Construction method of Larsen steel sheet pile cofferdam diversion canal in narrow river channel

The Larsen steel sheet pile method for constructing diversion channels in narrow rivers offers a fast and efficient solution by using a single-row cantilever and double-row internally supported channels, enhancing stability and reducing environmental impact.

CN119061919APending Publication Date: 2024-12-03HENAN SEVEN CONSTR ENG GRP CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411442592.2
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-10-16
Publication Date
2024-12-03

AI Technical Summary

Technical Problem

Traditional construction methods for river channel projects in narrow channels face challenges such as poor stability, long construction periods, and significant environmental damage due to earth cofferdams, sandbag cofferdams, and river diversion.

Method used

A method utilizing Larsen steel sheet piles to construct a diversion channel with a single-row cantilever cofferdam and a double-row internally supported diversion channel, involving construction preparation, site clearing, steel sheet pile positioning, earthwork excavation, and concrete sealing, ensuring structural stability and efficient diversion.

Benefits of technology

The method provides a fast construction speed, high operational efficiency, reduces earthwork excavation, and minimizes land occupation while effectively diverting water, thus addressing the limitations of traditional methods.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119061919A_ABST
    Figure CN119061919A_ABST
Patent Text Reader

Abstract

The invention provides a narrow river channel Larsen steel sheet pile cofferdam diversion channel construction method, and relates to the technical field of wading engineering, the method adopts Larsen steel sheet piles to construct a cofferdam and a diversion channel, and through combination of a single-row cantilever steel sheet pile cofferdam and a double-row inner support steel sheet pile diversion open channel, river channel full-section closure and diversion are realized. The method is high in construction speed and efficient in operation, earth excavation and land occupation are reduced, and the diversion effect of the diversion channel is excellent.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of water-related engineering, and in particular to a construction method for a diversion channel of a Larsen steel sheet pile cofferdam in a narrow river. Background Art

[0002] At present, for urban water-related projects such as river channel flood control and drainage reconstruction projects, bridge projects, concrete sluice pump projects, etc., when the river channel is wide (greater than the width of the project structure), traditional construction methods include earth cofferdams, sandbag cofferdams, steel sheet pile cofferdams, steel pipe pile plus steel sheet pile cofferdams, river diversion, etc., to ensure the smooth progress of construction. These methods can better meet the construction needs when the river channel is wide (greater than the width of the project structure), but there are many limitations when the river channel is narrow (less than or equal to the width of the project structure). For example, the stability of earth cofferdams and sandbag cofferdams is poor and it is difficult to withstand long-term water impact; although the steel sheet pile cofferdam has good rigidity, it is difficult to form an effective supporting structure in a narrow river channel; river diversion requires large-scale excavation of the river embankment, which not only has a long construction period, but also causes great damage to the surrounding environment. Summary of the invention

[0003] The purpose of the present invention is to provide a method for constructing a diversion channel of a Larsen steel sheet pile cofferdam in a narrow river channel, so as to solve the technical problems in the prior art of long construction period and great damage to the surrounding environment.

