Safe operation auxiliary decision-making method of electric power system in extreme weather and related device
By combining weather data and transformer operation data for risk assessment and taking corresponding decisions for different risk levels, the problem of error prediction of power system failure rate in extreme weather is solved, the calculation efficiency and decision-making accuracy of the power system are improved, and the power is ensured. The safe operation of the system.
Patent Information
- Application Number
- CN202411384352.1
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-09-30
- Publication Date
- 2024-12-06
AI Technical Summary
The existing technology lacks analysis conditions for the user side in extreme weather, resulting in errors in the prediction of power system failure rate, affecting decision-making accuracy and safe operation of power system.
Combining the weather data in the area where the power system is located and the comprehensive operating data of each transformer for risk assessment, by adjusting the operating parameters of the step-down transformer and starting the backup transformer, we will adopt the reduction of tracking intervals and reduce load for low, medium and high risks. Quantity and parallel backup transformer decision.
It improves the computing efficiency and decision-making accuracy of the power system, accurately predicts the risks of urban power systems, reduces failure rate prediction errors, and ensures the safe operation of the power system.
Smart Images

Figure CN119090280A_ABST
Abstract
Description
Technical Field
[0001] The present application relates to the field of electric power technology, and in particular to a method and related devices for auxiliary decision-making for safe operation of electric power systems under extreme weather conditions. Background Art
[0002] As the last stop before the power system enters the user, the step-down transformer has the function of reducing the high-voltage power grid to the low voltage entering the household. However, when the city encounters extreme weather, such as extremely high temperature and extremely low temperature, the user's power consumption will increase exponentially, which will have a greater impact on the load of the power system, and then cause the step-down transformer in the power system to overload, and then cause the step-down transformer to malfunction and be damaged, affecting the safe operation of the power system. In extreme rainy weather, the probability of the step-down transformer contacting water will increase, causing the step-down transformer to short-circuit, and finally causing the step-down transformer to malfunction. In addition, in this weather, it is often accompanied by strong winds of level 6 or above, which will damage the electrical equipment on the street and cause the transmission line to leak, posing a safety hazard. Based on this situation, the power grid operation and maintenance personnel generally make an advance estimate of the operation risk of the power system, and then make corresponding decisions based on the evaluation results.
[0003] At present, there are methods for assisting decision-making of power systems in extreme weather, such as a method for stable control and auxiliary decision-making of power systems under extreme weather conditions disclosed in Chinese patent (CN118095685A), and a method and system for stable control and auxiliary decision-making of power systems under extreme weather disasters disclosed in Chinese patent (CN115204713A). Both methods use mathematical models to simulate and predict meteorological changes, and then evaluate the operating risk of the power system by detecting the failure rate of equipment, and finally formulate corresponding control plans. However, since both methods evaluate and control the entire power system, the size of the weather simulation algorithm is large, which affects the calculation efficiency. More importantly, since the above methods mostly use historical data and operating data of equipment in the power system for calculation during the risk assessment process, lack analysis on the user side, and thus when encountering extreme weather, due to the lack of analysis conditions on the user side, it is easy to cause errors in the prediction of the failure rate of the power system, which leads to errors in the corresponding decision-making, affecting the safe operation of the power system. Summary of the invention
[0004] The present application provides a method and related devices for auxiliary decision-making for safe operation of power systems under extreme weather conditions, which are used to solve the problem that the existing technology lacks analysis conditions on the user side, which easily leads to errors in the prediction of power system failure rate, thereby causing corresponding decisions to be wrong.
[0005] In view of this, the first aspect of the present application provides a method for assisting decision-making for safe operation of a power system under extreme weather conditions, the method comprising:
[0006] Combine weather data of the area where the power system is located and comprehensive operation data of each transformer to evaluate the operation risk of the power system and obtain risk assessment results, which include: low risk, medium risk and high risk;
[0007] When the risk assessment result of the power system is low risk, shortening the time interval for tracking the step-down transformers in the power system;
[0008] When the risk assessment result of the power system is medium risk, reducing the load of the step-down transformer by adjusting the operating parameters of the step-down transformer;
[0009] When the risk assessment result of the power system is high risk, a decision is made to start a standby step-down transformer, wherein the standby transformer is connected in parallel with the main transformer.
