Lifting device for erecting rolling mill housing

By using fixed beams, tension sensors and control modules in the lifting device of the rolling mill arch, the lifting process is monitored and adjusted in real time, the shaking problem during the erecting process of the rolling mill arch is solved, safety and efficiency are improved, and the stability of the structure is ensured. .

CN119079771APending Publication Date: 2024-12-06ZHONGSHAN YIMA HARDWARE CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411430030.6
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-10-14
Publication Date
2024-12-06

AI Technical Summary

Technical Problem

During the erecting of the rolling mill arch, the existing technology has shaking problems, resulting in damage to the structure and low safety, and the bending of the sling leads to shaking, affecting product quality and safe production.

Method used

A lifting device including fixed beam, tension sensor and control module is designed. By detecting the tension variance of the steel cable and the vertical angle of the rolling mill arch, the variance threshold and the stop time are adjusted, and the lifting process is monitored and adjusted in real time to reduce the lifting process. Shake and improve safety.

Benefits of technology

It effectively reduces shaking during lifting, improves safety and operating efficiency, reduces structural damage, and ensures the stable upright of the rolling mill arch.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119079771A_ABST
    Figure CN119079771A_ABST
Patent Text Reader

Abstract

The invention relates to a lifting device for erecting a rolling mill housing, which belongs to the technical field of equipment installation and comprises a fixed beam, the fixed beam comprises a plurality of central lifting lugs and a plurality of edge lifting lugs, and the plurality of central lifting lugs are arranged close to the middle of the fixed beam and are connected with a crane through steel cables; the plurality of edge lifting lugs are close to the edge of the fixed beam and are connected with the rolling mill housing through steel cables; the device further comprises a control module, the control module is electrically connected with a plurality of tension sensors, the tension sensors are arranged at the steel cables and correspond to the steel cables one to one, and the tension sensors are used for detecting the tension of the steel cables and uploading tension data to the control module. The control module judges whether the variance of the tension data is larger than a threshold value or not and gives an alarm when the judgment result is yes.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention belongs to the technical field of equipment installation, and in particular relates to a lifting device used for erecting a rolling mill arch. Background Art

[0002] The rolling mill arch is one of the key parts in the manufacture of steel rolling equipment. Its weight is generally around 40 to 400 tons and its height is generally around 8 to 16 meters. When the rolling mill is trial-assembled in the manufacturing plant and finally installed at the installation site, the rolling mill arch must be put in the final working upright state. Since the arch is a heavy and high sheet-like component, there are several difficulties in the erection process.

[0003] The general installation method is to set a lifting lug at one end of the mill arch, lay the mill arch horizontally and assemble the parts, then connect the lifting lug of the mill arch with the hook of the crane through a steel cable, and then the crane pulls the lifting lug through the steel cable to lift one end of the mill arch, and finally complete the erection of the mill arch. However, in this method, during the process of erecting and lifting the mill arch, the wire rope will interfere with the outer corner above the mill arch, which will not only scratch the machined surface of the mill arch or the corners of the mill arch will bite the wire rope, but also Moreover, the erection process of the rolling mill arch will be unstable due to the scraping, which makes the erection process of the rolling mill arch very unsafe, affecting product quality and safe production. For this reason, Chinese patent CN103496631B discloses a lifting method for erecting a rolling mill arch, the steps comprising: step 1) hanging one end of a total of four groups of equal-length steel wire ropes on the crane hook, and the other end on the two groups of hanging shafts on the inner side of the hanger beam, and hanging the two ends of the two groups of equal-length steel wire ropes on the two groups of hanging shafts on the outer side of the hanger beam, and the four groups of hanging Anti-slip plates 1 are installed at both ends of the shaft; step 2) the rolling mill arch is placed flat on the ground in advance, wooden blocks are placed under the rolling mill arch, and the middle parts of the two sets of equally long steel wire ropes 2 are hung on the two lifting ears of the rolling mill arch; step 3) during the process of erecting and lifting the rolling mill arch, the crane hook moves upward, and the crane hook also moves in the direction of rotation of the upper end of the rolling mill arch accordingly until the rolling mill arch is completely erected and lifted. The method has the characteristics of simple and easy operation, high safety. point; however, due to the extremely large mass of the rolling mill arch, the shaking during the lifting process will cause the structure of the rolling mill arch to be damaged under the action of its own weight. Therefore, during the lifting process, it is necessary to reduce the shaking of the rolling mill arch as much as possible. In the above structure, the crane and the sling are connected by a sling, and the sling and the lifting lug are connected by a sling. When one of the slings is bent, the whole structure will shake. For this reason, a lifting device for erecting the rolling mill arch with less impact of shaking during the lifting process is needed. Summary of the invention

[0004] In order to solve the above problems existing in the prior art, the present invention provides a lifting device for erecting a rolling mill arch, which has the characteristic of small impact caused by shaking during the lifting process.

