Secondary structure preposed construction method
Through the method of simultaneous construction of primary and secondary structures, steel bar binding and formwork support are used to solve the problems of construction intervals and joint parts, achieving seamless connection and crack resistance improvement, shortening construction period and saving costs.
Patent Information
- Application Number
- CN202411353825.1
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-09-26
- Publication Date
- 2024-11-29
AI Technical Summary
In construction, the existing technology leads to a long construction interval between the primary structure and the secondary structure, cumbersome processes, easy to be misaligned in the joint parts, foam concrete walls can easily cause gap cracks, poor quality of the planting tends to lead to secondary structures Unable to anchor into primary structural concrete.
The primary structure and secondary structure are constructed simultaneously, and the foam concrete wall is poured by binding steel bars, supporting the formwork at the same time, pouring the structural concrete once after the final set, and using extruded plates and self-adhesive fiberglass mesh to avoid cracks. Realize anchoring of steel bars into primary structural concrete.
It achieves seamless connection, shortens construction period, saves costs, avoids construction intervals, ensures flatness and perpendicularity, enhances crack and seismic resistance, and is directly anchored into the primary structural concrete, protecting the integrity of the primary structure.
Smart Images

Figure CN119041556A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of building construction, and in particular to a secondary structure pre-construction method. Background Art
[0002] During the construction process, the building structure is divided into primary structure and secondary structure. The primary structure mainly refers to the foundation and main structure of the building project, including but not limited to foundation beams, bottom plates, basements, side wall top plates, structural beams / plates / columns, shear walls and stairs, etc. These parts usually bear the main load-bearing function of the building and are the core parts of the building structure. In terms of construction sequence, the primary structure is constructed before the secondary structure, and they together constitute the main frame and support system of the building; the secondary structure mainly involves non-load-bearing components in the frame, shear wall, frame-shear engineering, such as structural columns, lintels, infill walls, partition walls, etc. These components need to be completed before decoration. The construction time of the secondary structure is usually after the construction of the primary structure (referring to the load-bearing component part of the main structure) is completed. The secondary structure includes but is not limited to masonry, structural columns, lintels, water-stop beams, parapets, cappings, infill walls, partition walls, post-cast strips, etc., among which masonry structure is the most important component; the existing traditional construction process is to construct the secondary structure after the primary structure is completed, especially when constructing foam concrete walls and primary structures, the primary structure body is now constructed first, and the secondary structure can only be constructed when the construction reaches at least six floors. First, holes are drilled on the wall columns of the primary structure to implant anchor reinforcement, and then the reinforcement is tied to support the formwork and concrete is poured; the defects of the existing technology are as follows: the construction interval between the primary structure and the secondary structure is long; the process is cumbersome, and the joints of the two structure constructions are prone to misalignment; the foam concrete is not easy to fill the bottom of the beam, which can easily cause gaps and cracks; the quality of the embedded reinforcement is not guaranteed, and the drilling position is not easy to grasp, thereby damaging the primary structure concrete; the secondary structure mesh reinforcement cannot be anchored into the primary structure concrete.
[0003] Therefore, it is an issue worthy of study to provide a method for pre-construction of secondary structure that can simultaneously construct and complete the primary structure and secondary structure to shorten the construction period and save costs. Summary of the invention
[0004] The purpose of the present invention is to provide a secondary structure pre-construction method in which a primary structure and a secondary structure are constructed and completed simultaneously to shorten the construction period and save costs.
[0005] The object of the present invention is achieved in that: A secondary structure pre-construction method comprises the following steps: Step 1: Position and lay out the lines and tie the steel bars. Pre-embed the water and electricity pipes and boxes. Anchor the steel mesh into the primary structure beam, column and wall. The upper end of the steel mesh should not be anchored into the beam to prevent the steel mesh from bending after the beam is stressed, causing cracks in the foam concrete wall. The upper end of the steel mesh should be flush with the bottom of the extruded board.
[0006] Step 2: The formwork of the primary structure and the formwork of the secondary structure are set up simultaneously; Step 3: Casting a secondary structure; the secondary structure is a foam concrete wall; Step 4: After the foam concrete wall in step 3 is finally set, pour the structural concrete again; Step 5: Remove the mold.
[0007] Step 6: After removing the mold and before removing the steel pipe bracket, use a 15mm diameter soldering iron to hot-melt a hole every 3cm in the extruded board at the middle third of the beam (the hole depth is the same as the wall thickness) to allow the structural beam to fully exert its force and avoid the foam concrete wall from being under pressure; after the structural beam is fully stressed, fill the holes with polyurethane foam glue, and use a 20cm wide self-adhesive fiberglass mesh to fully stick along the extruded board to avoid cracks, and then use putty to prime the surface for decorative purposes.
[0008] The steel bars of the secondary structure are anchored into the concrete of the primary structure.
[0009] The concrete of the primary structure and the concrete of the secondary structure are separated by a 2 cm thick extruded board to achieve a soft connection.
