Special construction method for upper cross beam of main bridge tower column of bridge

By using support systems and concrete pre-pressure technologies in the construction of cross beams on the main bridge tower columns of the bridge, the problems of bridge stability and load uniform distribution are solved, and the high stability and safety of the bridge are achieved.

CN119061793APending Publication Date: 2024-12-03ANHUI HIGHWAY BRIDGE ENG CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411213274.9
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-08-30
Publication Date
2024-12-03

AI Technical Summary

Technical Problem

The construction method of cross beams on the main bridge column of the existing bridge is difficult to ensure the overall stability and uniform distribution of the bridge load, resulting in problems such as offset, tilt or collapse of the bridge deck.

Method used

The bracket system is composed of reinforced pre-embedded boxes, brackets, load-bearing beams, XT300 trusses, distribution beams, square wood and bamboo plyboards, and combined with concrete pre-pressure, steel bar straightening, welded joints, prestressed tensioning and anchor sealing technology to ensure the cross beam stability and load distribution.

Benefits of technology

It enhances the overall stability of the bridge, achieves uniform distribution of loads, reduces the stress concentration of bridge components, prevents the bridge deck from offset, inclination and collapse, and improves construction quality and safety.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119061793A_ABST
    Figure CN119061793A_ABST
Patent Text Reader

Abstract

The invention discloses a special construction method for an upper cross beam of a main bridge tower column of a bridge, and relates to the technical field of main bridge tower columns of the bridge, an upper cross beam support system is arranged, the support system is composed of a reinforced embedded box, a bracket, a bearing beam, an XT300 truss, a distribution beam and square wood bamboo plywood, and the specific arrangement form of a support from bottom to top is that the reinforced embedded box is embedded in the bracket; reinforcing type embedded boxes are embedded in the upper end and the lower end of the tower column in the longitudinal bridge direction respectively, six rows of brackets are arranged on the support in the transverse bridge direction to serve as supports, transverse parallel connection and inclined struts between the brackets are connected through [14] and [10] combined channel steel respectively, the overall stability of the support is guaranteed, the stability of the bridge is enhanced, and cross beams can prevent the bridge floor from deviating, inclining, collapsing and the like. The overall stability of the bridge is enhanced; loads are distributed, through the effect of the transverse beam structure, the loads on the bridge can be evenly distributed to the pier columns and the foundation of the lower structure through the transverse beams, the stress concentration ratio of bridge components is reduced, and reasonable layout and evenly-distributed loads of the bridge are achieved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of bridge main bridge tower columns, and in particular to a special construction method for a cross beam on a bridge main bridge tower column. Background Art

[0002] The crossbeam on the main bridge tower is an important component of the bridge structure. Its construction method and function are crucial to the overall stability and safety of the bridge. The crossbeam spans across the piers or bridge towers, and bears the forces from the bridge deck and other loads, such as vehicles, pedestrians and wind loads, and transfers these loads to the lower structure, such as piers and abutments, to ensure the stability and safety of the bridge. Therefore, the present invention proposes a special construction method for the crossbeam on the main bridge tower. Summary of the invention

[0003] To achieve the above object, the present invention provides the following technical solution: a special construction method for the cross beam on the main bridge tower column of a bridge, comprising the following steps:

[0004] S1: Layout of the upper crossbeam support system. The support system consists of a reinforced embedded box, bracket, load-bearing beam, XT300 truss, distribution beam, and square wood bamboo plywood. The specific layout of the support from bottom to top is that the reinforced embedded boxes are embedded in the upper and lower ends of the tower column in the longitudinal direction, and 6 rows of brackets are set in the transverse direction of the support as support. The horizontal parallel connection and diagonal bracing between the brackets are connected by [14 and [10 combined channel steels to ensure the overall stability of the support. Two rows of double-jointed Gong 56 combined steel are placed on the top of the bracket. The top of the load-bearing beam is arranged with XT300 trusses along the longitudinal direction, and double grooves 20 are added on the top of the load-bearing beam. The maximum span is 19.71m. Gong 22 steel is set on the top of the truss upper chord as a distribution beam with a maximum spacing of 80cm; square wood is placed on the distribution beam, and the bottom mold is made of 15mm bamboo plywood and 10cmx10cm square wood;

[0005] After the upper crossbeam bracket is installed, concrete blocks are used for preloading to eliminate the inelastic deformation of the bracket. The load weight is 1.2 times the sum of the design weight of the crossbeam and the weight of the bracket. During preloading, the load is symmetrically distributed along the center line on both sides of the structure. The load on the bracket is divided into units for preloading, which is 1.2 times the actual weight of the simulated load of the designed section in the unit. The preloading load is evenly distributed in the unit. The bracket preloading adopts a four-level loading method, and the load applied in sequence is 60% of the preloading load value in the unit. , 80%, 100%, 120%; temporary leveling points are set near the preloading area, and the elevation of the leveling points is set as the basis for observation. After the leveling points are set, they should be protected and marked in time to prevent them from being damaged during construction. A monitoring section is arranged every 1 / 5 of the span along the longitudinal direction of the concrete structure. For the cross beam on the tower column (bottom plate width 6.6m), 3 monitoring points are arranged in the longitudinal direction of the bridge, with spacing of 1.3m, 3.3m, and 5.3m respectively, and the transverse direction of the bridge (length 28m) is arranged at a spacing of 5m;

[0006] S2: The steel bars are straightened by long-line cold-drawing straightening or straightening machine; the steel bars are cut by cutting machine; the steel bars are bent by bending machine, and the bending size is controlled by template; the steel bar joints with a diameter greater than 25 mm are connected by mechanical sleeves. The steel bars are straightened by long-line cold-drawing straightening or straightening machine before processing and bending. The oil stains, paint stains, cement slurry and floating rust and rust that can be peeled off by hammering on the surface of the steel bars must be cleaned. During the steel bar cutting process, any appearance defects of the welding joints and steel materials shall be removed. The position of the fixed-length baffle shall be checked after it is fixed. The length error of long steel bars without hooks is ±15mm. The elongation of steel bars with hooks and bends shall be considered after bending. The actual cutting length shall be determined based on experience;

[0007] The upper cross beam body reinforcement is tied, considering the installation of the inner formwork, the cross beam body reinforcement is divided into two parts: the bottom web reinforcement skeleton and the top plate reinforcement skeleton;

[0008] ①The steel bar joints in the axial tension and slightly eccentric tension rods should be welded;

[0009] ②For steel bars with a diameter of more than 12mm, welded joints are preferred;

[0010] ③ When the diameter of the tensile steel bar is greater than 28mm and the diameter of the compressive steel bar is greater than 32mm, it is not advisable to use a tied lap joint;

[0011] ④ In structural members that directly bear dynamic loads, the longitudinal tensile reinforcement shall not be tied.

[0012] Tie lap joints;

[0013] ⑤ The joints of cold-drawn low-carbon steel wires can only be tied together, and contact butt welding or arc welding is not allowed;

[0014] ⑥The distance between the welding joint and the bending part of the steel bar should not be less than 10d;

[0015] S3: The bottom formwork of the crossbeam is made of high-quality bamboo plywood with a thickness of δ=15mm, which is directly placed on the 10×10cm longitudinal square wood. The center-to-center spacing of the web and cross partition wood is 20cm, and the center-to-center spacing of the other square wood is 30cm. The inner and outer formworks of the upper crossbeam on the support system are both made of 1.5cm thick bamboo plywood. The side formwork uses 10*10cm square wood as vertical ribs with a spacing of 25cm; double-jointed [8 channel steel is used as transverse ribs, and the transverse rib spacing is 75cm. The formwork joints are connected with M25 screws. The crossbeam formwork is installed by a tower crane and adjusted by a hand winch. After the formwork is in place, the adjacent formworks are fixed with bolts, and the inner and outer formworks are fixed with tension screws; The connection between the corrugated pipe and the anchor plate: The connection between the corrugated pipe and the anchor plate adopts a tube-sheet joint. The end of the corrugated pipe is screwed into one end of the tube-sheet joint, and the other end of the tube-sheet joint is extended into At the tail of the anchor plate, the connection between the corrugated pipe and the tube sheet, and the tube sheet joint and the anchor plate should have an overlap length of more than 6cm and be sealed with tape to prevent leakage when pouring concrete; Corrugated pipe joint treatment: Use plastic connectors with sealing properties to extend the length, and the connector should have a length of not less than 200mm; Corrugated pipe positioning: First, calculate the position of the prestressed pipe according to the prestressed steel beam curve parameter table, and calculate the corrugated pipe coordinates every 50cm as the basis for positioning the corrugated pipe. The position guarantee measures of the corrugated pipe mainly rely on the "well"-shaped positioning steel bars. The spacing of the positioning steel bars of the straight section of the corrugated pipe is not more than 0.5m, and the spacing of the curved section is not more than 0.3m. The positioning steel bars should be appropriately adjusted according to the distance from the outer wall of the corrugated pipe to the outer edge of the box beam to ensure that the distance from the end of the steel bar to the outer edge of the box beam is not less than 2.5cm;