[0005] The purpose of the present invention can be achieved through the following technical solutions:

[0006] A lifting device for erecting a mill arch, comprising a fixed beam, the fixed beam comprising a plurality of central lifting ears and a plurality of edge lifting ears, a plurality of the central lifting ears being arranged near the middle of the fixed beam and connected to the crane through steel cables, and a plurality of the edge lifting ears being arranged near the edges of the fixed beam and connected to the mill arch through steel cables;

[0007] It also includes a control module, which is electrically connected to a plurality of tension sensors, which are arranged at a plurality of steel cables and correspond to the plurality of steel cables one by one, and are used to detect the tension of the plurality of steel cables and upload the tension data to the control module, and the control module determines whether the variance of the plurality of tension data is greater than a threshold value, and issues an alarm when the determination result is yes.

[0008] As a preferred technical solution of the present invention, the control module is pre-input with a variance threshold S0, and the tension sensors are used to detect the tension p of the cables and upload the tension data p to the control module. The control module determines S p Whether it exceeds S0, and an alarm is issued if the judgment result is yes; where S p is the variance of some tension data p.

[0009] As a preferred technical solution of the present invention, the control module is electrically connected to an angle detector, which is used to detect the vertical angle of the rolling mill arch and upload the angle data to the control module. The control module increases the variance threshold when the angle data is greater than the threshold, and lowers the variance threshold when the angle data is greater than the threshold.

[0010] As a preferred technical solution of the present invention, the control module is pre-input with a reference angle a0, the angle detector is used to detect the vertical angle a of the rolling mill arch and upload the angle data a to the control module, the control module determines whether the variance of several tension data is greater than F0×A1, and issues an alarm when the judgment result is yes; wherein A1=a / a0×c, 0°≤a≤90°.

[0011] As a preferred technical solution of the present invention, it also includes a control panel, and the control panel is used to input the values ​​of a0, c and S0.

[0012] As a preferred technical solution of the present invention, the control module is pre-input with the standard value t0 of the crane's stop time. The control module is electrically connected to the crane and sets the crane's stop time instruction to t, where t=S p / S0×t0, the stop time is the time it takes for the crane to completely stop after the control module issues a stop command.

[0013] The beneficial effects of the present invention are:

[0014] (1) By setting up a number of tension sensors to detect the tension of a number of steel cables, and judging the consistency of the tension of the several steel cables according to the variance of the tension data of the several steel cables, and then judging whether shaking occurs during the erection process, and reminding the operator if the judgment result is yes, so as to reduce the impact of shaking during the lifting process;

[0015] (2) An angle detector is set to detect the lifting angle, and the control module is made to adjust the variance threshold according to the lifting angle. When the vertical angle a is small and the variance threshold for judging whether the variance is too large needs to be increased, the judgment standard is lowered, and when the vertical angle a is large, the judgment standard is maintained unchanged;

[0016] (3) By adjusting the crane stop time according to the variance of a number of tension data, the probability of accidents can be reduced when the shaking is large, and the operating efficiency can be improved when the shaking is small. BRIEF DESCRIPTION OF THE DRAWINGS

[0017] In order to facilitate understanding by those skilled in the art, the present invention is further described below with reference to the accompanying drawings.

[0018] Figure 1 It is a structural schematic diagram of the present invention;

[0019] Figure 2 It is a structural schematic diagram of the present invention when the lifting is completed;

[0020] Figure 3 It is a structural schematic diagram of the fixed beam of the present invention.

[0021] Description of main component symbols:

[0022] In the figure: 1. Fixed beam; 2. Lifting eye; 3. Rolling mill arch. DETAILED DESCRIPTION

[0023] In order to further explain the technical means and effects adopted by the present invention to achieve the predetermined invention purpose, the specific implementation methods, structures, features and effects of the present invention are described in detail below in conjunction with the accompanying drawings and preferred embodiments.

