Monitoring and early warning method and system for electromagnetic chuck control system of excavator
By calculating historical early warning coefficients and monitoring early warning factors, we can judge the abnormal situation of the excavator electromagnetic suction cup control system, and solve the problem of singularity and one-sidedness of traditional monitoring early warning methods, achieving more efficient and accurate early warning reminders to ensure the stability and reliability of the system sex.
Patent Information
- Application Number
- CN202411239221.4
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-09-05
- Publication Date
- 2024-11-29
- Estimated Expiration
- Not applicable · inactive patent
AI Technical Summary
The monitoring and early warning method of traditional excavator electromagnetic suction cup control system is relatively single, and it is difficult to achieve accurate monitoring and early warning. Especially in the case of multiple monitoring indicators, how to efficiently process and analyze data and issue accurate early warning is a technical problem that needs to be solved urgently.
By collecting the historical operation behavior of the excavator electromagnetic suction cup control system, calculate the historical warning coefficient, and calculate the monitoring and warning factor based on real-time feature data, adjust the warning factor based on the preset adjustment coefficient, determine whether there are abnormalities in the system, issue warning reminders in real time, and improve monitoring The level of intelligence of early warning.
It realizes more efficient and accurate status monitoring and abnormal warning, ensures the stable and reliable operation of the excavator electromagnetic suction cup control system, and improves the intelligent level of monitoring and early warning.
Smart Images

Figure CN119049243A_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of electromagnetic chucks for excavators, and in particular to a monitoring and early warning method and system for an electromagnetic chuck control system for an excavator. Background Art
[0002] The excavator electromagnetic chuck control system is a control system used to improve the electromagnetic chuck under unstable power supply and hydraulic flow supply. Through fine component coordination and electronic control devices, it can ensure that the electromagnetic chuck can work stably even when the external load changes, thereby ensuring the safety and reliability of the operation. With the continuous improvement of industrial automation and informatization, the monitoring and early warning of the excavator electromagnetic chuck control system has become one of the key technologies to ensure the normal operation of the equipment.
[0003] The traditional monitoring and early warning method is to set an early warning threshold. When a monitoring indicator exceeds the early warning threshold, an early warning operation is performed. This monitoring and early warning method is relatively simple and has a certain one-sidedness, making it difficult to achieve accurate monitoring and early warning. When there are many monitoring indicators, how to efficiently process and analyze these data and issue accurate early warnings is a technical problem that needs to be solved urgently. Summary of the invention
[0004] In view of this, the present invention proposes a monitoring and early warning method and system for an electromagnetic chuck control system of an excavator, which improves the intelligence level of monitoring and early warning and realizes more efficient and accurate status monitoring and abnormal early warning.
[0005] The present invention proposes a monitoring and early warning method for an electromagnetic chuck control system of an excavator, comprising: Collecting historical operation behaviors of the electromagnetic chuck control system of the excavator, analyzing the historical operation behaviors, and calculating the historical warning coefficient of the electromagnetic chuck control system of the excavator based on the analysis results; Acquire real-time characteristic data of the electromagnetic chuck control system of the excavator, and acquire historical characteristic data corresponding to the real-time characteristic data in the previous safety historical operation behavior, and calculate the monitoring and early warning factor of the electromagnetic chuck control system of the excavator based on the real-time characteristic data and the historical characteristic data; Selecting a corresponding preset adjustment coefficient according to the historical warning coefficient, and adjusting the monitoring warning factor based on the preset adjustment coefficient to obtain a target monitoring warning factor; It is determined whether there is an abnormality in the electromagnetic suction cup control system of the excavator according to the target monitoring early warning factor. If so, an early warning reminder is issued in real time.
[0006] Furthermore, when collecting historical operation behaviors of the electromagnetic chuck control system of the excavator, analyzing the historical operation behaviors, and calculating the historical warning coefficient of the electromagnetic chuck control system of the excavator based on the analysis results, it includes: Based on the analysis results, the historical operation behaviors are divided into abnormal historical operation behaviors and safe historical operation behaviors; Counting the number of first behaviors of the abnormal historical operating behaviors and counting the number of second behaviors of the safe historical operating behaviors respectively; Determine an abnormal historical operation time fitting curve and a safe historical operation time fitting curve according to the abnormal historical operation behavior and the safe historical operation behavior, and determine an abnormal offset value corresponding to each abnormal historical operation behavior based on the abnormal historical operation time fitting curve and the safe historical operation time fitting curve; The historical warning coefficient of the electromagnetic chuck control system of the excavator is calculated according to the abnormal deviation value corresponding to each abnormal historical operating behavior.
[0007] Further, when determining an abnormal historical operation time fitting curve and a safe historical operation time fitting curve according to the abnormal historical operation behavior and the safe historical operation behavior, and determining an abnormal offset value corresponding to each abnormal historical operation behavior based on the abnormal historical operation time fitting curve and the safe historical operation time fitting curve, it includes: Determine the safety history control time corresponding to each safety history operation behavior; Based on the collection time series, all the safety history manipulation times are smoothly fitted to determine the safety history manipulation time fitting curve, wherein the horizontal axis of the safety history manipulation time fitting curve is the collection time, and the vertical axis is the safety history manipulation time; Determine the abnormal historical operation time corresponding to each abnormal historical operation behavior; Based on the acquisition time series, all abnormal historical manipulation times are smoothly fitted to determine an abnormal historical manipulation time fitting curve, wherein the abscissa of the abnormal historical manipulation time fitting curve is the acquisition time, and the ordinate is the abnormal historical manipulation time; Determine whether there is an intersection between the safety history operation time fitting curve and the abnormal history operation time fitting curve. If so, extract the abnormal history operation time at the intersection, calculate the shortest distance from the remaining abnormal history operation time on the abnormal history operation time fitting curve to the safety history operation time fitting curve, and use the shortest distance as the corresponding abnormal offset value; Extract the minimum shortest distance from all the shortest distances and use it as the abnormal offset value of the abnormal historical manipulation time at the intersection; If not, the shortest distance from each abnormal historical operation time on the abnormal historical operation time fitting curve to the safe historical operation time fitting curve is calculated, and the shortest distance is used as the corresponding abnormal offset value.
