Method for supporting beam and pulling column under traffic condition of heavy metallurgy workshop

By strengthening the bearing and installing the support trusses in the heavy metallurgical plant, and gradually cutting off the original steel structural columns using jacks, the problem of limiting the distance between the middle columns of the equipment transformation is solved, and continuous production and cost control of the equipment transformation is achieved.

CN119062152APending Publication Date: 2024-12-03SHANGHAI BAOYE GRP CORP
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411383178.9
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-09-30
Publication Date
2024-12-03

AI Technical Summary

Technical Problem

In the renovation of heavy metallurgical plant equipment, the column distance or position of the original factory often becomes an obstacle to the installation of new equipment, resulting in the suspension of production and removal of the original driving beam for renovation of the platform foundation and steel structure columns, affecting normal production.

Method used

By adding drilled pile reinforcement outside the original support, expanding the column cross-section, installing support trusses and lifting cow legs, the original steel structural column is gradually cut off by using a jack to make room to adapt to the installation of new equipment and maintain production continuity.

Benefits of technology

It is realized that the columns of the steel structure factory building are removed without affecting the driving operation, and space is freed for equipment transformation, reducing production stagnation time and cost, and providing a better production organization and cost control solution.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119062152A_ABST
    Figure CN119062152A_ABST
Patent Text Reader

Abstract

The invention relates to the construction field of fixed building supports, in particular to a method for supporting a beam and pulling a column under the traveling traffic condition of a heavy metallurgy plant. The method for supporting the beam and pulling the column under the traffic condition of the heavy metallurgy workshop is characterized by being implemented according to the following steps in sequence: S1, expanding and reinforcing; s2, an expansion column is poured; s3, actual measurement; s4, installation is carried out; s5, a jacking bracket is welded; s6, cutting off the original steel structure column; s7, recording; s8, grading unloading is carried out; and S9, the middle column is cut off. The cost is reduced, and the influence on production is small.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the construction field of fixed building supports, in particular to a method for supporting beams and pulling out columns under the condition of vehicle traffic in a heavy metallurgical plant. Background Art

[0002] In recent years, the steel industry has been undergoing environmental protection transformation and industrial restructuring, and the original process equipment needs to be adjusted. The column spacing or position of the original plant often becomes an obstacle to the installation of new equipment, and some columns must be removed to form a larger column spacing space. The conventional solution is to stop production and construction, first remove the original crane beam, then renovate the foundation and steel structure columns, and finally install a new crane beam, which has a great impact on normal production. Summary of the invention

[0003] In order to overcome the defects of the prior art and provide a construction method with reduced cost and little impact on production, the present invention discloses a method for supporting beams and pulling out columns under the condition of vehicle traffic in a heavy metallurgical plant.

[0004] The present invention achieves the purpose of the invention through the following technical solutions: A method for supporting beams and pulling out columns in a heavy metallurgical plant under the condition of vehicle traffic, characterized by: performing the following steps in sequence: S1. Add bored cast-in-place piles outside the original column foundation cap to expand and reinforce the original cap; S2. Tie steel bars around the original frame column, and use micro-expansive concrete to expand the column cross-section after supporting the formwork; S3. Measure the relevant dimensions of the original factory columns and fine-tune the processing dimensions of the underpinning trusses according to the measurement results; S4. Each underpinning truss is installed in two pieces, and then the connection between the two pieces is connected; S5. Weld the jacking bracket on the center column; S6. Drive away from the reconstruction area, place the jack between the two brackets, and cut off the original steel structure column from the column cutting section A after slightly applying force to the jack, leaving a gap of 5mm to 8mm; S7. Drive the vehicle over the center column with no load or with a heavy load, and record the pressure of the jack; S8, unload the pressure of the jack in stages, and at the same time, drive the vehicle to perform the test according to step S7, and observe the maximum settlement at the cut-off point A; S9. When the jack is completely depressurized and the settlement value of the middle column meets the design requirements, cut off the middle column from column cutoff point B and remove the lower half of the middle column.

[0005] The method for supporting beams and pulling out columns under the condition of vehicle traffic in a heavy metallurgical plant is characterized in that: in step S2, the cross-sectional dimensions of the columns are expanded to (original length + 100mm) × (original width + 100mm), and the height is 100mm to the bottom surface of the original vehicle system.

[0006] The method for supporting beams and pulling out columns under the condition of vehicle traffic in a heavy metallurgical plant is characterized in that in step S5, four lifting brackets are welded near the middle column 1.2m above the ground.

[0007] The method for supporting beams and pulling out columns under the condition of vehicle traffic in a heavy metallurgical plant is characterized in that: in step S6, the jack is slightly stressed and then the original steel structure column is cut off from the column cutting section A and a gap of 5mm to 8mm is left.

[0008] The method for supporting beams and pulling out columns under the condition of vehicle traffic in a heavy metallurgical plant is characterized in that: in step S9, when the heavy-loaded vehicle passes through the middle column, if the settlement value of the middle column meets the design requirements, the middle column is cut off from the column cutting point B and the lower half of the middle column is removed.