[0004] In order to solve the above problems, the present invention relates to a narrow river channel Larsen steel sheet pile cofferdam diversion channel construction method adopts the following technical solutions: The invention provides a method for constructing a narrow river channel Larsen steel sheet pile cofferdam diversion channel, which comprises at least the following steps: Construction preparation: comprehensively organize construction preparation work, including technical preparation and site preparation, according to the design requirements of the construction drawings, geological conditions, hydrological conditions and on-site construction environment; Bank and river clearing: Clean up the construction site and construction material storage area, remove surface obstacles, and provide a clean and safe working environment for subsequent construction activities; Positioning and setting out: Use total station and level to measure and record the original surface of the diversion channel. According to the design and construction requirements, measure the location line of the Larsen steel sheet pile in the river or water area and mark it with markers; Steel sheet pile construction: The Larsen steel sheet piles are driven into the pre-determined depth one by one by using the vibration method to form the side walls of the cofferdam and the diversion channel. Grease is applied to the locking mouth of the steel sheet piles to prevent the entry of mud and ensure the verticality and position accuracy of the steel sheet piles. Angle steel is used for welding at the corners of the steel sheet piles. Earthwork excavation: Earthwork excavation is carried out between the two side walls of the diversion channel, following the principle of excavation from top to bottom and in layers, until the channel bottom elevation required by the design is reached; Steel sheet pile purlin and support construction: Steel purlins are set at the ends of the steel sheet piles, and steel supports are set between the purlins to enhance the structural stability of the cofferdam and diversion channel; Concrete bottom slab sealing of diversion channel: Lay graded crushed stone on the bottom of the excavated diversion channel and compact it, then pour concrete bottom slab on it to ensure that the surface of the bottom slab concrete is flat, smooth and dense; Backfilling of single-row cantilever steel sheet pile cofferdam: Use the soil excavated from the diversion channel to backfill the side of the cofferdam away from the river flow. Before backfilling, the on-site water should be removed, and the silt, humus, weeds and tree roots should be removed, and the soil should be rolled and compacted in layers; Inspection and acceptance: After the construction of diversion open channels and river interception cofferdams is completed, inspection and acceptance will be carried out to ensure that the construction quality meets the design requirements; Demolition, backfilling and restoration: After the construction is completed, the cofferdam will be dismantled, and the double-row internal support steel sheet pile open channel and single-row cantilever steel sheet pile cofferdam will be backfilled and restored in layers.

[0005] Preferably, earth excavation should follow the principle of layered excavation. When the excavation approaches the designed channel bottom, the reserved protective layer should be manually trimmed.

[0006] Preferably, the steel perimeter purlin is made of H-shaped steel, the steel support is made of H-shaped steel, and the steel support and the steel perimeter purlin are welded.

[0007] Preferably, C20 plain concrete is used for the concrete bottom seal, and the pouring speed and vibration frequency should be strictly controlled to ensure the quality of the concrete.

[0008] Preferably, technical preparation includes design optimization plan, determination of material specifications and quantity, preparation of special construction plan for cofferdam diversion open channel, emergency plan, technical briefing for construction personnel, and site preparation includes investigation of underground pipelines, preparation of facilities, purchase of materials and equipment, setting up safety warning signs, appearance inspection of incoming steel sheet piles, material inspection and taking corrective measures.

[0009] Preferably, in the backfill of double-row internally supported steel sheet piles in the open channel, the moisture content of the backfill material is required to be such that it can be held in a ball by hand and fall to the ground. When the moisture content is too high, measures such as loosening, drying, and adding dry soil should be taken. If the backfill soil is too dry, it should be sprinkled with water to moisten it. The backfill should be carried out in layers, and the thickness of each layer should not exceed 300mm. It should be spread and leveled mechanically in layers, and compacted by vibration with a roller.

[0010] The beneficial effects of the present invention are as follows: The invention provides a method for constructing a narrow river channel Larsen steel sheet pile cofferdam diversion channel, which is different from the prior art in that Larsen steel sheet piles are used to construct the cofferdam and diversion channel, and the whole section of the river channel is intercepted and diverted by combining a single row of cantilever steel sheet pile cofferdam and a double row of inner support steel sheet pile diversion open channel. The method has fast construction speed, high operation efficiency, reduces earthwork excavation and land occupation, and has excellent diversion effect of the diversion channel. BRIEF DESCRIPTION OF THE DRAWINGS

[0011] In order to more clearly illustrate the technical solution of the embodiment of the present invention, the following briefly introduces the drawings required for use in the embodiment: Figure 1 It is a flow chart of a method for constructing a diversion channel of Larsen steel sheet pile cofferdam in a narrow river; Figure 2 This is a cross-sectional view of a single-row cantilever steel sheet pile cofferdam; Figure 3 This is a cross-section of a double-row internally supported steel sheet pile diversion open channel; Figure 4 It is the layout diagram of river channel construction; Figure 5 for Figure 4 A simple diagram of the.

[0012] In the figure: 1. Canal water; 2. River channel; 3. Single-row cantilever steel sheet pile cofferdam; 4. Double-row internally supported steel sheet pile diversion open channel. DETAILED DESCRIPTION

[0013] In order to make the technical purpose, technical solution and beneficial effects of the present invention more clear, the technical solution of the present invention is further described below in conjunction with the accompanying drawings and specific embodiments.