[0010] In step 3, an extruded board is arranged on the top of the foam concrete wall. The width of the extruded board on the top of the foam concrete wall is the same as the thickness of the foam concrete wall. The length of the extruded board is fully spread along the foam concrete wall. The extruded board on the top of the foam concrete wall is placed on the tension screw support for reinforcing the formwork on both sides.
[0011] The extruded board has suitable holes reserved at both ends of the middle one-third section of the structural beam for pouring foam concrete and exhausting. After the foam concrete is poured, the holes are blocked with the extruded board; the width of the extruded board separating the foam concrete wall end from the primary structure wall column is the same as the width of the foam concrete wall, and the height of the extruded board separating the foam concrete wall end from the primary structure wall column is the same as the height of the foam concrete wall. The extruded board is tied to the wall column steel bars of the primary structure, and a tension screw is set on one side of the primary structure formwork to support and fix it.
[0012] In the step 2, before pouring concrete on the primary structural beam, a steel pipe support is used to support the bottom of the primary structural beam, and the steel pipe support is removed after the concrete of the primary structural beam reaches 100% strength to prevent the secondary structural wall from being stressed.
[0013] The steel pipe supports are arranged at intervals of no more than one meter within the clear span of the primary structural beam and are firmly connected to other full-frame supports.
[0014] After the formwork is removed in step 5, during the construction of the through-wall pipe hole, a pipe with the same length and diameter as the embedded wall is used as a mold to prefabricate concrete prefabricated blocks with the same grade as the wall. After the formwork and the through-wall pipe are removed, adhesive is applied to the surface of the prefabricated block and plugged into the hole.
[0015] The beneficial effects of the present invention are as follows: the primary structure and the secondary structure of the present invention are constructed and completed at the same time, achieving seamless connection, avoiding a long process interval, greatly shortening the construction period, and saving costs; the layout and positioning are performed once, and the formwork is supported and cast once, and the joint between the primary structure and the secondary structure has no cracks and no misalignment, and the appearance is good, the flatness and verticality are easy to control, and the plastering and leveling layer can be avoided; the mesh reinforcement of the secondary structure is directly anchored into the concrete of the primary structure, and the steel mesh is anchored into the beam, column and wall of the primary structure during the steel bar binding in step 1. The upper end of the steel mesh should not be anchored into the beam to prevent the steel mesh from bending after the beam is stressed, causing cracks in the foam concrete wall. The upper end of the steel mesh can be flush with the bottom of the extruded board, so the crack resistance and earthquake resistance are better. At the same time, the anchor is firmly pulled, eliminating the need to set anchor reinforcement separately, saving labor and cost, and protecting the integrity of the primary structure concrete. BRIEF DESCRIPTION OF THE DRAWINGS
[0016] Figure 1 A perspective view of the present invention; Figure 2 It is an elevation view of the present invention; Figure 3 It is a cross-sectional view along the AA direction of the present invention; In the figure: primary structure wall column 1, foam concrete wall 2, extruded board 3, primary structure beam 4, floor slab 5, vertical pipe 6, wall pipe 7, small cross bar 8, steel mesh 9. DETAILED DESCRIPTION
[0017] The present invention is further described below in conjunction with the accompanying drawings and embodiments.
[0018] like Figures 1 to 3 As shown, a secondary structure pre-construction method comprises the following steps: Step 1: Positioning, laying out and tying steel bars; the steel bars of the secondary structure are anchored into the concrete of the primary structure, and the steel mesh is anchored into the beams, columns and walls of the primary structure. The upper end of the steel mesh should not be anchored into the beam to prevent the steel mesh from bending after the beam is stressed, causing cracks in the foam concrete wall. The upper end of the steel mesh should be flush with the bottom of the extruded board.
[0019] Step 2: The formwork of the primary structure and the formwork of the secondary structure are set up at the same time; the concrete of the primary structure is separated from the concrete of the secondary structure by a 2 cm thick extruded board to achieve a soft connection. Before pouring concrete on the primary structure beam, a steel pipe bracket is used to support the bottom of the primary structure beam 4, and it is removed after the concrete of the primary structure beam 4 reaches 100% strength to avoid stress on the secondary structure wall.
[0020] The steel pipe bracket is arranged at intervals of no more than one meter within the clear span of the primary structural beam and is firmly connected to other full-frame brackets. The steel pipe bracket includes a vertical pipe 6, a wall-penetrating pipe 7 and a small cross bar 8.
