Pouring equipment for underground garage building construction joint treatment
The pouring device automates hole drilling and pipe insertion in underground garage construction joints, addressing operational complexity and dust interference, enhancing the grouting process efficiency and convenience.
Patent Information
- Application Number
- CN202411342818.1
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-09-25
- Publication Date
- 2024-12-03
- Estimated Expiration
- 2044-09-25
AI Technical Summary
Existing grouting devices for underground garage construction joints are cumbersome to operate, often leading to improper fixation of grouting heads, which affects the grouting process due to manual twisting, and generate dust that can interfere with the drilling process.
A pouring device equipped with a drill bit, servo motors, and a cleaning brush that automates hole drilling and pipe insertion, includes a dust discharge system, and ensures proper pipe fixation without manual tools, utilizing servo motors and a mechanism for adjusting dust discharge direction.
The device facilitates convenient and efficient hole drilling and pipe fixation, effectively managing dust discharge, thereby simplifying the grouting process and ensuring proper pipe placement within underground garage construction joints.
Smart Images

Figure CN119061952A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of seam treatment, in particular to a pouring device for treating construction seams of underground garage buildings. Background Art
[0002] As underground garages are used for a longer time, they are prone to cracks. These cracks may become larger over time, which has a greater impact on the overall strength of the building. This requires timely repair of the cracks. Most existing grouting devices use viscous grouting to repair. When grouting, it is necessary to first drill a hole in the crack area, then insert the grouting head into the hole, and use a wrench to twist the grouting head to fix it. The operation steps are relatively cumbersome. Manually twisting the grouting head can easily cause the grouting head to not be fixed in place, affecting the subsequent grouting work. Summary of the invention
[0003] In view of the deficiencies in the prior art, the present invention provides a pouring device for treating construction joints in underground garage buildings, which solves the problems raised in the above-mentioned background technology.
[0004] To achieve the above objectives, the present invention is implemented through the following technical solutions: a pouring device for treating construction joints in underground garages, comprising a working box, a storage chamber is provided inside the working box, a first screw is rotatably connected to the bottom of the inner cavity of the storage chamber, a moving block is threadedly connected to the outer side of the first screw, a second servo motor is fixedly connected to the top of the moving block, an output end of the second servo motor extends to the bottom of the moving block and is fixedly connected to a drill bit, a through hole is provided at the bottom of the working box, a fixing ring is fixedly connected to the bottom of the working box, a cleaning brush is fixedly connected to the inside of the fixing ring, a stopper is slidably connected to the outside of the fixing ring, a side groove is provided on one side of the stopper, and the fixing ring has a side groove inside. An annular groove is provided on the outer side of the cleaning brush, an annular plate is slidably connected inside the annular groove, the top of the annular plate is fixedly connected with a gear ring, the bottom of the annular plate and the inside of the stop sleeve are fixedly connected with a plurality of pushing fan blades, a connecting rod is rotatably connected inside the annular groove, a transmission gear matching with the gear ring is fixedly sleeved on the outer side of the connecting rod, a transmission cavity is provided inside the working box and below the storage cavity, the bottom end of the first screw rod extends into the transmission cavity, the top end of the connecting rod extends into the transmission cavity and is rotatably connected with the top of the inner cavity of the transmission cavity, a one-way bearing is provided on the outer side of the first screw rod, and pulleys connected by belt drive are fixedly sleeved on the one-way bearing and the outer side of the connecting rod.
[0005] Optionally, the stop sleeve is fixedly connected with two fixed boxes, each of which is rotatably connected to a ball screw, each of which is threadedly connected to an insert block, and a plurality of slots are provided on the outside of the fixing ring, one end of each insert block extends into the corresponding slot, and one end of each ball screw extends to the outside of the fixed box.
