Progress management and control method, device and equipment for linear engineering and readable storage medium

By establishing the association relationship between the three-dimensional model and the project list, matching and synchronizing the on-site output value progress information, the problem of low accuracy in two-dimensional table recording output value progress data in linear engineering is solved, and more accurate and intuitive progress display is achieved, which improves the project Data management efficiency.

CN119090211APending Publication Date: 2024-12-06GLODON CO LTD +1
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411152965.2
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-08-21
Publication Date
2024-12-06

AI Technical Summary

Technical Problem

The accuracy of recording output value progress data in existing linear projects is low, resulting in inconsistent with the actual situation on site, which reduces the accuracy of statistics.

Method used

By receiving three-dimensional model data and project list, establishing association relationships, obtaining on-site output value progress information, and matching it with the three-dimensional model data, determining the real-time progress project volume of the target modeling part, displaying it in the three-dimensional model, real-time data synchronization is achieved and display.

Benefits of technology

It improves the accuracy of on-site progress data recording, enhances data interoperability and visualization, facilitates the management and use of engineers, and reduces data missed items and delays.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119090211A_ABST
    Figure CN119090211A_ABST
Patent Text Reader

Abstract

The invention discloses a progress management and control method, device and equipment for linear engineering and a readable storage medium, and the method comprises the steps: receiving three-dimensional model data and a project list sent by a first business system, and building an incidence relation between the three-dimensional model data and the project list; acquiring field output value progress information sent by a second service system; matching the field output value progress information with the three-dimensional model data, and determining a target modeling part corresponding to the field progress information; and determining the engineering quantity of the real-time progress of the target modeling part based on the project list, and displaying the engineering quantity of the real-time progress of the target modeling part in the three-dimensional model data. According to the method, the WBS structure is used for integrating the data of the multiple service systems, the purpose of reconstructing the incidence relation between the linear engineering BIM three-dimensional model and the production data is achieved, effective fusion of the two-dimensional field progress data, the project list and the three-dimensional model data is achieved by reconstructing the incidence relation, and management, control and use of engineers are facilitated.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of engineering construction, and in particular to a linear engineering progress control method, device, equipment and readable storage medium. Background Art

[0002] Linear engineering is a type of engineering project, including but not limited to railways, highways, oil and gas pipelines, channels, pipelines, urban integrated roads, transmission lines and cableways. It is characterized by complex natural and social environments, high quality standards, and is a social project that is closely related to people's daily lives. During the construction of linear engineering, the statistics of output progress data is an important part of the daily work of engineering personnel.

[0003] The existing statistical method of output value progress data is mainly based on two-dimensional tables, that is, engineering personnel will collect the completion status of the site and fill it into various standard tables to summarize the dynamic data of output value, and report the completion status to the accounting department at the end of the month. The accounting department will conduct output value statistics based on the reported completion content. However, the data summary time is delayed compared with the on-site construction situation. At the same time, due to the large number of contents of linear projects and the large number of people involved in statistics, it is easy to miss items in the statistical dynamic output value data, resulting in inconsistency between the dynamic output value data and the actual situation on site, which reduces the accuracy of the statistical output value progress data of linear projects.

[0004] There is currently no effective solution to the technical problem that the existing technology uses two-dimensional tables to record output progress data with low accuracy. Summary of the invention

[0005] The purpose of the present invention is to provide a linear engineering progress control method, device, equipment and readable storage medium, which can solve the technical problem of low accuracy of recording output value progress data using a two-dimensional table.

[0006] One aspect of the present invention provides a progress control method for a linear project, the method comprising: receiving three-dimensional model data and a project list sent by a first business system, and establishing an association relationship between the three-dimensional model data and the project list; obtaining on-site output value progress information sent by a second business system; matching the on-site output value progress information with the three-dimensional model data, and determining a target modeling part corresponding to the on-site progress information; determining the real-time progress engineering quantity of the target modeling part based on the project list, and displaying the real-time progress engineering quantity of the target modeling part in the three-dimensional model data.

[0007] Optionally, an association relationship is established between the three-dimensional model data and the project list, including: screening the three-dimensional model data to obtain identity information and geometric attribute information of the three-dimensional model data; respectively associating the identity information and geometric attribute information with corresponding unit price information of the project list; synchronizing the geometric attribute information with the total output value, and synchronizing the overall project parts corresponding to the identity information and the total output value.

