Boiler drain recovery processing device
Through the design of boiler hydrophobic recovery and treatment device, including extraction, heat exchange and chemical treatment, the problems of heat energy recovery and water resource waste in boiler hydrophobic are solved, energy efficiency is improved, scale is prevented, and the effective utilization of hydrophobic is achieved.
Patent Information
- Application Number
- CN202411031507.3
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-07-30
- Publication Date
- 2024-11-29
AI Technical Summary
The heat energy in the boiler's hydrophobic water is difficult to recycle, resulting in large energy consumption and serious waste of water resources. The high salt content in the hydrophobic water is likely to lead to scaling and corrosion.
A boiler hydrophobic recycling and treatment device is designed, including a extraction part, a converter and a drug release assembly. The hydrophobic is extracted through a spiral tube and heat is recovered by a heat exchanger. The collector collects hydrophobicity and releases chemical treatment agents as needed to remove impurities and scrapes them. Parts prevent scaling.
It effectively improves energy efficiency, reduces operating costs, reduces water resource waste, and prevents the occurrence of scaling.
Smart Images

Figure CN119042613A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of thermal power plant boilers, and in particular to a boiler drain recovery and processing device. Background Art
[0002] During the startup of a thermal power plant, the boiler drain expansion tank will recycle water from the boiler cold water wash and the boiler hot water top discharge. When the water quality test is qualified, it will be recycled to the condenser. The recovery temperature of the cold water wash will not be too high, so the condenser temperature will not be high after recycling. As the temperature and pressure of the boiler rise, a large amount of hot water enters the condenser, causing the condenser temperature to rise, which is not conducive to the cold startup of the unit. Therefore, the water balance of the boiler hot water top discharge is often maintained by discharging it to the unit drain tank.
[0003] The water quality of this drain is close to that of desalted water and can only be treated as wastewater and discharged into the drain tank. The drain contains a large amount of heat energy, which is difficult to recycle and utilize reasonably. The boiler consumes a lot of energy, and the drain is directly discharged without recycling and reasonable utilization, which causes a great waste of water resources and increases the cost of starting up the thermal power plant. In addition, the salt content in the drain is high, and no matter where it is discharged, it may cause scaling and corrosion. Summary of the invention
[0004] The purpose of this section is to summarize some aspects of embodiments of the present invention and briefly introduce some preferred embodiments. Some simplifications or omissions may be made in this section and the specification abstract and the invention title of this application to avoid blurring the purpose of this section, the specification abstract and the invention title, and such simplifications or omissions cannot be used to limit the scope of the present invention.
[0005] In view of the above-mentioned problems that the heat of hydrophobicity is difficult to recycle, water resources are wasted, and hydrophobicity easily causes scaling and corrosion, the present invention is proposed.
[0006] Therefore, an object of the present invention is to provide a boiler drain recovery and processing device.
[0007] In order to solve the above-mentioned technical problems, the present invention provides the following technical solutions: a boiler drain recovery and treatment device, comprising a conversion component, including a mounting component, an extraction component arranged on the mounting component, and a conversion component arranged on the mounting component; a medicine release component, comprising a collecting component arranged in the mounting component, a medicine release component arranged on the mounting component, and an opening component arranged on the medicine release component; and a cleaning component, comprising a pressing component arranged on the collecting component, a scraping component arranged on the collecting component, and a connecting component arranged in the collecting component.
[0008] As a preferred solution of the boiler drain recovery and treatment device of the present invention, the installation component includes a box body, a drain valve arranged on the box body, and a drain pipe arranged on the drain valve.
[0009] As a preferred solution of the boiler drain recovery and treatment device of the present invention, the extraction member includes a spiral tube arranged on the box body, a delivery pump arranged on the box body, and a delivery pipe arranged on the delivery pump.
[0010] As a preferred solution of the boiler drain recovery and treatment device of the present invention, the conversion component includes a heat exchanger arranged on the box body, a drain pipe arranged on the heat exchanger, and a hook arranged on the box body.
[0011] As a preferred solution of the boiler drain recovery and treatment device of the present invention, the collecting member includes a collecting cylinder arranged in the box body, a spring arranged on the collecting cylinder, and a connecting pipe arranged on the collecting cylinder.
[0012] As a preferred solution of the boiler drain recovery and treatment device of the present invention, the medicine placing member includes a placing box arranged on the box body and an opening opened on the placing box.
[0013] As a preferred solution of the boiler drain recovery and treatment device described in the present invention, the opening member includes a slide arranged in the placement box, a movable plate arranged on the slide, a connecting rod arranged on the movable plate, a push rod arranged on the connecting rod, and a tilting rod rotatably connected to the box body.
