By installing cladding on the coal spray pipe, dust feed pipe and deflector of the tin smelting top blower gun, the problem of easy erosion and leakage of the spray gun is solved, extending the service life and improving wear resistance, and is suitable for High temperature and high pressure environment.

CN119082482APending Publication Date: 2024-12-06YUNNAN TIN CO LTD TIN BRANCH
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411209158.X
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-08-30
Publication Date
2024-12-06

AI Technical Summary

Technical Problem

In the application of the existing tin smelting top blowing furnace spray guns in the application of high-efficiency melting pool smelting technology of dry powder materials, the pulverized coal connecting pipe and dust feeding pipe are prone to flushing and leakage, resulting in a short service life and affecting production efficiency and cost.

Method used

The coal spraying pipe, dust feeding pipe, gun barrel and sleeve air duct structure are arranged at intervals between the inner and outer upper and lower sides, and a cladding layer is provided on its outer and inner walls. A third cladding layer is provided between the diversion plate gap, and through the stack Welding forms a wear-resistant layer to improve wear-resistant performance.

Benefits of technology

Effectively prevents rapid wear of the spray gun, extends service life, improves production efficiency, and reduces maintenance costs. It is suitable for high-temperature, high-pressure and solid-particle airflow environments.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119082482A_ABST
    Figure CN119082482A_ABST
Patent Text Reader

Abstract

The invention discloses a spray gun for a tin smelting top-blown furnace. The spray gun comprises a coal injection pipe, a dust conveying pipe, a spray gun pipe and a sleeve air pipe which are arranged at intervals from inside to outside and sequentially and coaxially sleeved from inside to outside. A first cladding layer is arranged on the outer wall of the top of the coal injection duct; a second cladding layer is arranged on the inner wall, corresponding to the first cladding layer, of the dust conveying pipe; a plurality of guide plates are fixed on the outer wall of the coal injection pipe, and gaps are formed between the peripheral sides of the guide plates and the inner wall of the dust conveying pipe; a third cladding layer is arranged on the periphery of the guide plate; wherein the top end face of the dust conveying pipe is bolted with the bottom end face of the mounting seat; the top outer wall of the dust conveying pipe is bolted with the top end surface of the spray gun pipe; the coal injection pipe is slidably connected to an inner cavity of the dust conveying pipe, and the top end of the coal injection pipe communicates with pulverized coal equipment through a pipeline. According to the method, practical requirements and experience teaching training in tin smelting production practice are fully combined, existing production equipment is used for transformation, the transformation is minimum, but the effect is remarkable, and the equipment investment cost is greatly reduced.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of nonferrous metal smelting, and more particularly to a spray gun for a tin smelting top-blown furnace. Background Art

[0002] The tin smoke and recycled tin-containing materials generated in the original tin smelting process are first pelletized by a granulator, then transported to a top-blown furnace for further smelting after being reasonably mixed with tin concentrate by a belt conveyor. With the application of the high-efficiency molten pool smelting technology of dry powder materials in the independent top-blown furnace, the existing spray gun can no longer meet the production needs.

[0003] The spray gun is a key component of the top-blown molten pool smelting furnace. During production, the spray gun needs to be lowered and inserted into the high-temperature molten pool in the furnace to spray fuel, air or oxygen-enriched air into the furnace and stir the molten pool. The spray gun needs to be taken out of the furnace when production is finished or the furnace is shut down in an emergency. The existing spray gun is mainly divided into four layers, namely the pulverized coal connecting pipe, the dust delivery pipe, the spray gun pipe and the sleeve air duct. Due to the application of efficient molten pool smelting technology for dry powder materials, the smoke needs to be mixed into the spray gun air, and dry powder materials such as tin smoke need to enter the molten pool from the dust delivery pipe. This causes the original pulverized coal connecting pipe and dust delivery pipe to be frequently flushed and leaked, seriously affecting production.

