Preparation equipment for composite modified asphalt cold supplementing liquid
By adopting a multi-stage heating chamber and stirring structure in the asphalt cold liquid replenishment preparation equipment, the problems of inconvenient temperature adjustment and large power consumption of stirred tanks are solved, and efficient preparation and low-cost production of asphalt cold liquid replenishment are achieved.
Patent Information
- Application Number
- CN202411228546.2
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-09-03
- Publication Date
- 2024-12-03
AI Technical Summary
In the existing asphalt cold liquid replenishment preparation technology, the temperature adjustment of the stirred tank is inconvenient and consumes a lot of power, resulting in low preparation efficiency and high cost, and easily lead to asphalt aging.
The composite modified asphalt cold rehydration preparation equipment is adopted, including agitating and grinding integral, thermal oil heating component and cooling liquid temperature control component. The adaptive temperature regulation of different raw materials is achieved through multi-stage heating chambers and stirring structures, reducing repeated temperature regulation and improving Preparation efficiency.
It realizes efficient preparation of asphalt cold rehydration, reduces energy consumption, avoids asphalt aging, and improves preparation efficiency and product quality.
Smart Images

Figure CN119056324A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of asphalt preparation, and in particular to a composite modified asphalt cold make-up liquid preparation device. Background Art
[0002] Asphalt cold patching fluid is a new type of material specially used for road maintenance and repair. It is made of asphalt, diluent, additives and aggregates in a certain proportion. It is liquid or semi-liquid at room temperature and has good fluidity and permeability. Among them, the asphalt component provides bonding and waterproof properties to ensure that the repaired road surface can effectively resist water penetration and vehicle loads; the diluent reduces the viscosity of asphalt, so that it maintains a good flow state at room temperature, which is convenient for filling potholes and cracks in various shapes and sizes; the additive can improve the performance of the cold patching fluid, such as enhancing bonding, improving anti-aging ability, optimizing low-temperature performance, etc.; the aggregate increases the strength and stability of the cold patching fluid.
[0003] Compared with traditional hot-mix asphalt mixture, cold asphalt filling fluid does not need to be heated, which can save energy and construction time and reduce the interference of construction on traffic. It can be used in low temperature environment and even in wet road conditions, and has strong applicability. For example, in winter or rainy season, when the road is damaged, cold asphalt filling fluid can be put into use quickly to repair the road surface in time and ensure the normal traffic of the road.
[0004] In the prior art, the preparation of asphalt cold dressing fluid mainly relies on a mixing kettle and a conveying structure. The function of the mixing kettle is to fully mix asphalt, diluent, additives and aggregates at the same time, and then output them through a conveying pump. In this preparation process, there are mainly the following defects:
[0005] First, since the processing temperatures of different raw materials (such as diluents, additives, etc.) after being added into the stirring tank are different, the processing temperature of the stirring tank needs to be repeatedly adjusted and controlled, which makes it difficult to quickly meet the processing requirements when different raw materials are added.
[0006] Second, the mixing kettle is usually heated by electricity, which consumes a lot of electricity and has high operating costs for large-scale asphalt heating needs. In addition, the asphalt will be partially aged, which will affect the performance of the asphalt. Summary of the invention
[0007] The purpose of the present invention is to provide a composite modified asphalt cold make-up liquid preparation device, aiming to solve the technical problems in the above-mentioned background technology.