[0006] Optionally, a connecting groove is provided inside the working box and below the storage cavity, a third servo motor is fixedly connected to one side of the inner cavity of the connecting groove, a threaded rod is rotatably connected to the other side of the inner cavity of the connecting groove, an output end of the third servo motor is fixedly connected to one end of the threaded rod, a connecting block is threadedly connected to the outer side of the threaded rod, and a fixing frame is fixedly connected to one side of the connecting block.
[0007] Optionally, a fourth servo motor is fixedly connected to the bottom above the fixed frame, and the output end of the fourth servo motor is fixedly connected to a rotating column, and a plurality of guide rails are fixedly connected to the outside of the rotating column, and fixed blocks are slidably connected to the inside of the guide rails, and the bottom of the inner cavity of the guide rails is fixedly connected to a supporting spring, and the top of the supporting spring is fixedly connected to the bottom of the fixed block, one end of the fixed block extends to the outside of the guide rail and is fixedly connected to a fixing sleeve, and electric telescopic rods are fixedly connected to both sides of the fixing sleeve, and the telescopic ends of the electric telescopic rods extend to the inside of the fixing sleeve and are fixedly connected to clamping blocks, an injection tube is placed inside the fixing sleeve, and an installation sleeve is provided on the outside of the fixing sleeve, and the top of the injection tube extends to the top of the fixing sleeve, and the outside of the injection tube is fixedly connected to a threaded sleeve, and the outside of the threaded sleeve is threadedly connected to a threaded cover.
[0008] Optionally, a liquid cavity is provided inside the mounting sleeve, a plurality of liquid holes are provided on the outside of the mounting sleeve, the liquid holes are communicated with the inside of the liquid cavity, an annular cavity is provided inside the fixing sleeve, an elastic tube is fixedly connected to one side of the clamping block, one end of the elastic tube extends to the inside of the annular cavity, the other end of the elastic tube extends to one side of the clamping block and is fixedly connected to a plug, a connector is fixedly connected to the inside of the mounting sleeve, one end of the plug is inserted into the inside of the connector, and the other end of the connector extends to the inside of the liquid cavity.
[0009] Optionally, one end of the fixed block extends to the outside of the guide rail, the outside of the rotating column and on one side of the guide rail are fixedly connected to a piston cylinder, the inside of the piston cylinder is slidably connected to a piston block, the top of the piston block extends to the top of the piston cylinder and is fixedly connected to a pressure block, the outside of the piston block is movably sleeved with a connecting spring, the bottom end of the connecting spring is fixedly connected to the top of the piston cylinder, the top of the connecting spring is connected to the bottom of the pressure block, the bottom of the piston cylinder is fixedly connected to a suction head, the bottom ends of several of the suction heads are fixedly connected to a connecting pipe, one side of the piston cylinder is fixedly connected to a pipeline, one end of the pipeline extends to the inside of the rotating column, the other end of the rotating column is connected to the inside of the annular cavity through a hose, the pipeline and one end of the suction head extend to the inside of the piston cylinder and are provided with a one-way valve.
[0010] Optionally, a liquid tank is fixedly connected to the bottom of the connecting block, one end of the connecting pipe extends into the interior of the liquid tank, a liquid inlet valve is fixedly connected to one side of the liquid tank, one end of the liquid inlet valve passes through the connecting block and through a side hole opened on the working box to extend to the outside of the working box, and the outside of the connecting pipe is rotatably connected to the inside of the liquid tank.
[0011] Optionally, a handle is fixedly connected to one side of the work box, a controller is fixedly connected to the top of the handle, a first servo motor is fixedly connected to the top of the inner cavity of the storage chamber, an output end of the first servo motor is fixedly connected to the top of the first screw rod, and the diameter of the threaded cover matches the inner diameter of the through hole and the cleaning brush.
[0012] The present invention provides a pouring device for treating construction joints in underground garage buildings, which has the following beneficial effects: 1. The injection equipment for treating construction joints of underground garage buildings is equipped with an injection pipe, a drill bit and a second servo motor. The equipment can automatically drill holes, bury pipes and fix the pipes inside the holes, making injection more convenient. The pipes are fixed inside the holes by glue, and the staff does not need to use tools to fix the pipes, making the equipment easy to use.