[0004] Therefore, how to provide a spray gun for a tin smelting top-blown furnace with a simple structure and improved wear resistance without changing the original structure is a problem that technical personnel in this field urgently need to solve. Summary of the invention

[0005] In view of this, the present invention provides a spray gun for a tin smelting top-blown furnace, which solves the problem of short service life of the spray gun in the prior art, improves production efficiency and reduces costs.

[0006] In order to achieve the above object, the present invention adopts the following technical solution:

[0007] A spray gun for a tin smelting top-blown furnace, comprising:

[0008] The coal injection pipe, dust delivery pipe, spray gun pipe and sleeve air duct are arranged at intervals inside and outside and coaxially sleeved in sequence from inside to outside;

[0009] The outer wall of the top of the coal injection pipe is provided with a first cladding layer; the inner wall of the dust delivery pipe corresponding to the first cladding layer is provided with a second cladding layer; a plurality of guide plates are fixed to the outer wall of the coal injection pipe, and there is a gap between the peripheral sides of the plurality of guide plates and the inner wall of the dust delivery pipe; the outer periphery of the guide plate is provided with a third cladding layer;

[0010] Among them, the top end surface of the dust delivery pipe is bolted to the bottom end surface of the mounting seat; the top outer wall of the dust delivery pipe is bolted to the top end surface of the spray gun pipe; the top outer wall of the spray gun pipe is bolted to the top end surface of the sleeve air duct, and the coal injection pipe is slidably connected to the inner cavity of the dust delivery pipe and its top end is connected to the pulverized coal equipment through a pipeline.

[0011] The beneficial effects of the above technical solution are: the first cladding layer improves the resistance of the coal injection pipe to material erosion and high temperature environment, effectively preventing the rapid wear of the coal injection pipe; the second cladding layer improves the wear resistance inside the dust conveying pipe, preventing wear caused by frequent erosion of molten materials; the third cladding layer enables the guide plate to maintain a stable working state for a long time in a high temperature and high-speed airflow environment, effectively improving the service life of the spray gun.

[0012] Preferably, the coal injection pipe comprises a pulverized coal delivery pipe and a pulverized coal connecting pipe, the outer wall of the bottom end of the pulverized coal delivery pipe is welded and fixed to the inner wall of the top end of the pulverized coal connecting pipe, the top end of the pulverized coal delivery pipe is connected to the pulverized coal equipment through a hose, and the outer wall of the pulverized coal delivery pipe is welded to form the first cladding layer. The coal injection pipe is designed as two parts and is welded and fixed, and the first cladding layer formed by the cladding of the outer wall of the pulverized coal delivery pipe can form a solid wear-resistant layer on its outer surface, which greatly improves the resistance of the pulverized coal delivery pipe to material scouring and high temperature environment, and effectively prevents the rapid wear of the pulverized coal delivery pipe.

[0013] Preferably, the dust delivery pipe comprises a smoke conveying pipe and a smoke connecting pipe, the bottom end surface of the smoke conveying pipe is fixed to the top end surface of the smoke connecting pipe, a first connecting pipe connected to the inner cavity of the smoke conveying pipe is fixed vertically to the outer wall of the smoke conveying pipe to connect the smoke conveying equipment, and the inner walls of the smoke conveying pipe and the first connecting pipe are both welded to form the second cladding layer;

[0014] The top of the smoke conveying pipe is bolted to the bottom end surface of the mounting seat through a first connecting flange; the pulverized coal connecting pipe is coaxially sleeved in the inner cavity of the smoke connecting pipe, and the guide plate is fixed to the outer wall of the pulverized coal connecting pipe.

[0015] The beneficial effect of the above technical solution is that the inner wall of the smoke conveying pipe is welded to form a second cladding layer to form a wear-resistant protective layer on the inner surface of the smoke conveying pipe, so that it can still maintain a stable working state in a high temperature and high pressure environment, avoiding performance degradation and frequent maintenance due to wear, which not only extends its service life, but also improves its reliability in high temperature, high pressure, and airflow environments containing solid particles.