[0014] As a preferred solution of the boiler drain recovery and treatment device of the present invention, the pressing member includes a receiving rod arranged on the collecting cylinder, a base arranged on the receiving rod, and a spiral rod arranged on the base.
[0015] As a preferred solution of the boiler drain recovery and treatment device of the present invention, the scraper includes a first sleeve arranged on the collecting cylinder, a second sleeve arranged in the first sleeve, and an L-shaped scraper rod arranged on the first sleeve.
[0016] As a preferred solution of the boiler drain recovery and treatment device of the present invention, the connecting member includes a first ratchet arranged on the spiral rod, and a second ratchet arranged on the first sleeve.
[0017] The beneficial effects of the present invention are as follows: the present invention extracts boiler drain by setting a delivery pump connected to a spiral tube, and recovers the heat of the drain by a heat exchanger, thereby effectively improving energy efficiency and reducing operating costs; the drain is collected by setting a collecting component, and according to the amount of drain collected by the collecting tube, a drug release component is driven to release a suitable chemical treatment agent to remove impurities and undesirable components therein so that it can be reused, thereby reducing the waste of water resources; and the scraping component is used to scrape the inner wall of the collecting tube to effectively prevent scaling in the collecting tube. BRIEF DESCRIPTION OF THE DRAWINGS
[0018] In order to more clearly illustrate the technical solutions of the embodiments of the present invention, the accompanying drawings required for use in the description of the embodiments will be briefly introduced below. Obviously, the accompanying drawings described below are only some embodiments of the present invention. For ordinary technicians in this field, other accompanying drawings can be obtained based on these accompanying drawings without paying creative work.
[0019] Figure 1 The figure is an overall schematic diagram of a boiler drain recovery and treatment device.
[0020] Figure 2 The figure is an overall schematic diagram of a conversion assembly of a boiler drain recovery and treatment device.
[0021] Figure 3 The present invention is an overall schematic diagram of a drug dispensing component of a boiler drain recovery and treatment device.
[0022] Figure 4 for Figure 3 Enlarged view of point A in .
[0023] Figure 5 The present invention is a cross-sectional view of a cleaning component of a boiler drain recovery and processing device.
[0024] Figure 6 The present invention is an overall schematic diagram of a cleaning component of a boiler drain recovery and processing device.
[0025] Figure 7 for Figure 6 Enlarged view of point B in . DETAILED DESCRIPTION
[0026] In order to make the above-mentioned objects, features and advantages of the present invention more obvious and easy to understand, the specific implementation methods of the present invention are described in detail below in conjunction with the accompanying drawings.
[0027] In the following description, many specific details are set forth to facilitate a full understanding of the present invention, but the present invention may also be implemented in other ways different from those described herein, and those skilled in the art may make similar generalizations without violating the connotation of the present invention. Therefore, the present invention is not limited to the specific embodiments disclosed below.
[0028] Secondly, the term "one embodiment" or "embodiment" as used herein refers to a specific feature, structure, or characteristic that may be included in at least one implementation of the present invention. The term "in one embodiment" that appears in different places in this specification does not necessarily refer to the same embodiment, nor does it refer to a separate or selective embodiment that is mutually exclusive with other embodiments.
[0029] Secondly, the present invention is described in detail with reference to the schematic diagram. When describing the embodiments of the present invention in detail, for the sake of convenience, the cross-sectional diagrams showing the device structure will not be partially enlarged according to the general scale, and the schematic diagrams are only examples, which should not limit the scope of protection of the present invention. In addition, in actual production, the three-dimensional dimensions of length, width and depth should be included.
[0030] Example 1
[0031] Reference Figure 1-Figure 7 , which is the first embodiment of the present invention, and provides a boiler drain recovery and treatment device, including a conversion component 100, including a mounting member 101, used to receive an extraction member 102 and a conversion member 103, the extraction member 102 arranged on the mounting member 101 extracts the boiler drain, and the conversion member 103 arranged on the mounting member 101 transfers the heat in the drain to other media, such as boiler feed water or heating system, to reduce energy consumption, and discharges the condensed drain, and the medicine dispensing component 200, including a collecting member 201 arranged in the mounting member 101, for the boiler The hydrophobic material is collected, and the medicine releasing member 202 arranged on the mounting member 101 releases medicine according to the amount of the collected hydrophobic material, and the opening member 203 arranged on the medicine releasing member 202 controls the amount of medicine released by the medicine releasing member 202, and the cleaning component 300 includes a pressing member 301 arranged on the collecting member 201, which drives the connecting member 303 to rotate when pressed down, a scraping member 302 arranged on the collecting member 201 to scrape the collecting member 201, and a connecting member 303 arranged in the collecting member 201 rotates as the pressing member 301 is pressed down, and drives the scraping member 302 to rotate.