[0013] 2. The grouting equipment used for treating construction joints of underground garage buildings is equipped with a pushing fan blade, a baffle sleeve and a side groove, which can discharge the dust generated by the drill bit when drilling holes on the ground, and prevent the dust from entering the drill hole and affecting the connection between the drill hole and the pipeline. The direction of the side groove and the baffle sleeve can be adjusted according to multiple locations where holes need to be drilled, so that the position for discharging dust can be adjusted, making the use of this equipment more convenient. BRIEF DESCRIPTION OF THE DRAWINGS
[0014] Figure 1 It is a schematic diagram of the internal structure of the present invention; Figure 2This is a schematic diagram of the internal structure of the retaining sleeve of the present invention from a top view; Figure 3 This is a schematic diagram of the structure of the connection between the clamp block and the injection pipe of the present invention; Figure 4 For the present invention Figure 1 A magnified image of point A; Figure 5 For the present invention Figure 1 The enlarged view of point B; Figure 6 For the present invention Figure 1 Enlarged view of point C.
[0015] In the figure: 1, working box; 2, storage chamber; 3, first servo motor; 4, first screw rod; 5, moving block; 6, second servo motor; 7, drill bit; 8, through hole; 9, cleaning brush; 10, fixing ring; 11, stopper sleeve; 12, annular groove; 13, pushing fan blade; 14, side groove; 15, annular sheet; 16, gear ring; 17, connecting rod; 18, transmission gear; 19, transmission chamber; 20, pulley; 21, one-way bearing; 22, fixing box; 23, ball screw; 24, plug block; 25, slot; 26, third servo motor; 27, threaded rod; 28, connecting block; 29, fixing frame; 3 0. Through slot; 31. Fourth servo motor; 32. Rotating column; 33. Guide rail; 34. Fixed block; 35. Support spring; 36. Fixed sleeve; 37. Electric telescopic rod; 38. Clamp block; 39. Liquid injection pipe; 40. Mounting sleeve; 41. Plug; 42. Connector; 43. Liquid chamber; 44. Liquid hole; 45. Annular chamber; 46. Pipeline; 47. Piston cylinder; 48. Piston block; 49. Pressing block; 50. Connecting spring; 51. Suction head; 52. Connecting pipe; 53. Liquid tank; 54. Liquid inlet valve; 55. Elastic tube; 56. Threaded cover; 57. Threaded sleeve; 58. Connecting slot; 59. Handle. DETAILED DESCRIPTION
[0016] The technical solutions in the embodiments of the present invention will be described clearly and completely below in conjunction with the drawings in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, rather than all the embodiments.
[0017] Embodiment 1 See also Figures 1 to 6The present invention provides a technical solution: a pouring device for treating construction joints of underground garage buildings, comprising a working box 1, a storage chamber 2 is provided inside the working box 1, a first screw rod 4 is rotatably connected to the bottom of the inner cavity of the storage chamber 2, a moving block 5 is threadedly connected to the outer side of the first screw rod 4, a second servo motor 6 is fixedly connected to the top of the moving block 5, an output end of the second servo motor 6 extends to the bottom of the moving block 5 and is fixedly connected to a drill bit 7, a through hole 8 is provided at the bottom of the working box 1, a fixing ring 10 is fixedly connected to the bottom of the working box 1, a cleaning brush 9 is fixedly connected to the inside of the fixing ring 10, a stopper sleeve 11 is slidably connected to the outside of the fixing ring 10, a side groove 14 is provided on one side of the stopper sleeve 11, and an annular groove 1 is provided inside the fixing ring 10 and outside the cleaning brush 9 2, an annular plate 15 is slidably connected inside the annular groove 12, a gear ring 16 is fixedly connected to the top of the annular plate 15, a plurality of push blades 13 are fixedly connected to the bottom of the annular plate 15 and located inside the stopper sleeve 11, a connecting rod 17 is rotatably connected inside the annular groove 12, a transmission gear 18 matched with the gear ring 16 is fixedly sleeved on the outer side of the connecting rod 17, a transmission chamber 19 is opened inside the working box 1 and located below the storage chamber 2, the bottom end of the first screw rod 4 extends into the transmission chamber 19, the top end of the connecting rod 17 extends into the transmission chamber 19 and is rotatably connected to the top of the inner cavity of the transmission chamber 19, a one-way bearing 21 is arranged on the outer side of the first screw rod 4, and a pulley 20 connected by a belt drive is fixedly sleeved on the outer side of the one-way bearing 21 and the connecting rod 17.
