Power distribution network multi-objective optimization regulation and control method considering energy storage life

By building a multi-objective optimization model in the distribution network, considering the energy storage life loss and voltage deviation targets, optimizing the photovoltaic and energy storage power, the energy storage life loss problem in the existing technology is solved, and the energy storage life extension and grid stability are achieved Sex improvement.

CN119051004AActive Publication Date: 2024-11-29ELECTRIC POWER RES INST CHINA SOUTHERN POWER GRID CO LTD +3

Patent Information

Application Number
CN202411156637.X
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-08-22
Publication Date
2024-11-29
Estimated Expiration
2044-08-22

AI Technical Summary

Technical Problem

The existing distribution network optimization and regulation research has not taken into account the life loss problem caused by energy storage operations, which has caused energy storage to frequently change the charge and discharge state and deep discharge, affecting its life.

Method used

A multi-objective optimization and regulation method for distribution networks that calculates energy storage life is proposed. By constructing a recently-run optimization model based on the source load pre-date prediction data, solving the energy storage charge and discharge state and on-load voltage regulation transformer gear, combined with intraday prediction data Build a multi-objective operation optimization model, considering the energy storage life loss cost and voltage deviation targets, and optimizing the power instructions for photovoltaics and energy storage.

Benefits of technology

It effectively avoids the life loss caused by frequent energy conversion and deep discharge of energy storage, extends the energy storage life, reduces node voltage deviation, and ensures the safe and economical operation of the distribution network.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119051004A_ABST
    Figure CN119051004A_ABST
Patent Text Reader

Abstract

The invention discloses a power distribution network multi-objective optimization regulation and control method considering energy storage life. The method comprises the following steps: constructing a power distribution network day-ahead operation optimization model based on source load day-ahead prediction data; according to the day-ahead operation optimization model of the power distribution network, solving an output energy storage charging and discharging state, an on-load voltage regulation OLTC gear and a CB switching group result; constructing an energy storage life loss model according to the node cycle index, the discharge depth and the discharge rate, and calculating the energy storage life loss cost through the energy storage life loss model; constructing an intra-day multi-target operation optimization model of the power distribution network based on the intra-day prediction data of the source load; the objective function of the distribution network intra-day multi-objective operation optimization model comprises an economical efficiency objective and a voltage deviation objective; wherein the economical efficiency target is constructed according to the energy storage life loss cost, and the voltage deviation target is constructed according to the actual node voltage value; and according to the intra-day multi-target operation optimization model of the power distribution network, solving to obtain a photovoltaic and energy storage power instruction.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of power systems, and in particular to a multi-objective optimization control method for a distribution network taking into account the life of energy storage. Background Art

[0002] In recent years, distributed power sources have developed rapidly. With the continuous increase in their penetration rate in the distribution network, problems such as system economy and voltage over-limit have become increasingly prominent. Discrete equipment such as on-load tap-changing transformers and shunt capacitor banks on the distribution network side can effectively reduce voltage deviation and reduce the risk of voltage over-limit while improving system economy. Energy storage systems, as temporary energy storage devices, can solve the randomness and volatility of distributed energy. Connecting these resources to the distribution network can effectively solve the system economy and voltage over-limit problems caused by high distributed penetration, and promote stable and economical operation of the distribution network.

[0003] At present, relevant scholars have carried out some research on the optimization and regulation of distribution networks, but most of the existing research targets the cost of purchasing electricity, network loss costs, equipment operating costs, etc., and does not consider the life loss cost caused by energy storage actions. The life of energy storage is related to its number of cycles and discharge depth, and energy storage needs to frequently switch charge and discharge states to cope with intraday source and load fluctuations, and deep discharge behavior may exist. However, existing research on the optimization and regulation of distribution networks does not consider the life loss caused by energy storage actions. On the one hand, the energy storage is treated as a continuous device and its charge and discharge state is updated during the day, resulting in frequent conversion of the charge and discharge state of the energy storage, causing its life loss. On the other hand, when the energy storage output power is updated during the day to smooth the source and load fluctuations and regulate the node voltage, there may be deep discharge behavior, causing energy storage life loss. Therefore, it is necessary to consider the impact of the number of energy storage cycles and the depth of discharge on the life of energy storage to ensure high-quality and long-life operation of energy storage. Summary of the invention

[0004] In view of this, the present invention provides a multi-objective optimization and control method for distribution networks taking into account the life of energy storage, so as to at least solve the problem that the research on distribution network optimization and control in the prior art does not consider the life loss caused by energy storage action.

