Battery formation and capacity grading control method, device and equipment and storage medium
Through neural network models, the abnormal situation of the battery and test equipment are predicted, and the working status is adjusted to early warning and control the component capacity process, which solves the interruption problem caused by abnormal equipment data in the prior art, and improves battery production efficiency and quality.
Patent Information
- Application Number
- CN202411357152.7
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-09-26
- Publication Date
- 2024-11-29
AI Technical Summary
The existing battery-based component storage system requires manual intervention when equipment data is abnormal, resulting in interruption of the component storage process and affecting the quality and production efficiency of the battery product.
Through neural network models, predict whether the battery and test equipment will have abnormalities in the next time period. If the probability value is greater than or equal to the preset threshold, adjust the equipment's working status to early warning and control the component capacity process, improve production efficiency and ensure battery quality.
It realizes early warning control during the battery-based component capacity process, reduces manual intervention, improves production efficiency and product quality, and reduces calculation errors.
Smart Images

Figure CN119050519A_ABST
Abstract
Description
Technical Field
[0001] The embodiments of the present application relate to battery technology, and relate to but are not limited to a battery fractionation capacity control method, device, equipment and storage medium. Background Art
[0002] In the existing chemical composition and capacity system, if the equipment data in the operation process has various calculation anomalies or failures at the current moment and sends an alarm message by mistake, manual intervention is often required to eliminate the abnormal impact before the next step can be taken. Before manual intervention, the entire chemical composition and capacity process is interrupted. Although there is no hardware problem with the battery and test equipment, it still causes the material preparation to be unable to continue, affecting the product quality of the battery and also reducing production efficiency. Summary of the invention
[0003] In view of this, the battery fractionation and capacity control method, device, equipment and storage medium provided in the embodiments of the present application can improve battery production efficiency and ensure battery quality.
[0004] In a first aspect, a battery capacity control method provided by an embodiment of the present application includes:
[0005] In the process of performing capacity analysis on the battery, target data in a current time period is obtained, wherein the target data includes a battery parameter corresponding to the battery and a test parameter corresponding to the test equipment, wherein the test parameter includes at least one of air pressure and cooling liquid capacity;
[0006] Inputting the target data in the current time period into a preset neural network model, and outputting the probability value of abnormality of the battery and the test equipment in the next time period through the neural network model;
[0007] When the probability value of an abnormality occurring in the target device is greater than or equal to a preset abnormality threshold, the working state of the target device is adjusted, and the target device includes the battery and / or the test device.
[0008] In the above-mentioned battery capacity control method, during the process of battery capacity formation, target data within the current time period is obtained, and the target data includes battery parameters corresponding to the battery and test parameters corresponding to the test equipment; the target data within the current time period is input into a preset neural network model, and the probability value of abnormality of the battery and the test equipment within the next time period is output through the neural network model; when the probability value of abnormality of the target equipment is greater than or equal to the preset abnormal threshold, the working state of the target equipment is adjusted, and the target equipment includes the battery and / or the test equipment. Therefore, during the battery capacity formation process, it is possible to predict whether the battery and the test equipment will be abnormal within the next time period, and to perform early warning control of the capacity formation process in advance, thereby improving battery production efficiency and ensuring battery quality. At the same time, because the battery parameters within a time period and the air pressure and cooling liquid capacity of the test equipment need to be analyzed simultaneously when using the neural network model for analysis, the calculation error is also reduced.
[0009] In some embodiments, the target device includes the battery, the working state of the battery includes a charging state, a discharging state, and a stop state, and the adjusting the working state of the target device includes:
[0010] If the current working state of the battery is the charging state or the discharging state, the battery is controlled to be in the stopping state.
[0011] In some embodiments, the target device includes the test device, and adjusting the working state of the target device includes:
[0012] The test device is controlled to adjust a test parameter from a first parameter value to a second parameter value, wherein the first parameter value and the second parameter value are different.
[0013] In some embodiments, the test device includes a pressure applying device, the pressure applying device is used to adjust the air pressure value of the environment in which the battery is located, the test parameter includes the air pressure, and the control of adjusting the test parameter of the test device from a first parameter value to a second parameter value includes:
[0014] The pressure applying device is controlled to adjust the air pressure value of the environment where the battery is located from a first air pressure value to a second air pressure value.
[0015] In some embodiments, the test device includes a flow meter, the test parameter includes the cooling liquid capacity, the flow meter is respectively connected to the battery compartment where the battery is placed and the cooling liquid storage compartment, and the control of adjusting the test parameter of the test device from the first parameter value to the second parameter value includes:
[0016] The flow meter is controlled to adjust the capacity of the cooling liquid outputted from the cooling liquid storage bin, so that the capacity of the cooling liquid flowing to the battery bin is switched from a first capacity value to a second capacity value.
[0017] In some embodiments, the method further comprises:
[0018] Acquire target data of the battery within a target time period, where the target time period includes a period of time after the working state of the battery is adjusted;
[0019] Detecting whether target data of the battery within a target time period is normal;
[0020] If the target data of the battery within the target time period is normal, the battery is controlled to switch from the stop state to the charging state or the discharging state.
[0021] In some embodiments, the method further comprises:
[0022] If the target data of the battery within the target time period is abnormal, an alarm message is output to prompt the user that the battery is abnormal.
[0023] In some embodiments, the method further comprises:
[0024] Acquire target data of the test device within a target time period, where the target time period includes a period of time after the working state of the test device is adjusted;
[0025] Detecting whether the target data of the test device within the target time period is normal;
[0026] If the target data of the test device within the target time period is normal, the test parameter of the test device is controlled to be maintained at the second parameter value.
[0027] In some embodiments, the method further comprises:
[0028] If the target data of the test device within the target time period is abnormal, an alarm message is output to prompt the user that the test device is abnormal.
[0029] In some embodiments, before adjusting the working state of the target device, the method further includes:
[0030] Receive and respond to the start command sent by the host computer to start the predictive control function;
[0031] The adjusting the working state of the battery and / or the testing device comprises:
[0032] When the predictive control function is turned on, the working state of the target device is adjusted.
