Construction site wastewater treatment device and method
By using iron brushes and water pressure swing mechanisms to clean the mesh impurities of the circular filter mesh in the wastewater treatment device on construction site, the problem of poor cleaning effect in the prior art is solved, and a more comprehensive filter mesh cleaning and water quality improvement is achieved.
Patent Information
- Application Number
- CN202411579391.7
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-11-07
- Publication Date
- 2024-12-06
- Estimated Expiration
- Not applicable · inactive patent
AI Technical Summary
The existing wastewater treatment equipment on construction sites is not effective when cleaning the filter, and it is impossible to effectively clean up impurities such as sand and gravel inside the mesh, resulting in the filter screen being easily blocked and impurities silted.
The metal bristles with iron brushes are inserted into the mesh of the circular filter mesh. Combined with the gap change of water pressure, the circular filter mesh swings back and forth. The iron brush cleans up impurities in the mesh, and uses a small particle collection box to collect splashed impurities. Avoid it re-entering the water.
A comprehensive cleaning of the circular filter is achieved, the treatment effect is improved, impurities are silted, and the smooth flow of the filter and water quality are improved.
Smart Images

Figure CN119075488A_ABST
Abstract
Description
Technical Field
[0001] This invention relates to the field of wastewater treatment equipment technology, specifically to a wastewater treatment device and method for construction sites. Background Technology
[0002] Construction sites need to clean building materials and cure concrete during construction, which generates a large amount of wastewater. This wastewater contains impurities such as sand, cement, and dust, and can only be discharged or recycled after treatment.
[0003] For wastewater containing impurities, the most direct treatment method is filtration, such as the construction site wastewater treatment device disclosed in the prior art, CN220633208U.
[0004] After filtration, solid impurities remain on the filter screen. To prevent the filter screen from becoming clogged, it needs to be cleaned frequently to ensure that the filter screen is unobstructed, as exemplified by a construction site wastewater treatment device disclosed in the prior art, CN114275942B.
[0005] There are two existing cleaning solutions. One is to scrape off the impurities attached to the surface of the filter screen with a scraper ring. However, this method cannot clean the inside of the mesh and is not very effective at cleaning sand and gravel stuck in the mesh. Secondly, air pressure is used to impact the filter structure to prevent impurities from adhering to the filter. However, in this way, the impurities that are impacted still remain in the water, which will cause impurities to accumulate inside the device over time. Therefore, the existing technologies for cleaning filter structures are not comprehensive enough, and the cleaning effect is poor. Summary of the Invention
[0006] The purpose of this invention is to provide a construction site wastewater treatment device and method. By inserting the metal bristles of an iron brush into the mesh of a circular filter screen, the mesh is cleared, resulting in a more comprehensive and effective cleaning of the circular filter screen.
[0007] To achieve the above objectives, the present invention provides the following technical solution: a construction site wastewater treatment device, comprising a primary filter box and a treatment tank, wherein the treatment tank is fixedly disposed in front of the primary filter box, and a partition is fixedly disposed on the inner wall of the treatment tank, wherein the partition divides the interior of the treatment tank into a sewage chamber and a clean water chamber, and the clean water chamber is located in front of the sewage chamber. The treatment tank is equipped with two filtration assemblies. Each filtration assembly includes a fixed shaft mounted on the inner wall of the treatment tank via a rotating shaft. A torsion spring is provided between the fixed shaft and the inner wall of the treatment tank. One end of the torsion spring is fixed with an annular protrusion, which is fixed to the outer end of the fixed shaft. The other end of the torsion spring is fixedly connected to the inner wall of the treatment tank. A detachable mounting bracket is provided at the outer end of the fixed shaft. A circular filter screen for filtering sewage is provided at the rear of the mounting bracket. A waterproof motor for driving the circular filter screen to rotate is fixed at the front of the mounting bracket. A rubber frame with a buffering function is fixed at the outer end of the circular filter screen. The sewage chamber is equipped with a spray assembly, which includes two nozzles that spray sewage onto the lower half of two circular filter screens. An iron brush is provided diagonally below the upper half of the circular filter screen, and the bristles of the iron brush are made of tough metal wire.