[0008] Further, when calculating the historical warning coefficient of the excavator electromagnetic chuck control system according to the abnormal offset value corresponding to each abnormal historical operation behavior, it includes: The historical warning coefficient of the excavator electromagnetic suction cup control system is calculated according to the following formula: ; Among them, Y1 is the historical warning coefficient of the excavator electromagnetic suction cup control system, a is the first calculation coefficient, b is the second calculation coefficient, and a+b=1, a<b, n1 is the number of first behaviors, n2 is the number of second behaviors, k i is the abnormal offset value corresponding to the ith abnormal historical operation behavior, and kmax is the maximum abnormal offset value corresponding to the abnormal historical operation behavior.
[0009] Further, when the monitoring and early warning factor of the excavator electromagnetic chuck control system is calculated based on the real-time characteristic data and the historical characteristic data, it includes: Acquire a standard data value corresponding to the real-time characteristic data; Determining a controllable data range according to the standard data value and the historical characteristic data, and dividing the real-time characteristic data into long-term unstable data, short-term unstable data and safety characteristic data according to the controllable data range; Normalizing the long-term unstable data to obtain a normalized data sequence; Performing standardization processing on the long-term unstable data to obtain a standardized data sequence; Determine the maximum normalized value and the minimum normalized value in the normalized data sequence, and calculate the normalized sum and the normalized difference of the maximum normalized value and the minimum normalized value respectively; Determine the maximum standardized value and the minimum standardized value in the standardized processed data sequence, and calculate the standardized sum and the standardized difference of the maximum standardized value and the minimum standardized value respectively; Determining a first processed value of the normalized processed data sequence according to the normalized sum value and the normalized difference value; Determine a second processed value of the standardized processed data sequence according to the standardized sum value and the standardized difference value; Extracting all long-term unstable data greater than the first processing value in the normalized data sequence to construct a first data sequence, and extracting all long-term unstable data greater than the second processing value in the standardized data sequence to construct a second data sequence; Extracting long-term unstable data of the intersection of the first data sequence and the second data sequence; Analyze the short-term unstable data and the safety feature data respectively to determine corresponding intersection short-term unstable data and intersection safety feature data; The monitoring and early warning factor of the excavator electromagnetic chuck control system is calculated according to the intersection long-term instability data, the intersection short-term instability data and the intersection safety feature data.
[0010] Further, when determining a controllable data range according to the standard data value and the historical characteristic data, and dividing the real-time characteristic data into long-term unstable data, short-term unstable data and safety characteristic data according to the controllable data range, it includes: Determine the numerical value relationship between the standard data value and the historical characteristic data, and determine the left boundary value and the right boundary value based on the numerical value relationship; Constructing the controllable data range according to the left boundary value and the right boundary value; If the real-time feature data is less than or equal to the right boundary value, the corresponding real-time feature data is used as the security feature data; If the real-time feature data is greater than the right boundary value, an abnormal mark is generated for the corresponding real-time feature data; Analyze all abnormal historical operation behaviors and determine the abnormal characteristic data corresponding to each abnormal historical operation behavior; Pair the real-time feature data that generates the abnormal mark with all the abnormal feature data, and count the number of pairs; When the number of pairs is less than the preset number of pairs, the corresponding real-time feature data is used as the short-term unstable data; When the pairing quantity is greater than or equal to the preset pairing quantity, the corresponding real-time characteristic data is used as the long-term unstable data.
[0011] Further, when the monitoring and early warning factor of the excavator electromagnetic chuck control system is calculated according to the intersection long-term unstable data, the intersection short-term unstable data and the intersection safety feature data, it includes: Respectively counting the first data quantity of the intersection long-term unstable data, the second data quantity of the intersection short-term unstable data, and the third data quantity of the intersection safety feature data; The monitoring and early warning factor of the excavator electromagnetic suction cup control system is calculated according to the following formula: ; Among them, L is the monitoring and early warning factor of the excavator electromagnetic suction cup control system, G1 is the first data quantity, G2 is the second data quantity, and G3 is the third data quantity.
[0012] Furthermore, when a corresponding preset adjustment coefficient is selected according to the historical warning coefficient, and the monitoring warning factor is adjusted based on the preset adjustment coefficient to obtain a target monitoring warning factor, it includes: Presetting a first preset historical warning coefficient and a second preset historical warning coefficient; Presetting a first preset adjustment coefficient, a second preset adjustment coefficient, and a third preset adjustment coefficient; When the historical warning coefficient is less than the first preset historical warning coefficient, a first product value of the first preset adjustment coefficient and the monitoring warning factor is calculated, and the first product value is used as the target monitoring warning factor; When the historical warning coefficient is greater than or equal to the first preset historical warning coefficient and less than the second preset historical warning coefficient, a second product value of the second preset adjustment coefficient and the monitoring warning factor is calculated, and the second product value is used as the target monitoring warning factor; When the historical warning coefficient is greater than or equal to the second preset historical warning coefficient, a third product value of the third preset adjustment coefficient and the monitoring warning factor is calculated, and the third product value is used as the target monitoring warning factor.