[0033] In a second aspect, the battery fractionation control device provided in the embodiment of the present application includes:
[0034] A data acquisition module, used to obtain target data in a current time period during the process of performing capacity conversion on the battery, wherein the target data includes battery parameters corresponding to the battery and test parameters corresponding to the test equipment, wherein the test parameters include at least one of air pressure and cooling liquid capacity;
[0035] An abnormality prediction module, used for inputting the target data in the current time period into a preset neural network model, and outputting the probability value of abnormality of the battery and the test equipment in the next time period through the neural network model;
[0036] The state adjustment module is used to adjust the working state of the target device when the probability value of the target device being abnormal is greater than or equal to a preset abnormal threshold, and the target device includes the battery and / or the test device.
[0037] In a third aspect, a computer device provided in an embodiment of the present application includes a memory and a processor, wherein the memory stores a computer program executable on the processor, and the processor implements the method described in the embodiment of the present application when executing the program.
[0038] In a fourth aspect, the computer-readable storage medium provided in the embodiments of the present application has a computer program stored thereon, and when the computer program is executed by a processor, the method provided in the embodiments of the present application is implemented.
[0039] It should be understood that the second to fourth aspects of the embodiments of the present application are consistent with the technical solutions of the first aspect of the embodiments of the present application, and the beneficial effects achieved by each aspect and the corresponding feasible implementation methods are similar and will not be repeated here. BRIEF DESCRIPTION OF THE DRAWINGS
[0040] The drawings herein are incorporated into the specification and constitute a part of the specification. These drawings illustrate embodiments consistent with the present application and are used together with the specification to illustrate the technical solution of the present application.
[0041] Figure 1 One of the structural schematic diagrams of the battery capacity conversion system provided in the embodiment of the present application;
[0042] Figure 2 A schematic diagram of a flow chart of a battery capacity control method provided in an embodiment of the present application;
[0043] Figure 3 A schematic diagram of a flow chart of a battery capacity control method provided in an embodiment of the present application;
[0044] Figure 4 A schematic diagram of a flow chart of a battery capacity control method provided in an embodiment of the present application;
[0045] Figure 5 The second structural schematic diagram of the battery capacity conversion system provided in the embodiment of the present application;
[0046] Figure 6 The third structural diagram of the battery capacity division system provided in the embodiment of the present application;
[0047] Figure 7 A schematic diagram of a flow chart of a battery capacity control method provided in an embodiment of the present application;
[0048] Figure 8 A schematic diagram of a flow chart of a battery capacity control method provided in an embodiment of the present application;
[0049] Fig. 9 A schematic diagram of a flow chart of a battery capacity control method provided in an embodiment of the present application;
[0050] Fig.10 A schematic diagram of a flow chart of a battery capacity control method provided in an embodiment of the present application;
[0051] Fig.11 A schematic diagram of a flow chart of a battery capacity control method provided in an embodiment of the present application;
[0052] Fig.12 A schematic diagram of a flow chart of a battery capacity control method provided in an embodiment of the present application;
[0053] Fig.13 A schematic diagram of the structure of a battery capacity control device provided in an embodiment of the present application;
[0054] Fig.14 A schematic diagram of the structure of a computer device provided in an embodiment of the present application. DETAILED DESCRIPTION
[0055] In order to make the purpose, technical solution and advantages of the embodiments of the present application clearer, the specific technical solution of the present application will be further described in detail below in conjunction with the drawings in the embodiments of the present application. The following embodiments are used to illustrate the present application, but are not used to limit the scope of the present application.
[0056] Unless otherwise defined, all technical and scientific terms used herein have the same meaning as those commonly understood by those skilled in the art to which this application belongs. The terms used herein are only for the purpose of describing the embodiments of this application and are not intended to limit this application.
[0057] In the following description, reference is made to “some embodiments”, which describe a subset of all possible embodiments, but it will be understood that “some embodiments” may be the same subset or different subsets of all possible embodiments and may be combined with each other without conflict.
[0058] It should be pointed out that the terms "first\second\third" involved in the embodiments of the present application are used to distinguish similar or different objects, and do not represent a specific ordering of the objects. It can be understood that "first\second\third" can be interchanged in a specific order or sequence where permitted, so that the embodiments of the present application described here can be implemented in an order other than that illustrated or described here.
[0059] Figure 1 This is a schematic diagram of a battery capacity conversion system provided in an embodiment of the present application. Figure 1 As shown, the system includes an upper computer 10, a middle computer 20 and a lower computer 30. The middle computer 20 in this embodiment is connected to the upper computer 10 and the lower computer 30 respectively. Among them, the lower computer 30 is used to collect and upload the state parameters of the battery 40 to the middle computer 20; the middle computer 20 is used to process the state parameters of the battery 40 collected by the lower computer 30, and send an alarm message to the upper computer 10 when the data is abnormal; the upper computer 10 is used to receive the alarm message sent by the middle computer 20, and control the lower computer 30 to stop the dissolving process of the battery 40 through the middle computer 20 until the technician eliminates the alarm message.
[0060] Among them, the above-mentioned upper computer 10, middle computer 20 and lower computer 30 can communicate with each other through wired communication methods such as CAN bus or IIC bus, that is, the data flow and instructions between the upper computer 10, middle computer 20 and lower computer 30 are all transmitted through the CAN bus or IIC bus.
[0061] The lower computer may include a plurality of test devices, such as charge and discharge test devices, temperature test devices, and air pressure test devices, wherein the charge and discharge test devices are used to monitor the battery 40 parameters such as voltage and current during the charge and discharge process of the battery 40, the temperature test device is used to control the temperature of the battery 40 by controlling the volume of cooling liquid flowing to the battery 40, and the air pressure test device is used to control the air pressure value of the environment in which the battery 40 is located, so as to control the air pressure parameters of the fractionation process. The temperature test device is such as a flow meter, the air pressure test device is such as a negative pressure device, and the charge and discharge test device is such as a voltmeter and an ammeter.
[0062] The above-mentioned lower computer may further include a power supply to supply power to other devices in the lower computer through the power supply.
[0063] The above-mentioned intermediate computer 20 may include one or more electronic devices, which may be various types of devices with information processing capabilities during implementation. For example, the electronic device may include a personal computer, a laptop, a PDA or a server, etc.; the electronic device may also be a mobile terminal, for example, the mobile terminal may include a mobile phone, a car computer, a tablet computer or a projector, etc. The function implemented by the method can be implemented by calling the program code by the processor in the electronic device, and of course the program code can be stored in a computer storage medium. It can be seen that the electronic device at least includes a processor and a storage medium.