[0014] This embodiment takes the canal water flowing from west to east, connected to the river channel in the east, and the river water flowing from south to north as an example. The present invention provides a narrow river channel Larsen steel sheet pile cofferdam diversion channel construction method, which at least includes the construction of a diversion open channel (double-row internally supported steel sheet pile diversion open channel) and a river channel interception cofferdam (single-row cantilever steel sheet pile cofferdam) to build a stable waterless construction environment in the river channel. The single-row cantilever steel sheet pile cofferdam is located in the canal, and a single-row unsupported Type III Larsen steel sheet pile is used on the water-facing surface for full-section interception. The steel sheet pile back surface uses earth excavated from the foundation of the under-construction project as a cofferdam to resist the positive pressure caused by the canal water impacting the steel sheet piles, and at the same time serves as a temporary road and construction site at the construction site. The double-row internally supported steel sheet pile diversion channel is arranged on the north bank of the canal, outside the project under construction. The diversion channel consists of double-row Larsen steel sheet piles and steel internal supports. After the steel sheet piles are driven, the earthwork inside the steel sheet piles is excavated and transported out to form a diversion channel to divert the intercepted water in the canal to the river. A concrete base plate is poured at the bottom of the canal to prevent the river water from scouring and carrying away the soil. Specifically, it includes: 1. Construction preparation: Before the construction of steel sheet piles, the construction preparation work should be comprehensively organized according to the design requirements of the construction drawings, geological conditions, hydrological conditions and on-site construction environment, including technical preparation, site preparation, material delivery and acceptance.

[0015] Technical preparation: According to the geological and hydrological conditions of the construction area, make an optimized design plan for the Larsen steel sheet pile cofferdam diversion construction; according to the survey results and project requirements, design the specifications, length, quantity of Larsen steel sheet piles, as well as the size and layout of the cofferdam and diversion channel; prepare special construction plans and emergency plans for the cofferdam diversion open channel, and conduct technical briefings for construction personnel to ensure that they understand the construction requirements, operating specifications and safety precautions; prepare quality certification documents, quality inspection reports, construction process tests and other reference materials for related materials and their products.

[0016] Site preparation: Investigate underground pipelines, existing structures, dangerous buildings, etc. in the construction site and adjacent areas; prepare related facilities such as water supply, power supply, roads, drainage, and material yards required for construction; purchase Larsen steel sheet piles, connectors, reinforcements and other materials that meet the design requirements, and prepare mechanical equipment required for construction, such as vibratory hammers, excavators, cranes, etc.; set up necessary safety warning signs and protective facilities to ensure construction safety.

[0017] Material delivery and acceptance: Check the appearance and material quality of the steel sheet piles delivered to the site, and take relevant corrective measures. Steel sheet piles may be rusted, bruised, bent, twisted, or deformed during loading, unloading, and transportation. Steel sheet piles that do not meet the requirements will be replaced or processed.

[0018] Clearing of embankments and river channels: Clean up construction sites, steel sheet piles and other material storage areas, remove surface obstacles, including tree stumps, tree roots and planting soil layers within the excavation project area, to provide a clean and safe working environment for subsequent construction activities and ensure smooth construction.

[0019] Positioning and setting out: Use total station and level to measure and set out the original surface of the diversion channel and keep records. The measurement records and results will be sent to the supervision engineer for review and signature. According to the design and construction requirements, the location line of the Larsen steel sheet pile is measured in the river or water area. The measurement and setting out are carried out according to the conventional method and marked with white lime or other markers.