[0016] Preferably, it also includes a conical connecting pipe, the inner diameter of the smoke conveying pipe is larger than the inner diameter of the smoke conveying pipe, the large end of the conical connecting pipe is bolted to the bottom end face of the smoke conveying pipe, and the outer wall of the small end is welded and fixed to the inner wall of the top end of the smoke conveying pipe; the inner wall of the conical connecting pipe is welded to form a fourth cladding layer, and the sum of the lengths of the conical connecting pipe and the smoke conveying pipe is equal to the length of the pulverized coal conveying pipe. The conical connecting pipe can optimize the airflow, ensure that the dust can be efficiently transported and fully mixed with the smelting materials, thereby improving the efficiency and quality of the smelting process. The inner wall is welded to form a fourth cladding layer, so that its inner surface has a wear-resistant protective layer, so that it can still maintain a good condition under frequent smoke scouring, thereby effectively preventing performance degradation due to wear.

[0017] Preferably, the spray gun tube comprises an oxygen delivery tube and an oxygen connecting tube which are integrally formed, and the inner diameter of the oxygen delivery tube is larger than the inner diameter of the oxygen connecting tube;

[0018] A second connecting pipe connected to the inner cavity of the oxygen delivery pipe is fixed vertically to the outer wall of the oxygen delivery pipe to connect the oxygen supply equipment; the top end surface of the oxygen delivery pipe is bolted to the bottom end surface of the smoke delivery pipe through a second connecting flange, and the smoke connection pipe is coaxially and spacedly sleeved in the inner cavity of the oxygen connection pipe. The spray gun pipe provides oxygen provided by pulverized coal combustion, and the detachable connection method is convenient for maintenance.

[0019] Preferably, a third connecting pipe connected to the inner cavity of the sleeve air duct is fixed vertically to the outer wall of the top end of the sleeve air duct to connect the air supply equipment, the top end surface of the sleeve air duct is bolted to the bottom end surface of the oxygen delivery pipe through a third connecting flange, the oxygen delivery pipe is coaxially and spacedly sleeved in the inner cavity of the sleeve air duct, and the length of the oxygen connecting pipe is greater than that of the sleeve air duct. The sleeve air duct blows air into the top-blown furnace to improve combustion efficiency.

[0020] Preferably, the first connecting pipe, the second connecting pipe and the third connecting pipe are located on the same side of the spray gun, so as to facilitate connection with external equipment.

[0021] Preferably, the guide plate includes a support block and a connection block, the peripheral side of the support block is welded to form the third cladding layer; the bottom end of the connection block is fixed to the top of the support block, and the top cross-section of the connection block is conical for guiding. The third cladding layer formed by the stacking of the peripheral side of the guide plate support block can ensure that the guide plate can still maintain a good state under the scouring of high-speed airflow and solid particles, and the conical connection block enhances the wear resistance and support capacity of the guide plate.

[0022] Preferably, the guide plate has a length of 200 mm, a width of 10 mm, and a thickness of 28 mm, and a side wall of the guide plate in the length direction is fixed to the outer wall of the coal injection pipe, which significantly enhances the internal structural stability of the lance.

[0023] Preferably, there are no less than two guide plates along the radial direction of the coal injection pipe, and the axial distance between two adjacent guide plates along the coal injection pipe is 1.5m. Multiple guide plates arranged at intervals effectively avoid excessive wear caused by the scouring of high-speed airflow and solid particles, improve the overall operating efficiency of the spray gun, and provide reliable guarantee for long-term use.

[0024] It can be seen from the above technical solutions that, compared with the prior art, the present invention discloses a spray gun for a tin smelting top-blown furnace, which fully combines the actual needs and lessons learned in the tin smelting production practice, and uses the existing production equipment for transformation, with minimal changes and significant effects, greatly reducing the equipment investment cost. These improvement measures can not only be directly applied to existing equipment to improve the utilization rate of the original equipment, but also have a simple structural design, which is easy to maintain and promote in the future. BRIEF DESCRIPTION OF THE DRAWINGS

[0025] In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are only embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on the provided drawings without paying creative work.

