Temperature adjusting device for screw type central air conditioner

通过在中央空调系统中设计螺杆式中央空调调温装置,利用第一和第二换热器、冷水机和冷却塔在低电价时间进行蓄冰,解决了中央空调在高电价时间耗电量高 The problem of energy saving and cost reduction has been achieved.

CN119063101APending Publication Date: 2024-12-03ZIZHI HLDG GRP CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411105221.5
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-08-13
Publication Date
2024-12-03

AI Technical Summary

Technical Problem

The existing central air-conditioning system cannot adjust the power usage according to the electricity price time, resulting in a high electricity consumption at high electricity price time, affecting its promotion.

Method used

A screw central air conditioner temperature regulating device is designed, including the first and second heat exchangers, water chillers and cooling towers. By storing ice at low electricity price time and compensating the workload at high electricity price time, the central air conditioner is reduced Peak load.

Benefits of technology

It has achieved the reduction of energy consumption and operating costs of central air conditioners during high electricity prices, effectively saving energy, and conducive to the promotion of the system.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119063101A_ABST
    Figure CN119063101A_ABST
Patent Text Reader

Abstract

The invention relates to the technical field of central air conditioners, in particular to a temperature adjusting device for a screw type central air conditioner. According to the technical scheme, the system comprises a user side, a first heat exchanger, a first conveying pipe, a second heat exchanger, a control valve, a second conveying pipe, a cooling-water machine, a third conveying pipe and a cooling tower, the first heat exchanger is arranged on the outer wall of one side of the user side, and the second heat exchanger is arranged on the outer wall of one side of the first heat exchanger; a second conveying pipe is arranged on the outer wall of one side of the first heat exchanger and the outer wall of one side of the second heat exchanger, and the first heat exchanger and the second heat exchanger are both connected with a cooling-water machine through the second conveying pipe. Energy can be effectively saved, the operating cost of the central air conditioner is reduced, and popularization of the central air conditioner is facilitated.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of central air conditioners, in particular to a temperature control device for a screw-type central air conditioner. Background Art

[0002] The central air conditioning system consists of one or more cold and heat source systems and multiple air conditioning systems. This system is different from traditional refrigerant air conditioning (such as single unit, VRV) which centrally processes air to meet comfort requirements. The principle of liquid gasification refrigeration is used to provide the required cooling capacity for the air conditioning system to offset the heat load of the indoor environment; the heating system provides the required heat for the air conditioning system to offset the heating and cooling load of the indoor environment, and some central air conditioners use screw compressors to work, which are also called screw compressors. In the 1950s, oil-injected screw compressors were used in refrigeration devices. Due to their simple structure, few wearing parts, low exhaust temperature under large pressure difference or pressure ratio conditions, insensitive to large amounts of lubricating oil in the refrigerant, and good gas flow regulation, they quickly occupied the use range of large-capacity reciprocating compressors, and continued to extend to the medium-capacity range, and were widely used in refrigeration devices such as freezing, refrigeration, air conditioning and chemical processes.

[0003] After massive searches, it is found that the typical temperature control device in the prior art is a geothermal central air conditioning energy-saving device disclosed in publication number CN101749838A. This invention adds a geothermal central air conditioning system, and installs a temperature sensor on the water path of the geothermal collector. The sensor is connected to the frequency conversion device in the central controller. The frequency conversion device can adjust the system water flow at any time according to the geothermal energy attenuation of the geothermal collector to ensure the minimum water volume for normal operation of the unit. This device can greatly reduce the amount of groundwater exploitation by geothermal central air conditioning, maximize the use of geothermal resources, protect the environment, save resources, and achieve sustainable development of geothermal energy utilization.

[0004] During use, existing central air conditioners cannot adjust their power usage according to different electricity prices, resulting in higher power consumption when the central air conditioner is turned on during high electricity prices, which is not conducive to the promotion of central air conditioners. Summary of the invention

[0005] The object of the present invention is to provide a temperature control device for a screw-type central air conditioner to solve the problems raised in the above-mentioned background technology.

[0006] To achieve the above-mentioned purpose, the present invention provides the following technical solutions: a temperature control device for a screw-type central air conditioner, comprising a user end, a first heat exchanger, a first delivery pipe, a second heat exchanger, a control valve, a second delivery pipe, a chiller, a third delivery pipe and a cooling tower, wherein a first heat exchanger is arranged on an outer wall on one side of the user end, a second heat exchanger is arranged on an outer wall on one side of the first heat exchanger, a second delivery pipe is arranged on an outer wall on one side of the first heat exchanger and a second heat exchanger, and the first heat exchanger and the second heat exchanger are both connected to the chiller via the second delivery pipe.

