Method for quickly eliminating sea reclamation stress history through rammed pile

Through the tamping and expansion technology, the uneven settlement problem caused by the history of reclamation stress was solved under the 'soft layer-type' geological conditions. Through the combination of gravel piles and heavy tampers, a stable composite foundation was formed and shortened. The construction period was completed and the overall stability of the land reclamation area was improved.

CN119083408APending Publication Date: 2024-12-06NO 3 ENG COMPANY LTD OF CCCC FIRST HARBOR ENG COMPANY +1
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411421414.1
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-10-12
Publication Date
2024-12-06

AI Technical Summary

Technical Problem

Under the 'soft layer' geological conditions, the uneven settlement problem caused by different reclamation stress history in the reclamation project affects the stability and construction progress of the reclamation land area.

Method used

Through the tamping pile expansion technology, including construction preparation and investigation, crushed pile body construction, cover layer 'stone filling + light tamping' encryption, transitional heavy tamping expansion, pile diameter and bearing capacity detection, filling standards and elevation, etc., The gravel pile body and heavy tamper form a transitional pile diameter distribution, neutralize the historical influence of reclamation stress, and ensure the foundation bearing capacity and overall settlement effect.

Benefits of technology

It effectively reduces the waste of pile diameters of covered stone layers, shortens the construction period by about 40%, forms a stable composite foundation, controls the overall settlement effect of the reclamation land area, and ensures the stability of the reclamation land area.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119083408A_ABST
    Figure CN119083408A_ABST
Patent Text Reader

Abstract

The invention relates to the technical field of offshore land filling construction, in particular to a foundation construction method for forming a stone backfill layer on a marine silt layer, and belongs to the field of soft soil foundation treatment. Comprising the steps of S1, construction preparation and investigation; s2, gravel pile body construction; s3, covering layer stone filling and light ramming densification are carried out; s4, carrying out transition type heavy ramming and expanding; s5, pile diameter and bearing capacity detection; and S6, filling the elevation. According to the method, the problem of differential settlement caused by different sea reclamation stress histories under the soft layer clamping type geological condition is effectively solved, the pile diameter waste of a covering stone layer is reduced by about 50%, foundation treatment modes such as high-power vibroflotation or cast-in-place concrete piles are replaced with a dynamic compaction mode, the overall construction period is shortened by about 40%, and the construction period is shortened by about 40%. The formed transition type composite foundation controls the settlement effect of the whole land area, and the overall stability of the sea reclamation land area is guaranteed.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of offshore landfill construction, and is particularly suitable for a foundation construction method for forming a stone backfill layer on a marine silt layer, belonging to the field of soft soil foundation treatment. Background Art

[0002] Gravel ramming pile expansion refers to a foundation treatment method that uses vibration or impact pipe sinking to form a hole in a soft foundation, fill it with small-size gravel materials, and squeeze it into the hole to form a continuous and dense pile body with a certain diameter composed of gravel, and then further form a large-diameter pile body through the "light ramming + heavy ramming" method. Gravel piles improve the unfavorable factors of the soil through vibration compaction, tamping, drainage and pressure reduction, and reinforcement. However, in undrained soft soil with low shear strength (such as silty soil), the surrounding soft soil has a small constraint force, and it is easy to form a large-diameter pile body through external force.

[0003] Artificial land reclamation projects directly backfill stones on the "marine sedimentary rock + marine silt layer" in the original sea area, forming a large-scale special geological condition with stones (hard layer) on the top, marine silt (soft layer) in the middle, and terrestrial sedimentary rock (harder layer) on the bottom (hereinafter referred to as "sandwich soft layer" geological conditions). At the same time, many reclamation projects are progressing slowly, and the time difference between the land formed by the early reclamation and the later reclamation is very large. Even some reclamation projects have a construction period of more than 10 years, which has caused great interference to the subsequent control of the overall uniform settlement of the reclamation land. How to eliminate the stress history influence of different reclamation periods and ensure the stability of the upper structure foundation is a common problem faced by many reclamation projects at present. Summary of the invention

[0004] In order to solve the problem of different reclamation stress histories under "sandwich soft layer" geological conditions and control the overall uneven settlement of the reclaimed land, the present invention proposes a method for quickly eliminating the reclamation stress history by tamping and expanding piles.

