core structure comprises a hollow pipe pile, a reinforcement cage capable of being inserted into the pipe pile and a blocking assembly used for being inserted into the pipe pile along with the reinforcement cage to seal part or all of the internal space of the pipe pile to serve as a pouring space; the blocking assembly comprises a sealing plate connected to the first end of the reinforcement cage and a compaction plate arranged on the reinforcement cage in a sleeving mode in a position-adjustable mode, first through holes allowing the corresponding main reinforcements to penetrate through are formed in the positions, corresponding to the main reinforcements of the reinforcement cage, of the compaction plate, and the periphery of the sealing plate and the periphery of the compaction plate are both matched with the inner periphery of the pipe pile. A size-adjustable pouring space is formed in cooperation with the pipe pile; and the grouting assembly is used for pouring concrete into the pouring space and is arranged on the reinforcement cage or the blocking assembly. Core filling can be conducted on the pipe pile before the pipe pile is pressed into the ground, core filling materials are further compacted through the compacting plate, air is exhausted, the compactness of the pre-core-filling pipe pile is guaranteed, and the construction efficiency is high.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the field of building construction, and in particular to a prefabricated pipe pile pre-cast core structure and a casting method thereof. Background Art

[0002] The conventional construction method of pile pouring in the prior art is to press the pile into the ground, and after the earthwork is excavated to expose the pile head, clean the soil that falls into the hollow part of the pile, put in a steel cage, and finally pour concrete. Under this process, the hollow part of the hollow pile will be filled with soil after being pressed into the ground, which increases the subsequent cleaning process. Workers need to clean and dig out the soil of the pile core one by one, and carry it outside the foundation pit, which is extremely inefficient; therefore, the core is poured in advance before being pressed into the ground, which is different from pouring the core when the pipe pile is in a vertical state after being pressed into the ground. At this time, the density of the core pouring material is easy to be guaranteed under the action of gravity. Due to limited construction space, the pipe pile can only be placed horizontally when pouring the core in advance on the ground, and the density of the core pouring is difficult to guarantee when the pipe pile is placed horizontally. Summary of the invention

[0003] In order to solve the above problems, a prefabricated pipe pile pre-filled core structure and a filling method thereof are provided. Before the pipe pile is pressed into the ground, it can be filled with core, and the filling material is further compacted by a compaction plate and the air is discharged, so that the density can be guaranteed.

[0004] A prefabricated pipe pile precast core structure, comprising: a pipe pile with a hollow interior, a steel cage that can be inserted into the pipe pile, a blocking component for closing part or all of the interior space of the pipe pile as the steel cage is inserted into the pipe pile to serve as a casting space, the blocking component comprising a sealing plate connected to the first end of the steel cage and a compaction plate adjustably mounted on the steel cage, a first through hole for the corresponding main reinforcement to pass through is opened on the compaction plate at a position corresponding to each main reinforcement of the steel cage, the outer periphery of the sealing plate and the compaction plate are both adapted to the inner periphery of the pipe pile to achieve the casting space of adjustable size formed in cooperation with the pipe pile; a grouting component for pouring concrete into the casting space, the grouting component being arranged on the steel cage or the blocking component.

[0005] A further improvement of the present invention is that it also includes a lifting rod, the first end of which is fixed to the sealing plate, and the second end is formed with a threaded section, and the compacting plate is provided with a second through hole for the threaded section to pass through, and also includes a nut arranged on the side of the compacting plate facing away from the casting space and corresponding to the second through hole, and the part of the threaded section passing through the second through hole is threadedly connected to the nut.

[0006] A further improvement of the present invention is that the steel cage includes a plurality of main bars extending along the axial direction of the pipe pile, and the plurality of main bars are arranged in a circle along the circumference of the pipe pile; stirrups are tied at intervals along the vertical direction on the outside of the main bars, and the compaction plate is located between two adjacent stirrups.

[0007] A further improvement of the present invention is that the grouting assembly includes a slurry inlet pipe and a slurry outlet pipe connected to the compaction plate and communicated with the interior of the steel cage, and the pipe body of the slurry outlet pipe is transparent.

[0008] A further improvement of the present invention is that the grouting assembly includes an auxiliary grouting tube for being sleeved outside the steel cage and arranged inside the pipe pile, the auxiliary grouting tube is open at both ends, and a grouting groove connected to the interior of the auxiliary grouting tube is opened on the side wall of the auxiliary grouting tube, and the length of the auxiliary grouting tube is greater than the length of the casting space.