[0016] S4: Before mixing concrete, the quality and quantity of all raw materials must be confirmed. Production can only be started after meeting the construction needs. The metering system of the mixing equipment must be within the calibration validity period. Spot checks and verifications should be carried out when necessary. The workability and slump of concrete should be tested at the beginning of production and during the production process to ensure production quality. Concrete is transported to the construction site by a mixer truck. The transportation time should be strictly controlled. After arriving at the site, various performance indicators of the concrete should also be checked. It can only be pumped into the mold after meeting the requirements. If the waiting time is long, the tank truck should accelerate the rotation for 20 to 30 seconds and stir the concrete for the second time to ensure the uniformity of the concrete. The upper beam is poured in two times. The pouring is carried out in sections and layers. The tower column position is poured first, and then the beam position is poured. The first pouring height is 2 meters, and the second pouring height is 3 meters. The entire pouring sequence meets the left-right symmetry and the front-back symmetry. Concrete pouring procedure and sequence: first pour the tower column position → then pour the box room web → then pour the box room bottom plate → finally pour the box room top plate (second pouring). The concrete is poured in the order of "both sides → middle", and the bottom plate concrete is poured in the order of "both sides → middle". After the concrete at the chamfer inside the web is poured in place, pour the bottom plate concrete, and then pour the remaining concrete of the web; pour the top plate concrete for the second time; the upper crossbeam concrete is poured twice, and the pouring is carried out in sections and layers. First pour the tower column position, and then pour the bottom web at the crossbeam position. In order to facilitate the second mold erection and pouring of the top plate, after the bottom web is poured, the top plate bottom formwork is installed. Because the inner formwork has formed a frame, the top formwork can be quickly laid, and the contact surface of the construction concrete is cleaned, the top plate steel bars are installed and tied, and then the top plate concrete is poured for the second time. Before pouring the top plate concrete, the concrete on the contact surface between the bottom web and the top plate needs to be sprinkled with water to moisten it;

[0017] S5: Prestressing, grouting and anchor sealing construction. Before prestressing, check whether the concrete dimensions and appearance meet the quality requirements, whether the anchor pad is in the correct position, whether there are honeycombs and voids under the anchor pad, and take reinforcement measures if necessary. When prestressing the upper beam, in order to avoid the late shrinkage and creep having a greater impact on the structure, the transverse prestressing concrete strength should not be less than 90% of the design strength according to the design requirements, and the concrete curing age should not be less than 7 days. Only then can the jack, tensioning machine and other equipment be installed to prepare for prestressing. The prestressing tendon tensioning equipment (jack and oil gauge) should be calibrated to determine the relationship curve between the tensioning force and the oil gauge reading. The steel strands are inserted into the channel. Before the bundle is inserted, the anchor pad, channel and grouting hole should be checked first. The anchor pad should be in the correct position, the channel should be unobstructed, free of water and debris, and the tensioning personnel should be certified;

[0018] Complete the inspection of the tensioning equipment → The steel strand has been put in advance → Install the working anchor plate → Install the working anchor fixture → Install the limit plate → Install the jack → Install the tool anchor → Install the tool anchor clip → Preparatory work before prestressing → Prestressing procedure → Grouting the hole → Anchor sealing; The extended part of the steel bundle should be kept clean, without oil, mud and other debris, and the construction personnel should not step on it at will. The anchor ring and the clip should be cleaned with kerosene or diesel before use, and there should be no oil, iron filings, mud and other debris. The working anchor must be accurately placed in the positioning groove of the anchor pad and aligned with the hole; Clips are installed in each hole of the working anchor and put on with rubber rings. An iron pipe about 30 cm long can be used to penetrate the steel hinge wire and push forward lightly to align the clips. Be careful not to use too much force. The gap between the clips should be uniform and can be carefully adjusted with a screwdriver. There must be a specified number of clips in each hole, and there must be no shortage. After the clip is installed, its exposed length is generally 4-5mm, and it is uniform. If it is exposed too much, check the size and taper of the clamp and anchor ring hole used. If any unqualified ones are found, they must be replaced. Do not push or pull the oil pipe and joint when installing the jack. The oil pipe should be straight and not twisted into a ball. Before installing the tool anchor, the jack piston should be extended 3-5cm. When the steel bundle is inserted into the tool anchor, the position should correspond to the position of the working anchor steel bundle one by one, and no cross-twisting should be allowed. In order to smoothly withdraw the tool anchor, lubricant should be applied to the smooth surface of the tool anchor clip or the anchor hole of the tool anchor. The lubricant is paraffin. When using paraffin, melt it and apply it to the clip. The clip of the tool anchor should be placed separately from the clip of the working anchor. The number of times the tool anchor clip is reused shall not exceed 10 times. If the clip is found to be damaged, it should be replaced in time to prevent slipping and flying pieces during tensioning.

[0019] S6: Intelligent tensioning is adopted. Before tensioning, the friction resistance test of the hole should be carried out, and the friction resistance coefficient used for calculation is 0.2. The upper beam prestressed tendons are tensioned at both ends. Prestressing can be carried out only after the concrete strength and elastic modulus reach 100% of the design strength and meet the 7-day age period. The tensioning of the steel tendons adopts dual control of tensioning force and elongation, which is controlled by the reading of the main oil cylinder oil pressure gauge and checked by the elongation of the steel strand. The elongation error shall not exceed ±6%;

[0020] ① Tensioning procedure

[0021] 0→initial stress (final tension control stress is about 10%, measure the elongation of the steel strand and make a mark, measure the exposed amount of the tool anchor clip)→tension control stress (specified value of each period, measure the elongation value of the steel strand, measure the exposed amount of the tool anchor clip)→stop for 5 minutes, check the tension control stress and elongation;

[0022] ② Tensioning operation

[0023] a.0 stage: the jack is filled with oil and the piston extends 1 to 2 cm;

[0024] b. Initial tensioning: Before initial tensioning, adjust the tightness of the steel strand bundle, align the tensioning equipment with the channel axis, and evenly force it. After reaching the tonnage, install measurement marks on the steel strand, and measure the distance to the outer edge of the oil top as the initial reading.

[0025] c. Grading and cutting: measure the elongation value once;

[0026] d. Tensioning tonnage: When tensioning to the controlled stress, hold the load for 5 minutes, measure the elongation of the steel strand, and observe the condition of the steel strand and the clip;

[0027] e. Self-anchoring: After the tensioning is completed, the jack returns oil, the cylinder retracts, the tool anchor retreats, and the working anchor clip automatically anchors the steel strand. The oil return should be done slowly to achieve the purpose of self-anchoring;

[0028] f. Oil return: Open the jack's oil return and oil delivery valves, the jack's main oil cylinder continues to retract, the tool anchor is detached from the oil top port, the tool clips are gradually detached from the anchor hole, and the steel strands are carefully checked;

[0029] g. Retraction: Remove the tool anchor, jack and limit plate one by one, and use a vernier caliper to measure the exposed amount of the working anchor clip;

[0030] h. After the tensioning is completed, mark the steel strand at the anchor ring mouth and record the data as a mark to observe whether the steel strand anchorage is slipping after tensioning;

[0031] i. Tensioning construction requirements:

[0032] (a) The measurement accuracy of prestressed tendon elongation should reach 1.5mm, and the deviation between the measured elongation and the theoretical elongation should be less than ±6%. Otherwise, the cause should be analyzed and dealt with in time;

[0033] (b) Tensioning is controlled by tensioning force, and the theoretical elongation cannot be achieved by over-tensioning;

[0034] (c) After the tensioning is completed, it must be inspected and signed for approval by the technical staff;

[0035] (d) The longitudinal prestressing hole is long, and the elongation of the steel strand lags behind the growth of the tension force. The pressure holding time must be ensured and the tension force must be supplemented before anchoring;

[0036] (e) The contents of prestressing quality control at the construction site include: correct prestressing operation, tensioning force at each level controlled by pressure gauge, measuring actual tensioning elongation, checking for slipped or broken wires, and flatness of the clip after anchoring, etc.;

[0037] (f) As acceptance technical data, the actual tension elongation value measured on site should be collated as tension data and compared with the corrected theoretical elongation value to determine whether the tension is normal and whether there is any hole blockage, etc.;

[0038] S7: After tensioning, grouting should be carried out in time. Pipeline grouting should be carried out within 24 hours after tensioning. Before grouting, first use a vacuum pump to suck the air in the prestressed pores to make the vacuum degree in the pores reach between -0.06 and -0.08 MPa. Then, at the other end of the pores, a grouting machine is used to press cement slurry into the prestressed pores with a positive pressure of no more than 0.6 MPa. Since there is very little air in the pores, it is difficult to form bubbles. Due to the positive and negative pressure between the pores and the grouting machine, the pressure of the grouting machine is not greater than 0.6 MPa. The pressure difference greatly improves the fullness of the grouting in the hole. In the cement slurry, the water-cement ratio is reduced, and special additives are added to improve the fluidity of the cement slurry and reduce the shrinkage of the cement slurry. Sealing valves are connected at the outlet and inlet of the cement slurry, and the vacuum pump is connected to the non-grouting end, and the grouting pump is connected to the grouting end. The negative pressure container, the three-way valve and the anchor cap are connected in series, and a transparent throat is used between the anchor cap and the valve. Close all exhaust valves (including the exhaust valve) before grouting. (Except for those connected to the vacuum pump) and start the vacuum pump for ten minutes, the production of vacuum negative pressure should be displayed, and the negative pressure should be able to reach 0.092Mpa; if this data is not met, it means that the bellows is not completely closed, and it is necessary to check and correct it before continuing grouting. While keeping the vacuum pump running, start grouting to the cement slurry inlet at the grouting end. Note that the vacuum pressure will drop during the grouting process (about 0.03Mpa), and observe from the transparent throat whether the cement slurry has filled the bellows. Continue grouting until the cement slurry reaches the three-phase valve installed above the negative pressure container, operate the valve to isolate the vacuum pump and the cement slurry, and guide the cement slurry to the direction of the waste slurry barrel, and continue grouting until the overflowed cement slurry is a thick slurry; turn off the vacuum pump, close the valve at the grouting pump outlet, open the small cover on the exhaust hole of the grouting cap, open the valve at the grouting pump outlet until the overflowed cement slurry is uniform in shape, install the small cover on the exhaust pipe of the grouting cap, and maintain the pressure at 0.5Mpa and continue grouting for three minutes;

[0039] S8: After the grouting test is qualified, the notch of the tensioning end of the prestressed tendon is sealed and anchored. According to the design requirements, the anchor concrete of the cross beam on the tower column is C55. When sealing the anchor, the concrete outside the notch should be roughened first. After the roughening is qualified, the anchor steel mesh is tied and the template is installed. The template should be installed firmly and reliably and leave a mortar filling port. Most of the concrete engineering work at the anchor port is relatively small, so the operation is carried out by combining manual and mechanical methods. The concrete tamping should be dense.