[0032] Specifically, the mounting member 101 includes a housing 101a, a steam trap 101b fixedly connected to one side of the housing 101a, and a steam trap pipe 101c fixedly connected to the steam trap 101b. The housing 101a serves as a container. When the steam trap 101b is opened, boiler steam enters the steam trap pipe 101c through the steam trap 101b.
[0033] Furthermore, the extraction component 102 includes a spiral tube 102a fixedly connected to the top of the box body 101a, a delivery pump 102b fixedly connected to the top of the box body 101a, and a delivery pipe 102c fixedly connected to the delivery pump 102b. The spiral tube 102a is fixedly connected to the drain pipe 101c. The delivery pump 102b is started to extract drain through the spiral tube 102a. The delivery pipe 102c is used to connect the delivery pump 102b and the conversion component 103.
[0034] Furthermore, the conversion member 103 includes a heat exchanger 103a fixedly connected to the top of the housing 101a, a drain pipe 103b fixedly connected to one side of the heat exchanger 103a, and a hook 103c fixedly connected to the housing 101a. One end of the delivery pipe 102c away from the delivery pump 102b is fixedly connected to the heat exchanger 103a. The heat exchanger 103a transfers the heat in the drain to other media, and the condensed drain is discharged through the drain pipe 103b. The hook 103c is used to provide support for the drain pipe 103b.
[0035] Operation process: when the steam trap 101b is opened, the boiler drain enters the steam trap 101b and the drain pipe. When the delivery pump 102b is started, the delivery pump 102b extracts the drain through the spiral tube 102a. The spiral tube 102a uses a turbocharger to increase the flow rate of the boiler drain, which effectively improves the heat exchange efficiency. The drain is transported to the heat exchanger 103a through the delivery pipe 102c, so that its heat is converted into other media, and the condensed drain is discharged into the collecting element 201 through the drain pipe 103b, which makes full use of heat recovery and reduces energy waste.
[0036] Example 2
[0037] Reference Figure 3-Figure 4 , which is the second embodiment of the present invention. This embodiment is different from the first embodiment in that: a collecting member 201 includes a collecting cylinder 201a arranged in a casing 101a, a spring 201b fixedly connected to the bottom of the collecting cylinder 201a, and a connecting pipe 201c fixedly connected to the collecting cylinder 201a, the collecting cylinder 201a is used to store and collect condensed hydrophobic water, one end of the spring 201b away from the collecting cylinder 201a is fixedly connected to the bottom of the casing 101a, the connecting pipe 201c is made of a soft material, one end of the connecting pipe 201c away from the collecting cylinder 201a is fixedly connected to one side of the casing 101a, and the connecting pipe 201c is used to discharge the hydrophobic water in the collecting cylinder 201a.
[0038] Specifically, the medicine placing part 202 includes a placing box 202a fixedly connected to one side of the box body 101a, and an opening 202b opened on the placing box 202a. The placing box 202a is used to store chemical treatment agents, and the chemical treatment agents are discharged from the placing box 202a through the opening 202b. The placing box 202a is located above the collecting tube 201a.
[0039] Further, the opening member 203 includes a slide 203a fixedly connected to the placement box 202a, a moving plate 203b slidably connected to the slide 203a, a connecting rod 203c rotatably connected to the moving plate 203b, a push rod 203d rotatably connected to the end of the connecting rod 203c away from the moving plate 203b, and a tilting rod 203e rotatably connected to the inner wall of the box body 101a. The slide 203a provides a guide for the moving plate 203b, the moving plate 203b covers the opening 202b, and the connecting rod 203c drives the moving plate 203b to move on the slide 203a. The slide 203a is provided with two and opposite The size of the movable plate 203b is larger than the size of the opening 202b, and the end of the connecting rod 203c away from the movable plate 203b is rotatably connected to the end of the push rod 203d. The connecting rod 203c is retractable, and the connecting rod 203c is rotatably connected to the placement box 202a. The push rod 203d drives the connecting rod 203c to rotate, and the end of the push rod 203d away from the connecting rod 203c is rotatably connected to the end of the tilting rod 203e, and the end of the tilting rod 203e away from the push rod 203d is fixedly connected to the collecting tube 201a, and the rotation point of the tilting rod 203e rotating on the inner wall of the box body 101a is close to one end of the connecting push rod 203d.