[0064] Because in the related technology the lower computer is connected to the upper computer through the middle computer, when the middle computer fails and cannot continue to operate, the upper computer cannot normally receive the alarm information, resulting in the technical personnel being unable to deal with the danger in time when the alarm danger occurs. When the middle computer has a program abnormality that causes the alarm information to be sent incorrectly, the technical personnel need to manually intervene to eliminate the alarm before the battery capacity splitting system can continue the capacity splitting process. Before the manual intervention, the entire capacity splitting process is interrupted, resulting in the inability to continue the material preparation, affecting the product quality of the battery 40, and also reducing the production efficiency.
[0065] In view of this, the present invention provides a method for controlling battery capacity. Figure 1 The intermediate computer 20 in the process of cell-forming the battery 40 obtains the target data in the current time period, the target data including the battery 40 parameters corresponding to the battery 40 and the test parameters corresponding to the test equipment; the target data in the current time period is input into the preset neural network model, and the probability value of abnormality of the battery 40 and the test equipment in the next time period is output through the neural network model; when the probability value of abnormality of the target equipment is greater than or equal to the preset abnormality threshold, the working state of the target equipment is adjusted, and the target equipment includes the battery 40 and / or the test equipment, so that in the process of cell-forming, it is possible to predict whether the battery 40 and the test equipment will be abnormal in the next time period, and to pre-warn and control the cell-forming process in advance, thereby improving the production efficiency of the battery 40 and ensuring the quality of the battery 40. At the same time, because the battery 40 parameters and the air pressure and cooling liquid capacity of the test equipment in a time period need to be analyzed simultaneously when the neural network model is used for analysis, the calculation error is also reduced.
[0066] Figure 2 The flowchart of the battery capacity control method provided in the embodiment of the present application is as follows. Figure 2 As shown, the method may include the following steps:
[0067] Step S101, in the process of performing capacity analysis on the battery 40, target data in the current time period is obtained, the target data including battery 40 parameters corresponding to the battery 40 and test parameters corresponding to the test equipment, the test parameters including at least one of air pressure and cooling liquid capacity;
[0068] Step S102, inputting the target data in the current time period into a preset neural network model, and outputting the probability value of abnormality of the battery 40 and the test equipment in the next time period through the neural network model;
[0069] Step S103, when the probability value of the target device being abnormal is greater than or equal to a preset abnormal threshold, adjusting the working state of the target device, the target device including the battery 40 and / or the test device.
[0070] It should be understood that, in the process of converting the battery 40 into a capacity, the test equipment will affect the temperature, current, voltage, etc. of the battery 40 in the process of regulating the battery 40, and the battery 40 itself will also affect the current and voltage due to its own temperature factors and power factors during the charging and discharging process. Therefore, when the battery 40 parameters of the battery 40 are abnormal, it is impossible to clearly determine whether it is caused by the test equipment or the battery 40 itself. Therefore, if the battery 40 parameters in the current time period are used to predict the battery 40 parameters in the next time period, or the test parameters in the current time period are used to predict the test parameters in the next time period, the two will affect each other, thereby reducing the accuracy of the prediction. Therefore, in this embodiment, it is necessary to consider both the battery 40 parameters corresponding to the battery 40 and the test parameters corresponding to the test equipment, and include the influence of the two parameter data on each other in the calculation and analysis scope to improve the accuracy of the prediction.
[0071] Among them, the above-mentioned current time period can be a time period including the current moment and at least one moment before the current moment, or it can be a time period only including at least two moments before the current moment. The specific setting is made by technical personnel in this field according to actual conditions, and this application does not impose any restrictions.
[0072] Among them, the above-mentioned neural network model can be ARIMA or Seasonal Autoregressive Integrated Moving Average Model (SARIMA). After the technician inputs the target data in at least two historical time periods into the ARIMA or SARIMA model, the ARIMA or SARIMA model can know the data characteristics and corresponding data trends between the target data, so that the target data in the current time period can be input into the trained neural network model, and the target data in the next time period can be output to complete the prediction of the target data in the next time period.
[0073] It should be noted that the above neural network model is obtained by training with target data from at least two historical time periods. The specific training process uses common technical means and will not be repeated here.
[0074] Optionally, in addition to the above-mentioned neural network model, the method for judging whether the probability value of the target device having an abnormality is greater than or equal to a preset abnormality threshold value can also be obtained through a prediction algorithm, that is, based on the target data in the current time period and the preset prediction algorithm, the target data in the next time period is predicted, and when the difference between the target data and the standard data in the next time period is greater than the difference threshold, it is determined that the probability value of the target device corresponding to the target data having an abnormality is greater than or equal to the preset abnormality threshold value, wherein the target data in the above-mentioned next time period can be obtained by processing, analyzing and predicting the target data in the current time period in chronological order. Commonly used processing and analysis methods include an autoregressive integrated moving average model (ARIMA), or predicting future values by calculating the moving average between two adjacent target data. The moving average calculation method includes a simple moving average and a weighted moving average, so as to predict the target data in the next time period. The specific calculation process adopts commonly used technical means, which will not be repeated here.
[0075] Optionally, whether the target data in the next time period is abnormal can be determined by comparing the target data in the next time period with the corresponding parameter threshold range. For example, if the predicted current of the battery 40 in the next time period is 3A, and the corresponding current threshold range is 0 to 2A, then the current of the battery 40 in the next time period exceeds the current threshold range and is considered abnormal.
[0076] Optionally, the battery 40 parameters corresponding to the above-mentioned battery 40 can be sent to the central machine after being detected by testing equipment such as a fuel meter, an ammeter and a voltmeter, and the above-mentioned test parameters such as air pressure and cooling liquid capacity can be sent to the central machine after being tested by testing equipment such as a proportional valve and a flow meter.
[0077] Optionally, the above-mentioned battery 40 parameters may include output parameters such as the voltage and current of the battery 40, and may also include the charging state or discharging state of the battery 40 at this time, and may also include the temperature of the battery 40 and the ambient temperature, etc., which are specifically set by technical personnel in this field according to actual conditions, and this application does not impose any restrictions.
[0078] Optionally, in step S103, when one or several items of the target data are abnormal, a step of adjusting the working state of the battery 40 and / or the test equipment is executed, or when all data in the target data are abnormal, a step of adjusting the working state of the battery 40 and / or the test equipment is executed. The specific setting is made by technical personnel in this field according to actual conditions and is not limited in this application.
[0079] Optionally, when the target data in the next time period is abnormal, only the working state of the battery 40 may be adjusted, or only the working state of the test equipment may be adjusted, or the working state of the battery 40 and the test equipment may be adjusted. The specific setting is made by technical personnel in this field according to actual conditions, and this application does not impose any restrictions.