[0024] See also Figure 1-3A lifting device for erecting a mill arch, comprising a fixed beam 1, the fixed beam 1 comprising a plurality of central lifting ears 2 and a plurality of edge lifting ears 2, the plurality of central lifting ears 2 being arranged near the middle of the fixed beam 1 and connected to the crane through a steel cable, and the plurality of edge lifting ears 2 being arranged near the edge of the fixed beam 1 and connected to the mill arch 3 through a steel cable;

[0025] Specifically, the erection scheme of the rolling mill arch 3 is that the narrow side faces upward after the erection is completed, the fixed beam 1 is a quadrangular prism arranged parallel to the ground, the cross section of the quadrangular prism-shaped fixed beam 1 is a square, the axial length of the fixed beam 1 is consistent with the narrow side length of the rolling mill arch 3, one of the bottom surfaces of the regular quadrangular prism-shaped fixed beam 1 is parallel to the ground, and there are two side surfaces perpendicular to the ground, which are recorded as fixed surfaces, and each center lifting ear 2 is a cylindrical shape protruding from the fixed surface. In this embodiment, there are four center lifting ears 2, and the four center lifting ears 2 are arranged on two fixed surfaces in pairs, and the four center lifting ears 2 are symmetrically arranged around the geometric center of the fixed beam 1. Assuming that the axial length of the fixed beam 1 is a, the spacing between the two center lifting ears 2 on the same fixed surface is 0.1-0.2a;

[0026] At the same time, there are also four fixed lifting ears 2, each edge lifting ear 2 is also a cylindrical shape protruding from the fixed surface, and the four edge lifting ears 2 are arranged on the two fixed surfaces in pairs, and the four edge lifting ears 2 are symmetrically arranged around the geometric center of the fixed beam 1, and the spacing between the two center lifting ears 2 on the same fixed surface is 0.8-0.9a. Since the lifting ears 2 of the rolling mill arch 3 are arranged on both sides of the long side, the two edge lifting ears 2 are closer to the lifting ears 2 at the edge of the rolling mill arch 3;

[0027] When in use, the hook of the crane is located just above the geometric center of the fixed beam 1. At this time, the two center lifting ears 2 are close to the hook, and the two edge lifting ears 2 are close to the lifting ears 2 at the edges of the rolling mill arch 3. The four center lifting ears 2 are fixed to the crane through four steel cables, and the four edge lifting ears 2 are fixed to the lifting ears 2 of the rolling mill arch 3. Then the crane is raised, driving one end of the rolling mill arch 3 to tilt up, thereby completing the erection of the rolling mill arch 3.

[0028] During the above-mentioned erection process, due to the extremely large mass of the rolling mill arch 3, the shaking during the lifting process may cause the rolling mill arch 3 to be damaged under the action of its own weight. Therefore, during the lifting process, it is necessary to reduce the shaking of the rolling mill arch 3 as much as possible. In the above-mentioned structure, the crane and the sling are connected by a sling, and the sling and the lifting lug 2 are connected by a sling. When one of the slings is bent, the entire structure may shake. In order to detect the shaking in time, a control module is also included. The control module is electrically connected to a plurality of tension sensors, which are arranged at a plurality of steel cables and correspond to the plurality of steel cables one by one. The plurality of tension sensors are used to detect the tension of the plurality of steel cables and upload the tension data to the control module. The control module determines whether the variance of the plurality of tension data is greater than a threshold value, and issues an alarm when the judgment result is yes.

[0029] Specifically, the tension sensor is a steel cable tension meter arranged on the steel cable. The plurality of tension sensors upload the detected steel cable tension values ​​to the control module. At this time, the control module obtains the tension data of each steel cable. In this embodiment, there are 8 steel cables in total, so there are 8 tension data in total.

[0030] During the erection process, under normal circumstances, since the force is transmitted from the crane to the fixed beam 1 through the steel cable, and the fixed beam 1 is then transmitted to the rolling mill arch 3 through the steel cable, the forces on the steel cables are equal in the transmission direction. At this time, even if random errors and slight shaking are taken into account, the tension data of several steel cables are relatively close, and the variance of several tension data is small and below the threshold. At this time, the control module does not issue an alarm and continues to lift.

[0031] When the rolling mill arch 3 shakes, the relative positions of the lifting ears 2 on both sides of the rolling mill arch 3 will change, which will further cause the forces of the lifting ears 2 on the steel cables to change. At this time, the tension data of the steel cables deviate greatly from each other, and the variance of the tension data is large. When the variance is greater than the threshold, it means that the tension difference between the steel cables is large, and there is a greater probability of shaking. In the above process, specifically, the control module is pre-input with a variance threshold S0, and the tension sensors are used to detect the tension p of the steel cables and upload the tension data p to the control module. The control module determines S p Whether it exceeds S0; where S p is the variance of several tension data p, S0 is the pre-input variance reference value;

[0032] To ensure that the shaking is small during the lifting process, the control module determines S p When S0 is exceeded, the control module will sound an alarm to remind the operator that shaking has occurred. At this time, the operator will issue a stop command to the crane and check the cause of the shaking to ensure that the shaking is small during the lifting process;

[0033] By setting up a number of tension sensors to detect the tension of a number of steel cables, and judging the consistency of the tension of a number of steel cables according to the variance of the tension data of the several steel cables, it is further judged whether shaking occurs during the erection process, and the operating personnel are reminded when the judgment result is yes, thereby reducing the impact of shaking during the lifting process.