[0020] Steel sheet pile construction: Larsen steel sheet piles are used. According to the design requirements and the depth of soil penetration on site, the steel sheet piles are driven by vibration method, and the single piles are driven one by one. Before starting piling, check the steel sheet piles one by one, remove the steel sheet piles with rusted and severely deformed connection locks, and replace or correct the unqualified steel sheet piles; seal the bottom of the steel sheet pile groove, and apply butter or other grease to the lock to prevent soil from entering. After the pile driver is in place, transport the steel sheet piles to the vicinity of the river, fix the top of the steel sheet pile with the pile driver's vibrating hammer, and lift the steel sheet pile as a whole. When lifting the steel sheet pile off the ground, pay attention to avoid hitting the adjacent pile body. After the pile is lifted, stabilize the pile body, first align the pile with the pile position, straighten the pile body, use the deadweight to insert it along the lock, and then measure and observe the verticality and plane position of the steel sheet pile. At the beginning of piling, increase the vibration force appropriately and gradually increase it to the specified value. After meeting the requirements, turn on the vibrating hammer to vibrate while inserting and sinking, and then insert the pile into the soil. The verticality deviation of the pile shall not exceed 1%. After the pile is in place, the center line of the vibrating hammer and the pile body should be on the same axis to avoid eccentricity. When inserting and driving steel sheet piles, the first steel sheet pile must be inserted and driven straight to avoid affecting the subsequent steel sheet piles. Use a level to control the elevation of the pile top. The subsequent steel sheet piles should refer to the elevation of the previous pile. The elevation of the pile top should be checked with a level every 10 meters. Verticality should be observed during the entire piling process, and any problems should be corrected in time. The allowable tolerance for the deviation of the steel sheet pile axis is ±100mm, the allowable tolerance for the pile top elevation is ±100mm, and the allowable tolerance for the verticality of the sheet pile is 1% The backwater surface of the steel sheet piles in the single-row cantilever steel sheet pile cofferdam and the double-row internal support steel sheet pile diversion open channel is supported by backfill soil and original soil. The lock mouth does not need to be treated and water seepage is not considered. During the pile driving construction of the pile driver, if there are special circumstances, once the Larsen steel sheet pile is found to be damaged or deformed, the driving should be stopped immediately, the cause should be found out in time, and the damaged steel sheet pile should be replaced or repaired to ensure the integrity of the cofferdam steel sheet pile and the quality of the lock bite. The steel sheet piles are welded with angle steel at the corners to enhance the structural stability and connection strength at the corners. Before welding, the angle steel should be accurately located at the corner to ensure that its contact surface with the steel sheet pile is flat and aligned. Temporary fixtures or supports can be used to fix the angle steel in the predetermined position for subsequent welding work. After welding, the weld needs to be cleaned and polished to remove welding slag and spatter to make the weld surface flat and smooth.

[0021] Construction of internal support steel sheet pile diversion open channel: Earth excavation can only be carried out after the construction of Larsen steel sheet pile is completed. Earth excavation should be carried out strictly in accordance with the special construction plan, following the principle of top-to-bottom and layered excavation. Excavation should be carried out by excavator. The lower earth excavation can be carried out only after the excavated part is manually trimmed. When the earth excavation is close to the designed channel bottom, a 10-20cm thick protective layer is reserved for manual trimming until the required slope and flatness are reached to ensure the quality of earth excavation construction. During the excavation process, check the soil and bottom conditions on both sides of the steel sheet piles at any time, and take timely measures to deal with any abnormal conditions.

[0022] Steel sheet pile purlin and support construction: The setting of steel purlin and support is a key step to ensure the stability and bearing capacity of the structure. The steel purlin bracket is made of I-beam, and a steel purlin is set at the downward position of the ends of the steel sheet piles on both sides. For the installation of steel sheet pile purlin, first weld the purlin bracket below the purlin installation position. The purlin bracket is made of I-beam, and then hang the purlin steel on the purlin bracket. For the installation of steel supports, the spacing of steel supports is 4 meters and evenly distributed. The first steel support of the purlin is arranged at a downward position from the end. For the connection of steel supports, first weld two anti-fall steel bars at both ends along the flange on the same side of the H-shaped steel of the steel support. The anti-fall steel bars are placed above the H-shaped steel of the purlin. The steel support and the steel purlin are connected together by welding to form a stable support system. The quality of the weld should be ensured during the welding process to avoid defects such as cracks and slag inclusions.

[0023] Concrete bottom slab sealing of diversion channel: After the excavation of diversion open channel is completed, use light roller to compact the original soil at the bottom of the channel, and then lay 20cm thick graded crushed stone. After leveling and compacting, pour 20cm thick C20 plain concrete bottom slab on it. The pouring speed and vibration frequency of concrete should be strictly controlled to ensure the quality of concrete. The surface of bottom slab concrete should be smooth, dense, and without defects such as honeycomb surface.