[0005] In order to achieve the above object, the present invention adopts the following technical solution:

[0006] A multi-objective optimization control method for a distribution network taking into account energy storage life includes the following steps:

[0007] S1. Construct a distribution network day-ahead operation optimization model based on the source-load day-ahead forecast data;

[0008] S2. According to the day-ahead operation optimization model of the distribution network, the day-ahead optimization results are solved, where the day-ahead optimization results include the energy storage charging and discharging status, the gear position of the on-load tap-changing transformer, the switching results of the capacitor bank, and the output power of photovoltaic and energy storage;

[0009] S3. The energy storage charging and discharging state, on-load tap-changing transformer gear position and capacitor bank switching results in the day-ahead optimization results are taken as known quantities, and a distribution network intraday multi-objective operation optimization model is constructed based on the source-load intraday forecast data; the objective function of the distribution network intraday multi-objective operation optimization model includes an economic objective and a voltage deviation objective; among which, the economic objective takes into account the energy storage life loss cost, and the voltage deviation objective is constructed according to the actual value of the node voltage;

[0010] S4. Based on the multi-objective operation optimization model of the distribution network during the day, the power instructions of photovoltaic and energy storage are solved.

[0011] Preferably, the day-ahead operation optimization model of the distribution network in S1 aims to minimize the total operating cost of the distribution network and controllable resources, where the distribution network operating cost includes the power purchase cost C grid and distribution network loss cost C loss The operating cost of controllable resources includes the photovoltaic operation and maintenance cost C pv , Energy storage operation and maintenance cost C ess , OLTC action cost C OLTC , CB action cost C CB and the abandoned light cost C pl ;

[0012] The objective function of the distribution network day-ahead operation optimization model is:

[0013] minC=C grid +C loss +C pv +C ess +C OLTC +C CB +C pl (1)

[0014]

[0015]

[0016]

[0017]

[0018]

[0019]

[0020]

[0021] Where: is the electricity purchase price coefficient at time t; is the power purchased by the distribution network from the main grid at time t; Δt 1is the time scale of day-ahead scheduling, is the current value flowing from node i to node j at time t; R ij is the resistance value of line ij; c pv is the photovoltaic operation cost coefficient; is the actual consumption value of photovoltaic power at node j at time t; c ess is the energy storage operation cost coefficient; and are the charging power and discharging power of energy storage at node j at time t; c OLTC is the OLTC action cost coefficient; is the OLTC tap position on branch ij at time t; c CB is the CB action cost coefficient; is the number of capacitor groups in operation at node j at time t; c pl is the cost coefficient of abandoned light, is the output power of the photovoltaic node j at time t;

[0022] The day-ahead operation constraints of the distribution network are as follows:

[0023] 1) Distribution network flow constraints:

[0024]

[0025]

[0026] In the formula, and are the injected active power and reactive power of node j at time t respectively; and are the active power and reactive power of branch ij at time t respectively; σ(j) represents the set of nodes downstream of node j; δ(j) represents the set of nodes upstream of node j; is the voltage value of node j at time t; X ij is the reactance value of line ij;

[0027] 2) Constraints on safe operation of power grid:

[0028]

[0029] Where U min and U max The lower and upper limits of the full run; is the upper limit of the branch ij current;

[0030] 3) Photovoltaic output constraints:

[0031]

[0032] 4) Energy storage operation constraints:

[0033]

[0034]

[0035] In the formula, and are binary variables representing the charging state and discharging state of the energy storage at node j. When the value is 1, it means that the energy storage is working in the charging and discharging state, so as to limit the energy storage from being in the charging and discharging state at the same time. j,max is the upper limit of the energy storage charging and discharging power of node j; E is the energy storage charge of node j at time t; jmax and E jmin are the upper and lower limits of the energy storage charge of node j respectively;

[0036] 5) Operation constraints of on-load tap-changing transformers:

[0037]

[0038] In the formula, is the adjustable ratio of OLTC on branch ij at time t; and Δk ij are the standard transformation ratio and adjustment step of OLTC on branch ij respectively; K ijmax is the maximum value of the adjustable gear of OLTC in branch ij;

[0039] 6) Parallel capacitor bank operation constraints:

[0040]

[0041] In the formula, is the reactive output power of the capacitor bank; Y is the reactive output power of a single group of capacitors at node j; j,CBmax is the upper limit of the number of capacitor groups at node j.