[0018] Preferably, the retaining sleeve 11 is fixedly connected with two fixed boxes 22, and the fixed boxes 22 are rotatably connected with ball screws 23 inside, and the outer sides of the ball screws 23 are threadedly connected with plug blocks 24. A plurality of slots 25 are opened on the outer side of the fixing ring 10, and one end of the plug blocks 24 extends to the corresponding slots 25, and one end of the ball screws 23 extends to the outer side of the fixed box 22. When it is necessary to adjust the direction of dust discharge, the operator rotates the ball screw 23 so that the ball screw 23 drives one end of the plug block 24 to move out of the slot 25, and then rotates the retaining sleeve 11 to adjust the direction of the side groove 14. Then the operator resets and rotates the ball screw 23 so that the ball screw 23 drives one end of the plug block 24 to insert into the slot 25, thereby limiting and fixing the position of the retaining sleeve 11 and the position of the side groove 14.
[0019] Preferably, a connecting groove 58 is opened inside the working box 1 and below the storage cavity 2, a third servo motor 26 is fixedly connected to one side of the inner cavity of the connecting groove 58, a threaded rod 27 is rotatably connected to the other side of the inner cavity of the connecting groove 58, an output end of the third servo motor 26 is fixedly connected to one end of the threaded rod 27, a connecting block 28 is threadedly connected to the outer side of the threaded rod 27, a fixing frame 29 is fixedly connected to one side of the connecting block 28, and can drive the injection tube 39 fixed on the fixing sleeve 36 to move.
[0020] Preferably, a fourth servo motor 31 is fixedly connected to the bottom above the fixed frame 29, a rotating column 32 is fixedly connected to the output end of the fourth servo motor 31, a plurality of guide rails 33 are fixedly connected to the outside of the rotating column 32, a fixed block 34 is slidably connected to the inside of the guide rail 33, a support spring 35 is fixedly connected to the bottom of the inner cavity of the guide rail 33, the top of the support spring 35 is fixedly connected to the bottom of the fixed block 34, one end of the fixed block 34 extends to the outside of the guide rail 33 and is fixedly connected to a fixed sleeve 36, both sides of the fixed sleeve 36 are fixedly connected to an electric telescopic rod 37, and the electric telescopic rod The telescopic ends of 37 extend to the inner side of the fixed sleeve 36 and are fixedly connected with the clamping block 38. The fixed sleeve 36 is provided with an injection tube 39. The outer fixed sleeve of the injection tube 39 is provided with a mounting sleeve 40. The top of the injection tube 39 extends to the top of the fixed sleeve 36. The outer side of the injection tube 39 is fixedly connected with a threaded sleeve 57. The outer side of the threaded sleeve 57 is threadedly connected with a threaded cover 56. The threaded cover 56 can protect the top of the injection tube 39 to prevent dust from falling into the injection tube 39 and clogging the slurry delivery pipeline inside the injection tube 39, thereby affecting the slurry delivery of the injection tube 39.