[0008] The technical solution of the present invention is achieved in this way:
[0009] The technical solution of the present application provides a composite modified asphalt cold make-up fluid preparation device, comprising:
[0010] The stirring and grinding integrated assembly comprises a first processing tank, a second processing tank, a colloid mill and a third processing tank which are connected in sequence, wherein the first processing tank is independently connected with a feed pipe and a first addition pipe, and the first addition pipe is used to add SBS raw materials and SBR raw materials, the second processing tank is independently connected with a second addition pipe, and the second addition pipe is used to add an active agent and a stabilizer, the third processing tank is independently connected with a third addition pipe and a discharge pipe, and the third addition pipe is used to add a diluent and an enhancer, and the first processing tank, the second processing tank and the third processing tank are all provided with a stirring structure;
[0011] Wherein, the first processing tank, the second processing tank and the third processing tank are all provided with a first heating chamber and a second heating chamber, and the second heating chamber is located outside the first heating chamber;
[0012] The heat transfer oil heating assembly comprises a heat transfer oil heating body having an oil outlet and an oil return port, wherein the oil outlet is independently connected to three first flow guide pipes, and respectively connected to the first heating chambers of the first processing tank, the second processing tank and the third processing tank, and the oil return port is independently connected to three second flow guide pipes, and respectively connected to the first heating chambers of the first processing tank, the second processing tank and the third processing tank;
[0013] A cooling liquid temperature control component, comprising a liquid storage tank having a liquid outlet and a liquid return port, wherein the liquid outlet is independently connected to three third flow guide pipes, and respectively connected to the second heating chambers of the first processing tank, the second processing tank and the third processing tank, and the liquid return port is independently connected to three fourth flow guide pipes, and respectively connected to the second heating chambers of the first processing tank, the second processing tank and the third processing tank; and
[0014] The asphalt storage tank is used to connect to the above-mentioned feed pipe.
[0015] A further technical solution is that the stirring structure comprises a stirring shaft, stirring blades and a driving motor that cooperate with each other;
[0016] Wherein, the driving motor is arranged on the top of the outer side of the first processing tank, the second processing tank or the third processing tank.
[0017] A further technical solution is that the materials of the first flow guide tube and the second flow guide tube are both thermal insulation materials.
[0018] A further technical solution is that any of the fourth guide tubes comprises a first guide tube and a second guide tube, one end of the first guide tube is connected to the second heating chamber, and the other end is connected to one end of the second guide tube, and one end of the second guide tube away from the first guide tube is connected to the liquid return port;
[0019] Wherein, the second conduit is a spiral tube.
[0020] A further technical solution is to further include a heat dissipation fan unit for dissipating heat from the second conduit.
[0021] A further technical solution is that it also includes an installation base plate, and the above-mentioned stirring and grinding integrated component, the above-mentioned thermal oil heating component, the above-mentioned coolant temperature control component, the above-mentioned asphalt storage tank and the above-mentioned heat dissipation fan unit are all arranged on the above-mentioned installation base plate.
[0022] A further technical solution is that it further comprises a pretreatment tank, and the asphalt storage tank and the first processing tank are connected via the pretreatment tank;
[0023] Wherein, the pretreatment tank is provided with an electric heating system for heating the interior of the pretreatment tank.
[0024] A further technical solution is that it also includes a first booster pump, and the asphalt storage tank and the pretreatment tank are connected through the first booster pump.
[0025] A further technical solution is that the discharge pipe is connected to a second booster pump, and the outlet of the second booster pump is connected to a feed pipe.
[0026] A further technical solution is that the first processing tank, the second processing tank and the third processing tank are all provided with temperature detectors.
[0027] Compared with the prior art, the technical solution of the present invention has at least the following advantages or beneficial effects:
[0028] When preparing the asphalt cold filling fluid, the specific steps are as follows:
[0029] First, the asphalt in the asphalt storage tank is transported to the first processing tank, and then the SBS raw material and the SBR raw material are added to the first processing tank through the first adding pipe, and the stirring structure in the first processing tank is used for stirring. At the same time, the heat transfer oil heating body transports the heated heat transfer oil to the first heating chamber of the first processing tank through the first guide pipe, thereby heating the mixed material in the first processing tank. In addition, the coolant in the liquid storage tank is transported to the second heating chamber through the third guide pipe, so as to achieve the balance adjustment of the temperature in the first processing tank until the temperature in the first processing tank is controlled at 140-150 degrees Celsius.
[0030] Second, the mixed material processed in the first processing tank is transported to the second processing tank, and then the active agent and stabilizer are added to the second processing tank through the second adding pipe, and the stirring structure in the second processing tank is used for stirring. During this period, the thermal oil heating body transports the heated thermal oil to the first heating chamber of the second processing tank through the first guide pipe, thereby heating the mixed material in the second processing tank. In addition, the coolant in the liquid storage tank is transported to the second heating chamber through the third guide pipe, thereby achieving the balance adjustment of the temperature in the second processing tank until the temperature in the second processing tank is controlled at 170-180 degrees Celsius.