[0008] Optionally, establishing an association relationship between the three-dimensional model data and the project list also includes: defining unit projects, wherein a unit project is a building or structure in a linear project that has independent construction conditions and can be used independently; dividing the three-dimensional model data by unit projects, and establishing an association relationship between the unit projects and the divided three-dimensional model data; defining work points, wherein a work point is a construction project of the unit project; dividing the three-dimensional model data associated with the unit project into work points, and associating the three-dimensional model data corresponding to the work points with the project list.

[0009] Optionally, the on-site output value progress information includes a work site identification and a mileage completion number, and the real-time progress engineering quantity of the target modeling part is determined based on the project list, including: determining the target identity information and target geometric attribute information corresponding to the work site identification in the three-dimensional model data; determining the target unit price information corresponding to the target identity information and the target geometric attribute information in the project list information; calculating and obtaining the output value information corresponding to the target unit price information; and determining the real-time progress engineering quantity of the target modeling part through the output value information corresponding to the mileage completion number and the target unit price information.

[0010] Optionally, after obtaining the on-site output value progress information sent by the second business system, the method also includes: determining whether there is a data conflict between the on-site output value progress information and the project list; if so, processing the on-site output value progress information through a preset conflict resolution strategy; if not, determining the engineering quantity corresponding to the on-site output value progress information based on the project list.

[0011] Optionally, after matching the on-site output value progress information with the three-dimensional model data and determining the target modeling part corresponding to the on-site progress information, the method also includes: judging whether the mileage completion number exceeds a preset threshold; if so, increasing the number of concurrent processing threads or cache space of the system to calculate the engineering quantity corresponding to the target modeling part; if not, calculating the engineering quantity corresponding to the target modeling part through the system default server resources.

[0012] Another aspect of the present invention provides a progress control device for linear engineering, which includes: an association module for receiving three-dimensional model data and a project list sent by a first business system, and establishing an association relationship between the three-dimensional model data and the project list; an acquisition module for acquiring on-site output value progress information sent by a second business system; a matching module for matching the on-site output value progress information with the three-dimensional model data, and determining a target modeling part corresponding to the on-site progress information; a synchronization module for determining the real-time progress engineering quantity of the target modeling part based on the project list, and displaying the real-time progress engineering quantity of the target modeling part in the three-dimensional model data.

[0013] Optionally, the association module is also used to: filter the three-dimensional model data to obtain the identity information and geometric attribute information of the three-dimensional model data; respectively associate the identity information and geometric attribute information with the corresponding unit price information of the project list; synchronize the geometric attribute information with the total output value, and synchronize the overall project parts corresponding to the identity information and the total output value.

[0014] Another aspect of the present invention provides a computer device, which includes: a memory, a processor, and a computer program stored in the memory and executable on the processor, wherein the processor implements the linear engineering progress control method of any of the above-mentioned embodiments when executing the computer program.

[0015] Another aspect of the present invention provides a computer storage medium having a computer program stored thereon, and when the computer program is executed by a processor, the linear engineering schedule control method of any of the above embodiments is implemented. Further, the computer-readable storage medium may mainly include a program storage area and a data storage area, wherein the program storage area may store an operating system, an application required for at least one function, etc.; the data storage area may store data created according to the use of blockchain nodes, etc.

[0016] The present invention integrates the data of multiple business systems by using the WBS structure, aiming to reconstruct the association between the linear engineering BIM three-dimensional model and the production data. By reconstructing the association, the effective integration of two-dimensional site progress data, project list and three-dimensional model data is achieved, which is convenient for the management and use of engineering personnel and improves the accuracy of site progress data records. BRIEF DESCRIPTION OF THE DRAWINGS

[0017] Various other advantages and benefits will become apparent to those of ordinary skill in the art by reading the detailed description of the preferred embodiments below. The accompanying drawings are only for the purpose of illustrating the preferred embodiments and are not to be considered as limiting the present invention. Moreover, the same reference symbols are used throughout the accompanying drawings to represent the same components. In the accompanying drawings:

[0018] Figure 1An optional flow chart of the progress control method of a linear engineering project provided in the first embodiment of the present invention is shown;

[0019] Figure 2 A structural block diagram of a linear engineering progress control device provided by Embodiment 2 of the present invention is shown; and

[0020] Figure 3 A block diagram of a computer device suitable for implementing a progress control method for linear engineering provided in a third embodiment of the present invention is shown. DETAILED DESCRIPTION

[0021] In order to make the purpose, technical scheme and advantages of the present invention more clearly understood, the present invention is further described in detail below in conjunction with the accompanying drawings and embodiments. It should be understood that the specific embodiments described herein are only used to explain the present invention and are not intended to limit the present invention. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without making creative work are within the scope of protection of the present invention.

[0022] It should be noted that, in this article, the terms "include", "comprises" or any other variations thereof are intended to cover non-exclusive inclusion, so that a process, method, article or device including a series of elements includes not only those elements, but also other elements not explicitly listed, or also includes elements inherent to such process, method, article or device. In the absence of further restrictions, an element defined by the sentence "comprises a ..." does not exclude the existence of other identical elements in the process, method, article or device including the element.

[0023] Embodiment 1

[0024] This embodiment provides a linear engineering progress control method. Figure 1 The flowchart of the progress control method of the linear engineering is shown as follows: Figure 1 As shown, the linear engineering progress control method may include steps S101 to S104, wherein:

[0025] Step S101, receiving the three-dimensional model data and the project list sent by the first business system, and establishing an association relationship between the three-dimensional model data and the project list;

[0026] Specifically, the 3D model data includes identity information (e.g., component number), geometric attribute information, material information, texture information, etc. The project list is compiled based on the 3D model data and is a detailed list consisting of the project name, material type quantity, and unit price. The first business system may be a BIM software system.

[0027] Establishing an association between 3D model data and project lists provides a data basis for the effective integration of 2D data and 3D models, facilitating the management and control of the output value progress data of linear projects.

[0028] Step S102, obtaining on-site output value progress information sent by the second business system;

[0029] The on-site output progress information includes the name and mileage of the branch project completed on the day. The second business system can be a display system for inputting on-site construction progress information.

[0030] Step S103, matching the on-site production progress information with the three-dimensional model data to determine the target modeling part corresponding to the on-site progress information;

[0031] By determining the target modeling location, the construction positioning corresponding to the on-site output progress can be quickly achieved, improving the efficiency of the fusion of 2D progress data and 3D model data. At the same time, since the matching 3D model data format is in the form of text such as identity information and geometric attribute information, the model data and output data are seamlessly connected, avoiding the problem of inconsistent data types between multiple systems, and no additional conversion of data formats is required.

[0032] Step S104: determining the real-time progress of the engineering quantity of the target modeling part based on the project list, and displaying the real-time progress of the engineering quantity of the target modeling part in the three-dimensional model data.

[0033] This embodiment synchronizes the acquired 3D model data, project list and on-site output value progress information by constructing a unified data synchronization platform - WBS structure system, and displays the real-time progress of the project in the 3D model data. The progress image is displayed in real time in combination with the BIM model. The BIM model is unitized and can be bound to the progress plan and adjusted during the implementation process. The progress can be distinguished by BIM model and color, which not only intuitively expresses the normal, delayed and advanced progress, but also dynamically reflects the output value data, making it easier for engineering personnel to view the construction progress and improving the user experience.

[0034] Preferably, step S103 may include steps S1031 to S1033, wherein:

[0035] Step S1031, screening the three-dimensional model data to obtain identity information and geometric attribute information of the three-dimensional model data;

[0036] Identity information and geometric attribute information are data that can highlight the characteristics of the project. In the process of data fusion, only identity information and geometric attribute information are screened out for processing, which reduces the amount of data processed by the system and resource pressure, and improves the stability of system operation.

[0037] Step S1032, respectively associating the identity information and the geometric attribute information with the corresponding unit price information of the item list;

[0038] Step S1033, synchronizing the geometric attribute information with the total output value, and synchronizing the overall project parts corresponding to the identity information and the total output value.

[0039] Associating identity information, geometric attribute information and project lists enhances interoperability between data and enables the collective calling of related data.