[0009] The present invention is applied in metallurgical technical transformation projects. On the premise that the crane keeps running and normal production is not affected, the lower column of the steel structure plant building is removed to make room for equipment transformation.

[0010] The present invention has the following beneficial effects: it solves the contradiction between construction and production, enables continuous production during the process of reinforcing foundations and steel columns and installing underpinning trusses, and reduces the impact of local production during short intervals during the process of unloading and extracting columns, thus providing a better solution for the production organization and cost control of metallurgical enterprises. BRIEF DESCRIPTION OF THE DRAWINGS

[0011] Figure 1 is a front view of the present invention, Figure 2 It is a left side view of the present invention. DETAILED DESCRIPTION

[0012] The present invention is further described below by means of specific examples. Example

[0013] A method for supporting beams and pulling out columns in heavy metallurgical workshops under vehicle traffic conditions, such as Figure 1 and Figure 2 As shown, follow the steps below: S1. Add bored cast-in-place piles outside the original column foundation cap and expand and reinforce the original cap 1; S2. Tie steel bars around the original frame column 3, and after supporting the formwork, use micro-expansion concrete to cast the expanded column 2 with a cross-sectional size of (original length + 100mm) × (original width + 100mm), with a height of 100mm to the bottom of the original driving system 5; S3, measuring the relevant dimensions of the original factory columns, and fine-tuning the processing dimensions of the underpinning truss 4 according to the measurement results; S4, each underpinning truss 4 is divided into two pieces for installation, and then the connection between the two pieces is connected; S5. Weld four jacking brackets 7 at the center column 6 about 1.2 m from the ground; S6. Drive away from the reconstruction area, place the jack 8 between the two brackets 7, and make the jack 8 slightly stressed to cut off the original steel structure column from the column cutting section A 9, leaving a gap of 5mm to 8mm; S7, driving the vehicle without load and with load through the center column 6, and recording the pressure of the jack 8; S8, unload the pressure of the four jacks 8 in stages, and at the same time, drive the vehicle to perform the test according to step 7, and observe the maximum settlement of the cut-off point 9; S9. After the jack 8 is completely depressurized, when a heavy-loaded vehicle passes over the center column 6 and the settlement value of the center column meets the design requirements, the center column is cut off from the column cut-off point B 10 and the lower half of the center column is removed.

Claims

1. A method for supporting beams and pulling out columns under the condition of vehicle traffic in a heavy metallurgical plant, characterized by: Follow the steps below to implement: S1. Add bored cast-in-place piles outside the original column foundation pedestal to expand and reinforce the original pedestal (1); S2, tying steel bars around the original frame column (3), and after supporting the formwork, pouring micro-expansive concrete to expand the cross section of the column (2); S3, measuring the relevant dimensions of the original factory columns, and fine-tuning the processing dimensions of the underpinning truss (4) according to the measurement results; S4, each underpinning truss (4) is divided into two pieces for installation, and then the connection between the two pieces is connected; S5, welding a lifting bracket (7) on the center column (6); S6. The vehicle leaves the reconstruction area, and the jack (8) is placed between the two brackets (7). After the jack (8) is slightly stressed, the original steel structure column is cut off from the column cutting section A (9), leaving a gap of 5 mm to 8 mm. S7, driving the vehicle without load and with load through the center column (6), and recording the pressure of the jack (8); S8, unloading the pressure of the jack (8) in stages, while driving the vehicle to perform the test according to step S7, and observing the maximum settlement value of the cut-off point A (9); S9. When the jack (8) is completely depressurized and the settlement value of the middle column meets the design requirements, the middle column is cut off from the column cutting point B (10) and the lower half of the middle column is removed.

2. The method for supporting beams and pulling out columns in a heavy metallurgical plant under vehicle traffic conditions as claimed in claim 1, characterized in that: In step S2, the cross-sectional dimensions of the column (2) are enlarged to (original length + 100 mm) × (original width + 100 mm), and the height is 100 mm from the bottom surface of the original driving system (5).

3. The method for supporting beams and pulling out columns in a heavy metallurgical plant under vehicle traffic conditions as claimed in claim 2, characterized in that: In step S5, four lifting brackets (7) are welded to the center column (6) at a distance of 1.2 m from the ground.

4. The method for supporting beams and pulling out columns in a heavy metallurgical plant under vehicle traffic conditions as claimed in claim 3, characterized in that: In step S6, the jack (8) is slightly stressed to cut off the original steel structure column from the column cutting section 1 (9) and leave a gap of 5mm to 8mm.

5. The method for supporting beams and pulling out columns in a heavy metallurgical plant under vehicle traffic conditions as claimed in claim 4, characterized in that: In step S9, when a heavy-loaded vehicle passes through the middle column (6), if the settlement value of the middle column meets the design requirements, the middle column is cut off from the column cutting point B (10) and the lower half of the middle column is removed.