[0021] Preferably, a liquid cavity 43 is provided inside the mounting sleeve 40, a plurality of liquid holes 44 are provided on the outer side of the mounting sleeve 40, the liquid holes 44 are connected to the inside of the liquid cavity 43, an annular cavity 45 is provided inside the fixing sleeve 36, an elastic tube 55 is fixedly connected to one side of the clamping block 38, one end of the elastic tube 55 extends to the inside of the annular cavity 45, the other end of the elastic tube 55 extends to one side of the clamping block 38 and is fixedly connected to a plug 41, a connector 42 is fixedly connected to the inside of the mounting sleeve 40, one end of the plug 41 is inserted into the inside of the connector 42, and the other end of the connector 42 extends into the liquid cavity 43, when it is necessary to replenish the injection tube 39, the injection tube 39 is placed into the inside of the fixing sleeve 36 through the through groove 30, and the telescopic end of the electric telescopic rod 37 pushes the clamping block 38 to move, so that the clamping block 38 contacts the outside of the mounting sleeve 40, and the plug 41 is inserted into the inside of the connector 42, so that the position of the injection tube 39 and the mounting sleeve 40 is fixedly limited.
[0022] Preferably, one end of the fixed block 34 extends to the outside of the guide rail 33, the outside of the rotating column 32 and on one side of the guide rail 33 are fixedly connected with a piston cylinder 47, the piston cylinder 47 is slidably connected with a piston block 48, the top of the piston block 48 extends to the top of the piston cylinder 47 and is fixedly connected with a pressure block 49, the outside of the piston block 48 is movably sleeved with a connecting spring 50, the bottom end of the connecting spring 50 is fixedly connected to the top of the piston cylinder 47, the top of the connecting spring 50 is connected to the bottom of the pressure block 49, the bottom of the piston cylinder 47 is fixedly connected with a suction head 51, the bottom ends of several suction heads 51 are fixedly connected with a connecting pipe 52, one side of the piston cylinder 47 is fixedly connected with a pipeline 46, one end of the pipeline 46 extends to the inside of the rotating column 32, the other end of the rotating column 32 is connected to the inside of the annular cavity 45 through a hose, and one end of the pipeline 46 and the suction head 51 extend to the inside of the piston cylinder 47 and are provided with a one-way valve to control the flow direction of the glue.
[0023] Preferably, a liquid tank 53 is fixedly connected to the bottom of the connecting block 28, one end of the connecting pipe 52 extends into the interior of the liquid tank 53, a liquid inlet valve 54 is fixedly connected to one side of the liquid tank 53, one end of the liquid inlet valve 54 passes through the connecting block 28 and through a side hole provided on the working box 1 and extends to the outside of the working box 1, the outside of the connecting pipe 52 is rotatably connected to the inside of the liquid tank 53, so that when the rotating column 32 rotates, it can drive the piston cylinder 47 and the connecting pipe 52 to rotate.
[0024] Embodiment 2 See also Figure 1 and Figure 4 The present invention provides a technical solution: a handle 59 is fixedly connected to one side of the working box 1, a controller is fixedly connected to the top of the handle 59, a first servo motor 3 is fixedly connected to the top of the inner cavity of the storage chamber 2, an output end of the first servo motor 3 is fixedly connected to the top of the first screw rod 4, and the diameter of the threaded cover 56 matches the inner diameter of the through hole 8 and the cleaning brush 9, so that the threaded cover 56 can pass through the through hole 8 and the cleaning brush 9 and move to the outside of the device.