[0013] Further, when judging whether the electromagnetic chuck control system of the excavator is abnormal according to the target monitoring early warning factor, it includes: Determining whether there is an abnormality in the electromagnetic chuck control system of the excavator according to the relationship between the target monitoring warning factor and the preset target monitoring warning factor; When the target monitoring warning factor is less than the preset target monitoring warning factor, it is determined that there is no abnormality in the electromagnetic chuck control system of the excavator; When the target monitoring early warning factor is greater than or equal to the preset target monitoring early warning factor, it is determined that there is an abnormality in the excavator electromagnetic suction cup control system.
[0014] Compared with the prior art, the present invention has the following beneficial effects: Collect the historical operation behavior of the electromagnetic suction cup control system of the excavator and calculate the historical warning coefficient; obtain the real-time feature data of the electromagnetic suction cup control system of the excavator, and obtain the historical feature data corresponding to the real-time feature data in the previous safe historical operation behavior, and calculate the monitoring and warning factor of the electromagnetic suction cup control system of the excavator; select the corresponding preset adjustment coefficient according to the historical warning coefficient, adjust the monitoring and warning factor based on the preset adjustment coefficient, and obtain the target monitoring and warning factor; determine whether there is an abnormality in the electromagnetic suction cup control system of the excavator according to the target monitoring and warning factor, and if so, issue a warning reminder in real time to improve the intelligence level of monitoring and warning, realize more efficient and accurate status monitoring and abnormal warning, and ensure the stable and reliable operation of the electromagnetic suction cup control system of the excavator.
[0015] On the other hand, the present application also provides a monitoring and early warning system for an electromagnetic chuck control system of an excavator, comprising: The first module is used to collect the historical operation behavior of the electromagnetic chuck control system of the excavator, analyze the historical operation behavior, and calculate the historical warning coefficient of the electromagnetic chuck control system of the excavator based on the analysis result; The second module is used to obtain the real-time characteristic data of the electromagnetic chuck control system of the excavator, and obtain the historical characteristic data corresponding to the real-time characteristic data in the previous safety historical operation behavior, and calculate the monitoring and early warning factor of the electromagnetic chuck control system of the excavator based on the real-time characteristic data and the historical characteristic data; The third module is used to select a corresponding preset adjustment coefficient according to the historical warning coefficient, and adjust the monitoring warning factor based on the preset adjustment coefficient to obtain a target monitoring warning factor; The fourth module is used to determine whether there is any abnormality in the electromagnetic suction cup control system of the excavator according to the target monitoring and early warning factors. If so, an early warning reminder is issued in real time.
[0016] It can be understood that the monitoring and early warning system and method for the electromagnetic suction cup control system of the excavator provided above have the same beneficial effects, which will not be repeated here. BRIEF DESCRIPTION OF THE DRAWINGS
[0017] Various other advantages and benefits will become apparent to those of ordinary skill in the art by reading the detailed description of the preferred embodiments below. The accompanying drawings are only for the purpose of illustrating the preferred embodiments and are not to be considered as limiting the present invention. Moreover, the same reference symbols are used throughout the accompanying drawings to represent the same components. In the accompanying drawings: Figure 1 A flow chart of a monitoring and early warning method for an electromagnetic chuck control system of an excavator provided by an embodiment of the present invention; Figure 2A schematic structural diagram of a monitoring and early warning system for an electromagnetic chuck control system of an excavator provided in an embodiment of the present invention. DETAILED DESCRIPTION
[0018] Exemplary embodiments of the present disclosure will be described in more detail below with reference to the accompanying drawings. Although exemplary embodiments of the present disclosure are shown in the accompanying drawings, it should be understood that the present disclosure can be implemented in various forms and should not be limited by the embodiments described herein. On the contrary, these embodiments are provided in order to enable a more thorough understanding of the present disclosure and to fully convey the scope of the present disclosure to those skilled in the art. It should be noted that, in the absence of conflict, the embodiments of the present invention and the features described in the embodiments can be combined with each other. The present invention will be described in detail below with reference to the accompanying drawings and in combination with the embodiments.
[0019] like Figure 1 As shown, in some embodiments of the present application, this embodiment provides a monitoring and early warning method for an electromagnetic chuck control system of an excavator, comprising: S110: collecting historical operation behaviors of the electromagnetic chuck control system of the excavator, analyzing the historical operation behaviors, and calculating the historical warning coefficient of the electromagnetic chuck control system of the excavator based on the analysis results; In some embodiments of the present application, when collecting historical operating behaviors of the electromagnetic chuck control system of the excavator, analyzing the historical operating behaviors, and calculating the historical warning coefficient of the electromagnetic chuck control system of the excavator based on the analysis results, it includes: Based on the analysis results, the historical operation behaviors are divided into abnormal historical operation behaviors and safe historical operation behaviors; Counting the number of first behaviors of the abnormal historical operating behaviors and counting the number of second behaviors of the safe historical operating behaviors respectively; Determine an abnormal historical operation time fitting curve and a safe historical operation time fitting curve according to the abnormal historical operation behavior and the safe historical operation behavior, and determine an abnormal offset value corresponding to each abnormal historical operation behavior based on the abnormal historical operation time fitting curve and the safe historical operation time fitting curve; The historical warning coefficient of the electromagnetic chuck control system of the excavator is calculated according to the abnormal deviation value corresponding to each abnormal historical operating behavior.
[0020] In this embodiment, the excavator electromagnetic suction cup control system includes a power supply control device, an electromagnetic suction cup control device and a sensor control device, etc. Monitoring and warning the excavator electromagnetic suction cup control system means monitoring and warning these devices. When monitoring and warning, a specific device is selected as the monitoring and warning object.