[0009] A further improvement of the present invention is that a handle is provided at the second end of the auxiliary perfusion tube for facilitating the insertion or extraction of the auxiliary perfusion tube into or from the pipe pile.

[0010] The pouring method of the prefabricated pipe pile pre-cast core structure comprises the following steps:

[0011] S1, placing the pipe pile horizontally, moving the compaction plate, so that the distance between the compaction plate and the sealing plate is greater than the designed length of the cast-in-place pile;

[0012] S2, inserting the steel cage into the inner hollow part of the pipe pile, and pouring the grouting material into the pouring space through the grouting assembly;

[0013] S3, moving the compacting plate towards the sealing plate so that the distance between the compacting plate and the sealing plate is equal to the designed length of the cast-in-place pile, and exhausting the air in the casting space during the movement;

[0014] S4, after the injection material is solidified and formed, the compaction plate is removed.

[0015] A further improvement of the present invention is that the grouting assembly is a grouting pipe and a grouting pipe connected to the compaction plate and communicated with the interior of the steel cage. When executing step S2, the grouting material is poured into the casting space through the grouting pipe until grout is seen to emerge from the grouting pipe, and the pouring is stopped;

[0016] When executing step S3, the pipe pile is knocked to help exhaust the air in the casting space. If no slurry comes out of the slurry outlet pipe, continue to pour the casting material into the casting space and repeat step S3 until slurry comes out of the slurry outlet pipe again.

[0017] A further improvement of the present invention is that the grouting assembly is an auxiliary grouting tube, the two ends of the auxiliary grouting tube are open, and a grouting groove connected to the inside of the auxiliary grouting tube is opened on the side wall of the auxiliary grouting tube, and the length of the auxiliary grouting tube is greater than the length of the casting space; when executing step S2, the steel cage is sleeved in the auxiliary grouting tube, and the auxiliary grouting tube and the steel cage sleeved therein are slowly pushed into the pipe pile. During the pushing process, the grouting material is continuously poured into the auxiliary grouting tube near the end of the pipe pile until the space between the sealing plate and the compacting plate in the auxiliary grouting tube is completely filled, and the auxiliary grouting tube is pulled out after it is filled;

[0018] When executing step S3, the compaction plate is moved toward the sealing plate so that the distance between the compaction plate and the sealing plate is equal to the designed length of the bored pile, and the casting material is completely filled in the casting space, and the air in the casting space is discharged during the movement.

[0019] The prefabricated pipe pile pre-filling core structure and the filling method thereof provided by the present invention can achieve filling of the pipe pile before it is pressed into the ground, and further compact the filling core material and discharge the air through the compaction plate, so that the density can be guaranteed. BRIEF DESCRIPTION OF THE DRAWINGS

[0020] Figure 1 It is a schematic diagram of the overall structure of the invention;

[0021] Figure 2 For invention Figure 1 The cross-sectional view at 1-1 in FIG.

[0022] Figure 3 For the present invention Figure 1 The cross-sectional view at 2-2 in FIG.

[0023] Figure 4 It is a three-dimensional structural schematic diagram of the auxiliary perfusion cylinder of the present invention;

[0024] Figure 5 A side view of the auxiliary perfusion cylinder of the present invention;

[0025] Figure 6 It is a schematic diagram of the internal structure of the pipe pile of the present invention;

[0026] Figure 7 This is a schematic diagram of the core filling preparation stage of the second embodiment of the present invention;

[0027] Figure 8 This is a schematic diagram of the core filling process of the second embodiment of the present invention;

[0028] Fig. 9 This is a schematic diagram of the second embodiment of the present invention when the core filling is completed;

[0029] Fig.10 This is a schematic diagram of the second embodiment of the present invention when the auxiliary perfusion cylinder is pulled out;

[0030] Fig.11 This is a schematic diagram of the second embodiment of the present invention when a steel bar protection cover is installed;

[0031] Fig.12 This is a schematic diagram of the core filling process of the first embodiment of the present invention;

[0032] Fig.13 This is a schematic diagram of the first embodiment of the present invention when a steel bar protection cover is installed;

[0033] In the figure: 1. Threaded section fixing steel bar; 2. Threaded section; 3. Nut; 4. Gasket; 5. Compacting plate; 6. Compacting foam board; 7. Sealing plate; 8. Sealing foam board; 9. Main reinforcement; 10. Hoop reinforcement; 11. Auxiliary grouting tube; 12. Handle 13. Pipe pile; 14. Hollow part inside the pipe pile; 15. Micro-expansive concrete; 16. Vibrating rod; 17. Gap; 18. Steel bar protective cover 19. Slurry inlet pipe; 20. Slurry outlet pipe; 21. High-strength grouting material. DETAILED DESCRIPTION

[0034] The technical solutions in the embodiments of the present invention will be clearly and completely described below in conjunction with the accompanying drawings in the embodiments of the present invention.