[0026] Figure 1 A cross-sectional view of the spray gun provided by the present invention;

[0027] Figure 2 for Figure 1 A magnified schematic diagram of part A in FIG.

[0028] Figure 3 A schematic diagram of the structure of the pulverized coal conveying pipe provided by the present invention;

[0029] Figure 4 A half-section schematic diagram of a smoke conveying pipe provided by the present invention;

[0030] Figure 5 A half-section schematic diagram of a tapered connecting pipe provided by the present invention;

[0031] Figure 6 This is a schematic diagram of the guide plate structure provided by the present invention.

[0032] in,

[0033] 1- sleeve air duct; 11- third connecting pipe;

[0034] 2-spray gun pipe; 21-oxygen delivery pipe; 22-oxygen connecting pipe; 23-second connecting pipe;

[0035] 3-dust delivery pipe; 31-smoke conveying pipe; 32-smoke connecting pipe; 33-first connecting pipe; 34-second cladding layer; 35-conical connecting pipe; 36-fourth cladding layer;

[0036] 4-coal injection pipe; 41-pulverized coal conveying pipe; 42-pulverized coal connecting pipe; 43-first cladding layer;

[0037] 5-guide plate; 51-support block; 52-connecting block; 53-third cladding layer;

[0038] 6-first connecting flange; 7-second connecting flange; 8-third connecting flange. DETAILED DESCRIPTION

[0039] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0040] See attached Figures 1 to 6 The embodiment of the present invention discloses a spray gun for a tin smelting top-blown furnace, which transforms the existing spray gun structure. Although the modification is small, the service life of the spray gun can be greatly improved, including:

[0041] The coal injection pipe 4, the dust delivery pipe 3, the spray gun pipe 2 and the sleeve air duct 1 are arranged at intervals inside and outside and coaxially sleeved in sequence from inside to outside;

[0042] The top outer wall of the coal injection pipe 4 is provided with a first cladding layer 43; the inner wall of the dust conveying pipe 3 corresponding to the first cladding layer 43 is provided with a second cladding layer 34; a plurality of guide plates 5 are fixed to the outer wall of the coal injection pipe 4, and there is a gap between the peripheral sides of the plurality of guide plates 5 and the inner wall of the dust conveying pipe 3; the outer periphery of the guide plate 5 is provided with a third cladding layer 53;

[0043] Among them, the top end surface of the dust delivery pipe 3 is bolted to the bottom end surface of the mounting seat; the top outer wall of the dust delivery pipe 3 is bolted to the top end surface of the spray gun pipe 2; the top outer wall of the spray gun pipe 2 is bolted to the top end surface of the sleeve air duct 1, and the coal injection pipe 4 is slidably connected to the inner cavity of the dust delivery pipe 3 and its top end is connected to the pulverized coal equipment through a pipeline.

[0044] In order to further optimize the above technical solution, the coal injection pipe 4 includes a pulverized coal conveying pipe 41 and a pulverized coal connecting pipe 42. The outer wall of the bottom end of the pulverized coal conveying pipe 41 is welded and fixed to the inner wall of the top end of the pulverized coal connecting pipe 42. The top end of the pulverized coal conveying pipe 41 is connected to the pulverized coal equipment through a hose. The outer wall of the pulverized coal conveying pipe 41 is welded to form a first cladding layer 43.