[0021] In this embodiment, the historical operating behavior refers to the operation record of the excavator electromagnetic suction cup control system, that is, the operation record involved in the entire process from turning on the excavator electromagnetic suction cup control system to turning off the excavator electromagnetic suction cup control system, including but not limited to operating time, operating voltage, operating current, operating temperature, personnel participation, etc.
[0022] In this embodiment, abnormal historical operation behavior refers to the behavior with abnormal operation in a complete operation, and safe historical operation behavior refers to the behavior without abnormal operation in a complete operation.
[0023] The beneficial effect of the above technical solution is that the present invention can lay a foundation for the calculation of historical warning coefficients by classifying historical operating behaviors and counting the corresponding quantities.
[0024] In some embodiments of the present application, when determining an abnormal historical operation time fitting curve and a safe historical operation time fitting curve according to the abnormal historical operation behavior and the safe historical operation behavior, and determining an abnormal offset value corresponding to each abnormal historical operation behavior based on the abnormal historical operation time fitting curve and the safe historical operation time fitting curve, it includes: Determine the safety history control time corresponding to each safety history operation behavior; Based on the collection time series, all the safety history manipulation times are smoothly fitted to determine the safety history manipulation time fitting curve, wherein the horizontal axis of the safety history manipulation time fitting curve is the collection time, and the vertical axis is the safety history manipulation time; Determine the abnormal historical operation time corresponding to each abnormal historical operation behavior; Based on the acquisition time series, all abnormal historical manipulation times are smoothly fitted to determine an abnormal historical manipulation time fitting curve, wherein the abscissa of the abnormal historical manipulation time fitting curve is the acquisition time, and the ordinate is the abnormal historical manipulation time; Determine whether there is an intersection between the safety history operation time fitting curve and the abnormal history operation time fitting curve. If so, extract the abnormal history operation time at the intersection, calculate the shortest distance from the remaining abnormal history operation time on the abnormal history operation time fitting curve to the safety history operation time fitting curve, and use the shortest distance as the corresponding abnormal offset value; Extract the minimum shortest distance from all the shortest distances and use it as the abnormal offset value of the abnormal historical manipulation time at the intersection; If not, the shortest distance from each abnormal historical operation time on the abnormal historical operation time fitting curve to the safe historical operation time fitting curve is calculated, and the shortest distance is used as the corresponding abnormal offset value.
[0025] In this embodiment, the safety history control time refers to the time involved in the entire process from starting the excavator electromagnetic suction cup control system to closing the excavator electromagnetic suction cup control system.
[0026] In this embodiment, the acquisition time series is 0 seconds, 2 seconds, 4 seconds, etc., which specifically satisfies an arithmetic progression.
[0027] In this embodiment, the smoothing fitting method is complicated and mature, and will not be introduced in detail here.
[0028] In this embodiment, the abnormal historical control time refers to the time involved in the process from starting the excavator electromagnetic suction cup control system to discovering the abnormality.
[0029] In this embodiment, the shortest distance from the remaining abnormal historical operation time on the abnormal historical operation time fitting curve to the safe historical operation time fitting curve is calculated, that is, the shortest distance from a point to a line.
[0030] The beneficial effect of the above technical solution is: the present invention calculates the shortest distance from each abnormal historical control time on the abnormal historical control time fitting curve to the safe historical control time fitting curve, and analyzes it to determine the corresponding abnormal offset value, which can ensure the calculation accuracy of the historical warning coefficient and avoid errors.
[0031] In some embodiments of the present application, when calculating the historical warning coefficient of the excavator electromagnetic chuck control system according to the abnormal offset value corresponding to each abnormal historical operation behavior, it includes: The historical warning coefficient of the excavator electromagnetic suction cup control system is calculated according to the following formula: ; Among them, Y1 is the historical warning coefficient of the excavator electromagnetic suction cup control system, a is the first calculation coefficient, b is the second calculation coefficient, and a+b=1, a<b, n1 is the number of first behaviors, n2 is the number of second behaviors, k i is the abnormal offset value corresponding to the ith abnormal historical operation behavior, and kmax is the maximum abnormal offset value corresponding to the abnormal historical operation behavior.
[0032] S120: acquiring real-time characteristic data of the electromagnetic chuck control system of the excavator, and acquiring historical characteristic data corresponding to the real-time characteristic data in the previous safety historical operation behavior, and calculating the monitoring and early warning factor of the electromagnetic chuck control system of the excavator based on the real-time characteristic data and the historical characteristic data; In some embodiments of the present application, when the monitoring and warning factor of the excavator electromagnetic chuck control system is calculated based on the real-time feature data and the historical feature data, it includes: Acquire a standard data value corresponding to the real-time characteristic data; Determining a controllable data range according to the standard data value and the historical characteristic data, and dividing the real-time characteristic data into long-term unstable data, short-term unstable data and safety characteristic data according to the controllable data range; Normalizing the long-term unstable data to obtain a normalized data sequence; Performing standardization processing on the long-term unstable data to obtain a standardized data sequence; Determine the maximum normalized value and the minimum normalized value in the normalized data sequence, and calculate the normalized sum and the normalized difference of the maximum normalized value and the minimum normalized value respectively; Determine the maximum standardized value and the minimum standardized value in the standardized processed data sequence, and calculate the standardized sum and the standardized difference of the maximum standardized value and the minimum standardized value respectively; Determining a first processed value of the normalized processed data sequence according to the normalized sum value and the normalized difference value; Determine a second processed value of the standardized processed data sequence according to the standardized sum value and the standardized difference value; Extracting all long-term unstable data greater than the first processing value in the normalized data sequence to construct a first data sequence, and extracting all long-term unstable data greater than the second processing value in the standardized data sequence to construct a second data sequence; Extracting long-term unstable data of the intersection of the first data sequence and the second data sequence; Analyze the short-term unstable data and the safety feature data respectively to determine corresponding intersection short-term unstable data and intersection safety feature data; The monitoring and early warning factor of the excavator electromagnetic chuck control system is calculated according to the intersection long-term instability data, the intersection short-term instability data and the intersection safety feature data.