[0040] Preferably, establishing an association relationship between the three-dimensional model data and the project list further includes steps A1 to A4, wherein:

[0041] Step A1, defining a unit project, wherein a unit project is a building or structure in a linear project that has independent construction conditions and can be used independently;

[0042] The unit project can be a field consisting of a certain area name + roads, pipelines, channels, gas pipelines and other projects, for example, Chongqing Bridge Engineering Project Department.

[0043] Step A2, dividing the three-dimensional model data by unit projects, and establishing an association relationship between the unit projects and the divided three-dimensional model data;

[0044] Step A3, defining a work point, wherein a work point is a construction project of a unit project;

[0045] The construction site can be the lower-level regional name of the area + the local project name, for example, Yuecheng Village Left Line Bridge, Yuexi River Bridge, Zhaizipo Bridge, etc.

[0046] Step A4, dividing the three-dimensional model data associated with the unit project into work points, and associating the three-dimensional model data corresponding to the work points with the project list.

[0047] Continuing with the previous example, the lower structure of the left line bridge in Yuecheng Village includes 19 bored cast-in-place piles, a type of three-dimensional model component.

[0048] Unit projects and work sites are concepts of different levels. A unit name contains multiple work sites, and a work site contains multiple 3D model data. The project data is managed based on the hierarchical structure of individual projects, work sites, and 3D model data, which solves the problems of data being easily missed, untimely, and without a basis for control. By using individual projects and work sites as the basis for dividing project data, the project data is made more structured, making it easier to understand and locate the data when using it.

[0049] Preferably, step S104 may include steps S1041 to S1044, wherein:

[0050] Step S1041, determining the target identity information and target geometric attribute information corresponding to the work point identification in the three-dimensional model data;

[0051] The work site is identified by the name of the sub-project in step A3.

[0052] Step S1042, determining the target unit price information corresponding to the target identity information and the target geometric attribute information in the project list information;

[0053] Step S1043, calculating and obtaining the output value information corresponding to the target unit price information;

[0054] Step S1044, determining the real-time progress of the engineering quantity of the target modeling part through the output value information corresponding to the mileage completion number and the target unit price information.

[0055] Specifically, the real-time progress of the target modeling part can be obtained by calculating the product of the ratio of the mileage completion data to the total mileage of the work point identification and the output value information corresponding to the target unit price information.

[0056] Preferably, after acquiring the on-site output progress information sent by the second business system, the method further includes steps B1 to B3, wherein:

[0057] Step B1, determining whether there is data conflict between the on-site output value progress information and the project list;

[0058] Situations of data conflict include: the defined work point does not have a field with consistent work point identification, and the mileage completed exceeds the total mileage corresponding to a single project in the project list.

[0059] Step B2: If yes, process the on-site output progress information through a preset conflict resolution strategy;

[0060] The preset conflict resolution strategies include: the first method is to return the warning information of the data conflict to the second business system for correction; the second method is to call the preset information correction model for processing. Among them, for the situation where the work point does not meet the conditions, the model can match the work point identification with all defined work points for similarity. When the similarity exceeds a certain value, the corresponding work point is used as the name of the branch project corresponding to the on-site output value progress; for the situation where the mileage completion number does not meet the conditions, the model can use the difference between the total mileage corresponding to the work point identification at this time and the mileage previously counted as the current mileage completion number and replace the wrong mileage completion number.

[0061] Step B3: if not, determine the engineering quantity corresponding to the on-site output value progress information based on the project list.

[0062] By presetting the conflict resolution strategy, the data between multiple devices or multiple systems can be ensured to be consistent, thus avoiding data loss and errors and improving the accuracy of the fusion of two-dimensional progress data and three-dimensional model data.

[0063] Preferably, after matching the on-site production progress information with the three-dimensional model data and determining the target modeling part corresponding to the on-site progress information, the method further includes steps C1 to C3, wherein:

[0064] Step C1, determining whether the mileage completion number exceeds a preset threshold;

[0065] The preset threshold is determined by the actual scenario requirements.

[0066] Step C2: if yes, then increase the number of concurrent processing threads or cache space of the system to calculate the engineering quantity corresponding to the target modeling part;

[0067] Ways to increase cache space include: when physical memory is tight, the operating system will move some of the idle program data to the disk to free up a certain amount of space for the system to perform calculations; compress the data in memory through algorithms to reduce the actual physical memory space occupied; and pre-allocate a maximum memory usage limit for project processes whose mileage exceeds a preset threshold.