[0045] It should be noted that surfacing is an economical and fast process for modifying the surface of materials. Surfacing is a process in which a material with certain properties is melted onto the surface of a workpiece by welding. Surfacing is not for connecting workpieces, but for changing the surface properties of workpieces to obtain a cladding layer with special properties such as wear resistance, heat resistance, and corrosion resistance, or to repair workpieces (restore insufficient dimensions caused by severe wear of the workpiece and processing errors). Surfacing is characterized by high bonding strength, good impact resistance, cost savings, good economy, and strong operability. In order to most effectively play the role of the surfacing layer, the surfacing method used has less base material dilution, higher deposition speed, and excellent surfacing layer performance, that is, high-quality, high-efficiency, and low-dilution surfacing technology.

[0046] In this embodiment, the pulverized coal conveying pipe is a DN100 304 stainless steel pipe with a surfacing height of 3 mm. This treatment method greatly improves the resistance of the coal injection pipe to material scouring environments. The use of wear-resistant surfacing electrodes for multi-layer surfacing treatment significantly improves its wear resistance and effectively prevents the rapid wear of the pulverized coal conveying pipe, thereby extending its service life.

[0047] Through this treatment, the coal injection pipe can not only maintain stable performance in harsh working environments, but also significantly reduce the frequency of maintenance and replacement due to wear, thereby improving the overall operating efficiency of the equipment.

[0048] In order to further optimize the above technical solution, the dust delivery pipe 3 includes a smoke delivery pipe 31 and a smoke connection pipe 32. The bottom end surface of the smoke delivery pipe 31 is fixed to the top end surface of the smoke connection pipe 32. A first connection pipe 33 connected to the inner cavity of the vertical smoke delivery pipe 31 is fixed to the outer wall of the vertical smoke delivery pipe 31 to connect the smoke delivery equipment. The inner walls of the smoke delivery pipe 31 and the first connection pipe 33 are both welded to form a second cladding layer 34.

[0049] The top of the smoke conveying pipe 31 is bolted to the bottom end surface of the mounting seat through the first connecting flange 6 ; the pulverized coal connecting pipe 42 is coaxially sleeved in the inner cavity of the smoke connecting pipe 32 , and the guide plate 5 is fixed to the outer wall of the pulverized coal connecting pipe 42 .

[0050] In this embodiment, the smoke conveying pipe and the first connecting pipe are integrally prepared into a three-way pipe, which is used to connect the coal injection pipe, the dust conveying pipe and the sleeve air duct to ensure that the pulverized coal and smoke are transported to the furnace bottom molten pool according to the predetermined path. The three-way formed by the smoke conveying pipe and the first connecting pipe is made of 316L stainless steel, which has extremely strong corrosion resistance and stability in high temperature environment, and is particularly suitable for use in harsh industrial environments; its inner wall uses high-hardness wear-resistant materials through multi-layer cladding technology to form a second cladding layer as a wear-resistant protective layer, and the cladding height is 3mm, which significantly enhances the wear resistance of the three-way, so that it can still maintain a stable working state in a high temperature and high pressure environment, avoiding performance degradation and frequent maintenance requirements caused by wear. Through this treatment, the three-way not only extends its service life, but also improves its reliability in high temperature, high pressure, and air flow environments containing solid particles. In addition, the presence of the wear-resistant layer greatly reduces maintenance costs and improves the operating efficiency of the entire system. By performing multi-layer surfacing treatment on the inner wall of the tee, the smooth and stable transportation of pulverized coal and smoke is ensured, thereby further optimizing the overall performance of the dust conveying pipeline.

[0051] Through the above-mentioned optimized design, the tee at the top of the dust delivery pipe performs well in the working environment of high temperature, high pressure and high wear, ensuring the efficient transportation of pulverized coal and smoke, and providing reliable guarantee for the long-term stable operation of the system.

[0052] In order to further optimize the above technical solution, it also includes a conical connecting pipe 35, the inner diameter of the smoke conveying pipe 31 is larger than the inner diameter of the smoke conveying pipe 32, the large end of the conical connecting pipe 35 is bolted to the bottom end face of the smoke conveying pipe 31, and the outer wall of the small end is welded and fixed to the inner wall of the top end of the smoke conveying pipe 32; the inner wall of the conical connecting pipe 35 is welded to form a fourth cladding layer 36, and the sum of the lengths of the conical connecting pipe 35 and the smoke conveying pipe 31 is equal to the length of the pulverized coal conveying pipe 41.