[0040] S9: The support can be removed only after the construction of the upper crossbeam is completed. When removing the support, adjust the height of the unloading block at the bottom of the distribution beam to make the top surface of the support separate from the concrete at the bottom of the upper crossbeam; then use the steel wire ropes of the two tower cranes on the left and right sides of the main bridge to hang the Bailey beam and move the support as a whole outward. After it is moved to the bottom of the beam, it can be lowered as a whole to the 0# and 1# blocks for removal. Finally, remove the unloading block and steel bracket at the bottom of the distribution beam.

[0041] Preferably, in step S1, the content of the bracket pre-stressing observation includes: the settlement difference between the two observations before and after, the elastic deformation of the bracket and the inelastic deformation of the bracket, using a level to observe the vertical settlement deformation of the bracket after loading, using a total station to observe the displacement deformation of the bracket, and before pre-stressing, a group of observation points are set on the bracket along the longitudinal left and right sides on the bottom mold near the tower end, and each group of observation points is symmetrically arranged with 3 points. A thin iron wire with good strength and straightness is found to hang vertically on the observation point, and a measuring station is set on the ground to observe the elevation of the mark on the vertical wire.

[0042] Preferably, in step S3, the material is cut with a grinding wheel, and electric welding or oxygen is not allowed; before cutting the steel strands, they are first tied at 3 to 5 cm on both ends of the cutting line to prevent them from being scattered after cutting. During the cutting process of the steel bundles, they are evenly arranged, combed into bundles, and marked one by one. Since the hole positions of the steel strands are different, their lengths are also different. They should be numbered and marked with the cutting length in advance. The handover team cuts the materials accordingly, and the numbers are indicated at both ends to avoid mixing. The cutting length of the steel strands is based on the design drawing, and the working length of the tensioning end is considered. When the design does not determine the cutting length, it is calculated according to the following formula and corrected after trial use:

[0043] L=L0+2L1+n(L2+L3)+2L4

[0044] Where: L——cut-off length of steel strand (mm)

[0045] L0——Length of pipe between anchor support plates (mm)

[0046] L1——Working anchor thickness (mm)

[0047] L2——Length of tensioning jack (mm)

[0048] L3——Working anchor thickness (mm)

[0049] L4——Length margin (mm) (100mm is acceptable)

[0050] N——1 for single-end tensioning and 2 for both ends tensioning

[0051] Preferably, in step S4, the upper beam body concrete is vibrated by an inserted vibrator, and an experienced concrete worker is assigned to be responsible for it. When operating the inserted vibrator, it is advisable to "insert quickly and pull out slowly". The moving distance of the inserted vibrator does not exceed 1.5 times of its effective radius, and a distance of 5 to 10 cm should be maintained with the side form. It is inserted into the lower concrete for about 5 to 10 cm, and all parts are vibrated and compacted. The sign of compaction is that the concrete stops sinking, no more bubbles are emitted, the surface is flat, and the slurry is overflowing; first, the material is cut from the chamfer of the web of the beam, The concrete is vibrated through the web and the bottom plate. The concrete flows into the bottom plate through the web. When the height of the web concrete exceeds the thickness of the bottom plate by not less than 30cm and is confirmed to be compacted by vibration, the web vibration is stopped, and the delivery pump is used to pump concrete directly to the bottom plate of the beam until the bottom plate concrete pouring is completed; the discharge port of the pump truck is equipped with 5 vibrating rods. When pouring the web concrete, because the slump of the pumped concrete is relatively large, it is expected to flow obliquely about 1 meter at the bottom plate. At this time, 2 vibrating rods are arranged on the bottom plate, which are mainly responsible for the chamfering flow. The vibrator is mainly responsible for the vibration of the web concrete. The other three vibrators are mainly responsible for the vibration of the web concrete. When the concrete is poured, it is layered at about 30cm per layer. The concrete pouring should be carried out continuously, and the interval time shall not exceed 2.5h. When the bottom plate concrete pouring is completed and the web concrete is poured, the vibrator should not be inserted too deep to avoid disturbing the bottom plate concrete and causing the web concrete to flip out of the bottom plate. If such a situation occurs, the web concrete should be re-vibrated. The bubbling concrete should be processed after the concrete pouring is completed to avoid the continued loss of the web concrete and the appearance of defects such as grooves and holes due to premature removal. When the concrete surface hardens to the point where people can walk on it, the top surface of the beam is smoothed and finished. It takes about 4 hours from the end of concrete pouring to the surface hardening to the point where people can walk on it. In case of strong wind, high temperature and dry climate, the concrete surface is easily cracked. Timely covering with geotextile can prevent shrinkage cracks caused by water evaporation. After the concrete smoothing and finishing process is completed, the surface of the beam is covered with geotextile and sprinkled with water. The number of times the beam is sprinkled with water should be sufficient to keep the concrete surface moist.

[0052] Preferably, in step S7, low-alkali silicate cement or low-alkali ordinary silicate cement (the admixture is only fly ash or slag), the strength grade of cement is 42.5Mpa, the C3A content in cement clinker should not be greater than 8%, and it should not contain any lumps; water should not contain components harmful to prestressed tendons or cement, and clean drinking water can be used; admixtures with low water content, good fluidity, minimum seepage and expansibility should be used, they should not contain chemicals harmful to prestressed tendons or cement, and the amount of admixtures should be determined by experiments; the strength of the grouting slurry should meet the design requirements, and the compressive strength of the 40*40*160mm prism specimen after standard curing for 28 days should not be less than 50Mpa.

[0053] Preferably, in step S9, during the dismantling process, all loosened rod accessories should be promptly removed and transported away to avoid mistakenly supporting or leaning on loosened rods. Parts that need to be reinforced during the dismantling operation should be reinforced before dismantling to prevent the frame from collapsing. The removed parts and rods should be transported to the ground in batches according to specifications. Throwing is strictly prohibited, and they should be neatly stacked according to specifications and varieties. Operators should respond to each other and coordinate their movements without changing personnel in the middle. When personnel must be changed, the dismantling situation should be explained in detail. It is prohibited for one person to perform dangerous operations such as dismantling heavy rods. During the entire dismantling process, a dedicated person must be in charge of command and supervision.

[0054] Preferably, during the installation of the bracket, load-bearing beam, XT300 truss beam, etc., construction workers are required to strictly follow the safety operating procedures and wear personal protective equipment (safety helmets, safety belts, non-slip shoes). After the distribution beam is installed, a 48mm×2.7mm steel pipe is used to weld it to a whole at the cantilever, and then it is connected to the tower columns on both sides. A 1.2m high guardrail is erected, and a layer of waist bars is added at 60cm~80cm. The railing uprights are set at 3m each. The guardrail is fully covered with a dense safety net. The construction load on the working layer and the working platform must meet the calculation requirements, and overloading is not allowed. Templates, steel bars and other materials must not be stacked together.