[0008] Furthermore, the filter assembly is tilted towards the clean water chamber so that the filtered water can fall into the clean water chamber. A guide plate is fixed at the top of the partition and tilts towards the clean water chamber. During the filtration process, splashed sewage can flow back into the sewage chamber under the action of the guide plate. A drain pipe connected to the interior of the clean water chamber is fixed at the front end of the treatment tank. Water that has undergone two filtrations can be discharged out through the drain pipe.
[0009] Furthermore, the top of the partition is provided with a small particle collection box, the front side of the small particle collection box is provided with an inclined opening that fits with the filter assembly, and both ends of the small particle collection box are provided with detachable end plates, which are fixedly installed on the upper edge of the treatment tank. The top of the small particle collection box is bolted with a mounting plate, the front end of which extends to the front side of the small particle collection box, and the iron brush is detachably mounted on the front end of the mounting plate.
[0010] Furthermore, the rear side of the mounting frame is provided with a preliminary brushing assembly for cleaning the surface of the circular filter screen. The preliminary brushing assembly includes a bracket fixedly mounted on the rear side of the mounting frame, and a central shaft is provided on the inner wall of the bracket via a rotating shaft. Two support plates are fixedly provided at the outer end of the central shaft. A spring that is fixedly connected to the mounting bracket is fixedly provided on the support plate away from the circular filter screen. A detachable cleaning brush is provided on the support plate facing the circular filter screen. One end of the cleaning brush extends to the rear side of the circular filter screen and contacts the surface of the circular filter screen. Ordinary brush bristles can be used for the cleaning brush.
[0011] Furthermore, the top of the primary filter box is connected to a flow channel via a flange, and a primary filter screen for preliminary filtration of wastewater is fixed on the inner wall of the primary filter box. The front end of the primary filter screen is inclined downward, and a discharge port is opened on the front side of the primary filter box. The front end of the primary filter screen extends to the discharge port. The primary filter box is fixedly provided with a large particle collection box for placing solid impurities. The large particle collection box is provided with a cleaning door on the front side via a hinge. The primary filter box is provided with a connecting port on the front side, which communicates with the interior of the sewage chamber.
[0012] Furthermore, the jet assembly also includes two horizontal pipes located above the treatment tank. One end of each horizontal pipe is provided with a detachable vertical plate, which is fixedly installed on the upper edge of the treatment tank. Two nozzles are respectively fixedly installed on the outer ends of the two horizontal pipes. A dual-outlet water pump is provided between two horizontal pipes. The two horizontal pipes are respectively connected to the two outlets of the dual-outlet water pump. A water delivery pipe is provided at the inlet of the dual-outlet water pump. The bottom end of the water delivery pipe extends into the sewage chamber and is inserted into the sewage inside the sewage chamber.
[0013] Furthermore, a rubber bladder is fixedly provided at the outer end of the transverse pipe, and multiple communication ports located inside the rubber bladder are opened at the outer end of the transverse pipe. A drive motor is fixedly mounted on the upright plate. An adjusting wheel is fixedly mounted on one end of the output shaft of the drive motor. Two extrusion rollers are mounted on the outer end of the adjusting wheel. When the extrusion rollers come into contact with the rubber bladder, they will roll. There will be no sliding friction between them, which reduces the wear of the rubber bladder. The two adjusting wheels are located on the rear side of the two rubber bladders respectively.