[0053] The conical connecting pipe is designed to optimize the airflow, ensure that the dust can be efficiently transported and fully mixed with the smelting materials, thereby improving the efficiency and quality of the smelting process. The conical connecting pipe is made of 4mm thick 304 stainless steel, which not only has good corrosion resistance, but also can maintain stable mechanical properties in high temperature environment. The inner wall is clad to form a fourth cladding layer as a wear-resistant layer. The cladding height is 3mm. Special high-temperature and wear-resistant welding materials are used. Through multi-layer cladding treatment, the wear resistance of the dust pipe is significantly enhanced, so that it can remain in good condition under frequent smoke and dust scouring, thereby effectively preventing performance degradation caused by wear. The existence of the wear-resistant layer extends the service life of the dust pipe and further improves the operating efficiency of the equipment.

[0054] After testing, it was found that the conical connecting pipe performed excellently in the high-temperature and high-wear smelting environment, ensuring the efficient transportation and full mixing of smoke and dust, and providing reliable protection for the smelting process.

[0055] In order to further optimize the above technical solution, the spray gun tube 2 includes an oxygen delivery tube 21 and an oxygen connecting tube 22 which are integrally formed, and the inner diameter of the oxygen delivery tube 21 is larger than the inner diameter of the oxygen connecting tube 22;

[0056] A second connecting pipe 23 communicating with the inner cavity of the vertical oxygen delivery pipe 21 is fixed to the outer wall thereof to connect the oxygen supply equipment; the top end surface of the oxygen delivery pipe 21 is bolted to the bottom end surface of the smoke delivery pipe 31 through a second connecting flange 7, and the smoke connecting pipe 32 is coaxially and spacedly sleeved in the inner cavity of the oxygen connecting pipe 22.

[0057] A third connecting pipe 11 connected to the inner cavity of the vertical sleeve air duct 1 is fixed on the outer wall of the top end thereof to connect to the air supply equipment. The top end surface of the sleeve air duct 1 is bolted to the bottom end surface of the oxygen delivery pipe 21 through a third connecting flange 8. The oxygen delivery pipe 21 is coaxially and spacedly sleeved in the inner cavity of the sleeve air duct 1, and the length of the oxygen connecting pipe 22 is greater than the length of the sleeve air duct 1.

[0058] The sleeve air duct is bolted to the oxygen delivery pipe, and the oxygen connecting pipe is inserted into the inner cavity of the sleeve air duct; the oxygen delivery pipe is bolted to the smoke delivery pipe, and the smoke connecting pipe is inserted into the inner cavity of the oxygen connecting pipe; the pulverized coal connecting pipe is inserted into the inner cavity of the smoke connecting pipe, and a spray gun is formed by a multi-layer stacked sleeve structure.

[0059] In this embodiment, in order to facilitate the connection between the spray gun and external equipment, the first connecting pipe 33, the second connecting pipe 23 and the third connecting pipe 11 are located on the same side of the spray gun.

[0060] In order to further optimize the above technical solution, the guide plate 5 includes a support block 51 and a connecting block 52. The peripheral side of the support block 51 is welded to form a third cladding layer 53. The bottom end of the connecting block 52 is fixed to the top end of the support block 51, and the top cross-section of the connecting block 52 is conical for diversion.

[0061] The guide plate is made of 310 stainless steel plate, which has excellent high temperature resistance and corrosion resistance, and is very suitable for use in high temperature and harsh environments; the peripheral side of the support block of the guide plate is welded to form a third cladding layer used as a wear-resistant layer, with a welding height of 5mm. High-hardness and high-temperature resistant welding materials are used to ensure that the guide plate can still maintain a good condition under the scouring of high-speed airflow and solid particles; a conical connecting block is embedded in the top of the support block to further enhance the wear resistance and supporting capacity of the blade.