[0031] Third, the mixed material processed in the second processing tank is transported to the colloid mill for processing.
[0032] Fourth, the mixed material after the colloid mill processing is transported to the third processing tank, and then the diluent and the enhancer are added to the third processing tank through the third adding pipe, and the stirring structure in the third processing tank is used for stirring processing. At the same time, the heat transfer oil heating body transports the heated heat transfer oil to the first heating chamber of the third processing tank through the first guide pipe, so as to achieve the heating of the mixed material in the third processing tank. In addition, the coolant in the liquid storage tank is transported to the second heating chamber through the third guide pipe, thereby achieving the balance adjustment of the temperature in the third processing tank, until the temperature in the third processing tank is controlled at 100-110 degrees Celsius.
[0033] The finished asphalt cold make-up liquid is finally obtained through the above steps. In this processing, on the one hand, different raw materials are processed separately in different pipe bodies. Compared with the traditional single tank processing method, there is no need to frequently adjust the temperature repeatedly, which is more convenient and practical. On the other hand, the thermal oil heating component, the coolant temperature control component, the first heating chamber and the second heating chamber cooperate with each other to achieve adaptive balance adjustment of the temperature in the first processing tank, the second processing tank and the third processing tank, and to achieve rapid control of the processing temperature, which is conducive to improving the preparation efficiency of the asphalt cold make-up liquid. BRIEF DESCRIPTION OF THE DRAWINGS
[0034] In order to more clearly illustrate the technical solutions of the embodiments of the present invention, the drawings required for use in the embodiments are briefly introduced below. It should be understood that the following drawings only show certain embodiments of the present invention and therefore should not be regarded as limiting the scope. For ordinary technicians in this field, other related drawings can be obtained based on these drawings without creative work.
[0035] Figure 1 This is an axonometric diagram of a composite modified asphalt cold make-up fluid preparation device according to an embodiment of the present invention;
[0036] Figure 2A top view of a composite modified asphalt cold make-up fluid preparation device according to an embodiment of the present invention;
[0037] Figure 3 is a cross-sectional view of a first processing tank according to an embodiment of the present invention;
[0038] Figure 4 This is a schematic diagram of the structure of a thermal oil heating assembly according to an embodiment of the present invention;
[0039] Figure 5 This is a schematic diagram of the structure of a coolant temperature control assembly according to an embodiment of the present invention;
[0040] Figure 6 It is a schematic structural diagram of a colloid mill according to an embodiment of the present invention.
[0041] Icons: 1-asphalt storage tank, 2-pretreatment tank, 3-electric heating system, 4-colloid mill, 5-first processing tank, 6-first addition pipe, 7-second processing tank, 8-second addition pipe, 9-third processing tank, 10-third addition pipe, 11-first guide pipe, 12-second guide pipe, 13-third guide pipe, 14-fourth guide pipe, 1401-first conduit, 1402-second conduit, 15-heat transfer oil heating body, 16-liquid storage tank, 17-installation base plate, 18-cooling fan unit, 19-first booster pump, 20-second booster pump, 21-feeding pipe, 22-feeding pipe, 23-stirring structure, 2301-driving motor, 2302-stirring shaft, 2303-stirring blade, 24-first heating chamber, 25-second heating chamber. DETAILED DESCRIPTION
[0042] Example
[0043] Please refer to Figure 1-Figure 6A composite modified asphalt cold make-up liquid preparation equipment, comprising: a stirring and grinding integrated component, including a first processing tank 5, a second processing tank 7, a colloid mill 4 and a third processing tank 9 connected in sequence, the first processing tank 5 is independently connected with a feed pipe 22 and a first addition pipe 6, the first addition pipe 6 is used to add SBS raw materials and SBR raw materials, the second processing tank 7 is independently connected with a second addition pipe 8, the second addition pipe 8 is used to add an active agent and a stabilizer, the third processing tank 9 is independently connected with a third addition pipe 10 and a discharge pipe, the third addition pipe 10 is used to add a diluent and an enhancer, the first processing tank 5, the second processing tank 7 and the third processing tank 9 are all provided with a stirring structure 23; wherein the first processing tank 5, the second processing tank 7 and the third processing tank 9 are all provided with a first heating chamber 24 and a second heating chamber 25, and the second heating chamber 25 is located outside the first heating chamber 24; heat transfer oil A heating component includes a heat-conducting oil heating body 15 having an oil outlet and an oil return port, the oil outlet is independently connected to three first guide pipes 11, and is respectively connected to the first heating chambers 24 of the first processing tank 5, the second processing tank 7 and the third processing tank 9, and the oil return port is independently connected to three second guide pipes 12, and is respectively connected to the first heating chambers 24 of the first processing tank 5, the second processing tank 7 and the third processing tank 9; a cooling liquid temperature control component includes a liquid storage tank 16 having a liquid outlet and a liquid return port, the liquid outlet is independently connected to three third guide pipes 13, and is respectively connected to the second heating chambers 25 of the first processing tank 5, the second processing tank 7 and the third processing tank 9, and the liquid return port is independently connected to three fourth guide pipes 14, and is respectively connected to the second heating chambers 25 of the first processing tank 5, the second processing tank 7 and the third processing tank 9; and an asphalt storage tank 1 for connecting the feed pipe 22.