[0042] Preferably, the specific contents of calculating the energy storage life loss cost in S3 include:

[0043] The total equivalent discharge capacity of energy storage over its entire life cycle under rated conditions is expressed as:

[0044] E j,eq =E j,max N j,max D j,max (17)

[0045] Where: E j,eq N is the total equivalent discharge capacity of energy storage in the whole life cycle under rated conditions of node j; j,max is the rated number of cycles of energy storage at node j, D j,maxis the rated discharge depth of energy stored at node j;

[0046] Considering the charge and discharge rate and discharge depth in the actual operation process, ignoring the life loss caused by energy storage charging, the equivalent discharge capacity of energy storage at node j at time t is expressed as:

[0047]

[0048] Where: is the equivalent discharge amount of energy storage at node j at time t; is the actual number of energy storage cycles at node j at time t, P j,max is the upper limit of the energy storage charging and discharging power of node j; are the discharge power of energy storage at node j at time t; is the actual discharge amount of energy stored at node j at time t;

[0049] The actual cycle life of energy storage is obtained by fitting and is expressed as:

[0050]

[0051] Where: u 1 and u 2 are the fitting curve coefficients, is the actual discharge depth of energy storage at node j at time t;

[0052] The energy storage life loss cost is:

[0053]

[0054] Where: c el is the investment cost per unit capacity of energy storage.

[0055] Preferably, for the nonlinear function energy storage life loss cost F el Perform linearization:

[0056] The piecewise linearization method is used to linearize the nonlinear function energy storage life loss cost;

[0057] Due to the variable The value of is within [0,1], the interval [0,1] is divided into N-1 segments, corresponding to N segmentation points dod 1 , dod 2 ,···,dod N , introduce a continuous variable η in [0,1] n , then the energy storage life loss model is linearized as:

[0058]

[0059]

[0060] Where: f[dod n ] is the dod corresponding to the nth segment point n Segment F el function.

[0061] Preferably, the objective function of the distribution network intraday multi-objective operation optimization model in S3 is:

[0062] minF=ω 1 F 1 +ω 2 F 2 (twenty three)

[0063] f 1 =F grid +F loss +F pv +F ess +F el (twenty four)

[0064]

[0065] Where: 1 and ω 2 The target F 1 and F 2 The weight of F 1 The economic target of the day's operation; F 2 F is the voltage deviation target for daily operation; grid is the electricity purchase cost, F loss is the network loss cost, F pv is the abandoned light cost, F ess is the energy storage operation and maintenance cost, F el is the energy storage life loss cost; U j is the actual value of the node voltage;

[0066]

[0067] Where: Δt 2 The time scale for intraday scheduling;

[0068] The constraints of the distribution network daily operation optimization model include: energy storage operation constraints, solar curtailment cost constraints C pl , distribution network flow constraints, grid safety operation constraints and energy storage operation constraints, among which the curtailment cost constraint C pl As shown in formula (8);

[0069] The energy storage operation constraints are:

[0070]

[0071] In the formula, and is a binary variable of the energy storage charging and discharging state in the intraday stage, and its value is equal to the optimization result of the energy storage charging and discharging state variable the day before, that is,

[0072]

[0073] It can be seen from the above technical solutions that, compared with the prior art, the present invention discloses a multi-objective optimization control method for a distribution network taking into account the energy storage life, which has the following beneficial effects:

[0074] On the basis of the existing two-stage optimization and dispatching of distribution networks, in order to avoid the loss of energy storage life caused by frequent conversion of charging and discharging states of energy storage and deep discharge caused by smoothing source and load fluctuations and regulating node voltage, the present invention proposes a distribution network multi-objective optimization and control method that takes into account the energy storage life. On the basis of the existing distribution network optimization and control strategy, this method considers the damage caused to the energy storage life by frequent conversion of charging and discharging states within the day. The energy storage charging and discharging state is executed according to the optimization result of the day before, and it is not updated within the day. In addition, the loss of energy storage life caused by the depth of energy storage discharge and discharge rate is fully considered within the day. In addition, considering the voltage over-limit problem of distribution network nodes caused by source and load fluctuations, in addition to the economic target, the node voltage deviation target is considered, and a multi-objective operation optimization model of the distribution network within the day is established to update the power of photovoltaic and energy storage. This method comprehensively considers the energy storage life and voltage control, and on the basis of ensuring the economy of the distribution network, it prolongs the energy storage life and reduces the node voltage deviation, which is of great significance to the safe and economic operation of the distribution network. BRIEF DESCRIPTION OF THE DRAWINGS

[0075] In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative work.

[0076] Figure 1 It is a flow chart of the multi-objective optimization control strategy of the distribution network taking into account the energy storage life involved in the present invention;

[0077] Figure 2 is a schematic diagram of system topology provided by an embodiment of the present invention;

[0078] Figure 3 It is a schematic diagram of photovoltaic predicted output power and daily load provided by an embodiment of the present invention;

[0079] Figure 4Schematic diagram of the charging and discharging state of three energy storages in solution 1 provided by an embodiment of the present invention, (a) is the charging and discharging state of the energy storage connected to 11 nodes, (b) is the charging and discharging state of the energy storage connected to 24 nodes, and (c) is the charging and discharging state of the energy storage connected to 32 nodes;

[0080] Figure 5 Schematic diagram of the charging and discharging status of three energy storages in solution 2 provided in an embodiment of the present invention, (a) is the charging and discharging status of the energy storage connected to 11 nodes, (b) is the charging and discharging status of the energy storage connected to 24 nodes, and (c) is the charging and discharging status of the energy storage connected to 32 nodes;

[0081] Figure 6 Schematic diagram of the output power of three energy storages in solution 1 provided by an embodiment of the present invention, (a) is the output power of the energy storage connected to 11 nodes, (b) is the output power of the energy storage connected to 24 nodes, and (c) is the output power of the energy storage connected to 32 nodes;

[0082] Figure 7 Schematic diagram of the output power of three energy storages in solution 2 provided in an embodiment of the present invention, (a) is the output power of the energy storage connected to 11 nodes, (b) is the output power of the energy storage connected to 24 nodes, and (c) is the output power of the energy storage connected to 32 nodes;

[0083] Figure 8 This is a voltage deviation diagram of each node in a 24-hour 33-node distribution network according to a solution 1 provided in an embodiment of the present invention;

[0084] Fig. 9 This is a voltage deviation diagram of each node in a 24-hour 33-node distribution network according to Solution 2 provided in an embodiment of the present invention. DETAILED DESCRIPTION

[0085] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0086] The present invention provides a multi-objective optimization control method for a distribution network taking into account the energy storage life, comprising the following steps:

[0087] S1. Construct a distribution network day-ahead operation optimization model based on the source-load day-ahead forecast data;

[0088] S2. According to the day-ahead operation optimization model of the distribution network, the day-ahead optimization results are solved, where the day-ahead optimization results include the energy storage charging and discharging status, the gear position of the on-load tap-changing transformer, the switching results of the capacitor bank, and the output power of photovoltaic and energy storage;

[0089] S3. The energy storage charging and discharging state, on-load tap-changing transformer gear position and capacitor bank switching results in the day-ahead optimization results are taken as known quantities, and a distribution network intraday multi-objective operation optimization model is constructed based on the source-load intraday forecast data; the objective function of the distribution network intraday multi-objective operation optimization model includes an economic objective and a voltage deviation objective; among which, the economic objective takes into account the energy storage life loss cost, and the voltage deviation objective is constructed according to the actual value of the node voltage;

[0090] S4. Based on the multi-objective operation optimization model of the distribution network during the day, the power instructions of photovoltaic and energy storage are solved.

[0091] It should be noted that:

[0092] In this embodiment, according to the above-mentioned distribution network day-ahead operation optimization model, MATLAB is used to call the Gurobi solver for solution, and the energy storage charging and discharging state, OLTC gear position and CB switching group results are output and transmitted to the distribution network intraday multi-objective operation optimization model. According to the distribution network intraday multi-objective operation optimization model taking into account the energy storage life, MATLAB is used to call the Gurobi solver for solution to obtain the power of photovoltaic and energy storage.