[0033] In this embodiment, the real-time characteristic data include temperature, current, voltage, oil pressure, oil temperature, etc., which are not shown one by one.
[0034] In this embodiment, if the real-time characteristic data is temperature, the standard data value is 25° C., and can also be set according to actual conditions.
[0035] In this embodiment, the normalized sum value refers to the sum of the maximum normalized value and the minimum normalized value, and the normalized difference value refers to the difference between the maximum normalized value and the minimum normalized value.
[0036] In this embodiment, the first processed value=(normalized sum value+normalized difference value) / B, where B is the number of normalized processed data sequences.
[0037] In this embodiment, the second processed value=(standardized sum value+standardized difference value) / C, where C is the number of standardized processed data sequences.
[0038] In this embodiment, the intersection long-term unstable data refers to the long-term unstable data in which the first data sequence and the second data sequence exist simultaneously.
[0039] In this embodiment, the method for determining the intersection short-term unstable data and the intersection safety feature data is consistent with the method for determining the intersection long-term unstable data, and will not be repeated here.
[0040] The beneficial effect of the above technical solution is: the present invention calculates the monitoring and early warning factors of the excavator electromagnetic suction cup control system according to the intersection long-term unstable data, the intersection short-term unstable data and the intersection safety feature data, thereby realizing precise calculation, avoiding the calculation errors existing in human participation and the one-sidedness and subjectivity of the calculation, and at the same time avoiding the errors caused by the analysis of a single data, thereby further ensuring the accuracy of monitoring and early warning.
[0041] In some embodiments of the present application, when determining a controllable data range according to the standard data value and the historical characteristic data, and dividing the real-time characteristic data into long-term unstable data, short-term unstable data and safety characteristic data according to the controllable data range, it includes: Determine the numerical value relationship between the standard data value and the historical characteristic data, and determine the left boundary value and the right boundary value based on the numerical value relationship; Constructing the controllable data range according to the left boundary value and the right boundary value; If the real-time feature data is less than or equal to the right boundary value, the corresponding real-time feature data is used as the security feature data; If the real-time feature data is greater than the right boundary value, an abnormal mark is generated for the corresponding real-time feature data; Analyze all abnormal historical operation behaviors and determine the abnormal characteristic data corresponding to each abnormal historical operation behavior; Pair the real-time feature data that generates the abnormal mark with all the abnormal feature data, and count the number of pairs; When the number of pairs is less than the preset number of pairs, the corresponding real-time feature data is used as the short-term unstable data; When the pairing quantity is greater than or equal to the preset pairing quantity, the corresponding real-time characteristic data is used as the long-term unstable data.
[0042] In this embodiment, the previous safety history operation behavior refers to the safety history operation behavior most recent to the current behavior.
[0043] In this embodiment, the historical characteristic data refers to historical temperature, historical voltage, historical current, etc.
[0044] In this embodiment, if the temperature of the previous safety historical operation behavior is 23°C and the standard data value is 25°C, then the left boundary value is 23°C and the right boundary value is 25°C, and a controllable data range is constructed.
[0045] In this embodiment, abnormal characteristic data refers to data that causes abnormal historical operation behavior. For example, if a certain abnormal historical operation behavior is caused by temperature and voltage, then temperature and voltage are abnormal characteristic data.
[0046] In this embodiment, the preset pairing number is preferably 4.
[0047] The beneficial effect of the above technical solution is that the present invention divides the real-time characteristic data into long-term unstable data, short-term unstable data and safety characteristic data, thereby ensuring the comprehensiveness of monitoring and early warning and further ensuring the accuracy of early warning.
[0048] In some embodiments of the present application, when the monitoring and early warning factor of the excavator electromagnetic chuck control system is calculated according to the intersection long-term instability data, the intersection short-term instability data and the intersection safety feature data, it includes: Respectively counting the first data quantity of the intersection long-term unstable data, the second data quantity of the intersection short-term unstable data, and the third data quantity of the intersection safety feature data; The monitoring and early warning factor of the excavator electromagnetic suction cup control system is calculated according to the following formula: ; Among them, L is the monitoring and early warning factor of the excavator electromagnetic suction cup control system, G1 is the first data quantity, G2 is the second data quantity, and G3 is the third data quantity.
[0049] S130: selecting a corresponding preset adjustment coefficient according to the historical warning coefficient, and adjusting the monitoring warning factor based on the preset adjustment coefficient to obtain a target monitoring warning factor; In some embodiments of the present application, when selecting a corresponding preset adjustment coefficient according to the historical warning coefficient, and adjusting the monitoring warning factor based on the preset adjustment coefficient to obtain a target monitoring warning factor, it includes: Presetting a first preset historical warning coefficient and a second preset historical warning coefficient; Presetting a first preset adjustment coefficient, a second preset adjustment coefficient, and a third preset adjustment coefficient; When the historical warning coefficient is less than the first preset historical warning coefficient, a first product value of the first preset adjustment coefficient and the monitoring warning factor is calculated, and the first product value is used as the target monitoring warning factor; When the historical warning coefficient is greater than or equal to the first preset historical warning coefficient and less than the second preset historical warning coefficient, a second product value of the second preset adjustment coefficient and the monitoring warning factor is calculated, and the second product value is used as the target monitoring warning factor; When the historical warning coefficient is greater than or equal to the second preset historical warning coefficient, a third product value of the third preset adjustment coefficient and the monitoring warning factor is calculated, and the third product value is used as the target monitoring warning factor.