[0062] In order to further optimize the above technical solution, the guide plate 5 has a length of 200 mm, a width of 10 mm, and a thickness of 28 mm. One side wall of the guide plate 5 in the length direction is fixed to the outer wall of the coal injection pipe 4 .

[0063] The size of the guide plate meets the actual use requirements and significantly enhances the internal structural stability of the spray gun. The presence of the wear-resistant layer greatly improves the wear resistance of the supporting blades, effectively avoiding excessive wear caused by the scouring of high-speed airflow and solid particles, thereby extending the service life of the blades and reducing the frequency of maintenance and replacement.

[0064] In order to further optimize the above technical solution, there are no less than two guide plates 5 along the radial direction of the coal injection pipe 4, and the axial distance between two adjacent guide plates 5 along the coal injection pipe 4 is 1.5m. The purpose of this arrangement is to support the gap between the dust delivery pipe and the coal injection pipe to prevent the spray gun from swinging for a long time during use due to the large gap between the coal injection pipe and the dust delivery pipe, thereby causing breakage or falling off.

[0065] In this specification, each embodiment is described in a progressive manner, and each embodiment focuses on the differences from other embodiments. The same or similar parts between the embodiments can be referred to each other. For the device disclosed in the embodiment, since it corresponds to the method disclosed in the embodiment, the description is relatively simple, and the relevant parts can be referred to the method part.

[0066] The above description of the disclosed embodiments enables one skilled in the art to implement or use the present invention. Various modifications to these embodiments will be apparent to one skilled in the art, and the general principles defined herein may be implemented in other embodiments without departing from the spirit or scope of the present invention. Therefore, the present invention will not be limited to the embodiments shown herein, but rather to the widest scope consistent with the principles and novel features disclosed herein.

Claims

1. A spray gun for a tin smelting top-blown furnace, characterized in that: include: A coal injection pipe (4), a dust delivery pipe (3), a spray gun pipe (2) and a sleeve air duct (1) are arranged at intervals inside and outside and are coaxially sleeved in sequence from the inside to the outside; The top outer wall of the coal injection pipe (4) is provided with a first cladding layer (43); the inner wall of the dust conveying pipe (3) corresponding to the first cladding layer (43) is provided with a second cladding layer (34); a plurality of guide plates (5) are fixed to the outer wall of the coal injection pipe (4), and there is a gap between the peripheral sides of the plurality of guide plates (5) and the inner wall of the dust conveying pipe (3); the outer periphery of the guide plate (5) is provided with a third cladding layer (53); The top end surface of the dust conveying pipe (3) is bolted to the bottom end surface of the mounting seat; the top outer wall of the dust conveying pipe (3) is bolted to the top end surface of the spray gun pipe (2); the top outer wall of the spray gun pipe (2) is bolted to the top end surface of the sleeve air duct (1); the coal injection pipe (4) is slidably connected to the inner cavity of the dust conveying pipe (3) and its top end is connected to the pulverized coal equipment through a pipeline.

2. The spray gun for a tin smelting top-blown furnace according to claim 1, characterized in that: The coal injection pipe (4) comprises a pulverized coal conveying pipe (41) and a pulverized coal connecting pipe (42); the outer wall of the bottom end of the pulverized coal conveying pipe (41) is welded and fixed to the inner wall of the top end of the pulverized coal connecting pipe (42); the top end of the pulverized coal conveying pipe (41) is connected to the pulverized coal equipment via a hose; the outer wall of the pulverized coal conveying pipe (41) is welded to form the first cladding layer (43).