[0080] Furthermore, when the parameters of battery 40 in the next time period are abnormal, the working state of battery 40 can be adjusted, or the working state of the testing equipment can be adjusted. Similarly, when the test parameters in the next time period are abnormal, the working state of battery 40 can be adjusted, or the working state of the testing equipment can be adjusted.
[0081] Optionally, the above-mentioned method of adjusting the working state of the battery 40 may be to disconnect the charging circuit or the discharging circuit connected to the battery 40 to stop the charging process or the discharging process of the battery 40, or to speed up or slow down the discharge speed or the charging speed of the battery 40, etc., so as to achieve the purpose of adjusting the parameters of the battery 40 during the charging process or the discharging process. The specific setting is made by technical personnel in this field according to actual conditions, and this application does not impose any restrictions.
[0082] In some embodiments, Figure 3 As shown, if the target device includes a battery 40, the working state of the battery 40 may include a charging state, a discharging state and a stop state, and the step S103 may include:
[0083] Step S1031, if the current working state of the battery 40 is a charging state or a discharging state, the battery 40 is controlled to be in a stopped state.
[0084] Optionally, the method of controlling the battery 40 to be in a charging state or a discharging state can be that the battery 40 and the charging power supply are connected through a first switch, and the battery 40 and the load are connected through a second switch. When the neutral machine controls the first switch to be turned on and the second switch to be turned off, the battery 40 and the charging power supply are connected so that the battery 40 is in a charging state; when the neutral machine controls the second switch to be turned on and the first switch to be turned off, the battery 40 and the load are connected so that the battery 40 is in a discharging state.
[0085] Accordingly, the method of controlling the battery 40 to be in a stop state can be that the intermediate machine controls both the second switch and the first switch to be disconnected, thereby disconnecting the connection between the battery 40 and the load, and the connection between the battery 40 and the charging power supply, so that the battery 40 stops charging and discharging.
[0086] It can be understood that by controlling the battery 40 to be in a stopped state when the target data in the next time period is abnormal, the charge and discharge test of the battery 40 can be suspended to reduce damage to the battery 40.
[0087] Optionally, the above-mentioned method of adjusting the working state of the test device may be to adjust the working time of the test device, or to adjust the test parameters of the test device.
[0088] In some embodiments, Figure 4 As shown, if the target device includes a test device, the above step S103 may include:
[0089] When the probability value of an abnormality in the test parameter in the next time period is greater than or equal to a preset abnormality threshold, the test device is controlled to adjust the test parameter from a first parameter value to a second parameter value, and the first parameter value and the second parameter value are different.
[0090] It should be understood that adjusting the test parameter from the first parameter value to the second parameter value refers to slowing down the progress of the battery capacity conversion process, that is, by adjusting the test parameter, the purpose of reducing the rate of the charge and discharge process is achieved.
[0091] Among them, under normal circumstances, the battery 40 needs to be carried out in a test environment with a certain air pressure and temperature during the capacity splitting process, and the air pressure value and temperature value therein correspond to a target range. Therefore, the way to reduce the rate of the charging and discharging process can be to change the air pressure value and temperature value in the test environment so that the difference between the air pressure value and temperature value in the current test environment and the boundary value of the corresponding target range is less than a certain range, thereby slowing down the capacity splitting process.
[0092] Furthermore, the anomaly can appear to be larger than the normal value, or smaller than the normal value, and the size of the test parameter can be adjusted according to the size relationship between the target data and the normal value. For example, when the target data in the next time period is larger than the normal value, the size of the test parameter can be reduced; when the target data in the next time period is smaller than the normal value, the size of the test parameter can be increased.
[0093] In some embodiments, Figure 5 As shown, the above-mentioned test equipment may include a pressure device, the pressure device is used to adjust the air pressure value of the environment in which the battery 40 is located, the test parameter includes the air pressure, and the test parameter of the test equipment is controlled to be adjusted from the first parameter value to the second parameter value, including:
[0094] The pressure applying device is controlled to adjust the air pressure value of the environment where the battery 40 is located from the first air pressure value to the second air pressure value.
[0095] Among them, during the normal decomposition process, the pressure-applying device will apply an air pressure of the first air pressure value to the battery 40, but when it is determined that the target data in the next time period is abnormal, the air pressure of the pressure-applying device can be adjusted, that is, from the first air pressure value to the second air pressure value, thereby achieving the purpose of slowing down the decomposition process.
[0096] The specific values of the first air pressure value and the second air pressure value can be set by those skilled in the art according to actual conditions, and this application does not impose any limitation thereto.
[0097] In some embodiments, Figure 6 As shown, the above-mentioned test equipment may include a flow meter, and the test parameter includes the cooling liquid capacity. The flow meter is connected to the battery compartment where the battery 40 is placed and the cooling liquid storage compartment, respectively, and the test parameter of the test equipment is controlled to be adjusted from the first parameter value to the second parameter value, including:
[0098] The flow meter is controlled to adjust the capacity of the cooling liquid outputted from the cooling liquid storage bin, so that the capacity of the cooling liquid flowing to the battery bin is switched from a first capacity value to a second capacity value.
[0099] Among them, in the normal capacity splitting process, since the battery 40 will generate heat in the process of capacity splitting, the flow meter needs to control the capacity of the cooling liquid flowing through the battery 40, so as to achieve the purpose of controlling the temperature of the battery 40. When the flow meter controls the cooling liquid of the first capacity value to flow through the battery 40, the battery 40 can perform the capacity splitting process at a normal rate, but in the case of judging that the target data in the next time period is abnormal, the flow meter can be controlled to adjust the cooling liquid capacity output from the cooling liquid storage bin, that is, adjust it from the first capacity value to the second capacity value, so as to achieve the purpose of slowing down the capacity splitting process.
[0100] It should be noted that the test equipment may also include other equipment in the prior art that constitutes the test environment of the battery 40 during the capacity conversion process. The above-mentioned pressure device and flow meter are only examples and should not be used as a limitation on the present application. Based on the scheme in this embodiment, technical personnel in this field can deduce that the purpose of slowing down the battery capacity conversion process can be achieved by adjusting the test parameters of other test equipment.
[0101] It is understandable that by adjusting the test parameters of the test equipment when the target data in the next time period is abnormal, the progress of the battery capacity division process can be adjusted to reduce damage to the test equipment and the battery 40 .