[0044] When preparing the asphalt cold filling fluid, the specific steps are as follows:
[0045] First, the asphalt in the asphalt storage tank 1 is transported to the first processing tank 5, and then the SBS raw material and the SBR raw material are added to the first processing tank 5 through the first adding pipe 6, and the mixing process is performed with the help of the stirring structure 23 in the first processing tank 5. At the same time, the heat transfer oil heating body 15 transports the heated heat transfer oil to the first heating chamber 24 of the first processing tank 5 through the first guide pipe 11, thereby heating the mixed material in the first processing tank 5. Moreover, the coolant in the liquid storage tank 16 is transported to the second heating chamber 25 through the third guide pipe 13, so as to achieve the balance adjustment of the temperature in the first processing tank 5, until the temperature in the first processing tank 5 is controlled at 140-150 degrees Celsius.
[0046] Second, the mixed material processed in the first processing tank 5 is transported to the second processing tank 7, and then the active agent and stabilizer are added to the second processing tank 7 through the second adding pipe 8, and the stirring structure 23 in the second processing tank 7 is used for stirring. During this period, the thermal oil heating body 15 transports the heated thermal oil to the first heating chamber 24 of the second processing tank 7 through the first guide pipe 11, so as to achieve the heating of the mixed material in the second processing tank 7. In addition, the coolant in the liquid storage tank 16 is transported to the second heating chamber 25 through the third guide pipe 13, thereby achieving the balance adjustment of the temperature in the second processing tank 7, until the temperature in the second processing tank 7 is controlled at 170-180 degrees Celsius.
[0047] Third, the mixed material processed in the second processing tank 7 is transported to the colloid mill 4 for processing.
[0048] Fourth, the mixed material processed by the colloid mill 4 is transported to the third processing tank 9, and then the diluent and the enhancer are added to the third processing tank 9 through the third adding pipe 10, and the stirring structure 23 in the third processing tank 9 is used for stirring. At the same time, the heat transfer oil heating body 15 transports the heated heat transfer oil to the first heating chamber 24 of the third processing tank 9 through the first guide pipe 11, so as to heat the mixed material in the third processing tank 9. In addition, the coolant in the liquid storage tank 16 is transported to the second heating chamber 25 through the third guide pipe 13, thereby achieving the balance adjustment of the temperature in the third processing tank 9, until the temperature in the third processing tank 9 is controlled at 100-110 degrees Celsius.
[0049] The finished asphalt cold replenishment liquid is finally obtained through the above steps. In this processing, on the one hand, different raw materials are processed separately in different pipe bodies. Compared with the traditional single tank processing method, there is no need to frequently adjust the temperature repeatedly, which is more convenient and practical. On the other hand, the thermal oil heating component, the coolant temperature control component, the first heating chamber 24 and the second heating chamber 25 cooperate with each other to achieve adaptive balance adjustment of the temperature in the first processing tank 5, the second processing tank 7 and the third processing tank 9, and can achieve rapid control of the processing temperature, which is beneficial to improve the preparation efficiency of the asphalt cold replenishment liquid.