[0025] In summary, when using the grouting equipment for treating construction joints in underground garages, the device is held by the handle 59, and then the working box 1 is moved to the position where drilling and pipe burying are required, and then the controller is pressed. At this time, the output end of the first servo motor 3 drives the first screw rod 4 to rotate, so that the first screw rod 4 drives the moving block 5 to move, so that the moving block 5 drives the second servo motor 6 and the drill bit 7 to move downward, so that the drill bit 7 enters the cleaning brush 9 through the through hole 8, and then moves to the inside of the ground through the stopper sleeve 11, and then the output end of the second servo motor 6 drives the drill bit 7 to rotate, so that the drill bit 7 drills a hole in the ground, so that the dust generated during drilling enters the inside of the stopper sleeve 11, and when the first screw rod 4 rotates, the first screw rod 4 cannot drive the skin through the one-way bearing 21. The pulley 20 rotates with the connecting rod 17, and then drives the fan blades 13 to move in a circle around the outside of the drill bit 7 through the transmission gear 18, the gear ring 16 and the annular plate 15. After drilling, the output end of the first servo motor 3 drives the first screw rod 4 to reset and rotate, so that the first screw rod 4 drives the moving block 5 to drive the second servo motor 6 and the drill bit 7 from the ground to the inside of the storage chamber 2. At this time, the first screw rod 4 can drive the pulley 20 through the one-way bearing 21 to drive the connecting rod 17 to rotate, so that the connecting rod 17 drives the gear ring 16 to rotate through the transmission gear 18, so that the gear ring 16 drives the annular plate 15 to move in a circle, so that the annular plate 15 drives the fan blades 13 to move in a circle around the outside of the drill bit 7, so that the fan blades 13 can push the dust generated by drilling. It is pushed out to the outside of the stop sleeve 11 through the side groove 14, and then the output end of the third servo motor 26 drives the threaded rod 27 to rotate, so that the threaded rod 27 drives the connecting block 28 and the fixing frame 29 to move, so that the fixing frame 29 and the fourth servo motor 31 drive the fixing sleeve 36, the injection pipe 39 and the installation sleeve 40 to move to the top of the through hole 8, and then the output end of the first servo motor 3 drives the first screw rod 4 to rotate, so that the first screw rod 4 drives the moving block 5, the second servo motor 6 and the drill bit 7 to move downward, so that the drill bit 7 pushes the threaded cover 56 to move downward, so that the threaded cover 56 and the fixing sleeve 36 move downward, so that the injection pipe 39 and the installation sleeve 40 pass through the through hole 8, the cleaning brush 9 and the stop sleeve 11, and are inserted into the drill hole on the ground, and then with the movement of the fixing block 34, at this time The fixed block 34 pushes the pipeline 46 downward, so that the pressure block 49 pushes the piston block 48 downward, so that the glue inside the piston cylinder 47 enters the annular cavity 45 through the pipeline 46, then enters the elastic tube 55 through the annular cavity 45, then enters the connector 42 through the elastic tube 55, and then enters the liquid cavity 43 through the plug 41, and then the glue inside the liquid cavity 43 enters the gap inside the drill hole through the liquid hole 44, fills the gap between the installation sleeve 40 and the drill hole with glue, fixes the installation sleeve 40 and the drill hole, and then the telescopic end of the electric telescopic rod 37 drives the clamping block 38 to move, so that one end of the plug 41 moves out of the connector 42, and then the output end of the first servo motor 3 drives the first screw 4 to reset and rotate,The first screw rod 4 drives the moving block 5 to drive the second servo motor 6 and the drill bit 7 to move upward. At this time, the support spring 35 pushes the fixed block 34 to drive the fixed sleeve 36 to move upward, and then the connecting spring 50 pushes the pressing block 49 to drive the piston block 48 to move upward, so that the glue inside the liquid tank 53 is sucked into the piston cylinder 47 through the connecting pipe 52 and the suction head 51 for subsequent use. Then the output end of the third servo motor 26 drives the threaded rod 27 to rotate, so that the threaded rod 27 drives the connecting block 28 and the fixing frame 29 as well as the fourth servo motor 31 and the fixing sleeve 36 are moved to the initial position. At this time, the staff picks up the working box 1. At this time, the injection pipe 39 is inside the borehole. Then the operator continues to perform the grouting process and continues to drive the injection pipe 39 into the ground. When it is necessary to grout the ground, the threaded cover 56 is unscrewed from the outside of the threaded sleeve 57, and then the grouting machine is used to grout the inside of the injection pipe 39 to deal with the cracks in the underground garage. Then the injection pipe 39 and the installation sleeve 40 are broken off at the part above the borehole, and then smoothed. ,
[0026] The above description is only a preferred specific implementation manner of the present invention, but the protection scope of the present invention is not limited thereto. Any technician familiar with the technical field can make equivalent replacements or changes according to the technical scheme and inventive concept of the present invention within the technical scope disclosed by the present invention, which should be covered by the protection scope of the present invention.