[0005] To achieve the above object, the technical solution adopted by the present invention is as follows: a method for quickly eliminating the stress history of land reclamation by tamping and expanding piles, comprising the following steps: S1. Construction preparation and investigation; S2, gravel pile construction; S3, overburden layer "stone filling + light tamping" density; S4, transitional heavy tamping and expansion; S5, pile diameter and bearing capacity testing; S6, fill in the elevation; As a preferred technical solution of the present invention, the step S1 construction preparation and investigation includes: Before construction, based on engineering data, statistics are collected on the reclamation dates of different areas, and stress history survey reports for different land blocks are formed. The current bearing capacity of the foundation in different areas is tested, and key indicators such as tamping energy, pile diameter, and pile length are clarified in combination with the design to determine the model of tamping equipment and vibro-impact construction parameters.

[0006] As a preferred technical solution of the present invention, the step S2 of gravel pile construction includes: S201. Under the geological conditions on site, the specific process parameters are determined through experiments. The vibro-impact parameters can be selected from 75A to 100A and 8S to 10S. The pile diameter is guaranteed and a bottom-discharging vibrator is selected. S202. According to the characteristics of strong compaction, vibro-impact crushed stone piles and backfilling stone materials, the construction personnel are educated on site, and the mechanical performance report and material test report are checked to ensure that they meet the requirements. The material of the crushed stone pile body is 2cm to 5cm crushed stone; S203. Use a crawler crane to lift the vibrator, station it at the designed pile position, vibrate the water-flushing guide hole through the vibrator, send the vibrator to the bottom of the silt section at the pile position, and then discharge the material through the bottom of the vibrator hole, vibrate and lift it in sections to complete the pile construction; the pile spacing of the gravel pile is 1.0m to 3.0m, the pile diameter is 0.5 to 1.0m, and the pile length is 8m to 14m.

[0007] As a preferred technical solution of the present invention, the step S3 of "filling with stones + light tamping" of the covering layer includes: S301. In the construction area, the site is leveled and then filled with stones with a larger particle size of 30 to 50 cm and a filling thickness of 0.5 to 1.0 m to avoid local collapse caused by subsequent heavy tamping stress concentration and ensure the tamping effect of heavy tamping on the entire stone layer; S302. Use a light rammer to fully tamp the upper stone covering layer with a tamping energy of 1000-3000 kJ and 2 blows per point. The tamping marks must overlap and the overlapping part must not be less than 1 / 4 of the bottom area of ​​the rammer to ensure that the upper stone covering layer and the upper gravel pile body are dense and form a whole.

[0008] As a preferred technical solution of the present invention, the step S4 is transitional heavy tamping and expansion; S401. Use a large-diameter tamping hammer with a diameter of 3m to 5m to facilitate the overall force of the foundation. The heavy-duty tamping machine performs two tamping operations according to the designed points. The tamping points are spaced 10m apart and each point is tamped 10 to 15 times. After the first tamping operation, an excavator is used to flatten the tamping pit and then perform the second tamping operation. The second tamping operation is staggered with the first tamping operation. The tamping energy is 5000kJ to 15000kJ according to the historical transitional arrangement of land reclamation. S403. After the heavy tamping is completed, the tamping pit is leveled and the low stones are filled with high stones. The land elevation after tamping is measured and the land elevation drops by 1.0 to 3.2 m. As the constraint force around the pile body in the marine mud section is low, the gravel piles in the silt section are squeezed by the upper stone cover layer and the bottom terrestrial sedimentary rock layer. The theoretical pile diameter of the gravel pile body in the silt section is expanded to 1.0 m to 2.0 m. Combined with the land formation history, the falling height of the tamping hammer in different reclamation history areas is adjusted to control the tamping energy, and a transitional pile diameter distribution is formed through tamping to neutralize the influence of stress history.