[0040] The rest of the structure is the same as that of Example 1.
[0041] Operation process: When the condensed hydrophobic water is discharged into the collection tube 201a, the weight pressure of the hydrophobic water drives the collection tube 201a to move downward in the box 101a, and the spring 201b is tightened. The collection tube 201a drives the tilting rod 203e fixed thereon to rotate on the box 101a, and the end of the tilting rod 203e connected to the push rod 203d is tilted, so that the push rod 203d moves upward. When the push rod 203d moves upward, it pushes the connecting rod 203c downward, and the connecting rod 203c moves the moving plate 203b on the slide. The movable plate 203a moves downward to remove the cover on the opening 202b, and the chemical treatment agent stored in the placing box 202a is discharged into the collection through the opening 202b, and is fused with the hydrophobic agent to remove hardness and salt, so that the hydrophobic agent can be reused, thereby reducing the waste of water resources. The size of the opening 202b is opened according to the amount of hydrophobic agent collected by the collecting tube 201a to release the corresponding chemical treatment agent. On the contrary, when there is no hydrophobic agent in the collecting tube 201a, the movable plate 203b seals the opening 202b and no longer releases the chemical treatment agent.
[0042] Example 3
[0043] Reference Figure 5-Figure 7 , which is the third embodiment of the present invention. This embodiment is different from the above embodiments in that: the pressing member 301 includes a receiving rod 301a fixedly connected to the top of the collecting tube 201a, a base 301b fixedly connected to the end of the receiving rod 301a, and a spiral rod 301c fixedly connected to the bottom of the base 301b. The receiving rod 301a provides support for the base 301b. The receiving rod 301a is provided with multiple receiving rods 301a and is evenly distributed around the circumference. The base 301b plays a supporting role for the spiral rod 301c, and the end of the spiral rod 301c is arranged in the scraping member 302.
[0044] Specifically, the scraper 302 includes a first sleeve 302a rotatably connected to the bottom of the collecting tube 201a, a second sleeve 302b arranged in the first sleeve 302a, and an L-shaped scraper rod 302c fixedly connected to the side of the first sleeve 302a. The first sleeve 302a is sleeved on the second sleeve 302b, and the size of the second sleeve 302b is adapted to the size of the opening of the first sleeve 302a. The second sleeve 302b is fixedly connected to the bottom of the box body 101a. The L-shaped scraper rod 302c is inside the collecting tube 201a and is close to the inner wall of the collecting tube. Two L-shaped scraper rods 302c are provided and are symmetrically arranged.
[0045] Furthermore, the connecting member 303 includes a first ratchet 303a arranged on the spiral rod 301c, and a second ratchet 303b fixedly connected to the top of the first sleeve 302a. When the spiral rod 301c moves, the first ratchet 303a is driven by the spiral groove on the spiral rod 301c to rotate, and the second ratchet 303b is engaged with the first ratchet 303a, and the second ratchet 303b drives the first sleeve 302a to rotate.
[0046] The rest of the structure is the same as that of Example 2.
[0047] Operation process: When the collecting tube 201a collects the cooled drain, the collecting tube 201a presses down the receiving rod 301a on it, driving the base 301b to press down, and the base 301b drives the spiral rod 301c to move downward, and the spiral rod 301c passes through the first ratchet 303a and the second ratchet 303b and moves downward in the first sleeve 302a and the second sleeve 302b, the collecting tube 201a is pressed down, the spring 201b is tightened, the first sleeve 302a slides downward on the second sleeve 302b, and the first ratchet 303a is pressed down. The spiral rod 301c is pressed downward to drive the rotation, and because the first ratchet 303a is engaged with the second ratchet 303b, the second ratchet 303b rotates accordingly. The second ratchet 303b is fixedly connected to the top of the first sleeve 302a, so it drives the first sleeve 302a to rotate at the bottom of the collecting tube 201a. The rotation of the first sleeve 302a drives the two L-shaped scraping rods 302c fixedly connected thereto to scrape the inner wall of the collecting tube 201a to prevent scaling of the inner wall of the collecting tube 201a due to the high salt content in the hydrophobic water.