[0035] like Figures 1 to 13 As shown, a prefabricated pipe pile precast core structure comprises: a pipe pile 13 with a hollow interior, a steel cage that can be inserted into the hollow part 14 of the pipe pile 13, and a blocking component for closing part or all of the internal space of the pipe pile 13 as a casting space as the steel cage is inserted into the pipe pile 13, the blocking component comprises a sealing plate 7 connected to the first end of the steel cage and a compaction plate 5 that is adjustably mounted on the steel cage, a first through hole for the corresponding main reinforcement 9 to pass through is opened on the compaction plate 5 at a position corresponding to each main reinforcement 9 of the steel cage, the outer periphery of the sealing plate 7 and the compaction plate 5 are both adapted to the inner periphery of the pipe pile 13, so as to form the casting space with adjustable size in cooperation with the pipe pile 13; a grouting component for pouring concrete into the casting space, the grouting component is arranged on the steel cage or the blocking component.

[0036] like Figure 1 to Figure 3 As shown, it also includes a lifting rod, the first end of which is fixed to the sealing plate 7, and the second end is formed with a threaded section 2. The compacting plate 5 is provided with a second through hole for the threaded section 2 to pass through. It also includes a nut 3 which is arranged on the side of the compacting plate 5 facing away from the casting space and corresponds to the second through hole, and the part of the threaded section 2 passing through the second through hole is threadedly connected to the nut 3.

[0037] like Figure 1As shown, in this embodiment, a sealing foam plate 8 is further provided on the side of the sealing plate 7 close to the pouring space; a compacting foam plate 6 is further provided on the side of the compacting plate 5 close to the pouring space.

[0038] Preferably, if Figure 1 , 3 As shown, in this embodiment, a gasket 4 is sandwiched between the pressing plate 5 and the nut 3.

[0039] like Figure 1 As shown, the steel cage also includes a plurality of main bars 9, and the plurality of main bars 9 are arranged in a circle along the circumference of the pipe pile 13; stirrups 10 are tied to the outside of the circle of main bars 9 at intervals along the vertical direction, and the compaction plate 5 is located between two adjacent stirrups.

[0040] like Figure 1 , 3 As described in 12 and 13, the grouting assembly includes a slurry inlet pipe 19 and a slurry outlet pipe 20 connected to the interior of the steel cage on the compaction plate 5, and the slurry outlet pipe 20 is transparent.

[0041] like Figures 4-5 As shown, the grouting assembly includes an auxiliary grouting tube 11 which is used to be sleeved outside the steel cage and inside the pipe pile 13.

[0042] The auxiliary pouring tube 11 is opened at both ends, and a grouting groove communicating with the inside of the auxiliary pouring tube 11 is opened on the side wall of the auxiliary pouring tube 11. The length of the auxiliary pouring tube 11 is greater than the length of the casting space.

[0043] Preferably, if Figures 4-5 As shown, one end of the auxiliary perfusion tube 11 is provided with a handle 12 for facilitating the insertion or extraction of the auxiliary perfusion tube 11 into or out of the pipe pile 13 .

[0044] The pouring method of the pre-cast core structure of the pipe pile of the present invention is as follows: Figures 7 to 13 As shown, the following steps are included:

[0045] S1, place the pipe pile 13 horizontally, move the compaction plate 5, and make the distance between the compaction plate 5 and the sealing plate 7 greater than the designed length of the cast-in-place pile;

[0046] S2, inserting the steel cage into the inner hollow part of the pipe pile 13, and pouring the grouting material into the pouring space through the grouting assembly;

[0047] S3, move the compacting plate 5 towards the sealing plate 7, so that the distance between the compacting plate 5 and the sealing plate 7 is equal to the designed length of the cast-in-place pile, and exhaust the air in the casting space during the movement;

[0048] S4, after the injection material is solidified and formed, the compaction plate 5 is removed.