[0014] The present invention also includes a method for treating the wastewater from the construction site, the specific steps of which are as follows: Step 1: Untreated sewage from the construction site is fed into the primary filter box through a diversion channel. The sewage undergoes preliminary filtration through the primary filter screen and then falls into the primary filter box. The primary filter screen can only remove large solid impurities such as stones and soil from the sewage. Step 2: After the wastewater has undergone preliminary filtration in the primary filter box, it enters the wastewater chamber through the connecting port. Then, the dual-outlet water pump is turned on to draw the wastewater into the wastewater chamber through the water supply pipe. The wastewater is then directed into the two horizontal pipes and finally sprayed onto the filter components through the nozzles. Step 3: While spraying wastewater, the drive motor drives the adjusting wheel to rotate and drives the squeezing roller. During the rotation, the squeezing roller will contact the rubber bladder and squeeze the rubber bladder, thereby increasing the water pressure of the wastewater, so that the water pressure changes continuously when the wastewater comes into contact with the filter components. Step 4: When the water pressure is normal, the back of the circular filter screen contacts the front opening of the small particle collection box. The water jet from the nozzle passes through the circular filter screen and falls into the clean water chamber at an angle below, thereby further filtering impurities in the sewage and removing small particles such as sand and mud. When the water pressure increases, the impact force of the water jet increases, causing the circular filter screen to tilt further forward. This cycle continues, causing the circular filter screen to swing back and forth. Step 5: While filtering, the waterproof motor also drives the corresponding circular filter screen to rotate, adjusting the direction of the circular filter screen itself so that the part of the circular filter screen in contact with the sewage is effectively cleaned. The lower half of the filter screen that participates in the filtration work rotates upward to be cleaned, and the upper half that has been cleaned rotates downward to perform the filtration work, and so on.
[0015] The technical effects and advantages provided by the present invention in the above technical solution are as follows: 1. By installing an iron brush on the front side of the circular filter screen, when the circular filter screen is tilted forward, the metal bristles of the iron brush will insert into the mesh of the circular filter screen, which will unclog the mesh and make the cleaning of the circular filter screen more thorough and effective. 2. By intermittently increasing the water pressure, the circular filter screen swings back and forth. When the circular filter screen returns to its original position, it will hit the opening of the small particle collection box. The loose impurities on the surface of the circular filter screen will splash into the small particle collection box under the action of inertia, thus preventing these impurities from returning to the water and causing impurity accumulation. Attached Figure Description
[0016] To more clearly illustrate the technical solutions in the embodiments of this application or the prior art, the drawings used in the embodiments will be briefly introduced below. Obviously, the drawings described below are only some embodiments recorded in this invention. For those skilled in the art, other drawings can be obtained based on these drawings.
[0017] Figure 1 This is a front view structural diagram of the present invention; Figure 2 This is a rear view structural diagram of the present invention; Figure 3 This is a cross-sectional view of the primary filter box and treatment tank of the present invention; Figure 4 This is a bottom view of the filter assembly of the present invention; Figure 5 This is a side sectional view of the filter component of the present invention; Figure 6 This is a structural diagram of the circular filter screen of the present invention; Figure 7 This is a preliminary structural diagram of the brushing assembly of the present invention; Figure 8 This is a bottom view of the mounting plate structure of the present invention; Figure 9 This is a diagram of the jet assembly of the present invention; Figure 10 This is a lateral sectional view of the pipe of the present invention; Figure 11 This is a structural diagram of the primary filter box of the present invention.
[0018] Explanation of reference numerals in the attached figures: 1. Primary filter box; 101. Discharge port; 102. Primary filter screen; 2. Treatment tank; 201. Wastewater chamber; 202. Clean water chamber; 3. Filter assembly; 301. Fixed shaft; 302. Torsion spring; 303. Mounting bracket; 304. Circular filter screen; 305. Waterproof motor; 4. Large particle collection box; 5. Small particle collection box; 6. Spray assembly; 601. Horizontal pipe; 602. Nozzle; 603. Dual-outlet water pump; 604. Rubber bladder; 605. Connecting port; 606. Water supply pipe; 7. Mounting plate; 8. Partition plate; 9. Guide channel; 10. Vertical plate; 11. Drive motor; 12. Adjusting wheel; 13. Extrusion roller; 14. Iron brush; 15. Preliminary scrubbing assembly; 1501. Bracket; 1502. Spring; 1503. Support plate; 1504. Cleaning brush; 16. End plate. Detailed Implementation
[0019] To enable those skilled in the art to better understand the technical solution of the present invention, the present invention will be further described in detail below with reference to the accompanying drawings.