[0007] Preferably, a first delivery pipe is provided on the outer wall of one side of the first heat exchanger and the second heat exchanger, and the first heat exchanger and the second heat exchanger are connected to the user end through the first delivery pipe. The second heat exchanger has an ice storage function. The second heat exchanger cools at the required time through a chiller, thereby storing ice inside the ice storage tank. The first heat exchanger is used for normal working needs.

[0008] Preferably, a control valve is provided on the outer wall of one side of the first delivery pipe and the second delivery pipe, and the control valve is used to cut off the delivery pipelines of the first heat exchanger and the second heat exchanger, thereby ensuring the controlled use of the first heat exchanger and the second heat exchanger.

[0009] Preferably, a third delivery pipe is provided on the outer wall of one side of the two chillers, and the chillers are connected to cooling towers through the third delivery pipes. The cooling towers are used to reduce the temperature of the chillers, thereby cooling the cooling towers.

[0010] Compared with the prior art, the beneficial effects of the present invention are as follows: the present invention achieves the effect of ice storage in idle time by arranging the first heat exchanger, the second heat exchanger and the cooling tower. The first heat exchanger delivers cold to the user end through the chiller and the cooling tower to ensure the normal use of the central air conditioner. When it is in the period of low electricity price, the second heat exchanger performs refrigeration and ice storage through the chiller and the cooling tower, and stores ice in the external ice storage tank. Therefore, when it is in the period of high electricity price, the second heat exchanger can compensate for the workload of the first heat exchanger, thereby reducing the load peak of the central air conditioner, effectively saving energy, reducing the operating cost of the central air conditioner, and facilitating the promotion of the central air conditioner. BRIEF DESCRIPTION OF THE DRAWINGS

[0011] Figure 1 It is a schematic diagram of the process of the present invention.

[0012] In the figure: 1. User end; 2. First heat exchanger; 3. First delivery pipe; 4. Second heat exchanger; 5. Control valve; 6. Second delivery pipe; 7. Chiller; 8. Third delivery pipe; 9. Cooling tower. DETAILED DESCRIPTION

[0013] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0014] In the description of the present invention, it should be noted that the terms "upper", "lower", "inner", "outer", "front end", "rear end", "two ends", "one end", "the other end" and the like indicate positions or positional relationships based on the positions or positional relationships shown in the drawings, and are only for the convenience of describing the present invention and simplifying the description, and do not indicate or imply that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore cannot be understood as limiting the present invention. In addition, the terms "first" and "second" are used for descriptive purposes only and cannot be understood as indicating or implying relative importance.

[0015] In the description of the present invention, it should be noted that, unless otherwise clearly specified and limited, the terms "installed", "provided with", "connected", etc. should be understood in a broad sense. For example, "connected" can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection, or it can be indirectly connected through an intermediate medium, or it can be the internal communication of two components. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.

[0016] See also Figure 1 , the present invention provides two embodiments: Embodiment 1: A temperature control device for a screw-type central air conditioner, comprising a user end 1, a first heat exchanger 2, a first delivery pipe 3, a second heat exchanger 4, a control valve 5, a second delivery pipe 6, a chiller 7, a third delivery pipe 8 and a cooling tower 9. The first heat exchanger 2 is arranged on the outer wall on one side of the user end 1, the second heat exchanger 4 is arranged on the outer wall on one side of the first heat exchanger 2, the second delivery pipe 6 is arranged on the outer wall on one side of the first heat exchanger 2 and the second heat exchanger 4, and the first heat exchanger 2 and the second heat exchanger 4 are both connected to the chiller 7 through the second delivery pipe 6.

[0017] A first delivery pipe 3 is provided on the outer wall of one side of the first heat exchanger 2 and the second heat exchanger 4. The first heat exchanger 2 and the second heat exchanger 4 are connected to the user end 1 through the first delivery pipe 3. The second heat exchanger 4 has an ice storage function. The second heat exchanger 4 cools at the required time through the chiller 7, thereby storing ice inside the ice storage tank. The first heat exchanger 2 is used for normal working needs.

[0018] A third delivery pipe 8 is provided on the outer wall of one side of the two chillers 7. The chillers 7 are connected to a cooling tower 9 through the third delivery pipe 8. The cooling tower 9 is used to reduce the temperature of the chillers 7, thereby cooling the cooling tower 9. The first heat exchanger 2 delivers cold air to the user end 1 through the chillers 7 and the cooling tower 9 to ensure the normal use of the central air conditioner.

[0019] Embodiment 2: A temperature control device for a screw-type central air conditioner comprises a user end 1, a first heat exchanger 2, a first delivery pipe 3, a second heat exchanger 4, a control valve 5, a second delivery pipe 6, a chiller 7, a third delivery pipe 8 and a cooling tower 9. The first heat exchanger 2 is arranged on the outer wall on one side of the user end 1, the second heat exchanger 4 is arranged on the outer wall on one side of the first heat exchanger 2, the second delivery pipe 6 is arranged on the outer wall on one side of the first heat exchanger 2 and the second heat exchanger 4, and the first heat exchanger 2 and the second heat exchanger 4 are both connected to the chiller 7 via the second delivery pipe 6.