[0009] As a preferred technical solution of the present invention, the pile diameter and bearing capacity detection in step S5 includes: S501. After the construction is completed, each block is tested separately in combination with the block reports formed in different stress history periods. The diameter of the gravel piles and the bearing capacity of the foundation are tested through dynamic probing and bearing capacity tests.

[0010] S502. Based on the test results and in comparison with the theoretical calculation contents, further analyze the matching relationship between the tamping energy, the vibro-compaction pile diameter and the bearing capacity of the foundation, and form a test report to provide a basis for the subsequent transitional arrangement of the tamping energy and the pile diameter.

[0011] As a preferred technical solution of the present invention, the step S6 of filling in the elevation includes: After the inspection is completed, the site will be filled and leveled according to the handover elevation, and the site will be compacted in layers using a roller with a layer thickness of less than 0.5m to ensure that the filling material is dense.

[0012] The present invention uses the upper stone layer as a working platform, and forms the gravel pile body of the lower silt section through vibration. Taking advantage of the low shear strength of undrained silt and the low constraint force of pile formation, "stone filling + light tamping" is first used to form the "hard shell" of the upper stone layer to ensure that the stone layer is subsequently subjected to overall force, and then "heavy tamping" is used to reduce the overall elevation of the reclaimed land area, so as to achieve the effect of tamping and expanding the diameter of the gravel pile body in the silt section. By adjusting the tamping energy of "heavy tamping", a transitional arrangement of gravel pile diameters in different areas is formed, thereby neutralizing the historical influence of reclamation stress, and finally the unified delivery elevation of the reclaimed land area is ensured by supplementary stone filling on the upper part. The method is simple and quick to operate, and not only increases the bearing capacity of the foundation through strong tamping and vibration, but also further increases the strength of the pile body and the surrounding soil through the gravel pile composite foundation and drainage principle. The beneficial effects of the present invention are: The present invention effectively solves the problem of uneven settlement caused by different land reclamation stress histories under "soft layer sandwich" geological conditions, utilizes the special geological conditions of this project as the working platform and stress surface, and gives full play to the densification and pressurization principles of "stone filling + light tamping" and "heavy tamping". The gravel piles in the silt layer between the upper stone covering layer and the bottom terrestrial sedimentary rock are squeezed and expanded. By adjusting the tamping energy of "heavy tamping", a transitional arrangement of gravel piles with different diameters is formed, thereby neutralizing the influence of the land reclamation stress history. The method reduces the waste of pile diameter in the covering stone layer by about 50%, replaces foundation treatment methods such as high-power vibro-impact or concrete cast-in-place piles by strong tamping, and reduces the overall construction period by about 40%. The formed transitional composite foundation controls the settlement effect of the entire land area and ensures the overall stability of the reclaimed land area. BRIEF DESCRIPTION OF THE DRAWINGS

[0013] Figure 1 It is a cross-sectional view of a pile formed by foundation treatment according to the present invention.

[0014] Figure 2 It is a cross-sectional view of the foundation treatment and pile expansion of the present invention.

[0015] Figure 3 It is the layout diagram of the transitional heavy tamping points of the present invention.