[0020] This invention provides, for example Figure 1-11 The wastewater treatment device for a construction site shown includes a primary filter box 1 and a treatment tank 2. The treatment tank 2 is fixedly installed in front of the primary filter box 1. A partition 8 is fixedly installed on the inner wall of the treatment tank 2, which divides the interior of the treatment tank 2 into a sewage chamber 201 and a clean water chamber 202. The clean water chamber 202 is located in front of the sewage chamber 201.
[0021] The top of the primary filter box 1 is connected to a flow channel 9 via a flange. A primary filter screen 102 for preliminary filtration of wastewater is fixed on the inner wall of the primary filter box 1. The front end of the primary filter screen 102 is inclined downward. A discharge port 101 is opened on the front side of the primary filter box 1. The front end of the primary filter screen 102 extends to the discharge port 101. The primary filter screen 102 is used to filter large particles of impurities. Therefore, its mesh is relatively large, making it relatively easy to clean and less prone to clogging. The primary filter box 1 is fixedly provided with a large particle collection box 4 for placing solid impurities. The large particle collection box 4 is provided with a cleaning door on the front side via a hinge. The primary filter box 1 is provided with a communication port on the front side, which communicates with the interior of the sewage chamber 201.
[0022] Wastewater generated at construction sites contains solid impurities of varying sizes. Therefore, the wastewater is first introduced into the primary filter box 1 through the guide channel 9. The wastewater entering the primary filter box 1 is first filtered by the primary filter screen 102 to remove large particles such as stones and clods of soil. The wastewater that has undergone preliminary filtration falls to the bottom of the primary filter box 1 and can enter the wastewater chamber 201 through the connecting port. Only wastewater that has undergone further filtration can enter the clean water chamber 202. The filtered large particles roll along the inclined primary filter screen 102 and finally roll down through the discharge port 101 into the large particle collection box 4 for collection.
[0023] The wastewater after preliminary filtration still needs further filtration, such as... Figure 1 , 4 As shown in Figures 5, 6, and 9, the treatment tank 2 is equipped with two filter components 3. Each filter component 3 includes a fixed shaft 301 mounted on the inner wall of the treatment tank 2 via a rotating shaft. A torsion spring 302 is provided between the fixed shaft 301 and the inner wall of the treatment tank 2. One end of the torsion spring 302 is fixedly provided with an annular protrusion, which is fixed to the outer end of the fixed shaft 301. The other end of the torsion spring 302 is fixedly connected to the inner wall of the treatment tank 2. A detachable mounting bracket 303 is provided at the outer end of the fixed shaft 301. A circular filter screen 304 for filtering sewage is provided at the rear side of the mounting bracket 303. A waterproof motor 305 for driving the circular filter screen 304 to rotate is fixed at the front side of the mounting bracket 303. A rubber frame with a buffering function is fixed at the outer end of the circular filter screen 304. The sewage chamber 201 is equipped with a jet assembly 6, which includes two nozzles 602. The two nozzles 602 spray sewage onto the lower half of two circular filter screens 304 respectively. An iron brush 14 is provided diagonally below the upper half of the circular filter screen 304. The bristles of the iron brush 14 are made of tough metal wire. Tough metal wires generally refer to those that can withstand large plastic deformation without breaking when subjected to external forces. For example, 35NCD6 alloy steel wire and SS2338 stainless steel wire are metal wire materials with excellent strength and toughness.
[0024] Wastewater is drawn from the wastewater chamber 201 by the jet assembly 6, and sprayed into two circular filter screens 304 by two nozzles 602 in the form of water jets. The wastewater can be further filtered by passing through the circular filter screens 304 to remove small particles of impurities. The circular filter screens 304 are inclined towards the clean water chamber 202, so the water flowing through the circular filter screens 304 can fall into the clean water chamber 202. During filtration, the water jets contact the lower half of the circular filter screens 304, so the impurities being filtered only adhere to the lower half of the circular filter screens 304. However, at the same time as filtration, the waterproof motor 305 drives the circular filter screens 304 to rotate slowly, and the impurities that were originally attached to the lower half of the circular filter screens 304 also rotate with the circular filter screens 304. During the filtration process, the water jet pressure from nozzle 602 intermittently increases, and the impact of the water jet on the circular filter screen 304 generates a certain impact force. When the water jet pressure increases, the impact force also increases, causing the circular filter screen 304 to tilt further forward. The fixed shaft 301 rotates forward, and the torsion spring 302 tightens further. When the circular filter screen 304 tilts further, its upper part will contact the front iron brush 14. When the circular filter screen 304 with impurities rotates to this point, the dense metal bristles on the iron brush 14 will insert into the mesh of the circular filter screen 304, removing the sand or dirt stuck in it, thereby clearing the mesh and making the cleaning of the circular filter screen 304 more comprehensive and effective.