[0034] In the above process, since the rolling mill arch 3 is rotated during the erection process, when the lifting lug 2 of the rolling mill arch 3 is set on the side, perpendicular to the erection rotation direction, the lifting lug 2 also rotates around its own axis, and the steel cable needs to play a fixed role and will not rotate with the rotation of the lifting lug 2. Therefore, there is relative sliding between the steel cable and the lifting lug 2, that is, there is sliding friction between the lifting lug 2 and the steel cable. Under the action of friction, the tension of the steel cable in contact with different positions of the lifting lug 2 is different. For example, when the lifting lug 2 rotates, it automatically forms a part moving close to the fixed beam 1 and a part moving away from the fixed beam 1;

[0035] For the steel cable connecting the rolling mill arch 3 and the fixed beam 1, under the action of friction, the tension of the steel cable at the part moving with the lifting lug 2 close to the fixed beam 1 and the part moving away from the fixed beam 1 becomes smaller, and the tension of the steel cable at the part moving with the lifting lug 2 away from the fixed beam 1 and the part moving away from the fixed beam 1 becomes larger. At this time, the tension data uploaded by several tension sensors are affected by the friction and change. There is a probability that when no shaking occurs, the consistency of several tension data will cause the variance to exceed the variance threshold. At the same time, because in the process of erection, when the erection angle is small, the ground's support effect on the rolling mill arch 3 is small, the steel cable's bearing force is large, and the friction between the lifting lug 2 and the steel cable is large, the above tension data is affected by the friction and changes to a large extent;

[0036] Therefore, when the mill arch 3 is in the initial stage of the erection operation and the erection angle is small, there is a greater probability that the mill arch 3 does not shake, causing the variance to exceed the variance threshold and an alarm is issued, which in turn affects the operation efficiency. It is necessary to increase the variance threshold for judging whether the variance is too large and lower the judgment standard;

[0037] Similarly, when the mill arch 3 is in the second half of the erection operation and the erection angle is large, the foundation's support force on the mill arch 3 is large and the support effect is sufficient. At this time, the contact force between the mill lifting lug 2 and the steel cable is small, and the friction between the steel cable and the lifting lug 2 has little effect on the tension of the steel cable. At this time, there is no need to increase the variance threshold for judging whether the standard variance is too large, and lower the operation standard, that is, there is no need to change the variance;

[0038] Specifically, the control module is pre-input with a reference angle a0, the angle detector is used to detect the vertical angle a of the rolling mill arch 3 and upload the angle data a to the control module, the control module determines whether the variance of a number of tension data is greater than F0×A1, and issues an alarm when the judgment result is yes; wherein A1=a / a0×c, 0°≤a≤90°, a0 and c are both pre-input constants;

[0039] When the rolling mill arch 3 is in the initial stage of the erection operation and the erection angle a is small, it is necessary to increase the variance threshold for judging whether the variance is too large and lower the judgment standard. At this time, the value of A1=a / a0×c is large, and the judgment standard is lowered when the erection angle a is small;

[0040] When the rolling mill arch 3 is in the second half of the erection operation and the erection angle is large, there is no need to increase the variance threshold used to judge whether the standard variance is too large, and the operation standard is lowered. At this time, the value of A1=a / a0×c is small, and the judgment standard remains unchanged when the erection angle a is large;

[0041] An angle detector is set to detect the lifting angle, and the control module is made to adjust the variance threshold according to the lifting angle, so that when the vertical angle a is small and the variance threshold for judging whether the variance is too large needs to be increased, the judgment standard is lowered, and when the vertical angle a is large, the judgment standard is maintained unchanged;

[0042] In order to facilitate the input of the values ​​of a0, c and S0, a control panel is also included, and the control panel is used to input the values ​​of a0, c and S0.