[0093] In order to further implement the above technical solutions, the distribution network day-ahead operation optimization model in S1 aims to minimize the total operating cost of the distribution network and controllable resources, where the distribution network operating cost includes the power purchase cost C grid and distribution network loss cost C loss The operating cost of controllable resources includes the photovoltaic operation and maintenance cost C pv , Energy storage operation and maintenance cost C ess , OLTC action cost C OLTC , CB action cost C CB and the abandoned light cost C pl ;

[0094] The objective function of the distribution network day-ahead operation optimization model is:

[0095] minC=C grid +C loss +C pv +C ess +C OLTC +C CB +C pl (1)

[0096]

[0097]

[0098]

[0099]

[0100]

[0101]

[0102]

[0103] Where: is the electricity purchase price coefficient at time t; is the power purchased by the distribution network from the main grid at time t; Δt 1 is the time scale of day-ahead scheduling, is the current value flowing from node i to node j at time t; R ij is the resistance value of line ij; c pv is the photovoltaic operation cost coefficient; is the actual consumption value of photovoltaic power at node j at time t; c ess is the energy storage operation cost coefficient; and are the charging power and discharging power of energy storage at node j at time t; c OLTC is the OLTC action cost coefficient; is the OLTC tap position on branch ij at time t; c CB is the CB action cost coefficient; is the number of capacitor groups in operation at node j at time t; c pl is the cost coefficient of abandoned light, is the output power of the photovoltaic node j at time t;

[0104] The day-ahead operation constraints of the distribution network are as follows:

[0105] 1) Distribution network flow constraints:

[0106]

[0107]

[0108] In the formula, and are the injected active power and reactive power of node j at time t respectively; and are the active power and reactive power of branch ij at time t respectively; σ(j) represents the set of nodes downstream of node j; δ(j) represents the set of nodes upstream of node j; is the voltage value of node j at time t; X ij is the reactance value of line ij;

[0109] 2) Constraints on safe operation of power grid:

[0110]

[0111] Where U min and U max The lower and upper limits of the full run; is the upper limit of the branch ij current;

[0112] 3) Photovoltaic output constraints:

[0113]

[0114] 4) Energy storage operation constraints:

[0115]

[0116]

[0117] In the formula, and are binary variables representing the charging state and discharging state of the energy storage at node j. When the value is 1, it means that the energy storage is working in the charging and discharging state, so as to limit the energy storage from being in the charging and discharging state at the same time. j,max is the upper limit of the energy storage charging and discharging power of node j; E is the energy storage charge of node j at time t; jmax and E jmin are the upper and lower limits of the energy storage charge of node j respectively;

[0118] 5) Operation constraints of on-load tap-changing transformers:

[0119]

[0120] In the formula, is the adjustable ratio of OLTC on branch ij at time t; and Δk ij are the standard transformation ratio and adjustment step of OLTC on branch ij respectively; K ijmax is the maximum value of the adjustable gear of OLTC in branch ij;

[0121] 6) Parallel capacitor bank operation constraints:

[0122]

[0123] In the formula, is the reactive output power of the capacitor bank; Y is the reactive output power of a single group of capacitors at node j; j,CBmax is the upper limit of the number of capacitor groups at node j.

[0124] In order to further implement the above technical solution, the specific contents of calculating the energy storage life loss cost in S3 include:

[0125] The total equivalent discharge capacity of energy storage over its entire life cycle under rated conditions is expressed as:

[0126] E j,eq =E j,max N j,max D j,max (17)

[0127] Where: E j,eq N is the total equivalent discharge capacity of energy storage in the whole life cycle under rated conditions of node j; j,max is the rated number of cycles of energy storage at node j, D j,max is the rated discharge depth of energy stored at node j;

[0128] Considering the charge and discharge rate and discharge depth in the actual operation process, ignoring the life loss caused by energy storage charging, the equivalent discharge capacity of energy storage at node j at time t is expressed as:

[0129]

[0130] Where: is the equivalent discharge amount of energy storage at node j at time t; is the actual number of energy storage cycles at node j at time t, P j,max is the upper limit of the energy storage charging and discharging power of node j; are the discharge power of energy storage at node j at time t; is the actual discharge amount of energy stored at node j at time t;

[0131] The actual cycle life of energy storage is obtained by fitting and is expressed as:

[0132]

[0133] Where: u 1 and u 2 are the fitting curve coefficients, is the actual discharge depth of energy storage at node j at time t;

[0134] The energy storage life loss cost is:

[0135]

[0136] Where: c el is the investment cost per unit capacity of energy storage.