[0055] Compared with the prior art, the present invention has the following beneficial effects:

[0056] The present invention enhances the stability of the bridge. The cross beam can prevent the bridge deck from deflecting, tilting, collapsing, etc., thereby enhancing the overall stability of the bridge. The cross beam can distribute the load on the bridge evenly to the piers and foundation of the lower structure through the effect of the transverse beam structure, thereby reducing the stress concentration of the bridge components and achieving a reasonable layout of the bridge and evenly distributed load. BRIEF DESCRIPTION OF THE DRAWINGS

[0057] Figure 1 The figure is a flow chart of the upper crossbeam construction method of the present invention. DETAILED DESCRIPTION

[0058] See also Figure 1 The present invention provides a technical solution: a special construction method for the cross beam on the tower column of the main bridge, comprising the following steps:

[0059] S1: Layout of the upper crossbeam support system. The support system consists of a reinforced embedded box, bracket, load-bearing beam, XT300 truss, distribution beam, and square wood bamboo plywood. The specific layout of the support from bottom to top is that the reinforced embedded boxes are embedded in the upper and lower ends of the tower column in the longitudinal direction, and 6 rows of brackets are set in the transverse direction of the support as support. The horizontal parallel connection and diagonal bracing between the brackets are connected by [14 and [10 combined channel steels to ensure the overall stability of the support. Two rows of double-jointed Gong 56 combined steel are placed on the top of the bracket. The top of the load-bearing beam is arranged with XT300 trusses along the longitudinal direction, and double grooves 20 are added on the top of the load-bearing beam. The maximum span is 19.71m. Gong 22 steel is set on the top of the truss upper chord as a distribution beam with a maximum spacing of 80cm; square wood is placed on the distribution beam, and the bottom mold is made of 15mm bamboo plywood and 10cmx10cm square wood;

[0060] After the upper crossbeam bracket is installed, concrete blocks are used for preloading to eliminate the inelastic deformation of the bracket. The load weight is 1.2 times the sum of the design weight of the crossbeam and the weight of the bracket. During preloading, the load is symmetrically distributed along the center line on both sides of the structure. The load on the bracket is divided into units for preloading, which is 1.2 times the actual weight of the simulated load of the designed section in the unit. The preloading load is evenly distributed in the unit. The bracket preloading adopts a four-level loading method, and the load applied in sequence is 60% of the preloading load value in the unit. , 80%, 100%, 120%; temporary leveling points are set near the preloading area, and the elevation of the leveling points is set as the basis for observation. After the leveling points are set, they should be protected and marked in time to prevent them from being damaged during construction. A monitoring section is arranged every 1 / 5 of the span along the longitudinal direction of the concrete structure. For the cross beam on the tower column (bottom plate width 6.6m), 3 monitoring points are arranged in the longitudinal direction of the bridge, with spacing of 1.3m, 3.3m, and 5.3m respectively, and the transverse direction of the bridge (length 28m) is arranged at a spacing of 5m;

[0061] S2: The steel bars are straightened by long-line cold-drawing straightening or straightening machine; the steel bars are cut by cutting machine; the steel bars are bent by bending machine, and the bending size is controlled by template; the steel bar joints with a diameter greater than 25 mm are connected by mechanical sleeves. The steel bars are straightened by long-line cold-drawing straightening or straightening machine before processing and bending. The oil stains, paint stains, cement slurry and floating rust and rust that can be peeled off by hammering on the surface of the steel bars must be cleaned. During the steel bar cutting process, any appearance defects of the welding joints and steel materials shall be removed. The position of the fixed-length baffle shall be checked after it is fixed. The length error of long steel bars without hooks is ±15mm. The elongation of steel bars with hooks and bends shall be considered after bending. The actual cutting length shall be determined based on experience;

[0062] The upper cross beam body reinforcement is tied, considering the installation of the inner formwork, the cross beam body reinforcement is divided into two parts: the bottom web reinforcement skeleton and the top plate reinforcement skeleton;

[0063] ①The steel bar joints in the axial tension and slightly eccentric tension rods should be welded;

[0064] ②For steel bars with a diameter greater than 12mm, welded joints are preferred;

[0065] ③ When the diameter of the tensile steel bar is greater than 28mm and the diameter of the compressive steel bar is greater than 32mm, it is not advisable to use a tied lap joint;

[0066] ④ In structural members that directly bear dynamic loads, the longitudinal tensile reinforcement shall not be tied.

[0067] Tie lap joints;

[0068] ⑤ The joints of cold-drawn low-carbon steel wires can only be tied together, and contact butt welding or arc welding is not allowed;

[0069] ⑥The distance between the welding joint and the bending part of the steel bar should not be less than 10d;

[0070] S3: The bottom formwork of the crossbeam is made of high-quality bamboo plywood with a thickness of δ=15mm, which is directly placed on the 10×10cm longitudinal square wood. The center-to-center spacing of the web and cross partition wood is 20cm, and the center-to-center spacing of the other square wood is 30cm. The inner and outer formworks of the upper crossbeam on the support system are both made of 1.5cm thick bamboo plywood. The side formwork uses 10*10cm square wood as vertical ribs with a spacing of 25cm; double-jointed [8 channel steel is used as transverse ribs, and the transverse rib spacing is 75cm. The formwork joints are connected with M25 screws. The crossbeam formwork is installed by a tower crane and adjusted by a hand winch. After the formwork is in place, the adjacent formworks are fixed with bolts, and the inner and outer formworks are fixed with tension screws; The connection between the corrugated pipe and the anchor plate: The connection between the corrugated pipe and the anchor plate adopts a tube-sheet joint. The end of the corrugated pipe is screwed into one end of the tube-sheet joint, and the other end of the tube-sheet joint is extended into At the tail of the anchor plate, the connection between the corrugated pipe and the tube sheet, and the tube sheet joint and the anchor plate should have an overlap length of more than 6cm and be sealed with tape to prevent leakage when pouring concrete; Corrugated pipe joint treatment: Use plastic connectors with sealing properties to extend the length, and the connector should have a length of not less than 200mm; Corrugated pipe positioning: First, calculate the position of the prestressed pipe according to the prestressed steel beam curve parameter table, and calculate the corrugated pipe coordinates every 50cm as the basis for positioning the corrugated pipe. The position guarantee measures of the corrugated pipe mainly rely on the "well"-shaped positioning steel bars. The spacing of the positioning steel bars of the straight section of the corrugated pipe is not more than 0.5m, and the spacing of the curved section is not more than 0.3m. The positioning steel bars should be appropriately adjusted according to the distance from the outer wall of the corrugated pipe to the outer edge of the box beam to ensure that the distance from the end of the steel bar to the outer edge of the box beam is not less than 2.5cm;

[0071] S4: Before mixing concrete, the quality and quantity of all raw materials must be confirmed. Production can only be started after meeting the construction needs. The metering system of the mixing equipment must be within the calibration validity period. Spot checks and verifications should be carried out when necessary. The workability and slump of concrete should be tested at the beginning of production and during the production process to ensure production quality. Concrete is transported to the construction site by a mixer truck. The transportation time should be strictly controlled. After arriving at the site, various performance indicators of the concrete should also be checked. It can only be pumped into the mold after meeting the requirements. If the waiting time is long, the tank truck should accelerate the rotation for 20 to 30 seconds and stir the concrete for the second time to ensure the uniformity of the concrete. The upper beam is poured in two times. The pouring is carried out in sections and layers. The tower column position is poured first, and then the beam position is poured. The first pouring height is 2 meters, and the second pouring height is 3 meters. The entire pouring sequence meets the left-right symmetry and the front-back symmetry. Concrete pouring procedure and sequence: first pour the tower column position → then pour the box room web → then pour the box room bottom plate → finally pour the box room top plate (second pouring). The concrete is poured in the order of "both sides → middle", and the bottom plate concrete is poured in the order of "both sides → middle". After the concrete at the chamfer inside the web is poured in place, pour the bottom plate concrete, and then pour the remaining concrete of the web; pour the top plate concrete for the second time; the upper crossbeam concrete is poured twice, and the pouring is carried out in sections and layers. First pour the tower column position, and then pour the bottom web at the crossbeam position. In order to facilitate the second mold erection and pouring of the top plate, after the bottom web is poured, the top plate bottom formwork is installed. Because the inner formwork has formed a frame, the top formwork can be quickly laid, and the contact surface of the construction concrete is cleaned, the top plate steel bars are installed and tied, and then the top plate concrete is poured for the second time. Before pouring the top plate concrete, the concrete on the contact surface between the bottom web and the top plate needs to be sprinkled with water to moisten it;

[0072] S5: Prestressing, grouting and anchor sealing construction. Before prestressing, check whether the concrete dimensions and appearance meet the quality requirements, whether the anchor pad is in the correct position, whether there are honeycombs and voids under the anchor pad, and take reinforcement measures if necessary. When prestressing the upper beam, in order to avoid the late shrinkage and creep having a greater impact on the structure, the transverse prestressing concrete strength should not be less than 90% of the design strength according to the design requirements, and the concrete curing age should not be less than 7 days. Only then can the jack, tensioning machine and other equipment be installed to prepare for prestressing. The prestressing tendon tensioning equipment (jack and oil gauge) should be calibrated to determine the relationship curve between the tensioning force and the oil gauge reading. The steel strands are inserted into the channel. Before the bundle is inserted, the anchor pad, channel and grouting hole should be checked first. The anchor pad should be in the correct position, the channel should be unobstructed, free of water and debris, and the tensioning personnel should be certified;

[0073] Complete the inspection of the tensioning equipment → The steel strand has been put in advance → Install the working anchor plate → Install the working anchor fixture → Install the limit plate → Install the jack → Install the tool anchor → Install the tool anchor clip → Preparatory work before prestressing → Prestressing procedure → Grouting the hole → Anchor sealing; The extended part of the steel bundle should be kept clean, without oil, mud and other debris, and the construction personnel should not step on it at will. The anchor ring and the clip should be cleaned with kerosene or diesel before use, and there should be no oil, iron filings, mud and other debris. The working anchor must be accurately placed in the positioning groove of the anchor pad and aligned with the hole; Clips are installed in each hole of the working anchor and put on with rubber rings. An iron pipe about 30 cm long can be used to penetrate the steel hinge wire and push forward lightly to align the clips. Be careful not to use too much force. The gap between the clips should be uniform and can be carefully adjusted with a screwdriver. There must be a specified number of clips in each hole, and there must be no shortage. After the clip is installed, its exposed length is generally 4-5mm, and it is uniform. If it is exposed too much, check the size and taper of the clamp and anchor ring hole used. If any unqualified ones are found, they must be replaced. Do not push or pull the oil pipe and joint when installing the jack. The oil pipe should be straight and not twisted into a ball. Before installing the tool anchor, the jack piston should be extended 3-5cm. When the steel bundle is inserted into the tool anchor, the position should correspond to the position of the working anchor steel bundle one by one, and no cross-twisting should be allowed. In order to smoothly withdraw the tool anchor, lubricant should be applied to the smooth surface of the tool anchor clip or the anchor hole of the tool anchor. The lubricant is paraffin. When using paraffin, melt it and apply it to the clip. The clip of the tool anchor should be placed separately from the clip of the working anchor. The number of times the tool anchor clip is reused shall not exceed 10 times. If the clip is found to be damaged, it should be replaced in time to prevent slipping and flying pieces during tensioning.