[0025] The impurities removed from the 304 circular filter screen still need to be properly handled, such as... Figure 1 , 4 As shown in Figure 8, the filter assembly 3 is tilted towards the water purification chamber 202 so that the filtered water can fall into the water purification chamber 202. A guide plate is fixed at the top of the partition 8, and the guide plate is tilted towards the water purification chamber 202. During the filtration process, the splashed sewage can flow back into the sewage chamber 201 under the action of the guide plate. A drain pipe connected to the inside of the water purification chamber 202 is fixed at the front end of the treatment tank 2. The water after two filtrations can be discharged out through the drain pipe.
[0026] The top of the partition 8 is provided with a small particle collection box 5. The front side of the small particle collection box 5 is provided with an inclined opening that fits with the filter assembly 3. Both ends of the small particle collection box 5 are provided with detachable end plates 16. The end plates 16 are fixedly installed on the upper edge of the treatment tank 2. The top of the small particle collection box 5 is provided with a mounting plate 7 by bolts. The front end of the mounting plate 7 extends to the front side of the small particle collection box 5. The iron brush 14 is detachably provided at the front end of the mounting plate 7.
[0027] When the water pressure is normal, the rear end of the circular filter screen 304 is in close contact with the front opening of the small particle collection box 5 under the elastic force of the slightly contracted torsion spring 302. Therefore, when the water pressure decreases from high to normal, the elastic force of the torsion spring 302 is released and drives the fixed shaft 301 to rotate, causing the circular filter screen 304 to rotate back and forth and return to its original position. The circular filter screen 304, which has rotated back to its original position, will collide with the small particle collection box 5. The rubber frame of the circular filter screen 304 can prevent damage from the impact. The impurities attached to its surface have been loosened by the action of the iron brush 14 and the preliminary brushing component 15. When the circular filter screen 304 collides with the small particle collection box 5 backward, the impurities with strong adhesion will fall off the circular filter screen 304 under the action of inertia and splash backward into the small particle collection box 5. Since the impurities are wet, they will adhere to the inner wall of the small particle collection box 5 after entering it, thus collecting the cleaned impurities inside the small particle collection box 5 and preventing these impurities from returning to the water, thereby preventing the accumulation of impurities.
[0028] Besides the impurities stuck in the mesh, surface impurities also need to be scrubbed and cleaned, such as... Figure 6 , 7 As shown, the mounting bracket 303 is provided with a preliminary brushing assembly 15 for cleaning the surface of the circular filter screen 304. The preliminary brushing assembly 15 includes a bracket 1501 fixedly mounted on the rear side of the mounting bracket 303. A central shaft is provided on the inner wall of the bracket 1501 via a rotating shaft. Two support plates 1503 are fixedly provided at the outer end of the central shaft. A spring 1502 fixedly connected to the mounting bracket 303 is fixedly provided on the support plate 1503 away from the circular filter screen 304. A detachable cleaning brush 1504 is provided on the support plate 1503 facing the circular filter screen 304. One end of the cleaning brush 1504 extends to the rear side of the circular filter screen 304 and contacts the surface of the circular filter screen 304. Ordinary brush bristles can be used for the bristles of the cleaning brush 1504.