[0137] In order to further implement the above technical solution, the actual cycle life of energy storage represented by formula (18) is a nonlinear function, and the life loss cost is also a nonlinear function. For the nonlinear function energy storage life loss cost F el Perform linearization:

[0138] The piecewise linearization method is used to linearize the nonlinear function energy storage life loss cost;

[0139] Due to the variable The value of is within [0,1], the interval [0,1] is divided into N-1 segments, corresponding to N segmentation points dod 1 , dod 2 ,···,dod N , introduce a continuous variable η in [0,1] n , then the energy storage life loss model is linearized as:

[0140]

[0141]

[0142] Where: f[dod n ] is the dod corresponding to the nth segment point n Segment F el function.

[0143] In order to further implement the above technical solution, the objective function of the multi-objective operation optimization model of the distribution network in S3 is:

[0144] minF=ω 1 F 1 +ω 2 F 2 (twenty three)

[0145] f 1 =F grid +F loss +F pv +F ess +F el (twenty four)

[0146]

[0147] Where: 1 and ω 2 The target F 1 and F 2 The weight of F 1 The economic target of the day's operation; F 2 F is the voltage deviation target for daily operation; grid is the electricity purchase cost, F loss is the network loss cost, F pv is the abandoned light cost, F ess is the energy storage operation and maintenance cost, F el is the energy storage life loss cost; U j is the actual value of the node voltage;

[0148]

[0149] Where: Δt 2 The time scale for intraday scheduling;

[0150] The constraints of the distribution network daily operation optimization model include: energy storage operation constraints, solar curtailment cost constraints C pl , distribution network flow constraints, grid safety operation constraints and energy storage operation constraints, among which the curtailment cost constraint C pl As shown in formula (8);

[0151] The energy storage operation constraints are:

[0152]

[0153] In the formula, and is a binary variable of the energy storage charging and discharging state in the intraday stage, and its value is equal to the optimization result of the energy storage charging and discharging state variable the day before, that is,

[0154]

[0155] In order to verify the effectiveness and superiority of the method involved in the present invention, the IEEE 33-node distribution network system is taken as an example in this embodiment. The system topology diagram is as follows: Figure 2 As shown in the figure, the normalized photovoltaic predicted power and daily load curve are as follows Figure 3 As shown, the load power fluctuation is set to within ±5%, and the photovoltaic predicted power fluctuation is within ±10%. The access nodes and parameters of each device are shown in Table 1, the cost coefficient values ​​of each part are shown in Table 2, and the time-of-use electricity price is shown in Table 3:

[0156] Table 1 Equipment access nodes and parameters

[0157]

[0158] Table 2 Cost coefficient values ​​of each part

[0159]

[0160] Table 3 Time-of-use electricity prices

[0161]

[0162]

[0163] In order to verify the day-ahead and day-intraday optimization control method for distribution networks taking into account energy storage life and voltage control proposed in the present invention, the following scheme is set up for comparative analysis to illustrate the effectiveness of the scheme in this paper.

[0164] Option 1: The energy storage life is not considered, and the energy storage charging and discharging status is executed according to the intraday optimization results. The intraday optimization does not consider the energy storage life loss cost; the node voltage deviation is not considered, and the intraday optimization only aims at economy.

[0165] Solution 2 (solution of the present invention): Considering the energy storage life, the energy storage charging and discharging state is executed according to the day-ahead optimization result, and the intra-day optimization considers the energy storage life loss cost; considering the node voltage deviation, the intra-day optimization takes the economy and the node voltage deviation as the goal.

[0166] The energy storage life loss cost and node voltage deviation under the two schemes are calculated respectively, as shown in Table 4 below. Among them, the energy storage life loss cost and node voltage deviation of scheme 1 are numerically solved by bringing the optimization results into the numerical solution.