[0043] When the tension data of several steel cables deviate greatly from each other, that is, the variance of several tension data is large, it means that the shaking is more severe. At this time, even if the crane needs to be stopped, the stopping time needs to be extended to make the crane stop slowly to prevent the speed change rate of the crane and the arch from being too large and causing accidents. For this reason, the control module is pre-input with the standard value t0 of the crane's stopping time. The control module is electrically connected to the crane and sets the crane's stopping time instruction to t, where t=S p / S0×t0, the stop time is the time when the crane stops completely after the control module issues a stop command, and t0 is the reference time input in advance;

[0044] Specifically, each time the control module issues a stop command, the control module continuously reduces the current output to the crane until the current is reduced to 0. The control module controls the reduction time and thus the reduction speed, thereby adjusting the stop time of the crane;

[0045] At a certain moment in the lifting process, the variance S of several tension data p When the speed is large, the crane stop time needs to be extended, at this time t = S pThe value of / S0×t0 is large, which prolongs the stop time of the crane;

[0046] When the variance S of several tension data p When it is smaller, it means the shaking is smaller. There is no need to extend the crane's stop time. Instead, the crane needs to be stopped as soon as possible, the stop time needs to be shortened, and the crane needs to be stopped as soon as possible. At this time, t = S p The smaller the value of / S0×t0 is, the shorter the stop time of the crane is.

[0047] By adjusting the crane stop time according to the variance of several tension data, the probability of accidents can be reduced when the shaking is large, and the operating efficiency can be improved when the shaking is small.

[0048] The working principle and use process of the present invention:

[0049] When in use, the hook of the crane is located just above the geometric center of the fixed beam 1. At this time, the two center lifting ears 2 are close to the hook, and the two edge lifting ears 2 are close to the lifting ears 2 at the edges of the rolling mill arch 3. The four center lifting ears 2 are fixed to the crane through four steel cables, and the four edge lifting ears 2 are fixed to the lifting ears 2 of the rolling mill arch 3. Then the crane is raised, driving one end of the rolling mill arch 3 to tilt up, thereby completing the erection of the rolling mill arch 3.

[0050] The above description is only a preferred embodiment of the present invention and does not limit the present invention in any form. Although the present invention has been disclosed as a preferred embodiment as above, it is not used to limit the present invention. Any technical personnel in this field can make some changes or modify the technical contents disclosed above into equivalent embodiments without departing from the scope of the technical solution of the present invention. However, any brief modifications, equivalent changes and modifications made to the above embodiments based on the technical essence of the present invention without departing from the content of the technical solution of the present invention are still within the scope of the technical solution of the present invention.

Claims

1. A lifting device for erecting a rolling mill arch, Features: It includes a fixed beam, the fixed beam includes a plurality of central lifting ears and a plurality of edge lifting ears, a plurality of the central lifting ears are arranged near the middle of the fixed beam and connected to the crane through steel cables, and a plurality of the edge lifting ears are arranged near the edge of the fixed beam and connected to the mill arch through steel cables; It also includes a control module, which is electrically connected to a plurality of tension sensors, which are arranged at a plurality of steel cables and correspond to the plurality of steel cables one by one, and are used to detect the tension of the plurality of steel cables and upload the tension data to the control module, and the control module determines whether the variance of the plurality of tension data is greater than a threshold value, and issues an alarm when the determination result is yes.

2. A lifting device for erecting a rolling mill arch according to claim 1, Features: The control module is pre-input with a variance threshold S0, and the tension sensors are used to detect the tension p of the cables and upload the tension data p to the control module. The control module determines S p Whether it exceeds S0, and an alarm is issued if the judgment result is yes; where S p is the variance of some tension data p.

3. A lifting device for erecting a rolling mill arch according to claim 1, Features: The control module is electrically connected to an angle detector, which is used to detect the vertical angle of the rolling mill arch and upload the angle data to the control module. The control module increases the variance threshold when the angle data is greater than the threshold, and reduces the variance threshold when the angle data is greater than the threshold.

4. A lifting device for erecting a rolling mill arch according to claim 3, Features: The control module is pre-input with a reference angle a0, the angle detector is used to detect the vertical angle a of the rolling mill arch and upload the angle data a to the control module, the control module determines whether the variance of several tension data is greater than F0×A1, and issues an alarm when the judgment result is yes; wherein A1=a / a0×c, 0°≤a≤90°.

5. A lifting device for erecting a rolling mill arch according to claim 4, Features: A control panel is also included, and the control panel is used to input the values ​​of a0, c and S0.

6. A lifting device for erecting a rolling mill arch according to claim 1, Features: The control module is pre-input with the standard value t0 of the crane's stop time. The control module is electrically connected to the crane and sets the crane's stop time instruction to t, where t=S p / S0×t0, the stop time is the time it takes for the crane to completely stop after the control module issues a stop command.