[0102] Optionally, the number of the above-mentioned battery 40 can be one or more. When the number of the battery 40 is one, the lower computer collects data for a single battery 40. When the number of the battery 40 is more than one, the multiple batteries 40 can be numbered one by one, and the test parameters and battery 40 parameters corresponding to the number can be stored according to the number. In this way, the target data corresponding to the number can be quickly retrieved, thereby realizing the rapid collection and storage of production data.
[0103] In the above-mentioned battery capacity splitting control method, during the process of splitting the battery 40, the target data in the current time period is obtained, and the target data includes the battery 40 parameters corresponding to the battery 40 and the test parameters corresponding to the test equipment; according to the target data in the current time period, the target data in the next time period is predicted; and when the target data in the next time period is abnormal, the working state of the battery 40 and / or the test equipment is adjusted, so that during the battery capacity splitting process, the target data in the next time period can be predicted, and the capacity splitting process can be pre-warned and controlled in advance, thereby improving the production efficiency of the battery 40 and ensuring the quality of the battery 40.
[0104] In some embodiments, Figure 7 As shown, the above method also includes:
[0105] Step S104, obtaining target data of the battery 40 within a target time period, where the target time period includes a period of time after the working state of the battery 40 is adjusted;
[0106] Step S105, detecting whether the target data of the battery 40 within the target time period is normal;
[0107] Step S106 , if the target data of the battery 40 within the target time period is normal, the battery 40 is controlled to switch from the stop state to the charging state or the discharging state.
[0108] During the implementation process, after the working state of the battery 40 is adjusted according to the target data in the next time period, the target data of the battery 40 within a period of time after the adjustment can continue to be obtained. If the obtained target data is normal, it means that the capacity splitting process of the battery 40 has not shown the predicted abnormal phenomenon. Therefore, the battery 40 can be controlled to switch from the stop state to the charging state or the discharging state to continue the capacity splitting process of the battery 40.
[0109] The method of determining whether the target data of the battery 40 in the target time period is normal in the above step S105 can refer to the method of determining whether the target data in the next time period is normal in step S103, which will not be repeated here.
[0110] In other embodiments, Figure 8 As shown, the above method also includes:
[0111] Step S107 , if the target data of the battery 40 within the target time period is abnormal, an alarm message is output to prompt the user that the battery 40 is abnormal.
[0112] Optionally, the alarm information may be audio-visual information, or a prompt message sent to a host computer, which is specifically set by those skilled in the art according to actual conditions, and is not limited in this application.
[0113] It should be understood that if after adjusting the working state of battery 40, the battery 40 parameters of battery 40 are still abnormal, then an alarm message can be output at this time to prompt the technician that there may be an abnormality in the hardware of battery 40 and a thorough investigation is required, thereby helping the technician to find the cause of the abnormality in the decomposition process.
[0114] In some embodiments, Fig. 9 As shown, the above method also includes:
[0115] Step S108, obtaining target data of the test device within a target time period, where the target time period includes a period of time after the working state of the test device is adjusted;
[0116] Step S109, detecting whether the target data of the test device within the target time period is normal;
[0117] Step S110 , if the target data of the test device within the target time period is normal, then the test parameter of the test device is controlled to be maintained at a second parameter value.
[0118] During the implementation process, after the working state of the test equipment is adjusted according to the target data in the next time period, the target data of the test equipment within a period of time after the adjustment can continue to be obtained. If the obtained target data is normal, it means that the capacity splitting process of the battery 40 has not shown the predicted abnormal phenomenon, or the abnormal phenomenon has been eliminated after the test parameters have been adjusted. Therefore, the test parameters of the test equipment can be controlled to maintain at the second parameter value at this time to continue the capacity splitting process of the battery 40.
[0119] The method of determining whether the target data of the test device in the target time period is normal in the above step S109 can refer to the method of determining whether the target data in the next time period is normal in step S103, which will not be repeated here.
[0120] It should be noted that the process of steps S108 to S110 and the process of steps S104 to S106 can be to execute only one of the processes or both processes; when both processes are executed, the steps S108 to S110 and the steps S104 to S106 can be executed simultaneously or in sequence, which is specifically configured by those skilled in the art according to actual conditions and is not limited in this application.
[0121] In some embodiments, Fig.10 As shown, the above method also includes:
[0122] Step S111: if the target data of the test device within the target time period is abnormal, an alarm message is output to prompt the user that the test device is abnormal.
[0123] Optionally, the alarm information may be audio-visual information, or a prompt message sent to a host computer, which is specifically set by those skilled in the art according to actual conditions, and is not limited in this application.
[0124] It should be understood that if after adjusting the working state of the test equipment, the test parameters of the test equipment are still abnormal, then an alarm message can be output at this time to remind the technician that there may be an abnormality in the hardware of the test equipment and a thorough investigation is required, thereby helping the technician to find the cause of the abnormality in the chemical composition process.
[0125] In some embodiments, Fig.11 As shown, before adjusting the working state of the battery 40 and / or the test equipment, the method further includes:
[0126] Step S112, receiving and responding to the start instruction sent by the host computer, and starting the predictive control function;
[0127] Accordingly, the working status of the battery 40 and / or the testing device includes:
[0128] Step S1033, when the predictive control function is turned on, the working state of the battery 40 and / or the test equipment is adjusted.
[0129] Among them, the upper computer can set a function button for turning on the predictive control function of the intermediate computer. When the technician does not need to execute the battery capacity control method in this embodiment, the predictive control function can be turned off by triggering the function button, and the intermediate computer does not participate in automatic control and is switched to manual control; when the technician needs to execute the battery capacity control method in this embodiment, the predictive control function can be turned on by triggering the function button. When the target data in the next time period is abnormal, the intermediate computer adjusts the working status of the battery 40 and / or the test equipment to realize automatic control of the battery capacity control process.
[0130] It can be understood that by setting a function switch for the method flow of this embodiment, more abundant battery fraction capacity control means can be provided to technicians.
[0131] Optionally, when the predictive control function is turned off, the intermediate computer can still train the neural network model based on the collected target data to improve the prediction accuracy of the neural network model for the target data in the next time.
[0132] Optionally, the method further includes: when receiving a target instruction sent by the host computer and the target instruction does not belong to a preset instruction, filtering the target instruction and outputting a prompt message to the host computer to prompt that the target instruction is invalid. Thus, the intermediate computer can detect in real time whether the technician's operation meets the production requirements.