[0050] In this embodiment, the first preset historical warning coefficient is smaller than the second preset historical warning coefficient. The first preset historical warning coefficient is preferably 0.6, and the second preset historical warning coefficient is preferably 0.8.
[0051] In this embodiment, the first preset adjustment coefficient is smaller than the second preset adjustment coefficient and smaller than the third preset adjustment coefficient. The first preset adjustment coefficient is preferably 0.95, the second preset adjustment coefficient is preferably 1, and the third preset adjustment coefficient is preferably 1.15.
[0052] The beneficial effect of the above technical solution is: the present invention selects the corresponding preset adjustment coefficient according to the relationship between the historical warning coefficient, the first preset historical warning coefficient and the second preset historical warning coefficient, and adjusts the monitoring warning factor, thereby realizing dynamic adjustment of the monitoring warning factor.
[0053] S140: Determine whether there is an abnormality in the electromagnetic suction cup control system of the excavator according to the target monitoring warning factor, and if so, issue a warning reminder in real time.
[0054] In some embodiments of the present application, when judging whether the excavator electromagnetic chuck control system is abnormal according to the target monitoring early warning factor, it includes: Determining whether there is an abnormality in the electromagnetic chuck control system of the excavator according to the relationship between the target monitoring warning factor and the preset target monitoring warning factor; When the target monitoring warning factor is less than the preset target monitoring warning factor, it is determined that there is no abnormality in the electromagnetic chuck control system of the excavator; When the target monitoring early warning factor is greater than or equal to the preset target monitoring early warning factor, it is determined that there is an abnormality in the excavator electromagnetic suction cup control system.
[0055] In this embodiment, the preset target monitoring early warning factor is preferably 1.2.
[0056] The beneficial effect of the above technical solution is: the present invention judges whether there is an abnormality in the excavator electromagnetic suction cup control system according to the relationship between the target monitoring and warning factors and the preset target monitoring and warning factors, thereby ensuring the convenience of the judgment process, improving the intelligence level of monitoring and warning, and realizing more efficient and accurate status monitoring and abnormal warning.
[0057] like Figure 2 As shown, in another preferred embodiment based on the above embodiment, this embodiment provides a monitoring and early warning system for an electromagnetic chuck control system of an excavator, comprising: The first module is used to collect the historical operation behavior of the electromagnetic chuck control system of the excavator, analyze the historical operation behavior, and calculate the historical warning coefficient of the electromagnetic chuck control system of the excavator based on the analysis result; The second module is used to obtain the real-time characteristic data of the electromagnetic chuck control system of the excavator, and obtain the historical characteristic data corresponding to the real-time characteristic data in the previous safety historical operation behavior, and calculate the monitoring and early warning factor of the electromagnetic chuck control system of the excavator based on the real-time characteristic data and the historical characteristic data; The third module is used to select a corresponding preset adjustment coefficient according to the historical warning coefficient, and adjust the monitoring warning factor based on the preset adjustment coefficient to obtain a target monitoring warning factor; The fourth module is used to determine whether there is an abnormality in the electromagnetic suction cup control system of the excavator according to the target monitoring and early warning factors. If so, an early warning reminder is issued in real time.
[0058] Those skilled in the art will appreciate that the embodiments of the present application may be provided as methods, systems or computer program products. Therefore, the present application may take the form of a complete hardware embodiment, a complete software embodiment, or an embodiment combining software and hardware. Moreover, the present application may take the form of a computer program product implemented on one or more computer-usable storage media (including but not limited to disk storage, CD-ROM, optical storage, etc.) containing computer-usable program codes.
[0059] The present application is described with reference to the flowcharts and / or block diagrams of the methods, devices (systems) and computer program products according to the embodiments of the present application. It should be understood that each process and / or box in the flowchart and / or block diagram, as well as the combination of processes and / or boxes in the flowchart and / or block diagram, can be implemented by computer program instructions. These computer program instructions can be provided to a processor of a general-purpose computer, a special-purpose computer, an embedded processor or other programmable data processing device to produce a machine, so that the instructions executed by the processor of the computer or other programmable data processing device generate instructions for implementing the processes in the flowchart and / or block diagram. Figure 1 A process or multiple processes and / or boxes Figure 1 A device that provides the functions specified in a block or multiple blocks.
[0060] These computer program instructions may also be stored in a computer-readable memory capable of directing a computer or other programmable data processing device to operate in a specific manner, so that the instructions stored in the computer-readable memory produce an article of manufacture comprising an instruction device, which implements the process Figure 1 A process or multiple processes and / or boxes Figure 1 A function specified in one or more boxes.
[0061] These computer program instructions can also be loaded onto a computer or other programmable data processing device so that a series of operating steps are executed on the computer or other programmable device to produce a computer-implemented process, thereby providing instructions for implementing the process. Figure 1 A process or multiple processes and / or boxes Figure 1 The steps for the functions specified in one or more boxes.
[0062] Finally, it should be noted that the above embodiments are only used to illustrate the technical solutions of the present invention rather than to limit it. Although the present invention has been described in detail with reference to the above embodiments, ordinary technicians in the relevant field should understand that the specific implementation methods of the present invention can still be modified or replaced by equivalents, and any modifications or equivalent replacements that do not depart from the spirit and scope of the present invention should be covered within the scope of protection of the present invention.