[0016] In the figure: 1. Backfill stone covering layer, 2. Marine silt layer, 3. Continental sedimentary rock layer, 4. Large-size stone cushion layer, 5. Initial formation of gravel pile body, 6. Transitional variable-diameter silt section ramming and expansion of pile body, 7. Lower-level heavy ramming impact energy, 8. Intermediate heavy ramming impact energy, 9. Higher-level heavy ramming impact energy, 10. First time of spot ramming, 11. Second time of spot ramming. DETAILED DESCRIPTION

[0017] The present invention is further described below in conjunction with the accompanying drawings, but the present invention is not limited to the specific embodiments. Example 1

[0018] For the artificial island formed by artificial reclamation, the construction sea area is backfilled with mountain rocks without dredging, and the stone is backfilled directly on the "marine sedimentary rock + marine silt layer" of the original sea area, forming a special geological condition with large-scale stone (hard layer) on the upper part, marine silt (soft layer) in the middle part and terrestrial sedimentary rock (relatively hard layer) on the bottom. According to the different positions of the section, the thickness of the overlying silt layer is different, the thickness of the upper stone layer (hard layer) is mainly between 5 and 7 meters, and the thickness of the middle silt layer (hard layer) is mainly between 4 and 6 meters.

[0019] A method for quickly eliminating the stress history of reclamation by tamping and expanding piles is adopted, which includes the following steps: S1. Construction preparation and investigation; Before construction, according to the engineering data, the reclamation dates of different areas are counted, and the stress history investigation reports of different land blocks are formed to detect the current status of foundation bearing capacity in different areas, determine key indicators such as tamping energy, pile diameter, pile length, and determine the model of dynamic tamping equipment and vibroflotation construction parameters; S2, gravel pile construction; S201. Under the geological conditions on site, the specific process parameters are determined through experiments. The vibro-impacting parameters are 100A and 10S, and a bottom-discharging vibrator is used. S202. According to the characteristics of strong compaction, vibro-impact crushed stone piles and backfilling stone materials, the construction personnel are educated on site, and the mechanical performance report and material test report are checked to ensure that they meet the requirements. The material of the crushed stone pile body is 2cm to 5cm crushed stone; S203, use crawler crane to lift vibrator, station it at the designed pile position, vibrate water through vibrator, send vibrator to the bottom of pile mud section, discharge material through vibrator hole bottom, vibrate and lift in sections to complete pile construction; the pile spacing of gravel pile is 3.0m, the pile diameter is 1.0m, and the pile length is 10m. This is the initial formation of gravel pile body 5, such as Figure 1 shown.

[0020] S3, Covering layer filling with stones + light tamping and densification: S301. In the construction area, the site is leveled and then filled with stones with a larger particle size of 30 to 50 cm and a filling thickness of 1.0 m to avoid local collapse caused by subsequent heavy tamping stress concentration and ensure the tamping effect of heavy tamping on the entire stone layer; S302. Use a light rammer to fully tamp the upper stone covering layer with a tamping energy of 1500kJ and 2 blows per point. The tamping marks must overlap and the overlapping part must not be less than 1 / 4 of the bottom area of ​​the rammer to ensure that the upper stone covering layer and the upper gravel pile body are dense and form a whole.

[0021] S4, transitional heavy tamping and expansion; S401. Use a large diameter rammer with a diameter of 4m and a weight of 80t to facilitate the overall force of the foundation. The heavy rammer rams twice according to the designed points, with a spacing of 10m between the ramming points and 10 to 15 rammings per point. Figure 3 As shown, after the first point tamping 10, the tamping pit is leveled by an excavator and then the second point tamping 11 is performed. The second point tamping 11 is arranged alternately with the first point tamping 10. The point tamping impact energy is divided into three areas according to the transitional arrangement of the reclamation history. The lower-level heavy tamping impact energy 7, the medium-level heavy tamping impact energy 8, and the higher-level heavy tamping impact energy 9 are 8000 kJ, 10000 kJ, and 15000 kJ respectively. S403. After the re-tamping is completed, the tamping pit is leveled and the low stones are filled with high stones. The land elevation after tamping is measured. The average elevation of each block drops by 1.0m, 2.0m, and 2.7m. Due to the low constraint force around the pile body of the marine silt section, the gravel piles in the silt section are squeezed by the upper stone covering layer and the bottom terrestrial sedimentary rock layer. The theoretical pile diameter of the gravel pile in the silt section is expanded to 1.2m, 1.5m, and 2m. This is a transitional variable diameter silt section tamping expansion pile body 6. Figure 2 As shown in the figure, the falling height of the rammer in different reclamation history areas is adjusted in combination with the land formation history, so as to control the ramming energy, form a transitional pile diameter distribution through ramming, and neutralize the influence of stress history.