[0024] Backfill of earthwork for single-row cantilever steel sheet pile cofferdam: The backfill of earthwork uses the soil excavated from the dam foundation. Before backfilling, the water on site should be removed, and the silt, humus, weeds and tree roots should be cleared. The backfill soil should not contain garbage, large stones and other debris. The moisture content of the backfill soil should be controlled within an appropriate range, and it is appropriate to hold it in a ball and fall to the ground. The backfill of earthwork should be rolled and compacted in layers, and the thickness of each layer should not exceed 300mm. After the layers are spread and leveled, a flat roller should be used for backfilling and compaction. The method of "thin filling, slow driving, and multiple times" should be adopted. The rolling and laying should be gradually from both sides to the middle. The overlapping width of the roller each time is about 15~25cm. The corners and slope edges that cannot be compacted should be supplemented by manpower. After the backfill is completed, use a spirit level to level the backfill to ensure that the surface flatness meets the design requirements and that it meets the requirements for temporary roads and work areas planned for the construction site. During the leveling and compaction process, check whether the drainage measures are in place to ensure that there is no water accumulation in the backfill, so as not to affect the density and stability of the backfill.

[0025] Inspection and acceptance: After the construction of the diversion channel and cofferdam is completed, timely inspection and acceptance should be carried out. The construction quality should meet the design requirements to ensure the safety and stability of the project. Things to note for acceptance: 1. Strictly follow the requirements of construction drawings, design documents and relevant standards and specifications. 2. Be comprehensive and meticulous, leaving no blind spots, to ensure that every detail meets the quality requirements. 3. If any problems are found during the inspection, they should be recorded in time and notified to the relevant subcontractors for processing.

[0026] Dismantling, backfilling and restoration: After the integrated gate pump is completely constructed, the cofferdam is dismantled, and the double-row internal support steel sheet pile open channel and the single-row cantilever steel sheet pile cofferdam are backfilled and restored in layers.

[0027] Larsen steel sheet pile removal: Use a 90 vibration hammer to pull out the piles. The pulling method is: first clamp the head of the steel sheet pile with a vibration hammer and vibrate for 1min~2min to loosen the soil around the steel sheet pile, produce "liquefaction", destroy the cohesion of the soil around the steel sheet pile to overcome the resistance to pile pulling, and then slowly vibrate upwards and pull it out with the help of the additional lifting force of the crawler crane. Before pulling out the steel sheet piles, all welded connections between the steel sheet piles should be removed, and the sequence of pile pulling methods, pile pulling time and soil hole treatment should be carefully studied according to the construction conditions of each steel sheet pile. Pay attention to the impact of vibration when pulling out piles, which may cause ground settlement and displacement; Double-row inner support steel sheet pile open channel backfill: earthwork backfill should first remove garbage on the base, remove stagnant water, silt and impurities, and take corresponding measures to prevent surface stagnant water from flowing into the filling area; the water content of the filling material should be such that it can be held in a ball and fall to the ground. When the water content is too high, measures such as loosening, drying, and mixing with dry soil should be taken; if the backfill soil is too dry, it should be sprinkled with water to moisten it. Earthwork backfill should be carried out in layers, and the virtual paving thickness of each layer should not exceed 300mm. It should be mechanically paved and leveled in layers, and vibrated and compacted by a 10t roller. After the backfill operation is completed, it will be repaired, mainly based on the existing river type and river flow, and the existing mortar stone protection on both sides of the river channel will be maintained. The earthwork on the backwater surface of the single-row cantilever steel sheet pile cofferdam is excavated and transported. The earthwork excavation method is carried out according to the conventional method. After the earthwork excavation is completed, the damaged dry stone bottom protection at the bottom of the West Main Canal will be repaired.

[0028] Finally, it should be noted that the above embodiments are only used to illustrate but not to limit the technical solutions of the present invention. Any equivalent substitutions of the present invention and any modifications or partial substitutions that do not depart from the spirit and scope of the present invention should be included in the scope of protection of the claims of the present invention.