[0020] A first delivery pipe 3 is provided on the outer wall of one side of the first heat exchanger 2 and the second heat exchanger 4. The first heat exchanger 2 and the second heat exchanger 4 are connected to the user end 1 through the first delivery pipe 3. The second heat exchanger 4 has an ice storage function. The second heat exchanger 4 cools at the required time through the chiller 7, thereby storing ice inside the ice storage tank. The first heat exchanger 2 is used for normal working needs.

[0021] A control valve 5 is provided on the outer wall of one side of the first delivery pipe 3 and the second delivery pipe 6. The control valve 5 is used to cut off the delivery pipelines of the first heat exchanger 2 and the second heat exchanger 4, so as to ensure that the first heat exchanger 2 and the second heat exchanger 4 are used in a controlled manner.

[0022] A third delivery pipe 8 is provided on the outer wall of one side of the two chillers 7. The chillers 7 are connected to a cooling tower 9 through the third delivery pipe 8. The cooling tower 9 is used to reduce the temperature of the chillers 7, thereby cooling the cooling tower 9. When the electricity price is low, the second heat exchanger 4 cools and stores ice through the chillers 7 and the cooling tower 9, and stores ice in the external ice storage tank. Therefore, when the electricity price is high, the second heat exchanger 4 can compensate for the workload of the first heat exchanger 2, thereby reducing the load peak of the central air conditioner, effectively saving energy, reducing the operating cost of the central air conditioner, and facilitating the promotion of the central air conditioner.

[0023] Working principle: The first heat exchanger 2 delivers cold air to the user end 1 through the chiller 7 and the cooling tower 9 to ensure the normal use of the central air conditioner. When it is at a low electricity price, the second heat exchanger 4 cools and stores ice through the chiller 7 and the cooling tower 9, and stores ice in an external ice storage tank. Therefore, when it is at a high electricity price, the second heat exchanger 4 can compensate for the workload of the first heat exchanger 2, thereby reducing the load peak of the central air conditioner.

[0024] It will be apparent to those skilled in the art that the invention is not limited to the details of the exemplary embodiments described above and that the invention can be implemented in other specific forms without departing from the spirit or essential features of the invention. Therefore, the embodiments should be considered exemplary and non-limiting in all respects, and the scope of the invention is defined by the appended claims rather than the foregoing description, and it is intended that all variations falling within the meaning and scope of the equivalent elements of the claims be included in the invention. Any reference numeral in a claim should not be considered as limiting the claim to which it relates.

Claims

1. A temperature control device for a screw-type central air conditioner, comprising a user end (1), a first heat exchanger (2), a first delivery pipe (3), a second heat exchanger (4), a control valve (5), a second delivery pipe (6), a chiller (7), a third delivery pipe (8) and a cooling tower (9), characterized in that: A first heat exchanger (2) is arranged on an outer wall of one side of the user end (1), a second heat exchanger (4) is arranged on an outer wall of one side of the first heat exchanger (2), a second delivery pipe (6) is arranged on an outer wall of one side of the first heat exchanger (2) and the second heat exchanger (4), and the first heat exchanger (2) and the second heat exchanger (4) are both connected to a chiller (7) via the second delivery pipe (6).

2. A temperature control device for a screw-type central air conditioner according to claim 1, characterized in that: A first delivery pipe (3) is provided on the outer wall of one side of the first heat exchanger (2) and the second heat exchanger (4); the first heat exchanger (2) and the second heat exchanger (4) are connected to the user end (1) via the first delivery pipe (3); the second heat exchanger (4) has an ice storage function; the second heat exchanger (4) performs cooling at a required time via a chiller (7) so as to store ice inside the ice storage tank; the first heat exchanger (2) is used for normal working needs.

3. A temperature control device for a screw-type central air conditioner according to claim 1, characterized in that: A control valve (5) is provided on one side outer wall of the first delivery pipe (3) and the second delivery pipe (6), and the control valve (5) is used to cut off the delivery pipelines of the first heat exchanger (2) and the second heat exchanger (4), thereby ensuring that the first heat exchanger (2) and the second heat exchanger (4) are used in a controlled manner.

4. A temperature control device for a screw-type central air conditioner according to claim 1, characterized in that: A third delivery pipe (8) is provided on one side outer wall of the two water chillers (7); the water chillers (7) are connected to cooling towers (9) via the third delivery pipes (8); the cooling towers (9) are used to reduce the temperature of the water chillers (7), thereby cooling the cooling towers (9).