[0022] S5. Pile diameter and bearing capacity test: S501. After the construction is completed, each block is tested separately in combination with the block reports formed in different stress history periods. Through dynamic probing and bearing capacity tests, the diameter of the gravel piles and the bearing capacity of the foundation are tested to balance the bearing capacity of different reclamation stress areas and ensure the unified settlement effect of the subsequent project.

[0023] S502. Based on the test results and in comparison with the theoretical calculation contents, further analyze the matching relationship between the tamping energy, the vibro-compaction pile diameter and the bearing capacity of the foundation, and form a test report to provide a basis for the subsequent transitional arrangement of the tamping energy and the pile diameter.

[0024] S6. Filling elevation includes: S601. After the inspection is completed, the site will be filled and leveled according to the handover elevation, and the site will be compacted in layers using a roller with a layer thickness of less than 0.5m to ensure that the filling material is dense. Example 2

[0025] The steps of the method for quickly eliminating the stress history of land reclamation by tamping and expanding piles described in this embodiment are the same as those in Embodiment 1, except that: (1) In step S201, the vibro-impact parameters are selected as 75A, 8S; (2) In step S203, the pile spacing of the gravel pile is 1.0 m, the pile diameter is 0.5 m, and the pile length is 8 m; (3) Step S301: The stone filling thickness is 0.5 m; (4) The tamping energy in step S302 is 1000 kJ; (5) In step S401, the diameter of the rammer is 3 m. Example 3

[0026] The steps of the method for quickly eliminating the stress history of land reclamation by tamping and expanding piles described in this embodiment are the same as those in Embodiment 1, except that: (1) In step S201, the vibro-impact parameters are 85A, 9S; (2) In step S203, the pile spacing of the gravel pile is 2.0 m, the pile diameter is 0.75 m, and the pile length is 14 m; (3) Step S301: The stone filling thickness is 0.75 m; (4) The tamping energy in step S302 is 3000 kJ; (5) In step S401, the diameter of the rammer is 5 m.

[0027] The above is only a preferred embodiment of the present invention, but the protection scope of the present invention is not limited thereto. Any technician familiar with the technical field can make equivalent replacements or changes according to the technical solution and inventive concept of the present invention within the technical scope disclosed by the present invention, which should be included in the protection scope of the present invention.

Claims

1. A method for rapidly eliminating land reclamation stress history by tamping and expanding piles, characterized in that: The following steps are involved: S1. Construction preparation and investigation; S2, gravel pile construction; S3, overburden filling + light tamping; S4, transitional heavy tamping and expansion; S5, pile diameter and bearing capacity testing; S6. Fill in the elevation.

2. A method for rapidly eliminating land reclamation stress history by tamping and expanding piles according to claim 1, characterized in that: The step S1 construction preparation and investigation specifically includes the following steps: Before construction, based on engineering data, statistics are collected on the reclamation dates of different areas, and stress history survey reports for different land blocks are formed. The bearing capacity status of the foundation in different areas is tested, and the key indicators of compaction are clarified in combination with the design, and the model of compaction equipment and vibro-impact construction parameters are determined.

3. A method for rapidly eliminating land reclamation stress history by tamping and expanding piles according to claim 2, characterized in that: The key indicators of tamping include impact energy, pile diameter and pile length.