[0074] S6: Intelligent tensioning is adopted. Before tensioning, the friction resistance test of the hole should be carried out, and the friction resistance coefficient used for calculation is 0.2. The upper beam prestressed tendons are tensioned at both ends. Prestressing can be carried out only after the concrete strength and elastic modulus reach 100% of the design strength and meet the 7-day age period. The tensioning of the steel tendons adopts dual control of tensioning force and elongation, which is controlled by the reading of the main oil cylinder oil pressure gauge and checked by the elongation of the steel strand. The elongation error shall not exceed ±6%;

[0075] ① Tensioning procedure

[0076] 0→initial stress (final tension control stress is about 10%, measure the elongation of the steel strand and make a mark, measure the exposed amount of the tool anchor clip)→tension control stress (specified value of each period, measure the elongation value of the steel strand, measure the exposed amount of the tool anchor clip)→stop for 5 minutes, check the tension control stress and elongation;

[0077] ② Tensioning operation

[0078] a.0 stage: the jack is filled with oil and the piston extends 1 to 2 cm;

[0079] b. Initial tensioning: Before initial tensioning, adjust the tightness of the steel strand bundle, align the tensioning equipment with the channel axis, and evenly force it. After reaching the tonnage, install measurement marks on the steel strand, and measure the distance to the outer edge of the oil top as the initial reading.

[0080] c. Grading and cutting: measure the elongation value once;

[0081] d. Tensioning tonnage: When tensioning to the controlled stress, hold the load for 5 minutes, measure the elongation of the steel strand, and observe the condition of the steel strand and the clip;

[0082] e. Self-anchoring: After the tensioning is completed, the jack returns oil, the cylinder retracts, the tool anchor retreats, and the working anchor clip automatically anchors the steel strand. The oil return should be done slowly to achieve the purpose of self-anchoring;

[0083] f. Oil return: Open the jack's oil return and oil delivery valves, the jack's main oil cylinder continues to retract, the tool anchor is detached from the oil top port, the tool clips are gradually detached from the anchor hole, and the steel strands are carefully checked;

[0084] g. Retraction: Remove the tool anchor, jack and limit plate one by one, and use a vernier caliper to measure the exposed amount of the working anchor clip;

[0085] h. After the tensioning is completed, mark the steel strand at the anchor ring mouth and record the data as a mark to observe whether the steel strand anchorage is slipping after tensioning;

[0086] i. Tensioning construction requirements:

[0087] (a) The measurement accuracy of prestressed tendon elongation should reach 1.5mm, and the deviation between the measured elongation and the theoretical elongation should be less than ±6%. Otherwise, the cause should be analyzed and dealt with in time;

[0088] (b) Tensioning is controlled by tensioning force, and the theoretical elongation cannot be achieved by over-tensioning;

[0089] (c) After the tensioning is completed, it must be inspected and signed for approval by the technical staff;

[0090] (d) The longitudinal prestressing hole is long, and the elongation of the steel strand lags behind the growth of the tension force. The pressure holding time must be ensured and the tension force must be supplemented before anchoring;

[0091] (e) The contents of prestressing quality control at the construction site include: correct prestressing operation, tensioning force at each level controlled by pressure gauge, measuring actual tensioning elongation, checking for slipped or broken wires, and flatness of the clip after anchoring, etc.;

[0092] (f) As acceptance technical data, the actual tension elongation value measured on site should be collated as tension data and compared with the corrected theoretical elongation value to determine whether the tension is normal and whether there is any hole blockage, etc.;

[0093] S7: After tensioning, grouting should be carried out in time. Pipeline grouting should be carried out within 24 hours after tensioning. Before grouting, first use a vacuum pump to suck the air in the prestressed pores to make the vacuum degree in the pores reach between -0.06 and -0.08 MPa. Then, at the other end of the pores, a grouting machine is used to press cement slurry into the prestressed pores with a positive pressure of no more than 0.6 MPa. Since there is very little air in the pores, it is difficult to form bubbles. Due to the positive and negative pressure between the pores and the grouting machine, the pressure of the grouting machine is not greater than 0.6 MPa. The pressure difference greatly improves the fullness of the grouting in the hole. In the cement slurry, the water-cement ratio is reduced, and special additives are added to improve the fluidity of the cement slurry and reduce the shrinkage of the cement slurry. Sealing valves are connected at the outlet and inlet of the cement slurry, and the vacuum pump is connected to the non-grouting end, and the grouting pump is connected to the grouting end. The negative pressure container, the three-way valve and the anchor cap are connected in series, and a transparent throat is used between the anchor cap and the valve. Close all exhaust valves (including the exhaust valve) before grouting. (Except for those connected to the vacuum pump) and start the vacuum pump for ten minutes, the production of vacuum negative pressure should be displayed, and the negative pressure should be able to reach 0.092Mpa; if this data is not met, it means that the bellows is not completely closed, and it is necessary to check and correct it before continuing grouting. While keeping the vacuum pump running, start grouting to the cement slurry inlet at the grouting end. Note that the vacuum pressure will drop during the grouting process (about 0.03Mpa), and observe from the transparent throat whether the cement slurry has filled the bellows. Continue grouting until the cement slurry reaches the three-phase valve installed above the negative pressure container, operate the valve to isolate the vacuum pump and the cement slurry, and guide the cement slurry to the direction of the waste slurry barrel, and continue grouting until the overflowed cement slurry is a thick slurry; turn off the vacuum pump, close the valve at the grouting pump outlet, open the small cover on the exhaust hole of the grouting cap, open the valve at the grouting pump outlet until the overflowed cement slurry is uniform in shape, install the small cover on the exhaust pipe of the grouting cap, and maintain the pressure at 0.5Mpa and continue grouting for three minutes;

[0094] S8: After the grouting test is qualified, the notch of the tensioning end of the prestressed tendon is sealed and anchored. According to the design requirements, the anchor concrete of the cross beam on the tower column is C55. When sealing the anchor, the concrete outside the notch should be roughened first. After the roughening is qualified, the anchor steel mesh is tied and the template is installed. The template should be installed firmly and reliably and leave a mortar filling port. Most of the concrete engineering work at the anchor port is relatively small, so the operation is carried out by combining manual and mechanical methods. The concrete tamping should be dense.

[0095] S9: The support can be removed only after the construction of the upper crossbeam is completed. When removing the support, adjust the height of the unloading block at the bottom of the distribution beam to make the top surface of the support separate from the concrete at the bottom of the upper crossbeam; then use the steel wire ropes of the two tower cranes on the left and right sides of the main bridge to hang the Bailey beam and move the support as a whole outward. After it is moved to the bottom of the beam, it can be lowered as a whole to the 0# and 1# blocks for removal. Finally, remove the unloading block and steel bracket at the bottom of the distribution beam.

[0096] In step S1, the content of the support preloading observation includes: the settlement difference between the two observations before and after, the elastic deformation of the support and the inelastic deformation of the support, the vertical settlement deformation of the support after loading is observed with a level, and the displacement deformation of the support is observed with a total station. Before preloading, a group of observation points are set on the bottom mold near the tower end along the left and right longitudinal widths of the support, and each group of observation points is symmetrically arranged with 3 points. A thin iron wire with good strength and straightness is hung vertically on the observation point, and a measuring station is set on the ground to observe the elevation of the mark on the vertical wire;

[0097] In step S3, the material is cut with a grinding wheel, and electric welding or oxygen is not allowed. Before cutting the steel strands, tie them together at 3 to 5 cm on both ends of the cutting line to prevent them from being scattered after cutting. During the cutting process of the steel strands, they are evenly arranged, combed into bundles, and marked one by one. Since the holes of the steel strands are different, their lengths are also different. They should be numbered and marked with the cutting length in advance. The handover team cuts the material accordingly and indicates the numbers at both ends to avoid mixing. The cutting length of the steel strands is based on the design drawing, and the working length of the tensioning end is considered. When the design does not determine the cutting length, it is calculated according to the following formula and corrected after trial use:

[0098] L=L0+2L1+n(L2+L3)+2L4

[0099] Where: L——cut-off length of steel strand (mm)

[0100] L0——Length of pipe between anchor support plates (mm)

[0101] L1——Working anchor thickness (mm)

[0102] L2——Length of tensioning jack (mm)

[0103] L3——Working anchor thickness (mm)

[0104] L4——Length margin (mm) (100mm is acceptable)