[0068] Step C3: If not, the engineering quantity corresponding to the target modeling part is calculated through the system default server resources.

[0069] Since the data to be processed in the construction project quantity calculation process is very complex, adding a certain amount of mileage will generate a large amount of data to be calculated. In the quantity calculation process, this embodiment dynamically adjusts the system resources through mileage completion data to ensure the stable operation of the system.

[0070] This embodiment integrates data from multiple business systems by using the WBS structure, aiming to reconstruct the association between the linear engineering BIM three-dimensional model and production data. By reconstructing the association, the effective integration of two-dimensional site progress data, project lists and three-dimensional model data is achieved, which facilitates the management and use of engineering personnel and improves the accuracy of site progress data records.

[0071] Embodiment 2

[0072] The second embodiment of the present invention further provides a linear engineering progress control device, which corresponds to the linear engineering progress control method provided in the first embodiment above. The corresponding technical features and technical effects are not described in detail in this embodiment, and the relevant parts can refer to the first embodiment above. Specifically, Figure 2 The structural block diagram of the progress control device of the linear engineering is shown in FIG. Figure 2As shown, the linear engineering progress control device 200 includes an association module 201, an acquisition module 202, a matching module 203 and a synchronization module 204, wherein:

[0073] The association module 201 is used to receive the three-dimensional model data and the project list sent by the first business system, and establish an association relationship between the three-dimensional model data and the project list;

[0074] The acquisition module 202 is connected to the association module 201 and is used to acquire the on-site output value progress information sent by the second business system;

[0075] The matching module 203 is connected to the acquisition module 202 and is used to match the on-site production progress information with the three-dimensional model data to determine the target modeling part corresponding to the on-site progress information;

[0076] The synchronization module 204 is connected to the matching module 203, and is used to determine the real-time progress of the engineering quantity of the target modeling part based on the project list, and display the real-time progress of the engineering quantity of the target modeling part in the three-dimensional model data.

[0077] Optionally, the association module is also used to: filter the three-dimensional model data to obtain the identity information and geometric attribute information of the three-dimensional model data; respectively associate the identity information and geometric attribute information with the corresponding unit price information of the project list; synchronize the geometric attribute information with the total output value, and synchronize the overall project parts corresponding to the identity information and the total output value.

[0078] Optionally, establishing an association relationship between the three-dimensional model data and the project list also includes: defining unit projects, wherein a unit project is a building or structure in a linear project that has independent construction conditions and can be used independently; dividing the three-dimensional model data by unit projects, and establishing an association relationship between the unit projects and the divided three-dimensional model data; defining work points, wherein a work point is a construction project of the unit project; dividing the three-dimensional model data associated with the unit project into work points, and associating the three-dimensional model data corresponding to the work points with the project list.

[0079] Optionally, the synchronization module is also used to: determine the target identity information and target geometric attribute information corresponding to the work point identification in the three-dimensional model data; determine the target unit price information corresponding to the target identity information and the target geometric attribute information in the project list information; calculate the output value information corresponding to the target unit price information; determine the real-time progress of the engineering quantity of the target modeling part through the mileage completion number and the output value information corresponding to the target unit price information.

[0080] Optionally, the device also includes a conflict processing module, which is used to: determine whether there is a data conflict between the on-site output value progress information and the project list; if so, process the on-site output value progress information through a preset conflict resolution strategy; if not, determine the engineering quantity corresponding to the on-site output value progress information based on the project list.

[0081] Optionally, the device also includes a resource adjustment module, which is used to: determine whether the mileage completion number exceeds a preset threshold; if so, increase the number of concurrent processing threads or cache space of the system to calculate the engineering volume corresponding to the target modeling part; if not, calculate the engineering volume corresponding to the target modeling part through the system default server resources.