[0049] Another embodiment of the grouting method of the pre-cast core structure of the pipe pile of the present invention, in this embodiment, the grouting assembly is a grouting pipe 19 and a grouting pipe 20 connected to the compaction plate 5 and communicating with the interior of the steel cage, such as Figures 12-13 As shown, when executing step S2, the pouring material is poured into the pouring space through the slurry inlet pipe 19 until slurry is seen to emerge from the slurry outlet pipe 20, and then the pouring is stopped;

[0050] When executing step S3, the pipe pile 13 is knocked to help exhaust the air in the pouring space. If no slurry comes out of the slurry outlet pipe 20, the pouring material continues to be poured into the pouring space, and step S3 is repeated until slurry comes out of the slurry outlet pipe 20 again.

[0051] Preferably, in this embodiment, the grouting material is a high-strength grouting material 21 .

[0052] Another embodiment of the pouring method of the pre-cast core structure of the pipe pile of the present invention, the grouting assembly in this embodiment adopts an auxiliary pouring tube 11, the two ends of the auxiliary pouring tube 11 are open, and a pouring groove connected to the inside of the auxiliary pouring tube 11 is opened on the side wall of the auxiliary pouring tube 11, and the length of the auxiliary pouring tube 11 is greater than the length of the pouring space. Figures 7 to 11 As shown, when executing step S2, the steel cage is sleeved in the auxiliary pouring tube 11, and the auxiliary pouring tube 11 and the steel cage sleeved therein are slowly pushed into the pipe pile 13. During the pushing process, the pouring material is continuously poured into the auxiliary pouring tube 11 through the pouring groove near the end of the pipe pile 13 until the auxiliary pouring tube 11 is completely filled between the sealing plate 7 and the compacting plate 5. After filling, the auxiliary pouring tube 11 is pulled out;

[0053] When executing step S3, the compaction plate 5 is moved in the direction of the sealing plate 7 so that the distance between the compaction plate 5 and the sealing plate 7 is equal to the design length of the bored pile, and the casting material is completely filled in the casting space, and the air in the casting space is discharged during the movement; the difference between the distance between the compaction plate 5 and the sealing plate 7 and the design length of the bored pile can be calculated, and the difference must satisfy the condition in step S3 that when the distance between the compaction plate 5 and the sealing plate 7 is equal to the design length of the bored pile, the air in the casting space is discharged.

[0054] Preferably, in this embodiment, the pouring material is micro-expansive concrete 15 .

[0055] Preferably, if Figure 7 to Figure 11 As shown, in this embodiment, a vibrating rod 16 is used to vibrate while pouring the pouring material.

[0056] like Fig.11 , 13 As shown, after the pouring is completed and the compaction plate 5 is removed, a steel bar protection sleeve 18 is sleeved on the second end of the steel bar cage.

[0057] Preferably, a plurality of completed pipe piles 13 can be spliced ​​together to meet the length requirement of the pile foundation of the building project during construction.

[0058] Finally, it should be noted that the above are only preferred embodiments of the present invention and are not intended to limit the present invention. Although the present invention has been described in detail with reference to the aforementioned embodiments, it is still possible for those skilled in the art to modify the technical solutions described in the aforementioned embodiments, or to make equivalent substitutions for some of the technical features therein. Any modifications, equivalent substitutions, improvements, etc. made within the spirit and principles of the present invention should be included in the protection scope of the present invention.

Claims

1. A prefabricated pipe pile pre-filled core structure, characterized in that: include: A hollow pipe pile and a steel cage that can be inserted into the pipe pile, a blocking component used to close part or all of the internal space of the pipe pile as the steel cage is inserted into the pipe pile to serve as a casting space, the blocking component includes a sealing plate connected to the first end of the steel cage and a compaction plate adjustably mounted on the steel cage, a first through hole for the corresponding main reinforcement to pass through is opened on the compaction plate at the position corresponding to each main reinforcement of the steel cage, the outer periphery of the sealing plate and the compaction plate are adapted to the inner periphery of the pipe pile to achieve the casting space of adjustable size formed in cooperation with the pipe pile; a grouting component used for pouring concrete into the casting space, the grouting component is arranged on the steel cage or the blocking component.

2. The prefabricated pipe pile pre-filled core structure according to claim 1, characterized in that: It also includes a lifting rod, a first end of which is fixed to the sealing plate, a second end of which is formed with a threaded section, a second through hole is opened on the compacting plate for the threaded section to pass through, and a nut is arranged on the side of the compacting plate facing away from the casting space and corresponding to the second through hole, and the part of the threaded section passing through the second through hole is threadedly connected to the nut.