[0133] Among them, the above-mentioned preset instructions can be pre-set in the intermediate machine by the technician, or sent from the upper machine to the intermediate machine. The specific setting is made by technical personnel in this field according to actual conditions, and this application does not impose any restrictions.
[0134] The following describes an exemplary application of the embodiments of the present application in a practical application scenario.
[0135] Fig.12 The overall process of the battery capacity control method provided in the embodiment of the present application is as follows. Fig.12 As shown, the method comprises the following steps:
[0136] Step S1101, the intermediate computer collects battery 40 parameters of the battery 40 and test parameters of the test equipment to form a database, wherein the test parameters include at least one of air pressure and cooling liquid capacity;
[0137] Step S1102, the intermediate computer trains the neural network model according to the data in the database to obtain a trained neural network model;
[0138] Step S1103, in the process of dividing the battery 40 into components, the intermediate computer obtains target data in the current time period, the target data including battery 40 parameters corresponding to the battery 40 and test parameters corresponding to the test equipment;
[0139] Step S1104, the median computer predicts the target data in the next time period based on the target data in the current time period and the neural network model;
[0140] Step S1105, when the target data in the next time period is abnormal and the predictive control function is turned on, if the current working state of the battery 40 is a charging state or a discharging state, the intermediate machine controls the battery 40 to be in a stopped state;
[0141] Step S1106, the intermediate computer obtains target data of the battery 40 within a target time period, where the target time period includes a period of time after the working state of the battery 40 is adjusted;
[0142] Step S1107, the intermediate computer detects whether the target data of the battery 40 within the target time period is normal;
[0143] Step S1108, if the target data of the battery 40 within the target time period is normal, the intermediate computer controls the battery 40 to switch from the stop state to the charging state or the discharging state;
[0144] Step S1109, if the target data of the battery 40 within the target time period is abnormal, the intermediate computer outputs an alarm message to the upper computer to prompt the user that the battery 40 is abnormal;
[0145] Step S1110, when the target data in the next time period is abnormal and the predictive control function is turned on, the intermediate computer controls the test device to adjust the test parameter from the first parameter value to the second parameter value;
[0146] Step S1111, the intermediate computer obtains target data of the test equipment within a target time period, where the target time period includes a period of time after the working state of the test equipment is adjusted;
[0147] Step S1112, the intermediate computer detects whether the target data of the test equipment within the target time period is normal;
[0148] Step S1113, if the target data of the test device within the target time period is normal, the intermediate computer controls the test parameter of the test device to maintain at the second parameter value;
[0149] Step S1114, if the target data of the test device within the target time period is abnormal, the intermediate computer outputs an alarm message to the upper computer to prompt the user that the test device is abnormal.
[0150] It should be understood that although Figure 2-11 The steps in the flowchart are shown in sequence as indicated by the arrows, but these steps are not necessarily executed in the order indicated by the arrows. Unless otherwise specified in this document, there is no strict order restriction for the execution of these steps, and these steps can be executed in other orders. Moreover, Figure 2-11 At least part of the steps may include multiple sub-steps or multiple stages. These sub-steps or stages are not necessarily executed at the same time, but can be executed at different times. The execution order of these sub-steps or stages is not necessarily sequential, but can be executed in turn or alternately with other steps or at least part of the sub-steps or stages of other steps.
[0151] Based on the foregoing embodiments, the embodiments of the present application provide a battery capacity control device, which includes the modules included and the units included in the modules, which can be implemented by a processor; of course, it can also be implemented by a specific logic circuit; in the implementation process, the processor can be a central processing unit (CPU), a microprocessor (MPU), a digital signal processor (DSP) or a field programmable gate array (FPGA), etc.
[0152] Fig.13 The schematic diagram of the structure of the battery capacity control device provided in the embodiment of the present application is as follows: Fig.13 As shown, the battery capacity control device includes:
[0153] The data acquisition module 1201 is used to obtain target data in a current time period during the process of performing capacity analysis on the battery 40, wherein the target data includes battery 40 parameters corresponding to the battery 40 and test parameters corresponding to the test equipment, wherein the test parameters include at least one of air pressure and cooling liquid capacity;
[0154] The data prediction module 1202 is used to input the target data in the current time period into a preset neural network model, and output the probability value of abnormality of the battery 40 and the test equipment in the next time period through the neural network model;
[0155] The state adjustment module 1203 is used to adjust the working state of the target device when the probability value of the target device being abnormal is greater than or equal to a preset abnormal threshold, and the target device includes the battery 40 and / or the test device.
[0156] In some embodiments, the target device includes the battery, the working state of the battery includes a charging state, a discharging state and a stop state, and the state adjustment module 1203 is specifically used for:
[0157] If the current working state of the battery is a charging state or a discharging state, the battery is controlled to be in a stopped state.
[0158] In some embodiments, the target device includes a test device, and the state adjustment module 1203 is specifically used to:
[0159] The test device is controlled to adjust the test parameter from a first parameter value to a second parameter value, wherein the first parameter value and the second parameter value are different.
[0160] In some embodiments, the test device includes a pressure device, which is used to adjust the air pressure value of the battery environment, and the test parameters include the air pressure. The state adjustment module 1203 is specifically used to:
[0161] The pressure applying device is controlled to adjust the air pressure value of the battery environment from the first air pressure value to the second air pressure value.
[0162] In some embodiments, the test equipment includes a flow meter, the test parameters include the cooling liquid capacity, the flow meter is respectively connected to the battery compartment where the battery is placed and the cooling liquid storage compartment, and the state adjustment module 1203 is specifically used for:
[0163] The flow meter is controlled to adjust the capacity of the cooling liquid outputted from the cooling liquid storage bin, so that the capacity of the cooling liquid flowing to the battery bin is switched from a first capacity value to a second capacity value.
[0164] In some embodiments, the above apparatus may further include:
[0165] A data acquisition module, used to acquire target data of the battery within a target time period, where the target time period includes a period of time after the working state of the battery is adjusted;
[0166] A data detection module is used to detect whether the target data of the battery within the target time period is normal;
[0167] The state recovery module is used to control the battery to switch from the stop state to the charging state or the discharging state if the target data of the battery within the target time period is normal.
[0168] In some embodiments, the above apparatus may further include:
[0169] The status warning module is used to output an alarm message if the target data of the battery within the target time period is abnormal, so as to prompt the user that the battery is abnormal.