Claims
1. A pouring device for treating construction joints in underground garages, comprising a working box (1), characterized in that: The working box (1) is provided with a storage chamber (2) inside, the bottom of the inner chamber of the storage chamber (2) is rotatably connected to a first screw rod (4), the outer side of the first screw rod (4) is threadedly connected to a moving block (5), the top of the moving block (5) is fixedly connected to a second servo motor (6), the output end of the second servo motor (6) extends to the bottom of the moving block (5) and is fixedly connected to a drill bit (7), the bottom of the working box (1) is provided with a through hole (8), the bottom of the working box (1) is fixedly connected to a fixing ring (10), the inside of the fixing ring (10) is fixedly connected to a cleaning brush (9), the outside of the fixing ring (10) is slidably connected to a stopper sleeve (11), one side of the stopper sleeve (11) is provided with a side groove (14), the inside of the fixing ring (10) and the outside of the cleaning brush (9) is provided with an annular groove (12), the inside of the annular groove (12) is slidably connected to an annular The annular plate (15) is fixedly connected to a gear ring (16) at the top of the annular plate (15), and a plurality of push blades (13) are fixedly connected to the bottom of the annular plate (15) and located inside the stop sleeve (11). A connecting rod (17) is rotatably connected to the inside of the annular groove (12). A transmission gear (18) matching the gear ring (16) is fixedly sleeved on the outer side of the connecting rod (17). A transmission chamber (19) is provided inside the working box (1) and located below the storage chamber (2). The bottom end of the first screw rod (4) extends into the transmission chamber (19), and the top end of the connecting rod (17) extends into the transmission chamber (19) and is rotatably connected to the top of the inner chamber of the transmission chamber (19). A one-way bearing (21) is provided on the outer side of the first screw rod (4), and a pulley (20) connected by a belt drive is fixedly sleeved on the outer side of the one-way bearing (21) and the connecting rod (17).
2. The pouring equipment for processing a construction joint of an underground garage according to claim 1, characterized in that: The stopper sleeve (11) is fixedly connected to two fixed boxes (22), each of which is rotatably connected to a ball screw (23), and each of which is threadedly connected to an insert block (24) on the outside of the ball screw (23). A plurality of slots (25) are provided on the outside of the fixed ring (10), and one end of each of the insert blocks (24) extends into the inside of a corresponding slot (25), and one end of each of the ball screws (23) extends to the outside of the fixed box (22).
3. The pouring equipment for processing a construction joint of an underground garage according to claim 2, characterized in that: A connecting groove (58) is provided inside the working box (1) and below the storage cavity (2); a third servo motor (26) is fixedly connected to one side of the inner cavity of the connecting groove (58); a threaded rod (27) is rotatably connected to the other side of the inner cavity of the connecting groove (58); an output end of the third servo motor (26) is fixedly connected to one end of the threaded rod (27); a connecting block (28) is threadedly connected to the outer side of the threaded rod (27); and a fixing frame (29) is fixedly connected to one side of the connecting block (28).
4. The pouring equipment for treating a construction joint of an underground garage according to claim 3, characterized in that: A fourth servo motor (31) is fixedly connected to the bottom of the upper part of the fixed frame (29); a rotating column (32) is fixedly connected to the output end of the fourth servo motor (31); a plurality of guide rails (33) are fixedly connected to the outer side of the rotating column (32); a fixed block (34) is slidably connected to the inside of each of the guide rails (33); a support spring (35) is fixedly connected to the bottom of the inner cavity of each of the guide rails (33); a top end of each of the support springs (35) is fixedly connected to the bottom of the fixed block (34); one end of each of the fixed blocks (34) extends to the outer side of the guide rail (33) and is fixedly connected to a fixed sleeve (36), both sides of the fixed sleeve (36) are fixedly connected to electric telescopic rods (37), the telescopic ends of the electric telescopic rods (37) extend to the inner side of the fixed sleeve (36) and are fixedly connected to clamping blocks (38), a liquid injection tube (39) is placed inside the fixed sleeve (36), a mounting sleeve (40) is provided on the outer fixed sleeve of the liquid injection tube (39), the top of the liquid injection tube (39) extends to the upper side of the fixed sleeve (36), the outer side of the liquid injection tube (39) is fixedly connected to a threaded sleeve (57), and the outer side of the threaded sleeve (57) is threadedly connected to a threaded cover (56).