[0105] N——1 for single-end tensioning and 2 for both ends tensioning

[0106] In step S4, the upper beam body concrete is vibrated with an inserted vibrator, and an experienced concrete worker is assigned to be responsible for it. When operating the inserted vibrator, it is advisable to "insert quickly and pull out slowly". The moving distance of the inserted vibrator shall not exceed 1.5 times of its effective radius, and a distance of 5 to 10 cm should be maintained with the side form. It should be inserted into the lower concrete for about 5 to 10 cm, and all parts should be vibrated to make them dense. The sign of density is that the concrete stops sinking, no more bubbles are emitted, the surface is flat, and there is slurry. First, the material is cut from the chamfer of the web of the beam, and the concrete is vibrated through the web and the bottom plate. The concrete flows into the bottom plate through the web. After the height of the web concrete exceeds the thickness of the bottom plate by not less than 30 cm and it is confirmed to be dense, the web is stopped. Vibrate, and then use the delivery pump to directly pump concrete to the bottom plate of the beam until the bottom plate concrete pouring is completed; the discharge port of the pump truck is equipped with 5 vibrators. When pouring the web concrete, because the slump of the pumped concrete is relatively large, it is expected to flow obliquely about 1 meter at the bottom plate. At this time, 2 vibrators are arranged on the bottom plate, which are mainly responsible for the concrete vibration at the chamfer flow. The other 3 vibrators are mainly responsible for the web concrete vibration. When the concrete is discharged, it is layered by about 30cm per layer. The concrete pouring should be carried out continuously, and the interval time shall not exceed 2.5h; when the bottom plate concrete pouring is completed and the web concrete is poured, the vibrator should not be inserted too deep to avoid disturbing the bottom plate concrete and causing the web concrete to flip out of the bottom plate. In such a situation, the web concrete should be re-vibrated; the bubbling concrete should be processed after the concrete pouring is completed to avoid the web concrete from continuing to flow out due to premature removal, resulting in defects such as grooves and holes. When the concrete surface hardens to the point where people can walk on it, the top surface of the beam is smoothed and finished. Since it takes about 4 hours from the end of concrete pouring to the surface hardening to the point where people can walk on it, it is very easy to cause the concrete surface to crack in case of strong winds, high temperatures, and dry climates. Timely covering with geotextiles can prevent shrinkage cracks caused by evaporation of water. After the concrete smoothing and finishing process is completed, the surface of the beam is covered with geotextiles and watered. The number of times the beam is watered should be sufficient to keep the concrete surface sufficiently moist. In step S7 In the process, low-alkali silicate cement or low-alkali ordinary silicate cement (the admixture is only fly ash or slag), the strength grade of cement is 42.5Mpa, the C3A content in cement clinker should not be greater than 8%, and no lumps should be contained; water should not contain any harmful components to prestressed tendons or cement, and clean drinking water can be used; admixtures with low water content, good fluidity, minimum seepage and expansion properties should be used; they should not contain chemical substances that are harmful to prestressed tendons or cement, and the amount of admixtures should be determined through tests; the strength of the grouting slurry should meet the design requirements, and the compressive strength of the 40*40*160mm prism specimen after standard curing for 28 days should not be less than 50Mpa;

[0107] In step S9, during the dismantling process, all loosened rod accessories should be removed and transported in time to avoid mistakenly supporting or leaning on loosened rods. Parts that need to be reinforced during the dismantling operation should be reinforced before dismantling to prevent the frame from collapsing. The dismantled parts and rods should be transported to the ground in batches according to specifications. Throwing is strictly prohibited, and they should be neatly stacked according to specifications and varieties. Operators should respond to each other and coordinate their actions. No one should be replaced in the middle. If a replacement is necessary, the dismantling situation should be explained in detail. It is prohibited for one person to perform dangerous operations such as dismantling heavy rods. During the whole dismantling process, a dedicated person must be in charge of command and supervision; brackets, load-bearing beams, XT300 trusses During the installation of beams, construction workers are required to strictly follow the safety operating procedures and wear personal protective equipment (safety helmets, safety belts, non-slip shoes). After the distribution beam is installed, 48mm×2.7mm steel pipes are welded to the distribution beam at the cantilever to form a whole, and then connected to the tower columns on both sides. A 1.2m high guardrail is set up, and a layer of waist bars is added at 60cm~80cm. The railing uprights are set at 3m each. The guardrail is fully covered with a dense safety net. The construction load on the working layer and the working platform must meet the calculation requirements, and overloading is not allowed. Templates, steel bars and other materials must not be stacked together.