[0170] In some embodiments, the above apparatus may further include:
[0171] A data acquisition module, used to acquire target data of the test equipment within a target time period, where the target time period includes a period of time after the working state of the test equipment is adjusted;
[0172] A data detection module is used to detect whether the target data of the test equipment within the target time period is normal;
[0173] The parameter maintaining module is used to control the test parameters of the test device to be maintained at a second parameter value if the target data of the test device within the target time period is normal.
[0174] In some embodiments, the above apparatus may further include:
[0175] The status warning module is used to output an alarm message if the target data of the test equipment within the target time period is abnormal, so as to prompt the user that there is an abnormality in the test equipment.
[0176] In some embodiments, the above apparatus may further include:
[0177] A function activation module is used to receive and respond to an activation instruction sent by a host computer to activate the predictive control function;
[0178] Accordingly, the data acquisition module 1201 is specifically used for:
[0179] When the predictive control function is turned on, the working state of the target device is adjusted.
[0180] The description of the above device embodiment is similar to the description of the above method embodiment, and has similar beneficial effects as the method embodiment. For technical details not disclosed in the device embodiment of the present application, please refer to the description of the method embodiment of the present application for understanding.
[0181] It should be noted that in the embodiments of this application Fig.13 The division of modules in the battery capacity control device shown is schematic and is only a logical functional division. There may be other division methods in actual implementation. In addition, each functional unit in each embodiment of the present application can be integrated into a processing unit, or it can exist physically separately, or two or more units can be integrated into one unit. The above-mentioned integrated unit can be implemented in the form of hardware or in the form of a software functional unit. It can also be implemented in the form of a combination of software and hardware.
[0182] It should be noted that in the embodiment of the present application, if the above method is implemented in the form of a software function module and sold or used as an independent product, it can also be stored in a computer-readable storage medium. Based on such an understanding, the technical solution of the embodiment of the present application can be essentially or partly embodied in the form of a software product that contributes to the relevant technology. The computer software product is stored in a storage medium, including several instructions to enable an electronic device to execute all or part of the methods described in each embodiment of the present application. The aforementioned storage medium includes: various media that can store program codes, such as a U disk, a mobile hard disk, a read-only memory (ROM), a magnetic disk or an optical disk. In this way, the embodiment of the present application is not limited to any specific combination of hardware and software.
[0183] The embodiment of the present application provides a computer device, which may be a server, and its internal structure diagram may be as follows: Fig.14 As shown. The computer device includes a processor, a memory and a network interface connected through a system bus. Among them, the processor of the computer device is used to provide computing and control capabilities. The memory of the computer device includes a non-volatile storage medium and an internal memory. The non-volatile storage medium stores an operating system, a computer program and a database. The internal memory provides an environment for the operation of the operating system and the computer program in the non-volatile storage medium. The database of the computer device is used to store data. The network interface of the computer device is used to communicate with an external terminal through a network connection. When the computer program is executed by the processor, a battery capacity control method is implemented.
[0184] An embodiment of the present application provides a computer-readable storage medium on which a computer program is stored. When the computer program is executed by a processor, the steps in the method provided in the above embodiment are implemented.
[0185] An embodiment of the present application provides a computer program product including instructions, which, when executed on a computer, enables the computer to execute the steps of the method provided in the above method embodiment.
[0186] Those skilled in the art will understand that Fig.14 The structure shown in the figure is only a block diagram of a part of the structure related to the solution of the present application, and does not constitute a limitation on the computer device to which the solution of the present application is applied. The specific computer device may include more or fewer components than those shown in the figure, or combine certain components, or have a different arrangement of components.
[0187] In one embodiment, the battery capacity control device provided in the present application can be implemented in the form of a computer program. The computer program can be Fig.14The computer device shown in the figure is run. The memory of the computer device can store various program modules constituting the electronic device. The computer program composed of various program modules enables the processor to execute the steps of the battery fractionation capacity control method of various embodiments of the present application described in this specification.
[0188] In one embodiment, a computer device is provided, including a memory and a processor, wherein the memory stores a computer program, and the processor implements the steps of the above-mentioned battery fractionation capacity control method when executing the computer program.
[0189] It should be noted here that the description of the above storage medium and device embodiments is similar to the description of the above method embodiments, and has similar beneficial effects as the method embodiments. For technical details not disclosed in the storage medium, storage medium and device embodiments of this application, please refer to the description of the method embodiments of this application for understanding.
[0190] It should be understood that "one embodiment" or "an embodiment" or "some embodiments" mentioned throughout the specification means that specific features, structures or characteristics related to the embodiment are included in at least one embodiment of the present application. Therefore, "in one embodiment" or "in one embodiment" or "in some embodiments" appearing throughout the specification may not necessarily refer to the same embodiment. In addition, these specific features, structures or characteristics can be combined in one or more embodiments in any suitable manner. It should be understood that in various embodiments of the present application, the size of the sequence number of the above-mentioned processes does not mean the order of execution, and the execution order of each process should be determined by its function and internal logic, and should not constitute any limitation on the implementation process of the embodiment of the present application. The above-mentioned sequence numbers of the embodiments of the present application are only for description and do not represent the advantages and disadvantages of the embodiments. The above description of each embodiment tends to emphasize the differences between the various embodiments, and the same or similar aspects can be referenced to each other. For the sake of brevity, this article will not repeat them.
[0191] The term "and / or" in this article is only a description of the association relationship of associated objects, indicating that there may be three relationships. For example, object A and / or object B can represent three situations: object A exists alone, object A and object B exist at the same time, and object B exists alone.
[0192] It should be noted that, in this article, the terms "include", "comprises" or any other variations thereof are intended to cover non-exclusive inclusion, so that a process, method, article or device including a series of elements includes not only those elements, but also other elements not explicitly listed, or also includes elements inherent to such process, method, article or device. In the absence of further restrictions, an element defined by the sentence "comprises a ..." does not exclude the existence of other identical elements in the process, method, article or device including the element.
[0193] In the several embodiments provided in the present application, it should be understood that the disclosed devices and methods can be implemented in other ways. The embodiments described above are only schematic. For example, the division of the modules is only a logical function division. There may be other division methods in actual implementation, such as: multiple modules or components can be combined, or can be integrated into another system, or some features can be ignored, or not executed. In addition, the coupling, direct coupling, or communication connection between the components shown or discussed can be through some interfaces, and the indirect coupling or communication connection of devices or modules can be electrical, mechanical or other forms.