[0050] Furthermore, the heat transfer oil in the first heating chamber 24 can flow back to the heat transfer oil heating body 15 through the second flow conduit 12, so as to realize the recycling of the heat transfer oil. The coolant in the second heating chamber 25 can flow back to the liquid storage tank 16 through the fourth flow conduit 14, so as to realize the recycling of the coolant.
[0051] Specifically, for the first processing tank 5, the second processing tank 7, the colloid mill 4 and the third processing tank 9 which are connected in sequence, a pump body (not shown in the figure) is provided at the connection point of any two devices to improve the fluidity of the mixed material and make the mixed material flow more easily.
[0052] Optionally, the first processing tank 5, the second processing tank 7 and the third processing tank 9 are all cylindrical, and the first heating chamber 24 and the second heating chamber 25 are both arranged along the circumferential direction of the tank body (the first processing tank 5, the second processing tank 7 or the third processing tank 9).
[0053] The thermal oil heating system consists of several main parts, including burners (or electric heaters), heat exchangers, circulating oil pumps, expansion tanks, oil storage tanks, pipes and valves. The burners generate heat by burning fuel (such as natural gas, diesel, etc.), while the electric heaters generate heat by resistive heating. They are the source of heat. The heat exchanger transfers the heat generated by the burner or electric heater to the thermal oil. The circulating oil pump promotes the circulation of the thermal oil in the system to ensure even heat distribution. The expansion tank accommodates the increased volume of the thermal oil due to the increase in temperature, and also plays the role of exhaust, oil replenishment and dehydration. The oil storage tank is used to store the thermal oil. The pipes and valves connect the various components to control the flow direction and flow of the thermal oil. Its working principle is as follows: the heat generated by the burner or electric heater is transferred to the heat transfer oil in the heat exchanger, and the circulating oil pump allows the heat transfer oil to circulate continuously in the system. When the heat transfer oil flows through the first processing tank 5, the second processing tank 7 or the third processing tank 9, the heat is transferred to the mixed material in the tank body, thereby achieving the purpose of heating. When the heat transfer oil expands in volume due to the increase in temperature, the excess heat transfer oil will enter the expansion tank to ensure the safe and stable operation of the system.
[0054] In some embodiments of the present invention, the stirring structure 23 includes a stirring shaft 2302, a stirring blade 2303 and a driving motor 2301 that cooperate with each other;
[0055] The driving motor 2301 is disposed on the top of the outer side of the first processing tank 5 , the second processing tank 7 or the third processing tank 9 .
[0056] In the above embodiment, when the external power supply of the driving motor 2301 starts to work, it will drive the stirring shaft 2302 to rotate in the first processing tank 5, the second processing tank 7 or the third processing tank 9. In this way, the stirring function of the mixed material in the tank body is realized. It is worth noting that the driving motor 2301 is arranged at the center position of the top of the tank body, and the stirring shaft 2302 is also arranged at the center of the tank body. In this way, the stirring effect of the mixed material in the tank body can be more outstanding, the stirring is more uniform, and the processing quality and efficiency are improved.
[0057] In some embodiments of the present invention, the first flow guiding tube 11 and the second flow guiding tube 12 are both made of heat-insulating materials.
[0058] In the above embodiment, the materials of the first flow guide tube 11 and the second flow guide tube 12 are both made of thermal insulation materials, which brings many benefits. The thermal insulation materials can effectively reduce the heat loss of the heat transfer oil during the transportation process, so that the heat transfer oil still maintains a high temperature when it reaches the target heating chamber, ensuring stable and efficient heating effect and reducing energy waste; it can reduce the impact of the surrounding environment on the temperature of the heat transfer oil in the flow guide tube, and even if the external temperature is low, the temperature of the heat transfer oil in the tube can be well maintained, ensuring the stability and reliability of the entire heating system; reducing heat loss can also reduce the system's demand for heating power and save equipment operating costs; good thermal insulation performance helps to extend the service life of the flow guide tube and reduce the risk of pipeline aging and damage caused by temperature changes.
[0059] Preferably, the first flow guide tube 11 and the second flow guide tube may be made of ceramic fiber, glass fiber reinforced plastic (FRP) or polytetrafluoroethylene (PTFE).