Claims

1. A special construction method for the cross beam on the main bridge tower column, characterized in that: The following steps are involved: S1: Layout of the upper crossbeam support system. The support system consists of a reinforced embedded box, bracket, load-bearing beam, XT300 truss, distribution beam, and square wood bamboo plywood. The specific layout of the support from bottom to top is that the reinforced embedded boxes are embedded in the upper and lower ends of the tower column in the longitudinal direction, and 6 rows of brackets are set in the transverse direction of the support as support. The horizontal parallel connection and diagonal bracing between the brackets are connected by [14 and [10 combined channel steels to ensure the overall stability of the support. Two rows of double-jointed Gong 56 combined steel are placed on the top of the bracket. The top of the load-bearing beam is arranged with XT300 trusses along the longitudinal direction, and double grooves 20 are added on the top of the load-bearing beam. The maximum span is 19.71m. Gong 22 steel is set on the top of the truss upper chord as a distribution beam with a maximum spacing of 80cm; square wood is placed on the distribution beam, and the bottom mold is made of 15mm bamboo plywood and 10cmx10cm square wood; After the upper crossbeam bracket is installed, concrete blocks are used for preloading to eliminate the inelastic deformation of the bracket. The load weight is 1.2 times the sum of the design weight of the crossbeam and the weight of the bracket. During preloading, the load is symmetrically distributed along the center line on both sides of the structure. The load on the bracket is divided into units for preloading, which is 1.2 times the actual weight of the simulated load of the designed section in the unit. The preloading load is evenly distributed in the unit. The bracket preloading adopts a four-level loading method, and the load applied in sequence is 60% of the preloading load value in the unit. , 80%, 100%, 120%; temporary leveling points are set near the preloading area, and the elevation of the leveling points is set as the basis for observation. After the leveling points are set, they should be protected and marked in time to prevent them from being damaged during construction. A monitoring section is arranged every 1 / 5 of the span along the longitudinal direction of the concrete structure. For the cross beam on the tower column (bottom plate width 6.6m), 3 monitoring points are arranged in the longitudinal direction of the bridge, with spacing of 1.3m, 3.3m, and 5.3m respectively, and the transverse direction of the bridge (length 28m) is arranged at a spacing of 5m; S2: The steel bars are straightened by long-line cold-drawing straightening or straightening machine; the steel bars are cut by cutting machine; the steel bars are bent by bending machine, and the bending size is controlled by template; the steel bar joints with a diameter greater than 25 mm are connected by mechanical sleeves. The steel bars are straightened by long-line cold-drawing straightening or straightening machine before processing and bending. The oil stains, paint stains, cement slurry and floating rust and rust that can be peeled off by hammering on the surface of the steel bars must be cleaned. During the steel bar cutting process, any appearance defects of the welding joints and steel materials shall be removed. The position of the fixed-length baffle shall be checked after it is fixed. The length error of long steel bars without hooks is ±15mm. The elongation of steel bars with hooks and bends shall be considered after bending. The actual cutting length shall be determined based on experience; The upper cross beam body reinforcement is tied, considering the installation of the inner formwork, the cross beam body reinforcement is divided into two parts: the bottom web reinforcement skeleton and the top plate reinforcement skeleton; ①The steel bar joints in the axial tension and slightly eccentric tension rods should be welded; ②For steel bars with a diameter greater than 12mm, welded joints are preferred; ③ When the diameter of the tensile steel bar is greater than 28mm and the diameter of the compressive steel bar is greater than 32mm, it is not advisable to use a tied lap joint; ④ In structural members that directly bear dynamic loads, the longitudinal tensile reinforcement shall not be tied with lap joints; ⑤ The joints of cold-drawn low-carbon steel wires can only be tied together, and contact butt welding or arc welding is not allowed; ⑥The distance between the welding joint and the bending part of the steel bar should not be less than 10d; S3: The bottom formwork of the crossbeam is made of high-quality bamboo plywood with a thickness of δ=15mm, which is directly placed on the 10×10cm longitudinal square wood. The center-to-center spacing of the web and cross partition wood is 20cm, and the center-to-center spacing of the other square wood is 30cm. The inner and outer formworks of the upper crossbeam on the support system are both made of 1.5cm thick bamboo plywood. The side formwork uses 10*10cm square wood as vertical ribs with a spacing of 25cm; double-jointed [8 channel steel is used as transverse ribs, and the transverse rib spacing is 75cm. The formwork joints are connected with M25 screws. The crossbeam formwork is installed by a tower crane and adjusted by a hand winch. After the formwork is in place, the adjacent formworks are fixed with bolts, and the inner and outer formworks are fixed with tension screws; The connection between the corrugated pipe and the anchor plate: The connection between the corrugated pipe and the anchor plate adopts a tube-sheet joint. The end of the corrugated pipe is screwed into one end of the tube-sheet joint, and the other end of the tube-sheet joint is extended into At the tail of the anchor plate, the connection between the corrugated pipe and the tube sheet, and between the tube sheet and the anchor plate should have an overlap length of more than 6cm and be sealed with tape to prevent leakage when pouring concrete; Corrugated pipe joint treatment: Use plastic connectors with sealing properties to extend the length, and the connector should have a length of not less than 200mm; Corrugated pipe positioning: First, calculate the position of the prestressed pipe according to the prestressed steel beam curve parameter table, and calculate the coordinates of the corrugated pipe every 50cm as the basis for positioning the corrugated pipe. The position guarantee measures of the corrugated pipe mainly rely on the "well" type positioning steel bars. The spacing of the positioning steel bars of the straight section of the corrugated pipe is not more than 0.5m, and the spacing of the curved section is not more than 0.3m. The positioning steel bars should be appropriately adjusted according to the distance from the outer wall of the corrugated pipe to the outer edge of the box beam to ensure that the distance from the end of the steel bar to the outer edge of the box beam is not less than 2.5cm; S4: Before mixing concrete, the quality and quantity of all raw materials must be confirmed. Production can only be started after meeting the construction needs. The metering system of the mixing equipment must be within the calibration validity period. Spot checks and verifications should be carried out when necessary. The workability and slump of concrete should be tested at the beginning of production and during the production process to ensure production quality. Concrete is transported to the construction site by a mixer truck. The transportation time should be strictly controlled. After arriving at the site, various performance indicators of the concrete should also be checked. It can only be pumped into the mold after meeting the requirements. If the waiting time is long, the tank truck should accelerate the rotation for 20 to 30 seconds and stir the concrete for the second time to ensure the uniformity of the concrete. The upper beam is poured in two times. The pouring is carried out in sections and layers. The tower column position is poured first, and then the beam position is poured. The first pouring height is 2 meters, and the second pouring height is 3 meters. The entire pouring sequence meets the left-right symmetry and the front-back symmetry. Concrete pouring procedure and sequence: first pour the tower column position → then pour the box room web → then pour the box room bottom plate → finally pour the box room top plate (second pouring). The concrete is poured in the order of "both sides → middle", and the bottom plate concrete is poured in the order of "both sides → middle". After the concrete at the chamfer inside the web is poured in place, pour the bottom plate concrete, and then pour the remaining concrete of the web; pour the top plate concrete for the second time; the upper crossbeam concrete is poured twice, and the pouring is carried out in sections and layers. First pour the tower column position, then pour the bottom web at the crossbeam position. In order to facilitate the second mold erection and pouring of the top plate, after the bottom web is poured, the top plate bottom formwork is installed. Because the inner formwork has formed a frame, the top formwork can be quickly laid, the contact surface of the construction concrete is cleaned, the top plate steel bars are installed and tied, and then the second top plate concrete pouring is carried out. Before pouring the top plate concrete, the concrete on the contact surface between the bottom web and the top plate needs to be sprinkled with water to moisten it; S5: Prestressing, grouting and anchor sealing construction. Before prestressing, check whether the concrete dimensions and appearance meet the quality requirements, whether the anchor pad is in the correct position, whether there are honeycombs and voids under the anchor pad, and take reinforcement measures if necessary. When prestressing the upper beam, in order to avoid the late shrinkage and creep having a greater impact on the structure, the transverse prestressing concrete strength should not be less than 90% of the design strength according to the design requirements, and the concrete curing age should not be less than 7 days. Only then can the jack, tensioning machine and other equipment be installed to prepare for prestressing. The prestressing tendon tensioning equipment (jack and oil gauge) should be calibrated to determine the relationship curve between the tensioning force and the oil gauge reading. The steel strands are inserted into the channel. Before the bundle is inserted, the anchor pad, channel and grouting hole should be checked first. The anchor pad should be in the correct position, the channel should be unobstructed, free of water and debris, and the tensioning personnel should be certified; Complete the inspection of the tensioning equipment → The steel strand has been put in advance → Install the working anchor plate → Install the working anchor fixture → Install the limit plate → Install the jack → Install the tool anchor → Install the tool anchor clip → Preparatory work before prestressing → Prestressing procedure → Grouting the hole → Anchor sealing; The extended part of the steel bundle should be kept clean, without oil, mud and other debris, and the construction personnel should not step on it at will. The anchor ring and the clip should be cleaned with kerosene or diesel before use, and there should be no oil, iron filings, mud and other debris. The working anchor must be accurately placed in the positioning groove of the anchor pad and aligned with the hole; Clips are installed in each hole of the working anchor and put on with rubber rings. An iron pipe about 30 cm long can be used to penetrate the steel hinge wire and push forward lightly to align the clips. Be careful not to use too much force. The gap between the clips should be uniform and can be carefully adjusted with a screwdriver. There must be a specified number of clips in each hole, and there must be no shortage. After the clip is installed, its exposed length is generally 4-5mm, and it is uniform. If it is exposed too much, check the size and taper of the clamp and anchor ring hole used. If any unqualified ones are found, they must be replaced. Do not push or pull the oil pipe and joint when installing the jack. The oil pipe should be straight and not twisted into a ball. Before installing the tool anchor, the jack piston should be extended 3-5cm. When the steel bundle is inserted into the tool anchor, the position should correspond to the position of the working anchor steel bundle one by one, and no cross-twisting should be allowed. In order to smoothly withdraw the tool anchor, lubricant should be applied to the smooth surface of the tool anchor clip or the anchor hole of the tool anchor. The lubricant is paraffin. When using paraffin, melt it and apply it to the clip. The clip of the tool anchor should be placed separately from the clip of the working anchor. The number of times the tool anchor clip is reused shall not exceed 10 times. If the clip is found to be damaged, it should be replaced in time to prevent slipping and flying pieces during tensioning. S6: Intelligent tensioning is adopted. Before tensioning, the friction resistance test of the hole should be carried out, and the friction resistance coefficient used for calculation is 0.

2. The upper beam prestressed tendons are tensioned at both ends. Prestressing can be carried out only after the concrete strength and elastic modulus reach 100% of the design strength and meet the 7-day age period. The tensioning of the steel tendons adopts dual control of tensioning force and elongation, which is controlled by the reading of the main oil cylinder oil pressure gauge and checked by the elongation of the steel strand. The elongation error shall not exceed ±6%; ① Tensioning procedure 0→initial stress (final tension control stress is about 10%, measure the elongation of the steel strand and make a mark, measure the exposed amount of the tool anchor clip)→tension control stress (specified value of each period, measure the elongation value of the steel strand, measure the exposed amount of the tool anchor clip)→stop for 5 minutes, check the tension control stress and elongation; ② Tensioning operation a.0 stage: the jack is filled with oil and the piston extends 1 to 2 cm; b. Initial tensioning: Before initial tensioning, adjust the tightness of the steel strand bundle, align the tensioning equipment with the channel axis, and evenly force it. After reaching the tonnage, install measurement marks on the steel strand, and measure the distance to the outer edge of the oil top as the initial reading. c. Grading and cutting: measure the elongation value once; d. Tensioning tonnage: When tensioning to the controlled stress, hold the load for 5 minutes, measure the elongation of the steel strand, and observe the condition of the steel strand and the clip; e. Self-anchoring: After the tensioning is completed, the jack returns oil, the cylinder retracts, the tool anchor retreats, and the working anchor clip automatically anchors the steel strand. The oil return should be done slowly to achieve the purpose of self-anchoring; f. Oil return: Open the jack's oil return and oil delivery valves, the jack's main oil cylinder continues to retract, the tool anchor is detached from the oil top port, the tool clips are gradually detached from the anchor hole, and the steel strands are carefully checked; g. Retraction: Remove the tool anchor, jack and limit plate one by one, and use a vernier caliper to measure the exposed amount of the working anchor clip; h. After the tensioning is completed, mark the steel strand at the anchor ring mouth and record the data as a mark to observe whether the steel strand anchorage is slipping after tensioning; i. Tensioning construction requirements: (a) The measurement accuracy of prestressed tendon elongation should reach 1.5mm, and the deviation between the measured elongation and the theoretical elongation should be less than ±6%. Otherwise, the cause should be analyzed and dealt with in time; (b) Tensioning is controlled by tensioning force, and the theoretical elongation cannot be achieved by over-tensioning; (c) After the tensioning is completed, it must be inspected and signed for approval by the technical staff; (d) The longitudinal prestressing hole is long, and the elongation of the steel strand lags behind the growth of the tension force. The pressure holding time must be ensured and the tension force must be supplemented before anchoring; (e) The contents of prestressing quality control at the construction site include: correct prestressing operation, tensioning force at each level controlled by pressure gauge, measuring actual tensioning elongation, checking for slipped or broken wires, and flatness of the clip after anchoring, etc.; (f) As acceptance technical data, the actual tension elongation value measured on site should be collated as tension data and compared with the corrected theoretical elongation value to determine whether the tension is normal and whether there is any hole blockage, etc.; S7: After tensioning, grouting should be carried out in time. Pipeline grouting should be carried out within 24 hours after tensioning. Before grouting, first use a vacuum pump to suck the air in the prestressed pores to make the vacuum degree in the pores reach between -0.06 and -0.08 MPa. Then, at the other end of the pores, a grouting machine is used to press cement slurry into the prestressed pores with a positive pressure of no more than 0.6 MPa. Since there is very little air in the pores, it is difficult to form bubbles. Due to the positive and negative pressure between the pores and the grouting machine, the pressure of the grouting machine is not greater than 0.6 MPa. The pressure difference greatly improves the fullness of the grouting in the hole. In the cement slurry, the water-cement ratio is reduced, and special additives are added to improve the fluidity of the cement slurry and reduce the shrinkage of the cement slurry. Sealing valves are connected at the outlet and inlet of the cement slurry, and the vacuum pump is connected to the non-grouting end, and the grouting pump is connected to the grouting end. The negative pressure container, the three-way valve and the anchor cap are connected in series, and a transparent throat is used between the anchor cap and the valve. Close all exhaust valves (including the exhaust valve) before grouting. (Except for those connected to the vacuum pump) and start the vacuum pump for ten minutes, the production of vacuum negative pressure should be displayed, and the negative pressure should be able to reach 0.092Mpa; if this data is not met, it means that the bellows is not completely closed, and it is necessary to check and correct it before continuing grouting. While keeping the vacuum pump running, start grouting to the cement slurry inlet at the grouting end. Note that the vacuum pressure will drop during the grouting process (about 0.03Mpa), and observe from the transparent throat whether the cement slurry has filled the bellows. Continue grouting until the cement slurry reaches the three-phase valve installed above the negative pressure container, operate the valve to isolate the vacuum pump and the cement slurry, and guide the cement slurry to the direction of the waste slurry barrel, and continue grouting until the overflowed cement slurry is a thick slurry; turn off the vacuum pump, close the valve at the grouting pump outlet, open the small cover on the exhaust hole of the grouting cap, open the valve at the grouting pump outlet until the overflowed cement slurry is uniform in shape, install the small cover on the exhaust pipe of the grouting cap, and maintain the pressure at 0.5Mpa and continue grouting for three minutes; S8: After the grouting test is qualified, the notch of the tensioning end of the prestressed tendon is sealed and anchored. According to the design requirements, the anchor concrete of the cross beam on the tower column is C55. When sealing the anchor, the concrete outside the notch should be roughened first. After the roughening is qualified, the anchor steel mesh is tied and the template is installed. The template should be installed firmly and reliably and leave a mortar filling port. Most of the concrete engineering work at the anchor port is relatively small, so the operation is carried out by combining manual and mechanical methods. The concrete tamping should be dense. S9: The support can be removed only after the construction of the upper crossbeam is completed. When removing the support, adjust the height of the unloading block at the bottom of the distribution beam to make the top surface of the support separate from the concrete at the bottom of the upper crossbeam; then use the steel wire ropes of the two tower cranes on the left and right sides of the main bridge to hang the Bailey beam and move the support as a whole outward. After it is moved to the bottom of the beam, it can be lowered as a whole to the 0# and 1# blocks for removal. Finally, remove the unloading block and steel bracket at the bottom of the distribution beam.