[0029] During the process of the waterproof motor 305 driving the circular filter screen 304 to rotate, the circular filter screen 304 will pass through the preliminary brushing component 15, while the spring 1502 is in a compressed state. Its elastic force pushes the support plate 1503 connected to it upward, thereby causing the cleaning brush 1504 fixed on another support plate 1503 to come into close contact with the circular filter screen 304. As a result, the circular filter screen 304 that rotates and passes through this point will rub against the cleaning brush 1504. The cleaning brush 1504 thus plays a brushing role on the circular filter screen 304, cleaning the impurities attached to its surface and reducing the adhesion of the impurities on the circular filter screen 304, causing the impurities to loosen.
[0030] Wastewater needs to form a water column and be sprayed onto filter assembly 3, such as Figure 1 and 9As shown, the jet assembly 6 also includes two horizontal pipes 601 located above the treatment tank 2. One end of each horizontal pipe 601 is provided with a detachable vertical plate 10. The vertical plate 10 is fixedly installed on the upper edge of the treatment tank 2. Two nozzles 602 are respectively fixedly installed on the outer ends of the two horizontal pipes 601. A dual-outlet water pump 603 is provided between two horizontal pipes 601. The two horizontal pipes 601 are respectively connected to the two outlets of the dual-outlet water pump 603. A water delivery pipe 606 is provided at the inlet of the dual-outlet water pump 603. The bottom end of the water delivery pipe 606 extends into the sewage chamber 201 and is inserted into the sewage inside the sewage chamber 201. The bottom end of the water pipe 606 is inserted into the sewage inside the sewage chamber 201. The sewage is drawn out by the dual-outlet water pump 603 and flows into two horizontal pipes 601 respectively. The sewage that enters the horizontal pipes 601 is finally sprayed out through the nozzle 602.
[0031] To make the water pressure increase regularly and intermittently, such as Figure 1 , 9 As shown in Figure 10, a rubber bladder 604 is fixedly provided at the outer end of the transverse pipe 601, and a plurality of connecting ports 605 located inside the rubber bladder 604 are provided at the outer end of the transverse pipe 601. A drive motor 11 is fixedly mounted on the upright plate 10. An adjusting wheel 12 is fixedly mounted on one end of the output shaft of the drive motor 11. Two compression rollers 13 are provided on the outer end of the adjusting wheel 12. When the compression rollers 13 come into contact with the rubber bladder 604, they will roll. No sliding friction will occur between them, which reduces the wear of the rubber bladder 604. The two adjusting wheels 12 are located on the rear side of the two rubber bladders 604 respectively.
[0032] During this process, the sewage entering the horizontal pipe 601 will also enter the rubber bladder 604 through the connecting port 605. At the same time as water is sprayed, the drive motor 11 is turned on, and the drive motor 11 drives the adjusting wheel 12 and the squeezing roller 13 at its outer end to rotate. The adjusting wheel 12 rotates once every 5 seconds, and when the squeezing roller 13 rotates to the corresponding rubber bladder 604, it will squeeze the rubber bladder 604. The squeezing will cause the water pressure to increase at this moment, intermittently and regularly increasing the water pressure of the water column sprayed by the nozzle 602.
[0033] The specific steps of the construction site wastewater treatment method of the present invention are as follows: Step 1: Untreated sewage from the construction site enters the primary filter box 1 through the diversion channel 9. The sewage undergoes preliminary filtration through the primary filter screen 102 and then falls into the primary filter box 1. The primary filter screen 102 can only remove large solid impurities such as stones and soil from the sewage. Step 2: The wastewater that has undergone preliminary filtration in the primary filter box 1 enters the wastewater chamber 201 through the connecting port. Then, the dual-outlet water pump 603 is turned on, and the wastewater in the wastewater chamber 201 is sucked in through the water supply pipe 606. The wastewater is then introduced into the two horizontal pipes 601, and finally sprayed onto the filter assembly 3 through the nozzle 602. Step 3: While spraying wastewater, the drive motor 11 drives the adjusting wheel 12 to rotate and drive the squeezing roller 13. During the rotation, the squeezing roller 13 will contact the rubber bladder 604 and squeeze the rubber bladder 604, thereby increasing the water pressure of the wastewater, so that the water pressure of the wastewater changes continuously when it comes into contact with the filter component 3. Step 4: When the water pressure is normal, the rear side of the circular filter screen 304 contacts the front opening of the small particle collection box 5. The water jet sprayed from the nozzle 602 passes through the circular filter screen 304 and falls into the water purification chamber 202 at an angle below, thereby further filtering impurities in the sewage and removing small particles such as sand and mud. When the water pressure increases, the impact force of the water jet increases, causing the circular filter screen 304 to tilt further forward. This cycle continues, causing the circular filter screen 304 to swing back and forth. Step 5: While filtering, the waterproof motor 305 also drives the corresponding circular filter screen 304 to rotate, adjusting the direction of the circular filter screen 304 so that the part of the circular filter screen 304 in contact with the sewage is effectively cleaned. The lower part participating in the filtration work rotates upward to be cleaned, and the upper part after being cleaned rotates downward to perform the filtration work, and so on.