[0048] Importantly, it should be noted that the construction and arrangement of the present application shown in a plurality of different exemplary embodiments are only exemplary. Although only a few embodiments are described in detail in this disclosure, it should be readily understood by those who refer to this disclosure that many modifications are possible (e.g., the size, scale, structure, shape and proportion of various elements, and parameter values (e.g., temperature, pressure, etc.), installation arrangement, use of materials, color, directional changes, etc.) without substantially departing from the novel teachings and advantages of the subject matter described in the application. For example, the element shown as integrally formed can be composed of multiple parts or elements, the position of the element can be inverted or otherwise changed, and the nature or number or position of the discrete element can be changed or changed. Therefore, all such modifications are intended to be included in the scope of the present invention. The order or sequence of any process or method steps can be changed or reordered according to alternative embodiments. In the claims, any "device plus function" clause is intended to cover the structure of performing the function described herein, and is not only structurally equivalent but also equivalent structure. Without departing from the scope of the present invention, other replacements, modifications, changes and omissions can be made in the design, operating conditions and arrangement of the exemplary embodiments. Therefore, the invention is not limited to a specific embodiment, but extends to numerous modifications still falling within the scope of the appended claims.
[0049] Additionally, in order to provide a concise description of exemplary embodiments, all features of an actual embodiment (ie, those features that are not relevant to the best mode presently contemplated for carrying out the invention or those that are not relevant to implementing the invention) may not be described.
[0050] It will be appreciated that in the development of any actual implementation, as in any engineering or design project, numerous implementation-specific decisions may be made. Such a development effort may be complex and time-consuming, but will be a routine task of design, fabrication, and production for those of ordinary skill having the benefit of this disclosure without undue experimentation.
[0051] It should be noted that the above embodiments are only used to illustrate the technical solutions of the present invention rather than to limit it. Although the present invention has been described in detail with reference to the preferred embodiments, those skilled in the art should understand that the technical solutions of the present invention may be modified or replaced by equivalents without departing from the spirit and scope of the technical solutions of the present invention, which should all be included in the scope of the claims of the present invention.
Claims
1. A boiler drain recovery and treatment device, characterized in that: include, A conversion component (100) comprises a mounting member (101), an extraction member (102) arranged on the mounting member (101), and a conversion member (103) arranged on the mounting member (101); A medicine placing assembly (200) comprises a collecting member (201) arranged in the mounting member (101), a medicine placing member (202) arranged on the mounting member (101), and an opening member (203) arranged on the medicine placing member (202); and, The cleaning assembly (300) comprises a pressing member (301) arranged on the collecting member (201), a scraping member (302) arranged on the collecting member (201), and a connecting member (303) arranged in the collecting member (201).
2. The boiler drain recovery device according to claim 1, characterized in that: The mounting member (101) comprises a box body (101a), a drain valve (101b) arranged on the box body (101a), and a drain pipe (101c) arranged on the drain valve (101b).
3. The boiler drain recovery device according to claim 2, characterized in that: The extraction member (102) comprises a spiral tube (102a) arranged on the box body (101a), a delivery pump (102b) arranged on the box body (101a), and a delivery pipe (102c) arranged on the delivery pump (102b).
4. The boiler drain recovery device according to claim 3, characterized in that: The conversion component (103) comprises a heat exchanger (103a) arranged on the box body (101a), a drainage pipe (103b) arranged on the heat exchanger (103a), and a hook (103c) arranged on the box body (101a).
5. The boiler drain recovery device according to claim 4, characterized in that: The collecting member (201) comprises a collecting tube (201a) arranged in the box body (101a), a spring (201b) arranged on the collecting tube (201a), and a connecting tube (201c) arranged on the collecting tube (201a).
6. The boiler drain recovery device according to claim 5, characterized in that: The medicine placing member (202) comprises a placing box (202a) arranged on the box body (101a), and an opening (202b) opened on the placing box (202a).
7. The boiler drain recovery device according to claim 6, characterized in that: The opening member (203) comprises a slideway (203a) arranged in the placement box (202a), a movable plate (203b) arranged on the slideway (203a), a connecting rod (203c) arranged on the movable plate (203b), a push rod (203d) arranged on the connecting rod (203c), and a tilting rod (203e) rotatably connected to the box body (101a).
8. The boiler drain recovery device according to claim 7, characterized in that: The pressing member (301) comprises a receiving rod (301a) arranged on the collecting tube (201a), a base (301b) arranged on the receiving rod (301a), and a spiral rod (301c) arranged on the base (301b).
9. The boiler drain recovery device according to claim 8, characterized in that: The scraping member (302) comprises a first sleeve (302a) arranged on the collecting tube (201a), a second sleeve (302b) arranged inside the first sleeve (302a), and an L-shaped scraping rod (302c) arranged on the first sleeve (302a).
10. The boiler drain recovery device according to claim 9, characterized in that: The connecting member (303) comprises a first ratchet (303a) arranged on the spiral rod (301c), and a second ratchet (303b) arranged on the first sleeve (302a).