5. A pouring equipment for underground garage construction joint processing according to claim 4, characterized in that: The installation sleeve (40) is provided with a liquid cavity (43) inside, the installation sleeve (40) is provided with a plurality of liquid holes (44) on the outside, the liquid holes (44) are communicated with the inside of the liquid cavity (43), the fixing sleeve (36) is provided with an annular cavity (45) inside, one side of the clamping block (38) is fixedly connected to an elastic tube (55), one end of the elastic tube (55) extends into the inside of the annular cavity (45), the other end of the elastic tube (55) extends to one side of the clamping block (38) and is fixedly connected to a plug (41), the installation sleeve (40) is fixedly connected to a connector (42), one end of the plug (41) is inserted into the inside of the connector (42), and the other end of the connector (42) extends into the inside of the liquid cavity (43).
6. A pouring device for treating construction joints in an underground garage according to claim 5, characterized in that: One end of the fixed block (34) extends to the outside of the guide rail (33), the outside of the rotating column (32) and located on one side of the guide rail (33) is fixedly connected to a piston cylinder (47), the inside of the piston cylinder (47) is slidably connected to a piston block (48), the top of the piston block (48) extends to the top of the piston cylinder (47) and is fixedly connected to a pressure block (49), the outside of the piston block (48) is movably sleeved with a connecting spring (50), the bottom end of the connecting spring (50) is fixedly connected to the top of the piston cylinder (47), and the connecting spring (50) is 0) are connected to the bottom of the pressure block (49), the bottom of the piston cylinder (47) is fixedly connected to a suction head (51), the bottom ends of several suction heads (51) are fixedly connected to a connecting pipe (52), one side of the piston cylinder (47) is fixedly connected to a pipeline (46), one end of the pipeline (46) extends to the inside of the rotating column (32), the other end of the rotating column (32) is connected to the inside of the annular cavity (45) through a hose, and one end of the pipeline (46) and the suction head (51) extend to the inside of the piston cylinder (47) and are provided with a one-way valve.
7. A pouring device for treating construction joints in an underground garage according to claim 6, characterized in that: A liquid box (53) is fixedly connected to the bottom of the connecting block (28), one end of the connecting pipe (52) extends into the interior of the liquid box (53), one side of the liquid box (53) is fixedly connected to a liquid inlet valve (54), one end of the liquid inlet valve (54) passes through the connecting block (28) and through a side hole provided on the working box (1) to extend to the outside of the working box (1), and the outside of the connecting pipe (52) is rotatably connected to the inside of the liquid box (53).
8. A pouring device for treating construction joints in an underground garage according to claim 7, characterized in that: A handle (59) is fixedly connected to one side of the working box (1), a controller is fixedly connected to the top of the handle (59), a first servo motor (3) is fixedly connected to the top of the inner cavity of the storage cavity (2), an output end of the first servo motor (3) is fixedly connected to the top of the first screw rod (4), and the diameter of the threaded cover (56) matches the inner diameter of the through hole (8) and the cleaning brush (9).
Citation Information
Patent Citations
Foundation local collapse repairing equipment
CN115419128A
Wall crack repairing device and repairing method thereof
CN116856750A
Perfusion device of usefulness is handled in super dark underground garage building crack
CN208534083U
Underground engineering crack repairing structure
CN213625749U
A resin injection device for ballastless track repair construction
CN215164234U