[0034] The foregoing has only described certain exemplary embodiments of the present invention by way of illustration. Undoubtedly, those skilled in the art can modify the described embodiments in various ways without departing from the spirit and scope of the present invention. Therefore, the foregoing drawings and descriptions are illustrative in nature and should not be construed as limiting the scope of protection of the claims of the present invention.
Claims
1. A construction site wastewater treatment device, comprising a primary filter box (1) and a treatment tank (2), wherein the treatment tank (2) is fixedly arranged on the front side of the primary filter box (1), characterized in that: A partition (8) is fixedly provided on the inner wall of the treatment pool (2), and the partition (8) divides the interior of the treatment pool (2) into a sewage chamber (201) and a clean water chamber (202); Two filter assemblies (3) are provided inside the treatment pool (2), the filter assemblies (3) comprising a fixed shaft (301) arranged on the inner wall of the treatment pool (2) via a rotating shaft, a torsion spring (302) being arranged between the fixed shaft (301) and the inner wall of the treatment pool (2), a detachable mounting frame (303) being arranged at the outer end of the fixed shaft (301), a circular filter screen (304) for filtering sewage being arranged at the front side of the mounting frame (303), and a waterproof motor (305) for driving the circular filter screen (304) to rotate being fixedly arranged at the rear side of the mounting frame (303); A jet assembly (6) is provided inside the sewage chamber (201), the jet assembly (6) comprising two nozzles (602), the two nozzles (602) respectively spraying sewage toward the lower halves of two circular filter screens (304), an iron brush (14) being provided obliquely below the upper halves of the circular filter screens (304), the bristles of the iron brush (14) being made of tough metal wire.
2. A construction site wastewater treatment device according to claim 1, characterized in that: The filter assembly (3) is tilted as a whole towards the water purification chamber (202); a guide plate is fixedly provided at the top of the partition plate (8); the guide plate is tilted towards the water purification chamber (202); and a drainage pipe communicating with the interior of the water purification chamber (202) is fixedly provided at the front end of the treatment tank (2).
3. A construction site wastewater treatment device according to claim 1, characterized in that: A small particle collection box (5) is provided on the top of the partition (8); an inclined opening is provided on the front side of the small particle collection box (5) and is fitted with the filter assembly (3); and detachable end plates (16) are provided at both ends of the small particle collection box (5); the end plates (16) are fixedly arranged on the upper edge of the treatment pool (2); A mounting plate (7) is provided at the top of the small particle collection box (5) via bolts, the front end of the mounting plate (7) extends to the front side of the small particle collection box (5), and the iron brush (14) is detachably provided at the front end of the mounting plate (7).
4. A construction site wastewater treatment device according to claim 1, characterized in that: A preliminary brushing assembly (15) for cleaning the surface of the circular filter screen (304) is provided on the rear side of the mounting frame (303), the preliminary brushing assembly (15) comprising a bracket (1501) fixedly arranged on the rear side of the mounting frame (303), a central axis being arranged on the inner wall of the bracket (1501) via a rotating shaft; Two support plates (1503) are fixedly provided at the outer end of the central shaft; a spring (1502) fixedly connected to the mounting frame (303) is fixedly provided on the support plate (1503) away from the circular filter screen (304); a detachable cleaning brush (1504) is provided on the support plate (1503) facing the circular filter screen (304); one end of the cleaning brush (1504) extends to the rear side of the circular filter screen (304) and contacts the surface of the circular filter screen (304).