Claims

1. A method for constructing a diversion channel for Larsen steel sheet pile cofferdam in a narrow river, characterized in that: At least the following steps are included: Construction preparation: comprehensively organize construction preparation work, including technical preparation and site preparation, according to the design requirements of the construction drawings, geological conditions, hydrological conditions and on-site construction environment; Bank and river clearing: Clean up the construction site and construction material storage area, remove surface obstacles, and provide a clean and safe working environment for subsequent construction activities; Positioning and setting out: Use total station and level to measure and record the original surface of the diversion channel. According to the design and construction requirements, measure the location line of the Larsen steel sheet pile in the river or water area and mark it with markers; Steel sheet pile construction: The Larsen steel sheet piles are driven into the pre-determined depth one by one by using the vibration method to form the side walls of the cofferdam and the diversion channel. Grease is applied to the locking mouth of the steel sheet piles to prevent the entry of mud and ensure the verticality and position accuracy of the steel sheet piles. Angle steel is used for welding at the corners of the steel sheet piles. Earthwork excavation: Earthwork excavation is carried out between the two side walls of the diversion channel, following the principle of excavation from top to bottom and in layers, until the channel bottom elevation required by the design is reached; Steel sheet pile purlin and support construction: Steel purlins are set at the ends of the steel sheet piles, and steel supports are set between the purlins to enhance the structural stability of the cofferdam and diversion channel; Concrete bottom slab sealing of diversion channel: Lay graded crushed stone on the bottom of the excavated diversion channel and compact it, then pour concrete bottom slab on it to ensure that the surface of the bottom slab concrete is flat, smooth and dense; Backfilling of single-row cantilever steel sheet pile cofferdam: Use the soil excavated from the diversion channel to backfill the side of the cofferdam away from the river flow. Before backfilling, the on-site water should be removed, and the silt, humus, weeds and tree roots should be removed, and the soil should be rolled and compacted in layers; Inspection and acceptance: After the construction of diversion open channels and river interception cofferdams is completed, inspection and acceptance will be carried out to ensure that the construction quality meets the design requirements; Demolition, backfilling and restoration: After the construction is completed, the cofferdam will be dismantled, and the double-row internal support steel sheet pile open channel and single-row cantilever steel sheet pile cofferdam will be backfilled and restored in layers.

2. The method for constructing a narrow river channel Larsen steel sheet pile cofferdam diversion channel according to claim 1, characterized in that: Earth excavation should follow the principle of layered excavation. When the excavation approaches the designed channel bottom, the reserved protective layer should be manually trimmed.

3. The method for constructing a narrow river channel Larsen steel sheet pile cofferdam diversion channel according to claim 2 is characterized in that: The steel perimeter purlin is made of H-shaped steel, the steel support is made of H-shaped steel, and the steel support and the steel perimeter purlin are welded.

4. A method for constructing a narrow river channel Larsen steel sheet pile cofferdam diversion channel according to claim 3, characterized in that: The concrete bottom seal uses C20 plain concrete, and the pouring speed and vibration frequency should be strictly controlled to ensure the quality of the concrete.

5. The method for constructing a narrow river channel Larsen steel sheet pile cofferdam diversion channel according to claim 4 is characterized in that: Technical preparation includes design optimization plan, determination of material specifications and quantity, preparation of special construction plan for cofferdam diversion channel, emergency plan, technical briefing for construction personnel, and on-site preparation includes investigation of underground pipelines, preparation of facilities, purchase of materials and equipment, setting up safety warning signs, appearance inspection of incoming steel sheet piles, material inspection and taking corrective measures.

6. The method for constructing a narrow river channel Larsen steel sheet pile cofferdam diversion channel according to claim 1, characterized in that: In the backfill of open channel with double-row internally supported steel sheet piles, the moisture content of the backfill material is required to be able to be held in a ball by hand and to fall to the ground and bloom. When the moisture content is too high, measures such as loosening, drying and adding dry soil should be taken. If the backfill soil is too dry, it should be sprinkled with water to moisten it. The backfilling of soil should be carried out in layers. The thickness of each layer should not exceed 300mm. It should be spread and leveled in layers by machinery and compacted by vibration with a roller.