[0060] In some embodiments of the present invention, any of the fourth guide tubes 14 includes a first conduit 1401 and a second conduit 1402, one end of the first conduit 1401 is connected to the second heating chamber 25, and the other end is connected to one end of the second conduit 1402, and one end of the second conduit 1402 away from the first conduit 1401 is connected to the liquid return port;
[0061] The second conduit 1402 is a spiral tube.
[0062] In the above embodiment, the coolant in the second heating chamber 25 can flow back to the liquid storage tank 16 through the first conduit 1401 and the second conduit 1402 in sequence, thereby realizing the recycling of the coolant. When the coolant flows through the second conduit 1402, its spiral structure design makes it easier for the coolant to dissipate heat and is convenient for reuse.
[0063] In some embodiments of the present invention, a heat dissipation fan unit 18 is further included to dissipate heat from the second pipe 1402 .
[0064] In the above embodiment, the heat dissipation fan unit 18 plays an important role, which can significantly improve the cooling efficiency of the coolant passing through the second conduit 1402 and enhance the heat dissipation effect.
[0065] In some embodiments of the present invention, a mounting base plate 17 is further included, and the above-mentioned stirring and grinding integrated component, the above-mentioned thermal oil heating component, the above-mentioned coolant temperature control component, the above-mentioned asphalt storage tank 1 and the above-mentioned heat dissipation fan unit 18 are all arranged on the above-mentioned mounting base plate 17.
[0066] In the above embodiment, the design of the mounting base plate 17 integrates the above-mentioned stirring and grinding integrated component, the above-mentioned thermal oil heating component, the above-mentioned coolant temperature control component, the above-mentioned asphalt storage tank 1 and the above-mentioned heat dissipation fan unit 18 together, which is more convenient for transportation.
[0067] In some embodiments of the present invention, a pretreatment tank 2 is further included, and the asphalt storage tank 1 and the first processing tank 5 are connected through the pretreatment tank 2;
[0068] The pretreatment tank 2 is provided with an electric heating system 3 for heating the interior of the pretreatment tank 2 .
[0069] In the above embodiment, the cooperation of the pretreatment tank 2 and the electric heating system 3 can preheat the asphalt transported to the first processing tank 5. This measure can not only effectively prevent the condensation of the asphalt, but also significantly reduce the heating time of the asphalt in the first processing tank 5 (so that the asphalt can be quickly heated to the temperature required for processing).
[0070] In some embodiments of the present invention, a first booster pump 19 is further included, and the asphalt storage tank 1 and the pretreatment tank 2 are connected via the first booster pump 19 .
[0071] In the above embodiment, the design of the first booster pump 19 can promote the active circulation of asphalt, and facilitate the directional transportation of asphalt in the asphalt storage tank 1 to the pretreatment tank 2.
[0072] Specifically, a pump body is provided at the connection point between the liquid storage tank 16 and the third guide pipe 13, and its function is to promote the circulation of the coolant.
[0073] In some embodiments of the present invention, the discharge pipe is connected to a second booster pump 20 , and the outlet of the second booster pump 20 is connected to a feed pipe 21 .
[0074] In the above embodiment, the coordinated design of the second booster pump 20 and the feeding pipe 21 is conducive to the directional transportation of the processed asphalt to the place where it is needed.
[0075] In some embodiments of the present invention, the first processing tank 5 , the second processing tank 7 , and the third processing tank 9 are all provided with temperature detectors.
[0076] In the above embodiment, the careful design of the temperature detector facilitates the measurement of the processing temperature of the first processing tank 5, the second processing tank 7 or the third processing tank 9, thereby ensuring that the mixed material is processed at an appropriate temperature, so that the quality of the produced asphalt is better.
[0077] The above are only preferred embodiments of the present invention and are not intended to limit the present invention. For those skilled in the art, the present invention may have various modifications and variations. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the present invention shall be included in the protection scope of the present invention.