[0167] Table 4 Comparison of results of two schemes

[0168]

[0169] As shown in Table 4, under the scheme of the present invention, for the three nodes [11, 24, 32] to which the energy storage device is connected, the life loss cost of the energy storage is reduced by 8.18% compared with scheme 1. Figure 4 , 5 They are respectively the charging and discharging state diagrams of the energy storage connected to the three nodes under scheme 1 and the scheme of the present invention, as shown in Figure 6 , 7 The following are the output power diagrams of the energy storage connected to the three nodes under scheme 1 and the scheme of the present invention. It can be seen from the figure that the energy storage under the scheme of the present invention can reduce the number of charge and discharge state conversions and the depth of discharge, making the output power curve of the energy storage smoother and improving the life cycle of the energy storage; Figure 8 , 9 The table shows the node voltages under scheme 1 and the scheme of the present invention. It can be seen from the table and the figure that the scheme of the present invention can reduce the system node voltage deviation and maintain the stable operation of the system. That is, the scheme of the present invention can ensure the safe and economical operation of the distribution network.

[0170] The above embodiments are only used to illustrate the technical solutions of the present application, rather than to limit them. Although the present application has been described in detail with reference to the aforementioned embodiments, those skilled in the art should understand that they can still modify the technical solutions described in the aforementioned embodiments, or make equivalent replacements for some of the technical features therein. These modifications or replacements do not deviate the essence of the corresponding technical solutions from the spirit and scope of the technical solutions of the embodiments of the present application, and should all be included in the protection scope of the present application.

Claims

1. A multi-objective optimization control method for a distribution network taking into account the life of energy storage, characterized in that: The following steps are involved: S1. Construct a distribution network day-ahead operation optimization model based on the source-load day-ahead forecast data; S2. According to the day-ahead operation optimization model of the distribution network, solve the day-ahead optimization results, where the day-ahead optimization results include the energy storage charging and discharging status, the gear position of the on-load tap-changing transformer, the switching results of the capacitor bank, and the output power of photovoltaic and energy storage; S3. The energy storage charging and discharging state, on-load tap-changing transformer gear position and capacitor bank switching results in the day-ahead optimization results are taken as known quantities, and a distribution network intraday multi-objective operation optimization model is constructed based on the source-load intraday forecast data; the objective function of the distribution network intraday multi-objective operation optimization model includes an economic objective and a voltage deviation objective; among which, the economic objective takes into account the energy storage life loss cost, and the voltage deviation objective is constructed according to the actual value of the node voltage; S4. Update the output power instructions of photovoltaic and energy storage according to the multi-objective operation optimization model of the distribution network during the day.

2. A multi-objective optimization control method for distribution network taking into account energy storage life according to claim 1, characterized in that: The distribution network day-ahead operation optimization model in S1 aims to minimize the total operating cost of the distribution network and controllable resources, where the distribution network operating cost includes the power purchase cost C grid and distribution network loss cost C loss The operating cost of controllable resources includes the photovoltaic operation and maintenance cost C pv , Energy storage operation and maintenance cost C ess , OLTC action cost C OLTC , CB action cost C CB and the abandoned light cost C pl ; The objective function of the distribution network day-ahead operation optimization model is: minC=C grid +C loss +C pv +C ess +C OLTC +C CB +C pl (1) Where: T is the single-day scheduling cycle; is the electricity purchase price coefficient at time t; is the power purchased by the distribution network from the main grid at time t; Δt1 is the time scale of the day-ahead dispatch, is the current value flowing from node i to node j at time t; R ij is the resistance value of line ij; c pv is the photovoltaic operation cost coefficient; is the actual consumption value of photovoltaic power at node j at time t; c ess is the energy storage operation cost coefficient; and are the charging power and discharging power of energy storage at node j at time t; c OLTC is the OLTC action cost coefficient; is the OLTC tap position on branch ij at time t; c CB is the CB action cost coefficient; is the number of capacitor groups in operation at node j at time t; c pl is the cost coefficient of abandoned light, is the output power of the photovoltaic node j at time t; The day-ahead operation constraints of the distribution network are as follows: 1) Distribution network flow constraints: In the formula, and are the injected active power and reactive power of node j at time t respectively; and are the active power and reactive power of branch ij at time t respectively; σ(j) represents the set of nodes downstream of node j; δ(j) represents the set of nodes upstream of node j; is the voltage value of node j at time t; X ij is the reactance value of line ij; 2) Constraints on safe operation of power grid: Where U min and U max The lower and upper limits of the full run; is the upper limit of the branch ij current; 3) Photovoltaic output constraints: 4) Energy storage operation constraints: In the formula, and are binary variables representing the charging state and discharging state of the energy storage at node j. When the value is 1, it means that the energy storage is working in the charging and discharging state, so as to limit the energy storage from being in the charging and discharging state at the same time. j,max is the upper limit of the energy storage charging and discharging power of node j; E is the energy storage charge of node j at time t; jmax and E jmin are the upper and lower limits of the energy storage charge of node j respectively; 5) Operation constraints of on-load tap-changing transformers: In the formula, is the adjustable ratio of OLTC on branch ij at time t; and Δk ij are the standard transformation ratio and adjustment step of OLTC on branch ij respectively; K ijmax is the maximum value of the adjustable gear of OLTC in branch ij; 6) Parallel capacitor bank operation constraints: In the formula, is the reactive output power of the capacitor bank; Y is the reactive output power of a single group of capacitors at node j; j,CBmax is the upper limit of the number of capacitor groups at node j.