[0010] Optionally, the operation risk assessment of the power system is performed in combination with weather data of the area where the power system is located and comprehensive operation data of each transformer to obtain a risk assessment result, including:
[0011] Obtain weather data for the area where the power system to be evaluated is located, and obtain weather conditions that may affect the power system based on the weather data;
[0012] Obtaining comprehensive operating data of each transformer in the power system to be evaluated, wherein the comprehensive operating data includes: load data and operating data;
[0013] Predicting the load condition of the step-down transformer according to the load data, and evaluating the operating state of the step-down transformer according to the operating data;
[0014] In combination with the load condition and the operating status of the step-down transformer, as well as the weather conditions, a risk assessment is performed on the safe operation of the power system to be assessed.
[0015] Optionally, predicting the load condition of the step-down transformer according to the load data, and evaluating the operating state of the step-down transformer according to the operating data includes:
[0016] According to the load data, a time series prediction model is used to predict the load condition of the step-down transformer;
[0017] The temperature rise, real-time current data, real-time power load and historical failure rate of the transformer are calculated based on the operating data to evaluate the operating status of the step-down transformer.
[0018] Optionally, the step of performing risk assessment on the safe operation of the power system to be assessed in combination with the load condition and the operating state of the step-down transformer and the weather conditions includes:
[0019] Comparing the predicted load condition with the actual load value to obtain a load prediction error, determining an indicator of the equipment health status according to the operating status of the step-down transformer, and determining the impact of weather conditions according to the weather conditions;
[0020] Based on a weighted comprehensive score calculation formula, a risk index is calculated according to the load forecast error and the equipment health status index, as well as the influence of weather conditions, and a risk assessment is performed on the safe operation of the power system to be assessed according to the risk index;
[0021] The weighted comprehensive score calculation formula is:
[0022] ;
[0023] in, is a risk indicator, is the load forecast error, An indicator of the health status of the device. Due to the influence of weather conditions, , , is the weight of each factor.
[0024] Optionally, the weather data includes: current weather data and predicted weather data; the weather conditions include: extreme heavy rain weather, extremely high temperature weather and extremely low temperature weather.
[0025] Optionally, when the risk assessment result of the power system is medium risk, reducing the load of the step-down transformer by adjusting the operating parameters of the step-down transformer includes:
[0026] When the risk assessment result of the power system is medium risk, the load on the transformer is reduced so that the transformer operates within the rated capacity, and the step-down transformer in the adjacent area is connected in parallel to the step-down transformer.
[0027] Optionally, when the risk assessment result of the power system is high risk, the decision to start the standby step-down transformer, wherein the standby transformer is connected in parallel with the main transformer, includes:
[0028] According to the load condition of the step-down transformer, a standby transformer is arranged at the step-down transformer in the area where high load is likely to occur, wherein the standby transformer is connected in parallel with the main transformer;
[0029] When the risk assessment result of the power system is high risk, a decision is made to start the backup step-down transformer.
[0030] A second aspect of the present application provides a safe operation auxiliary decision-making system for a power system under extreme weather conditions, the system comprising:
[0031] An analysis unit, used to evaluate the operation risk of the power system by combining weather data of the area where the power system is located and comprehensive operation data of each transformer, and obtain a risk assessment result, wherein the risk assessment result includes: low risk, medium risk and high risk;
[0032] A first auxiliary decision-making unit, configured to shorten a time interval for tracking a step-down transformer in the power system when the risk assessment result of the power system is low risk;
[0033] a second auxiliary decision-making unit, configured to reduce the load of the step-down transformer by adjusting the operating parameters of the step-down transformer when the risk assessment result of the power system is medium risk;
[0034] The third auxiliary decision unit is used to make a decision to start a standby step-down transformer when the risk assessment result of the power system is high risk, wherein the standby transformer is connected in parallel with the main transformer.
[0035] A third aspect of the present application provides a safe operation decision-making auxiliary device for a power system under extreme weather conditions, the device comprising a processor and a memory:
[0036] The memory is used to store program code and transmit the program code to the processor;
[0037] The processor is used to execute the steps of the method for auxiliary decision-making for safe operation of the power system under extreme weather conditions as described in the first aspect above according to the instructions in the program code.