5. A construction site wastewater treatment device according to claim 1, characterized in that: The top of the primary filter box (1) is connected to a flow guide channel (9) via a flange, a primary filter screen (102) for preliminary filtering of sewage is fixedly provided on the inner wall of the primary filter box (1), a discharge port (101) is provided on the front side of the primary filter box (1), and the front end of the primary filter screen (102) extends to the discharge port (101); A large particle collection box (4) for storing solid impurities is fixedly provided on the front side of the primary filter box (1), a cleaning door is provided on the front side of the large particle collection box (4) via hinges, and a communication port is provided on the front side of the primary filter box (1), the communication port being in communication with the interior of the sewage chamber (201).
6. A construction site wastewater treatment device according to claim 5, characterized in that: The jet assembly (6) further comprises two transverse pipes (601) located above the treatment pool (2), one end of the transverse pipe (601) being provided with a detachable vertical plate (10), the vertical plate (10) being fixedly arranged on the upper edge of the treatment pool (2), and the two nozzles (602) being respectively fixedly arranged on the outer ends of the two transverse pipes (601); A double-outlet water pump (603) is provided between the two transverse pipes (601), and the two transverse pipes (601) are respectively connected to two liquid outlets of the double-outlet water pump (603). A water delivery pipe (606) is provided at the liquid inlet of the double-outlet water pump (603), and the bottom end of the water delivery pipe (606) extends to the interior of the sewage chamber (201).
7. A construction site wastewater treatment device according to claim 6, characterized in that: A rubber bag (604) is fixedly provided at the outer end of the transverse pipe (601), and a plurality of communication ports (605) located inside the rubber bag (604) are opened at the outer end of the transverse pipe (601); A driving motor (11) is fixedly provided on the vertical plate (10), an adjusting wheel (12) is fixedly provided at one end of the output shaft of the driving motor (11), two squeezing rollers (13) are provided at the outer end of the adjusting wheel (12), and the two adjusting wheels (12) are respectively located at the rear sides of the two rubber bags (604).
8. A method for treating construction site wastewater according to any one of claims 1 to 7, characterized in that: The specific steps are as follows: Step 1: Untreated sewage from the construction site is input into the primary filter box (1) through the diversion channel (9), and the sewage is initially filtered through the primary filter screen (102) and then falls into the primary filter box (1); Step 2: The sewage that has been initially filtered in the primary filter box (1) enters the sewage chamber (201) through the connecting port, and then the dual-outlet water pump (603) is turned on to suck the sewage in the sewage chamber (201) through the water pipe (606), and then the sewage is introduced into the two horizontal pipes (601), and finally the sewage is sprayed toward the filter assembly (3) through the nozzle (602); Step 3: while spraying the sewage, the regulating wheel (12) is driven by the driving motor (11) to rotate and drive the squeezing roller (13); during the rotation process, the squeezing roller (13) contacts the rubber bag (604) and squeezes the rubber bag (604), thereby increasing the water pressure of the sewage, so that the water pressure of the sewage changes continuously when it contacts the filtering component (3); Step 4: When the water pressure is normal, the rear side of the circular filter (304) contacts the front opening of the small particle collection box (5), and the water column sprayed by the nozzle (602) passes through the circular filter (304) and falls into the water purification chamber (202) at an angle below, thereby further filtering impurities in the sewage. When the water pressure increases, the impact force of the water column increases, causing the circular filter (304) to further tilt toward the front side, and this cycle causes the circular filter (304) to swing back and forth; Step 5: While filtering, the waterproof motor (305) also drives the corresponding circular filter (304) to rotate, adjusting the direction of the circular filter (304) itself, so that the part of the circular filter (304) that contacts the sewage is effectively cleaned.
Citation Information
Patent Citations
A construction site wastewater treatment device
CN114275942B
Construction site wastewater treatment device
CN220633208U
Anti-blocking urban sewage treatment device
CN115784401A
Sewage filter tank
CN211097771U
Water-saving wheel washing machine
CN212796812U