3. The spray gun for a tin smelting top-blown furnace according to claim 2, characterized in that: The dust conveying pipe (3) comprises a smoke conveying pipe (31) and a smoke connecting pipe (32); the bottom end surface of the smoke conveying pipe (31) is fixed to the top end surface of the smoke connecting pipe (32); a first connecting pipe (33) in communication with the inner cavity of the smoke conveying pipe (31) is fixed perpendicularly to the outer wall of the smoke conveying pipe (31) to connect with a smoke conveying device; the inner walls of the smoke conveying pipe (31) and the first connecting pipe (33) are both welded to form the second cladding layer (34); The top end of the smoke conveying pipe (31) is bolted to the bottom end surface of the mounting seat via a first connecting flange (6); the pulverized coal connecting pipe (42) is coaxially sleeved in the inner cavity of the smoke connecting pipe (32), and the guide plate (5) is fixed to the outer wall of the pulverized coal connecting pipe (42).

4. The spray gun for a tin smelting top-blown furnace according to claim 3, characterized in that: It also comprises a conical connecting pipe (35), the inner diameter of the smoke conveying pipe (31) is larger than the inner diameter of the smoke conveying pipe (32), the large end of the conical connecting pipe (35) is bolted to the bottom end surface of the smoke conveying pipe (31), and the outer wall of the small end is welded and fixed to the inner wall of the top end of the smoke conveying pipe (32); the inner wall of the conical connecting pipe (35) is welded to form a fourth cladding layer (36), and the sum of the lengths of the conical connecting pipe (35) and the smoke conveying pipe (31) is equal to the length of the pulverized coal conveying pipe (41).

5. The spray gun for a tin smelting top-blown furnace according to claim 3, characterized in that: The spray gun tube (2) comprises an oxygen delivery tube (21) and an oxygen connecting tube (22) which are integrally formed, and the inner diameter of the oxygen delivery tube (21) is larger than the inner diameter of the oxygen connecting tube (22); A second connecting pipe (23) is fixed vertically to the outer wall of the oxygen delivery pipe (21) and is in communication with the inner cavity thereof so as to connect to an oxygen supply device; the top end surface of the oxygen delivery pipe (21) is bolted to the bottom end surface of the smoke delivery pipe (31) via a second connecting flange (7), and the smoke connection pipe (32) is coaxially and spacedly sleeved in the inner cavity of the oxygen connection pipe (22).

6. The spray gun for a tin smelting top-blown furnace according to claim 5, characterized in that: A third connecting pipe (11) is fixed vertically to the outer wall of the top end of the sleeve air duct (1) and is in communication with the inner cavity thereof to connect to an air supply device; the top end surface of the sleeve air duct (1) is bolted to the bottom end surface of the oxygen delivery pipe (21) via a third connecting flange (8); the oxygen delivery pipe (21) is coaxially and spacedly sleeved in the inner cavity of the sleeve air duct (1); and the length of the oxygen connecting pipe (22) is greater than the length of the sleeve air duct (1).

7. The spray gun for a tin smelting top-blown furnace according to claim 6, characterized in that: The first connecting pipe (33), the second connecting pipe (23) and the third connecting pipe (11) are located on the same side of the spray gun.

8. The spray gun for a tin smelting top-blown furnace according to claim 1, characterized in that: The guide plate (5) comprises a support block (51) and a connection block (52); the peripheral side of the support block (51) is welded to form the third cladding layer (53); the bottom end of the connection block (52) is fixed to the top end of the support block (51); the top end of the connection block (52) is conical in cross section for guiding.

9. The spray gun for a tin smelting top-blown furnace according to claim 1, characterized in that: The guide plate (5) has a length of 200 mm, a width of 10 mm and a thickness of 28 mm. One side wall of the guide plate (5) in the length direction is fixed to the outer wall of the coal injection pipe (4).

10. The spray gun for tin smelting top-blown furnace according to claim 1, characterized in that: There are no less than two guide plates (5) radially along the coal injection pipe (4), and the axial distance between two adjacent guide plates (5) along the coal injection pipe (4) is 1.5 m.