[0194] The modules described above as separate components may or may not be physically separated, and the components displayed as modules may or may not be physical modules; they may be located in one place or distributed on multiple network units; some or all of the modules may be selected according to actual needs to achieve the purpose of the present embodiment.
[0195] In addition, all functional modules in the embodiments of the present application may be integrated into one processing unit, or each module may be a separate unit, or two or more modules may be integrated into one unit; the above-mentioned integrated modules may be implemented in the form of hardware or in the form of hardware plus software functional units.
[0196] A person skilled in the art can understand that all or part of the steps of implementing the above method embodiment can be completed by hardware related to program instructions, and the aforementioned program can be stored in a computer-readable storage medium. When the program is executed, it executes the steps of the above method embodiment; and the aforementioned storage medium includes: mobile storage devices, read-only memories (ROM), magnetic disks or optical disks, etc., various media that can store program codes.
[0197] Alternatively, if the above-mentioned integrated unit of the present application is implemented in the form of a software function module and sold or used as an independent product, it can also be stored in a computer-readable storage medium. Based on this understanding, the technical solution of the embodiment of the present application can essentially or in other words, the part that contributes to the relevant technology can be embodied in the form of a software product, and the computer software product is stored in a storage medium, including a number of instructions for enabling an electronic device to execute all or part of the methods described in each embodiment of the present application. The aforementioned storage medium includes: various media that can store program codes, such as mobile storage devices, ROMs, magnetic disks, or optical disks.
[0198] The methods disclosed in several method embodiments provided in this application can be arbitrarily combined without conflict to obtain new method embodiments.
[0199] The features disclosed in several product embodiments provided in this application can be arbitrarily combined without conflict to obtain new product embodiments.
[0200] The features disclosed in several method or device embodiments provided in this application can be arbitrarily combined without conflict to obtain new method embodiments or device embodiments.
[0201] The above is only an implementation method of the present application, but the protection scope of the present application is not limited thereto. Any person skilled in the art who is familiar with the present technical field can easily think of changes or substitutions within the technical scope disclosed in the present application, which should be included in the protection scope of the present application. Therefore, the protection scope of the present application should be based on the protection scope of the claims.
Claims
1. A battery capacity control method, characterized in that: The method comprises: In the process of performing capacity analysis on the battery, target data in a current time period is obtained, wherein the target data includes a battery parameter corresponding to the battery and a test parameter corresponding to the test equipment, wherein the test parameter includes at least one of air pressure and cooling liquid capacity; Inputting the target data in the current time period into a preset neural network model, and outputting the probability value of abnormality of the battery and the test equipment in the next time period through the neural network model; When the probability value of an abnormality occurring in the target device is greater than or equal to a preset abnormality threshold, the working state of the target device is adjusted, and the target device includes the battery and / or the test device.
2. The method according to claim 1, characterized in that The target device includes the battery, the working state of the battery includes a charging state, a discharging state, and a stop state, and the adjusting the working state of the target device includes: If the current working state of the battery is the charging state or the discharging state, the battery is controlled to be in the stopping state.
3. The method according to claim 1, characterized in that The target device includes the test device, and the adjusting the working state of the target device includes: The test device is controlled to adjust a test parameter from a first parameter value to a second parameter value, wherein the first parameter value and the second parameter value are different.
4. The method according to claim 3, characterized in that The testing device includes a pressure applying device, the pressure applying device is used to adjust the air pressure value of the environment where the battery is located, the test parameter includes the air pressure, and the control of adjusting the test parameter of the testing device from a first parameter value to a second parameter value includes: The pressure applying device is controlled to adjust the air pressure value of the environment where the battery is located from a first air pressure value to a second air pressure value.
5. The method according to claim 3, characterized in that The test device includes a flow meter, the test parameter includes the cooling liquid capacity, the flow meter is respectively connected to the battery compartment where the battery is placed and the cooling liquid storage compartment, and the control of adjusting the test parameter of the test device from a first parameter value to a second parameter value includes: The flow meter is controlled to adjust the capacity of the cooling liquid outputted from the cooling liquid storage bin, so that the capacity of the cooling liquid flowing to the battery bin is switched from a first capacity value to a second capacity value.
6. The method according to claim 2, characterized in that The method further comprises: Acquire target data of the battery within a target time period, where the target time period includes a period of time after the working state of the battery is adjusted; Detecting whether target data of the battery within a target time period is normal; If the target data of the battery within the target time period is normal, the battery is controlled to switch from the stop state to the charging state or the discharging state.
7. The method according to claim 6, characterized in that The method further comprises: If the target data of the battery within the target time period is abnormal, an alarm message is output to prompt the user that the battery is abnormal.
8. The method according to claim 3, characterized in that The method further comprises: Acquire target data of the test device within a target time period, where the target time period includes a period of time after the working state of the test device is adjusted; Detecting whether the target data of the test device within the target time period is normal; If the target data of the test device within the target time period is normal, the test parameter of the test device is controlled to be maintained at the second parameter value.
9. The method according to claim 8, characterized in that The method further comprises: If the target data of the test device within the target time period is abnormal, an alarm message is output to prompt the user that the test device is abnormal.
10. The method according to any one of claims 1 to 9, characterized in that: Before adjusting the working state of the target device, the method further includes: Receive and respond to the start command sent by the host computer to start the predictive control function; The adjusting the working state of the battery and / or the testing device comprises: When the predictive control function is turned on, the working state of the target device is adjusted.
11. A battery capacity control device, characterized in that: include: A data acquisition module, used to obtain target data in a current time period during the process of performing capacity conversion on the battery, wherein the target data includes battery parameters corresponding to the battery and test parameters corresponding to the test equipment, wherein the test parameters include at least one of air pressure and cooling liquid capacity; An abnormality prediction module, used for inputting the target data in the current time period into a preset neural network model, and outputting the probability value of abnormality of the battery and the test equipment in the next time period through the neural network model; The state adjustment module is used to adjust the working state of the target device when the probability value of the target device being abnormal is greater than or equal to a preset abnormal threshold, and the target device includes the battery and / or the test device.
12. A computer device comprising a memory and a processor, wherein the memory stores a computer program executable on the processor, wherein: When the processor executes the program, the steps of the method according to any one of claims 1 to 10 are implemented.
13. A computer-readable storage medium having a computer program stored thereon, characterized in that: When the computer program is executed by a processor, the method according to any one of claims 1 to 10 is implemented.
Citation Information
Cited By
Formation control method and device of battery, electronic equipment, medium and product
CN121862914A