Claims
1. A monitoring and early warning method for an electromagnetic chuck control system of an excavator, characterized in that: include: Collecting historical operation behaviors of the electromagnetic chuck control system of the excavator, analyzing the historical operation behaviors, and calculating the historical warning coefficient of the electromagnetic chuck control system of the excavator based on the analysis results; Acquire real-time characteristic data of the electromagnetic chuck control system of the excavator, and acquire historical characteristic data corresponding to the real-time characteristic data in the previous safety historical operation behavior, and calculate the monitoring and early warning factor of the electromagnetic chuck control system of the excavator based on the real-time characteristic data and the historical characteristic data; Selecting a corresponding preset adjustment coefficient according to the historical warning coefficient, and adjusting the monitoring warning factor based on the preset adjustment coefficient to obtain a target monitoring warning factor; It is determined whether there is an abnormality in the electromagnetic suction cup control system of the excavator according to the target monitoring early warning factor. If so, an early warning reminder is issued in real time.
2. The monitoring and early warning method for the electromagnetic chuck control system of an excavator according to claim 1 is characterized in that: When collecting historical operation behaviors of the electromagnetic chuck control system of the excavator, analyzing the historical operation behaviors, and calculating the historical warning coefficient of the electromagnetic chuck control system of the excavator based on the analysis results, it includes: Based on the analysis results, the historical operation behaviors are divided into abnormal historical operation behaviors and safe historical operation behaviors; Counting the number of first behaviors of the abnormal historical operating behaviors and counting the number of second behaviors of the safe historical operating behaviors respectively; Determine an abnormal historical operation time fitting curve and a safe historical operation time fitting curve according to the abnormal historical operation behavior and the safe historical operation behavior, and determine an abnormal offset value corresponding to each abnormal historical operation behavior based on the abnormal historical operation time fitting curve and the safe historical operation time fitting curve; The historical warning coefficient of the electromagnetic chuck control system of the excavator is calculated according to the abnormal deviation value corresponding to each abnormal historical operating behavior.
3. The monitoring and early warning method for the electromagnetic chuck control system of an excavator according to claim 2 is characterized in that: When determining an abnormal historical operation time fitting curve and a safe historical operation time fitting curve according to the abnormal historical operation behavior and the safe historical operation behavior, and determining an abnormal offset value corresponding to each abnormal historical operation behavior based on the abnormal historical operation time fitting curve and the safe historical operation time fitting curve, the method includes: Determine the safety history control time corresponding to each safety history operation behavior; Based on the collection time series, all the safety history manipulation times are smoothly fitted to determine the safety history manipulation time fitting curve, wherein the horizontal axis of the safety history manipulation time fitting curve is the collection time, and the vertical axis is the safety history manipulation time; Determine the abnormal historical operation time corresponding to each abnormal historical operation behavior; Based on the acquisition time series, all abnormal historical manipulation times are smoothly fitted to determine an abnormal historical manipulation time fitting curve, wherein the abscissa of the abnormal historical manipulation time fitting curve is the acquisition time, and the ordinate is the abnormal historical manipulation time; Determine whether there is an intersection between the safety history operation time fitting curve and the abnormal history operation time fitting curve. If so, extract the abnormal history operation time at the intersection, calculate the shortest distance from the remaining abnormal history operation time on the abnormal history operation time fitting curve to the safety history operation time fitting curve, and use the shortest distance as the corresponding abnormal offset value; Extract the minimum shortest distance from all the shortest distances and use it as the abnormal offset value of the abnormal historical manipulation time at the intersection; If not, the shortest distance from each abnormal historical operation time on the abnormal historical operation time fitting curve to the safe historical operation time fitting curve is calculated, and the shortest distance is used as the corresponding abnormal offset value.
4. The monitoring and early warning method for the electromagnetic chuck control system of an excavator according to claim 2 is characterized in that: When calculating the historical warning coefficient of the electromagnetic sucker control system of the excavator according to the abnormal offset value corresponding to each abnormal historical operation behavior, it includes: The historical warning coefficient of the excavator electromagnetic suction cup control system is calculated according to the following formula: ; Among them, Y1 is the historical warning coefficient of the excavator electromagnetic suction cup control system, a is the first calculation coefficient, b is the second calculation coefficient, and a+b=1, a<b, n1 is the number of first behaviors, n2 is the number of second behaviors, k i is the abnormal offset value corresponding to the ith abnormal historical operation behavior, and kmax is the maximum abnormal offset value corresponding to the abnormal historical operation behavior.
5. The monitoring and early warning method for the electromagnetic chuck control system of an excavator according to claim 2 is characterized in that: When the monitoring and early warning factor of the excavator electromagnetic sucker control system is calculated based on the real-time characteristic data and the historical characteristic data, it includes: Acquire a standard data value corresponding to the real-time characteristic data; Determining a controllable data range according to the standard data value and the historical characteristic data, and dividing the real-time characteristic data into long-term unstable data, short-term unstable data and safety characteristic data according to the controllable data range; Normalizing the long-term unstable data to obtain a normalized data sequence; Performing standardization processing on the long-term unstable data to obtain a standardized data sequence; Determine the maximum normalized value and the minimum normalized value in the normalized data sequence, and calculate the normalized sum and the normalized difference of the maximum normalized value and the minimum normalized value respectively; Determine the maximum standardized value and the minimum standardized value in the standardized processed data sequence, and calculate the standardized sum and the standardized difference of the maximum standardized value and the minimum standardized value respectively; Determining a first processed value of the normalized processed data sequence according to the normalized sum value and the normalized difference value; Determine a second processed value of the standardized processed data sequence according to the standardized sum value and the standardized difference value; Extracting all long-term unstable data greater than the first processing value in the normalized data sequence to construct a first data sequence, and extracting all long-term unstable data greater than the second processing value in the standardized data sequence to construct a second data sequence; Extracting long-term unstable data of the intersection of the first data sequence and the second data sequence; Analyze the short-term unstable data and the safety feature data respectively to determine corresponding intersection short-term unstable data and intersection safety feature data; The monitoring and early warning factor of the excavator electromagnetic chuck control system is calculated according to the intersection long-term instability data, the intersection short-term instability data and the intersection safety feature data.