[0021] Step 3: Cast the secondary structure; the secondary structure is a foam concrete wall; an extruded board 3 is set on the top of the foam concrete wall, the width of the extruded board 3 on the top of the foam concrete wall 2 is the same as the thickness of the foam concrete wall, the length of the extruded board 3 is fully spread along the foam concrete wall 2, and the extruded board 3 on the top of the foam concrete wall 2 is placed on the tension screw support that reinforces the templates on both sides. The extruded board 3 has suitable holes reserved at both ends of the middle third section of the structural beam for pouring foam concrete and exhausting. After the foam concrete is poured, the holes are blocked with the extruded board 3; the width of the extruded board 3 separating the end of the foam concrete wall 2 from the primary structure wall column 1 is the same as the width of the foam concrete wall 2, and the height of the extruded board 3 separating the end of the foam concrete wall 2 from the primary structure wall column 1 is the same as the height of the foam concrete wall 2. The extruded board 3 is tied to the steel bars of the primary structure wall column 1, and a tension screw support is set on one side of the primary structure template to fix it.
[0022] Step 4: After the foam concrete wall in step 3 has finally set, pour the structural concrete again.
[0023] Step 5: Demoulding. After the step 5 is demoulded, in the construction of the through-wall pipe hole, a pipe with the same length and diameter as the pre-embedded wall is used as a mould to prefabricate a concrete prefabricated block with the same grade as the wall. After the formwork and through-wall pipe 7 are removed, the surface of the prefabricated block is coated with adhesive and plugged into the hole.
[0024] Step 6: After removing the mold and before removing the steel pipe bracket, use a 15mm diameter soldering iron to hot-melt a hole every 3cm in the extruded board at the middle third of the beam (the hole depth is the same as the wall thickness) to allow the structural beam to fully exert its force and avoid the foam concrete wall from being under pressure; after the structural beam is fully stressed, fill the holes with polyurethane foam glue, and use a 20cm wide self-adhesive fiberglass mesh to fully stick along the extruded board to avoid cracks, and then use putty to prime the surface for decorative purposes.
Claims
1. A secondary structure pre-construction method, Features: The following steps are involved: Step 1: Position and lay out the lines and tie the steel bars. Pre-embed the water and electricity pipes and boxes. Anchor the steel mesh into the primary structural beam, column and wall. The upper end of the steel mesh is not anchored into the beam to prevent the steel mesh from bending after the beam is stressed, causing cracks in the foam concrete wall. The upper end of the steel mesh is flush with the bottom of the extruded board. Step 2: The formwork of the primary structure and the formwork of the secondary structure are set up simultaneously; Step 3: Casting the secondary structure; the secondary structure is a foam concrete wall; the concrete of the primary structure and the concrete of the secondary structure are separated by an extruded board to achieve a soft connection; Step 4: After the foam concrete wall in step 3 is finally set, pour the structural concrete again; Step 5: demoulding; Step 6: After removing the mold and before removing the steel pipe bracket, use a 15mm diameter soldering iron to hot-melt a hole every 3cm in the extruded board at the middle third of the beam, so that the structural beam can fully exert its force-bearing effect; after the structural beam is fully stressed, fill the holes with polyurethane foam glue, and use a 20cm wide self-adhesive fiberglass mesh to fully stick along the extruded board to avoid cracks, and then use putty to prime the surface for decorative purposes.
2. The secondary structure pre-construction method according to claim 1, Features: The steel bars of the secondary structure are anchored into the concrete of the primary structure.
3. The secondary structure pre-construction method according to claim 1, Features: In step 3, an extruded board is arranged on the top of the foam concrete wall. The width of the extruded board on the top of the foam concrete wall is the same as the thickness of the foam concrete wall. The length of the extruded board is fully spread along the foam concrete wall. The extruded board on the top of the foam concrete wall is placed on the tension screw support for reinforcing the formwork on both sides.
4. The secondary structure pre-construction method according to claim 3, Features: The extruded board has reserved holes at both ends of the middle one-third section of the structural beam for pouring foam concrete and exhausting. After the foam concrete is poured, the holes are blocked with the extruded board; the width of the extruded board separating the foam concrete wall end from the primary structure wall column is the same as the width of the foam concrete wall, and the height of the extruded board separating the foam concrete wall end from the primary structure wall column is the same as the height of the foam concrete wall. The extruded board is tied to the wall column steel bars of the primary structure, and a tension screw is set on one side of the primary structure formwork to support and fix it.
5. The secondary structure pre-construction method according to claim 1, Features: In the step 2, before pouring concrete on the primary structural beam, a steel pipe support is used to support the bottom of the primary structural beam, and the steel pipe support is removed after the concrete of the primary structural beam reaches 100% strength to prevent the secondary structural wall from being stressed.
6. The secondary structure pre-construction method according to claim 5, Features: The steel pipe supports are arranged at intervals of no more than one meter within the clear span of the primary structural beam and are firmly connected to other full-frame supports.
7. The secondary structure pre-construction method according to claim 1, Features: After the formwork is removed in step 5, during the construction of the through-wall pipe hole, a pipe with the same length and diameter as the embedded wall is used as a mold to prefabricate concrete prefabricated blocks with the same grade as the wall. After the formwork and the through-wall pipe are removed, adhesive is applied to the surface of the prefabricated block and plugged into the hole.