2. The special construction method for the cross beam on the main bridge tower column of the bridge according to claim 1 is characterized by: In the step S1, the support preloading observation contents include: the settlement difference between the two observations before and after, the elastic deformation of the support and the inelastic deformation of the support, the vertical settlement deformation of the support after loading is observed with a level, and the displacement deformation of the support is observed with a total station. Before preloading, a group of observation points are set on the bottom mold near the tower end along the longitudinal left and right sides of the support, and each group of observation points is symmetrically arranged with 3 points. A thin iron wire with good strength and straightness is found to hang vertically on the observation point, and a measuring station is set on the ground to observe the elevation of the mark on the vertical wire.

3. The special construction method for the cross beam on the main bridge tower column of the bridge according to claim 1 is characterized by: In the step S3, the material is cut by a grinding wheel, and electric welding or oxygen is not allowed. Before cutting the steel strands, they are first tied at 3 to 5 cm on both ends of the cutting line to prevent them from being scattered after cutting. During the cutting process of the steel strands, they are evenly arranged, combed into bundles, and marked one by one. Since the holes of the steel strands are different, their lengths are also different. They should be numbered and marked with the cutting length in advance. The handover team cuts the material accordingly, and the numbers are marked at both ends to avoid mixing. The cutting length of the steel strands is based on the design drawing, and the working length of the tensioning end is considered. When the design does not determine the cutting length, it is calculated according to the following formula and corrected after trial use: L=L0+2L1+n(L2+L3)+2L4 Where: L——cut-off length of steel strand (mm) L0——Length of pipe between anchor support plates (mm) L1——Working anchor thickness (mm) L2——Length of tensioning jack (mm) L3——Working anchor thickness (mm) L4——Length margin (mm) (100mm is acceptable) N: 1 for single-end tensioning and 2 for two-end tensioning.

4. The special construction method for the cross beam on the main bridge tower column of the bridge according to claim 1 is characterized by: In the step S4, the upper beam body concrete is vibrated by an inserted vibrator, and an experienced concrete worker is assigned to be responsible for it. When operating the inserted vibrator, it is advisable to "insert quickly and pull out slowly". The moving distance of the inserted vibrator shall not exceed 1.5 times of its effective radius, and a distance of 5 to 10 cm should be maintained with the side form. The inserted vibrator is inserted into the lower concrete for about 5 to 10 cm, and all parts are vibrated and compacted. The sign of compaction is that the concrete stops sinking, no more bubbles are emitted, the surface is flat, and the slurry is overflowing; first, the material is cut from the chamfer of the web of the beam, and through The web and bottom plate vibrate the concrete, and the concrete flows into the bottom plate through the web. When the web concrete height exceeds the bottom plate thickness by not less than 30cm and is confirmed to be compacted, the web vibration is stopped, and the delivery pump is used to directly pump concrete to the bottom plate of the crossbeam until the bottom plate concrete pouring is completed; the discharge port of the pump truck is equipped with 5 vibrators. When pouring the web concrete, because the slump of the pumped concrete is relatively large, it is expected to flow obliquely about 1 meter at the bottom plate. At this time, 2 vibrators are arranged on the bottom plate, which are mainly responsible for the concrete at the chamfer flow. Vibration. The other three vibrators are mainly responsible for the vibration of the web concrete. When the concrete is poured, it is layered with about 30cm per layer. The concrete pouring should be carried out continuously, and the interval time shall not exceed 2.5h. When the bottom plate concrete pouring is completed and the web concrete is poured, the vibrator should not be inserted too deep to avoid disturbing the bottom plate concrete and causing the web concrete to flip out of the bottom plate. If such a situation occurs, the web concrete should be re-vibrated. The bubbling concrete should be processed after the concrete pouring is completed to avoid the continued loss of web concrete and the appearance of defects such as grooves and holes due to premature removal. When the concrete surface hardens to the point where people can walk on it, the top surface of the beam is smoothed and finished. Since it takes about 4 hours from the end of concrete pouring to the surface hardening to the point where people can walk on it, in case of strong wind, high temperature and dry climate, the concrete surface is very likely to crack. Timely covering with geotextile can prevent water evaporation and shrinkage cracks. After the concrete smoothing and finishing process is completed, the surface of the beam is covered with geotextile and sprinkled with water. The number of times the beam is sprinkled with water should be sufficient to keep the concrete surface moist.

5. The special construction method for the cross beam on the main bridge tower column of the bridge according to claim 1 is characterized by: In step S7, low-alkali silicate cement or low-alkali ordinary silicate cement (the admixture is only fly ash or slag), the strength grade of cement is 42.5Mpa, the C3A content in cement clinker should not be greater than 8%, and no lumps should be contained; water should not contain any components harmful to prestressed tendons or cement, and clean drinking water can be used; admixtures with low water content, good fluidity, minimum seepage and expansion properties should be used, and they should not contain chemical substances harmful to prestressed tendons or cement, and the amount of admixtures should be determined by experiments; the strength of the grouting slurry should meet the design requirements, and the compressive strength of the 40*40*160mm prism specimen after standard curing for 28 days should not be less than 50Mpa.

6. The special construction method for the cross beam on the main bridge tower column of the bridge according to claim 1 is characterized by: In step S9, during the dismantling process, all loosened rod accessories should be removed and transported away in time to avoid accidentally supporting or leaning on loosened rods. Parts that need to be reinforced during the dismantling operation should be reinforced before dismantling to prevent the frame from collapsing. The dismantled parts and rods should be transported to the ground in batches according to specifications. Throwing is strictly prohibited, and they should be neatly stacked according to specifications and varieties. The operators should respond to each other and coordinate their movements without changing personnel in the middle. When personnel must be changed, the dismantling situation should be explained in detail. It is prohibited for one person to perform dangerous operations such as dismantling heavy rods. During the entire dismantling process, a dedicated person must be in charge of command and supervision.

7. The special construction method for the cross beam on the main bridge tower column of claim 1 is characterized by: During the installation of the brackets, load-bearing beams, XT300 truss beams, etc., construction workers are required to strictly follow the safety operating procedures and wear personal protective equipment (safety helmets, safety belts, non-slip shoes). After the distribution beam is installed, a 48mm×2.7mm steel pipe is used to weld it to a whole at the cantilever, and then it is connected to the tower columns on both sides. A 1.2m high guardrail is erected, and a layer of waist bars is added at 60cm~80cm. The railing uprights are set at 3m each, and the guardrail is fully covered with a dense safety net. The construction load on the working layer and the working platform must meet the calculation requirements, and overloading is not allowed. Templates, steel bars and other materials must not be stacked together.