4. A method for rapidly eliminating land reclamation stress history by tamping and expanding piles according to claim 1, characterized in that: The step S2 of gravel pile construction specifically includes the following steps: S201. Under the geological conditions on site, the specific process parameters are determined through experiments. The vibro-impact parameters can be selected from 75A to 100A and 8S to 10S. The pile diameter is guaranteed and a bottom-discharging vibrator is selected. S202. According to the characteristics of dynamic compaction, vibro-impact gravel piles and backfilling stone materials, educate the construction personnel on site, check the mechanical performance report and material test report to ensure that they meet the requirements. The gravel pile material is 2cm to 5cm gravel; S203. Use a crawler crane to lift the vibrator, station it at the designed pile position, vibrate the water-flushing guide hole through the vibrator, send the vibrator to the bottom of the silt section at the pile position, and then discharge the material through the bottom of the vibrator hole, vibrate and lift it in sections to complete the pile construction; the pile spacing of the gravel pile is 1.0m to 3.0m, the pile diameter is 0.5 to 1.0m, and the pile length is 8m to 14m.

5. The method of quickly eliminating land reclamation stress history by tamping and expanding piles according to claim 1, characterized in that: The step S3 of filling the overburden with stones and lightly tamping the overburden comprises the following steps: S301. In the construction area, the site is leveled and then filled with stones with a larger particle size of 30 to 50 cm and a filling thickness of 0.5 to 1.0 m to avoid local collapse caused by subsequent heavy tamping stress concentration and ensure the tamping effect of heavy tamping on the entire stone layer; S302. Use a light rammer to fully tamp the upper stone covering layer with a tamping energy of 1000-3000 kJ and 2 blows per point. The tamping marks must overlap and the overlapping part must not be less than 1 / 4 of the bottom area of ​​the rammer to ensure that the upper stone covering layer and the upper gravel pile body are dense and form a whole.

6. The method of quickly eliminating land reclamation stress history by tamping and expanding piles according to claim 1, characterized in that: The step S4 of transitional re-tamping and expansion specifically comprises the following steps: S401. Use a large-diameter tamping hammer with a diameter of 3m to 5m to facilitate the overall force of the foundation. The heavy-duty tamping machine performs two tamping operations according to the designed points. The tamping points are spaced 10m apart and each point is tamped 10 to 15 times. After the first tamping operation, an excavator is used to flatten the tamping pit and then perform the second tamping operation. The second tamping operation is staggered with the first tamping operation. The tamping energy is 5000kJ to 15000kJ according to the historical transitional arrangement of land reclamation. S403. After the heavy tamping is completed, the tamping pit is leveled and the low stones are filled with high stones. The land elevation after tamping is measured. The land elevation drops by 1.0 to 3.2 m. The theoretical pile diameter of the gravel pile in the silt section is expanded to 1.0 m to 2.0 m. Combined with the land formation history, the drop height of the tamping hammer in different reclamation history areas is adjusted to control the tamping energy. A transitional pile diameter distribution is formed through tamping to neutralize the influence of stress history.

7. The method of quickly eliminating land reclamation stress history by tamping and expanding piles according to claim 1, characterized in that: The step S5 of pile diameter and bearing capacity detection specifically includes the following steps: S501. After the construction is completed, each block is tested separately in combination with the block reports formed in different stress history periods, and the diameter of the gravel pile and the bearing capacity of the foundation are tested through dynamic probing and bearing capacity tests; S502. Based on the test results and in comparison with the theoretical calculation contents, further analyze the matching relationship between the tamping energy, the vibro-compaction pile diameter and the bearing capacity of the foundation, and form a test report to provide a basis for the subsequent transitional arrangement of the tamping energy and the pile diameter.

8. The method of quickly eliminating land reclamation stress history by tamping and expanding piles according to claim 1, characterized in that: The step S6 of filling in the elevation specifically comprises the following steps: After the inspection is completed, the site will be filled and leveled according to the handover elevation, and the site will be compacted in layers using a roller with a layer thickness of less than 0.5m to ensure that the filling material is dense2.