3. The prefabricated pipe pile pre-filled core structure according to claim 1, characterized in that: The steel cage includes a plurality of main bars extending along the axial direction of the pipe pile, and the plurality of main bars are arranged in a circle along the circumference of the pipe pile; stirrups are tied at intervals along the vertical direction on the outside of the main bars, and the compaction plate is located between two adjacent stirrups.

4. The prefabricated pipe pile pre-filled core structure according to claim 1, characterized in that: The grouting assembly includes a slurry inlet pipe and a slurry outlet pipe which are connected to the compaction plate and communicated with the interior of the steel cage, and the pipe body of the slurry outlet pipe is transparent.

5. The prefabricated pipe pile pre-filled core structure according to claim 1, characterized in that: The grouting assembly includes an auxiliary grouting tube that is used to be sleeved outside the steel cage and arranged in the pipe pile. The two ends of the auxiliary grouting tube are open, and a grouting groove that is connected to the inside of the auxiliary grouting tube is opened on the side wall of the auxiliary grouting tube. The length of the auxiliary grouting tube is greater than the length of the casting space.

6. The prefabricated pipe pile pre-cast core structure according to claim 5, characterized in that: The second end of the auxiliary perfusion tube is provided with a handle for facilitating the insertion or extraction of the auxiliary perfusion tube into or from the pipe pile.

7. A method for pouring a prefabricated pipe pile pre-cast core structure according to claim 1, characterized in that: The following steps are involved: S1, placing the pipe pile horizontally, moving the compaction plate, so that the distance between the compaction plate and the sealing plate is greater than the designed length of the cast-in-place pile; S2, inserting the steel cage into the inner hollow part of the pipe pile, and pouring the grouting material into the pouring space through the grouting assembly S3, moving the compacting plate towards the sealing plate so that the distance between the compacting plate and the sealing plate is equal to the designed length of the cast-in-place pile, and exhausting the air in the casting space during the movement; S4, after the injection material is solidified and formed, the compaction plate is removed.

8. The method for grouting a precast pipe pile precast core structure according to claim 7, wherein the grouting assembly is a grout inlet pipe and a grout outlet pipe connected to the compaction plate and communicating with the interior of the steel cage, characterized in that: When executing step S2, pouring the pouring material into the pouring space through the slurry inlet pipe until slurry is seen to emerge from the slurry outlet pipe, and then stopping the pouring; When executing step S3, the pipe pile is knocked to help exhaust the air in the casting space. If no slurry comes out of the slurry outlet pipe, continue to pour the casting material into the casting space and repeat step S3 until slurry comes out of the slurry outlet pipe again.

9. The method for pouring a prefabricated pipe pile pre-cast core structure according to claim 7, characterized in that: The grouting assembly is an auxiliary pouring tube, which is open at both ends, and a pouring groove connected to the inside of the auxiliary pouring tube is opened on the side wall of the auxiliary pouring tube, and the length of the auxiliary pouring tube is greater than the length of the casting space; When executing step S2, the steel cage is sleeved in the auxiliary pouring tube, and the auxiliary pouring tube and the steel cage sleeved therein are slowly pushed into the pipe pile. During the pushing process, the pouring material is continuously poured into the auxiliary pouring tube near the end of the pipe pile until the auxiliary pouring tube is completely filled between the sealing plate and the compacting plate. After it is filled, the auxiliary pouring tube is pulled out; When executing step S3, the compaction plate is moved toward the sealing plate so that the distance between the compaction plate and the sealing plate is equal to the designed length of the bored pile, and the casting material is completely filled in the casting space, and the air in the casting space is discharged during the movement.

10. The method for pouring a prefabricated pipe pile pre-cast core structure according to any one of claims 7 to 9, characterized in that: After the pouring is completed and the compaction plate is removed, a steel bar protection sleeve is sleeved on the second end of the steel bar cage.

Citation Information

Patent Citations

  • Method for pouring PHC pipe pile core under confined water condition

    CN115478533A

  • Steel pipe grouting pile

    CN211113612U

  • Construction method for cast-in-place concrete pile

    JP2000212961A

  • SC pile

    JP2013036269A

  • Compaction device and compaction method for cast-in-place concrete pile

    JP2014190128A