[0082] Embodiment 3

[0083] Figure 3 The block diagram of a computer device suitable for implementing a linear engineering schedule control method provided in the third embodiment of the present invention is shown. In this embodiment, the computer device 300 may be a smart phone, tablet computer, laptop computer, desktop computer, rack server, blade server, tower server or cabinet server (including an independent server or a server cluster composed of multiple servers) that executes a program. Figure 3 As shown, the computer device 300 of this embodiment includes at least but is not limited to: a memory 301, a processor 302, and a network interface 303 that can be interconnected through a system bus. It should be noted that Figure 3 Only computer device 300 having components 301 - 303 is shown, but it should be understood that implementing all of the components shown is not a requirement, and more or fewer components may alternatively be implemented.

[0084] In this embodiment, the memory 303 includes at least one type of computer-readable storage medium, and the readable storage medium includes flash memory, hard disk, multimedia card, card-type memory (for example, SD or DX memory, etc.), random access memory (RAM), static random access memory (SRAM), read-only memory (ROM), electrically erasable programmable read-only memory (EEPROM), programmable read-only memory (PROM), magnetic memory, disk, optical disk, etc. In some embodiments, the memory 301 can be an internal storage unit of the computer device 300, such as a hard disk or memory of the computer device 300. In other embodiments, the memory 301 can also be an external storage device of the computer device 300, such as a plug-in hard disk equipped on the computer device 300, a smart memory card (Smart Media Card, SMC), a secure digital (Secure Digital, SD) card, a flash card (Flash Card), etc. Of course, the memory 301 can also include both the internal storage unit of the computer device 300 and its external storage device. In this embodiment, the memory 301 is generally used to store the operating system and various application software installed on the computer device 300, such as the program code of the progress control method of linear engineering, etc.

[0085] In some embodiments, the processor 302 may be a central processing unit (CPU), a controller, a microcontroller, a microprocessor, or other data processing chips. The processor 302 is generally used to control the overall operation of the computer device 300. For example, the processor 302 performs control and processing related to data interaction or communication with the computer device 300. In this embodiment, the processor 302 is used to run the program code of the steps of the linear engineering schedule control method stored in the memory 301.

[0086] In this embodiment, the linear engineering progress control method stored in the memory 301 can also be divided into one or more program modules and executed by one or more processors (processor 302 in this embodiment) to complete the present invention.

[0087] The network interface 303 may include a wireless network interface or a wired network interface, and the network interface 303 is generally used to establish a communication link between the computer device 300 and other computer devices. For example, the network interface 303 is used to connect the computer device 300 to an external terminal through a network, and to establish a data transmission channel and a communication link between the computer device 300 and the external terminal. The network can be a wireless or wired network such as an intranet, the Internet, the Global System of Mobile communication (GSM), Wideband Code Division Multiple Access (WCDMA), 4G network, 5G network, Bluetooth, Wi-Fi, etc.

[0088] Embodiment 4

[0089] The present embodiment also provides a computer-readable storage medium, including a flash memory, a hard disk, a multimedia card, a card-type memory (for example, an SD or DX memory, etc.), a random access memory (RAM), a static random access memory (SRAM), a read-only memory (ROM), an electrically erasable programmable read-only memory (EEPROM), a programmable read-only memory (PROM), a magnetic memory, a disk, an optical disk, a server, an App application store, etc., on which a computer program is stored, and when the computer program is executed by a processor, the steps of the progress control method of the linear engineering are implemented.

[0090] Obviously, those skilled in the art should understand that the modules or steps of the above-mentioned embodiments of the present invention can be implemented by a general computing device, they can be concentrated on a single computing device, or distributed on a network composed of multiple computing devices, and optionally, they can be implemented by a program code executable by a computing device, so that they can be stored in a storage device and executed by the computing device, and in some cases, the steps shown or described can be executed in a different order from that here, or they can be made into individual integrated circuit modules, or multiple modules or steps therein can be made into a single integrated circuit module for implementation. In this way, the embodiments of the present invention are not limited to any specific combination of hardware and software.

[0091] It should be noted that the serial numbers of the embodiments of the present invention are only for description and do not represent the advantages or disadvantages of the embodiments.

[0092] Through the description of the above implementation methods, those skilled in the art can clearly understand that the above embodiment methods can be implemented by means of software plus a necessary general hardware platform, and of course by hardware, but in many cases the former is a better implementation method.