6. The monitoring and early warning method for the electromagnetic chuck control system of an excavator according to claim 5 is characterized in that: When determining a controllable data range according to the standard data value and the historical characteristic data, and dividing the real-time characteristic data into long-term unstable data, short-term unstable data and safety characteristic data according to the controllable data range, it includes: Determine the numerical value relationship between the standard data value and the historical characteristic data, and determine the left boundary value and the right boundary value based on the numerical value relationship; Constructing the controllable data range according to the left boundary value and the right boundary value; If the real-time feature data is less than or equal to the right boundary value, the corresponding real-time feature data is used as the security feature data; If the real-time feature data is greater than the right boundary value, an abnormal mark is generated for the corresponding real-time feature data; Analyze all abnormal historical operation behaviors and determine the abnormal characteristic data corresponding to each abnormal historical operation behavior; Pair the real-time feature data that generates the abnormal mark with all the abnormal feature data, and count the number of pairs; When the number of pairs is less than the preset number of pairs, the corresponding real-time feature data is used as the short-term unstable data; When the pairing quantity is greater than or equal to the preset pairing quantity, the corresponding real-time characteristic data is used as the long-term unstable data.
7. The monitoring and early warning method for the electromagnetic chuck control system of an excavator according to claim 5 is characterized in that: When the monitoring and early warning factor of the excavator electromagnetic chuck control system is calculated according to the intersection long-term unstable data, the intersection short-term unstable data and the intersection safety feature data, it includes: Respectively counting the first data quantity of the intersection long-term unstable data, the second data quantity of the intersection short-term unstable data, and the third data quantity of the intersection safety feature data; The monitoring and early warning factor of the excavator electromagnetic suction cup control system is calculated according to the following formula: ; Among them, L is the monitoring and early warning factor of the excavator electromagnetic suction cup control system, G1 is the first data quantity, G2 is the second data quantity, and G3 is the third data quantity.
8. The monitoring and early warning method for the electromagnetic chuck control system of an excavator according to claim 1 is characterized in that: When a corresponding preset adjustment coefficient is selected according to the historical warning coefficient, and the monitoring warning factor is adjusted based on the preset adjustment coefficient to obtain a target monitoring warning factor, the method includes: Presetting a first preset historical warning coefficient and a second preset historical warning coefficient; Presetting a first preset adjustment coefficient, a second preset adjustment coefficient, and a third preset adjustment coefficient; When the historical warning coefficient is less than the first preset historical warning coefficient, a first product value of the first preset adjustment coefficient and the monitoring warning factor is calculated, and the first product value is used as the target monitoring warning factor; When the historical warning coefficient is greater than or equal to the first preset historical warning coefficient and less than the second preset historical warning coefficient, a second product value of the second preset adjustment coefficient and the monitoring warning factor is calculated, and the second product value is used as the target monitoring warning factor; When the historical warning coefficient is greater than or equal to the second preset historical warning coefficient, a third product value of the third preset adjustment coefficient and the monitoring warning factor is calculated, and the third product value is used as the target monitoring warning factor.
9. The monitoring and early warning method for the electromagnetic chuck control system of an excavator according to claim 1, characterized in that: When judging whether the electromagnetic sucker control system of the excavator is abnormal according to the target monitoring and early warning factor, it includes: Determining whether there is an abnormality in the electromagnetic chuck control system of the excavator according to the relationship between the target monitoring warning factor and the preset target monitoring warning factor; When the target monitoring warning factor is less than the preset target monitoring warning factor, it is determined that there is no abnormality in the electromagnetic chuck control system of the excavator; When the target monitoring early warning factor is greater than or equal to the preset target monitoring early warning factor, it is determined that there is an abnormality in the excavator electromagnetic suction cup control system.
10. A monitoring and early warning system for an electromagnetic chuck control system of an excavator, characterized in that: include: The first module is used to collect the historical operation behavior of the electromagnetic chuck control system of the excavator, analyze the historical operation behavior, and calculate the historical warning coefficient of the electromagnetic chuck control system of the excavator based on the analysis result; The second module is used to obtain the real-time characteristic data of the electromagnetic chuck control system of the excavator, and obtain the historical characteristic data corresponding to the real-time characteristic data in the previous safety historical operation behavior, and calculate the monitoring and early warning factor of the electromagnetic chuck control system of the excavator based on the real-time characteristic data and the historical characteristic data; The third module is used to select a corresponding preset adjustment coefficient according to the historical warning coefficient, and adjust the monitoring warning factor based on the preset adjustment coefficient to obtain a target monitoring warning factor; The fourth module is used to determine whether there is any abnormality in the electromagnetic suction cup control system of the excavator according to the target monitoring and early warning factors. If so, an early warning reminder is issued in real time.
Citation Information
Cited By
Laboratory monitoring alarm system and method based on Internet of Things
CN119888991A