Claims
1. A composite modified asphalt cold make-up liquid preparation device, characterized in that: include: The stirring and grinding integrated component comprises a first processing tank (5), a second processing tank (7), a colloid mill (4) and a third processing tank (9) which are connected in sequence, wherein the first processing tank (5) is independently connected with a feed pipe (22) and a first addition pipe (6), the first addition pipe (6) is used to add SBS raw materials and SBR raw materials, the second processing tank (7) is independently connected with a second addition pipe (8), the second addition pipe (8) is used to add an active agent and a stabilizer, the third processing tank (9) is independently connected with a third addition pipe (10) and a discharge pipe, the third addition pipe (10) is used to add a diluent and an enhancer, and the first processing tank (5), the second processing tank (7) and the third processing tank (9) are all provided with a stirring structure (23); Wherein, the first processing tank (5), the second processing tank (7) and the third processing tank (9) are all provided with a first heating chamber (24) and a second heating chamber (25), and the second heating chamber (25) is located outside the first heating chamber (24); A heat transfer oil heating assembly comprises a heat transfer oil heating body (15) having an oil outlet and an oil return port, wherein the oil outlet is independently connected to three first flow guide pipes (11) and respectively connected to first heating chambers (24) of the first processing tank (5), the second processing tank (7) and the third processing tank (9), and the oil return port is independently connected to three second flow guide pipes (12) and respectively connected to first heating chambers (24) of the first processing tank (5), the second processing tank (7) and the third processing tank (9); A cooling liquid temperature control component, comprising a liquid storage tank (16) having a liquid outlet and a liquid return port, wherein the liquid outlet is independently connected to three third flow guide pipes (13) and respectively connected to the second heating chambers (25) of the first processing tank (5), the second processing tank (7) and the third processing tank (9), and the liquid return port is independently connected to three fourth flow guide pipes (14) and respectively connected to the second heating chambers (25) of the first processing tank (5), the second processing tank (7) and the third processing tank (9); and The asphalt storage tank (1) is used to be connected to the feed pipe (22).
2. The composite modified asphalt cold make-up liquid preparation equipment according to claim 1, characterized in that: The stirring structure (23) includes a stirring shaft (2302), a stirring blade (2303) and a driving motor (2301) that cooperate with each other; Wherein, the driving motor (2301) is arranged on the top of the outer side of the first processing tank (5), the second processing tank (7) or the third processing tank (9).
3. The composite modified asphalt cold make-up liquid preparation equipment according to claim 2, characterized in that: The first flow guide tube (11) and the second flow guide tube (12) are both made of heat-insulating materials.
4. The composite modified asphalt cold make-up liquid preparation equipment according to claim 3, characterized in that: Any of the fourth flow guide tubes (14) comprises a first conduit (1401) and a second conduit (1402), one end of the first conduit (1401) is connected to the second heating chamber (25), and the other end is connected to one end of the second conduit (1402), and one end of the second conduit (1402) away from the first conduit (1401) is connected to the liquid return port; Wherein, the second conduit (1402) is a spiral tube.
5. The composite modified asphalt cold make-up liquid preparation equipment according to claim 4, characterized in that: It also includes a heat dissipation fan unit (18) for dissipating heat from the second conduit (1402).
6. The composite modified asphalt cold make-up liquid preparation equipment according to claim 5, characterized in that: It also comprises a mounting base plate (17), on which the stirring and grinding integrated component, the thermal oil heating component, the coolant temperature control component, the asphalt storage tank (1) and the heat dissipation fan unit (18) are all arranged.
7. The composite modified asphalt cold make-up liquid preparation equipment according to claim 1, characterized in that: It also includes a pretreatment tank (2), and the asphalt storage tank (1) and the first processing tank (5) are connected through the pretreatment tank (2); Wherein, the pretreatment tank (2) is provided with an electric heating system (3) for heating the interior of the pretreatment tank (2).
8. The composite modified asphalt cold make-up liquid preparation equipment according to claim 7, characterized in that: It also comprises a first boosting pump (19), and the asphalt storage tank (1) and the pretreatment tank (2) are connected via the first boosting pump (19).
9. The composite modified asphalt cold make-up liquid preparation equipment according to claim 8, characterized in that: The discharge pipe is connected to a second booster pump (20), and the outlet of the second booster pump (20) is connected to a feed pipe (21).
10. The composite modified asphalt cold make-up liquid preparation equipment according to claim 1, characterized in that: The first processing tank (5), the second processing tank (7) and the third processing tank (9) are all provided with temperature detectors.