[0093] The above are only preferred embodiments of the present invention, and are not intended to limit the patent scope of the present invention. Any equivalent structure or equivalent process transformation made using the contents of the present invention specification and drawings, or directly or indirectly applied in other related technical fields, are also included in the patent protection scope of the present invention.

Claims

1. A linear engineering progress control method, characterized in that: The method comprises: Receiving the three-dimensional model data and the project list sent by the first business system, and establishing an association relationship between the three-dimensional model data and the project list; Obtaining on-site output progress information sent by the second business system; Matching the on-site production progress information with the three-dimensional model data to determine the target modeling part corresponding to the on-site progress information; The real-time progress of the engineering quantity of the target modeling part is determined based on the project list, and the real-time progress of the engineering quantity of the target modeling part is displayed in the three-dimensional model data.

2. The method according to claim 1, characterized in that The establishing of an association relationship between the three-dimensional model data and the project list includes: Screening the three-dimensional model data to obtain identity information and geometric attribute information of the three-dimensional model data; Respectively associating the identity information and the geometric attribute information with corresponding unit price information of the item list; The geometric attribute information is synchronized with the total output value, and the identity information is synchronized with the overall project part corresponding to the total output value.

3. The method according to claim 1 or 2, characterized in that: The establishing of an association relationship between the three-dimensional model data and the project list further includes: Define a unit project, wherein the unit project is a building or structure in a linear project that has independent construction conditions and can be used independently; Dividing the three-dimensional model data by the unit projects, and establishing an association relationship between the unit projects and the divided three-dimensional model data; Defining a work point, wherein the work point is a construction project of the unit project; The three-dimensional model data associated with the unit project is divided into work points, and the three-dimensional model data corresponding to the work points are associated with the project list.

4. The method according to claim 1, characterized in that The on-site output progress information includes a work point identification and a mileage completion number, and the engineering quantity of the real-time progress of the target modeling part determined based on the project list includes: Determining target identity information and target geometric attribute information corresponding to the work point identification in the three-dimensional model data; Determining target unit price information corresponding to the target identity information and the target geometric attribute information in the item list information; Calculate and obtain the output value information corresponding to the target unit price information; The real-time progress of the engineering quantity of the target modeling part is determined by the output value information corresponding to the mileage completion number and the target unit price information.

5. The method according to claim 1, characterized in that After acquiring the on-site output value progress information sent by the second business system, the method further includes: Determine whether there is a data conflict between the on-site output value progress information and the project list; If yes, the on-site output progress information is processed by a preset conflict resolution strategy; If not, the engineering quantity corresponding to the on-site output value progress information is determined based on the project list.

6. The method according to claim 1, characterized in that After matching the on-site production progress information with the three-dimensional model data to determine the target modeling part corresponding to the on-site progress information, the method further includes: Determining whether the mileage completion number exceeds a preset threshold; If yes, increase the number of concurrent processing threads or cache space of the system to calculate the engineering quantity corresponding to the target modeling part; If not, the engineering quantity corresponding to the target modeling part is calculated through the system default server resources.

7. A linear engineering progress control device, characterized in that: The device comprises: An association module, used for receiving the three-dimensional model data and the project list sent by the first business system, and establishing an association relationship between the three-dimensional model data and the project list; An acquisition module, used for acquiring on-site output value progress information sent by the second business system; A matching module, used to match the on-site production progress information with the three-dimensional model data to determine a target modeling part corresponding to the on-site progress information; A synchronization module is used to determine the real-time progress of the engineering quantity of the target modeling part based on the project list, and to display the real-time progress of the engineering quantity of the target modeling part in the three-dimensional model data.

8. The device according to claim 7, characterized in that The association module is also used for: Screening the three-dimensional model data to obtain identity information and geometric attribute information of the three-dimensional model data; Respectively associating the identity information and the geometric attribute information with corresponding unit price information of the item list; The geometric attribute information is synchronized with the total output value, and the identity information is synchronized with the overall project part corresponding to the total output value.

9. A computer device, comprising: A memory, a processor, and a computer program stored in the memory and executable on the processor, wherein the processor implements the method according to any one of claims 1 to 6 when executing the computer program.

10. A computer-readable storage medium having a computer program stored thereon, characterized in that: When the computer program is executed by a processor, the method according to any one of claims 1 to 6 is implemented.