3. A multi-objective optimization control method for distribution network taking into account energy storage life according to claim 1, characterized in that: The specific contents of calculating the energy storage life loss cost in S3 include: The total equivalent discharge capacity of energy storage over its entire life cycle under rated conditions is expressed as: E j,eq =E j,max N j,max D j,max (17) Where: E j,eq N is the total equivalent discharge capacity of energy storage in the whole life cycle under rated conditions of node j; j,max is the rated number of cycles of energy storage at node j, D j,max is the rated discharge depth of energy stored at node j; Considering the charge and discharge rate and discharge depth in the actual operation process, ignoring the life loss caused by energy storage charging, the equivalent discharge capacity of energy storage at node j at time t is expressed as: Where: is the equivalent discharge amount of energy storage at node j at time t; is the actual number of energy storage cycles at node j at time t, P j,max is the upper limit of the energy storage charging and discharging power of node j; are the discharge power of energy storage at node j at time t; is the actual discharge amount of energy stored at node j at time t; The actual cycle life of energy storage is obtained by fitting and is expressed as: Where: u1 and u2 are the fitting curve coefficients, is the actual discharge depth of energy storage at node j at time t; The energy storage life loss cost is: Where: c el is the investment cost per unit capacity of energy storage.

4. A multi-objective optimization control method for distribution network taking into account energy storage life according to claim 3, characterized in that: For nonlinear function energy storage life loss cost F el Perform linearization: The piecewise linearization method is used to linearize the nonlinear function energy storage life loss cost; Due to the variable The value of is within [0,1], the interval [0,1] is divided into N-1 segments, corresponding to N segmentation points dod1, dod2, ···, dod N , introduce a continuous variable η in [0,1] n , then the energy storage life loss model is linearized as: Where: f[dod n ] is the dod corresponding to the nth segment point n Segment F el function.

5. A multi-objective optimization control method for distribution network taking into account energy storage life according to claim 2, characterized in that: The objective function of the multi-objective operation optimization model of the distribution network in S3 is: Where: ω1 and ω2 are the weights of targets F1 and F2 respectively; F1 is the daily operation economic target; F2 is the daily operation voltage deviation target; F grid is the electricity purchase cost, F loss is the network loss cost, F pv is the abandoned light cost, F ess is the energy storage operation and maintenance cost, F el The energy storage life loss cost; Actual value of node voltage; Where: Δt2 is the time scale of intraday scheduling; The constraints of the distribution network daily operation optimization model include: energy storage operation constraints, curtailment cost constraints C pl , distribution network flow constraints, grid safety operation constraints and energy storage operation constraints, among which the curtailment cost constraint C pl As shown in formula (8); The energy storage operation constraints are: In the formula, and is a binary variable of the energy storage charging and discharging state in the intraday stage, and its value is equal to the optimization result of the energy storage charging and discharging state variable the day before, that is,

Citation Information

Patent Citations

  • Source network storage multi-time scale optimization method and device based on interval time division

    CN116316735A

  • Tiered power management system for microgrids

    US20140350743A1

Cited By

  • Large power grid in-situ balance regulation and control method combining load and new energy power prediction

    CN119695871A