[0038] A fourth aspect of the present application provides a computer-readable storage medium, which is used to store program code, and the program code is used to execute the method for auxiliary decision-making for safe operation of the power system under extreme weather conditions described in the first aspect above.
[0039] It can be seen from the above technical solutions that this application has the following advantages:
[0040] The present application provides a method for assisting decision-making in the safe operation of an electric power system under weather conditions. The method combines weather data in the area where the electric power system is located and the comprehensive operating data of each transformer to evaluate the operating risk of the electric power system, obtains risk assessment results, and adopts different control decisions for electric power systems with different operating risk levels, which can effectively reduce the amount of calculations and thus improve calculation efficiency; and gives corresponding decisions on the power consumption side of the electric power system, which can accurately predict the risks of the urban power system and make more accurate corresponding decisions. This solves the problem that the existing technology is prone to prediction errors in the failure rate of the electric power system due to the lack of analysis conditions on the user side, which leads to errors in the corresponding decisions. BRIEF DESCRIPTION OF THE DRAWINGS
[0041] Figure 1 A flowchart of a method for assisting decision-making in safe operation of a power system under extreme weather conditions provided in an embodiment of the present application;
[0042] Figure 2 A schematic diagram of the process of operating risk assessment provided in an embodiment of the present application;
[0043] Figure 3 This is a structural diagram of a safe operation auxiliary decision-making system for a power system under extreme weather conditions provided in an embodiment of the present application. DETAILED DESCRIPTION
[0044] In order to enable those skilled in the art to better understand the solution of the present application, the technical solution in the embodiments of the present application will be clearly and completely described below in conjunction with the drawings in the embodiments of the present application. Obviously, the described embodiments are only part of the embodiments of the present application, not all of the embodiments. Based on the embodiments in the present application, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of this application.
[0045] See also Figure 1 , an auxiliary decision-making method for safe operation of a power system under extreme weather conditions provided in an embodiment of the present application includes:
[0046] Step 101: Conduct an operation risk assessment on the power system in combination with weather data of the area where the power system is located and comprehensive operation data of each transformer to obtain a risk assessment result, which includes: low risk, medium risk and high risk.
[0047] Step 102: When the risk assessment result of the power system is low risk, shorten the time interval for tracking the step-down transformers in the power system.
[0048] It should be noted that under this decision, the normal operation of the step-down transformer will not be changed, but the time interval for tracking the corresponding step-down transformer will be shortened so that when the risk assessment level of the step-down transformer is increased, it can be discovered in time and corresponding decisions that are consistent with its risk assessment level can be made.
[0049] Step 103: When the risk assessment result of the power system is medium risk, the load of the step-down transformer is reduced by adjusting the operating parameters of the step-down transformer.
[0050] It should be noted that, under this decision, the load of the step-down transformer is reduced by adjusting the operating parameters of the step-down transformer. In one embodiment, the adjustment method includes:
[0051] ① Reduce the load on the transformer to ensure that it operates within the rated capacity, such as cutting off the power supply to non-user equipment on the step-down transformer;
[0052] ② Connect the step-down transformers in adjacent areas in parallel to the step-down transformer to share the load and increase the load of the medium-risk step-down transformer;
[0053] In this way, we can cope with the problem of increased load in extreme weather conditions;
[0054] It should be noted that in method ②, because the adjacent step-down transformers may also be in a medium-risk state, when connecting other step-down transformers in parallel, priority can be given to step-down transformers in low population density areas, where the step-down transformer load is generally in a rich state.
[0055] Step 104: When the risk assessment result of the power system is high risk, a decision is made to start the standby step-down transformer, wherein the standby transformer is connected in parallel with the main transformer.
[0056] It should be noted that, in one embodiment, step 104 includes: according to the load condition of the step-down transformer, setting a backup transformer at the step-down transformer in the area prone to high load, wherein the backup transformer is connected in parallel with the main transformer; when the risk assessment result of the power system is high risk, starting the decision of the backup step-down transformer.
[0057] It is understandable that the backup voltage device does not need to be installed in all places. According to the predicted load of the step-down transformer, the backup transformer can be installed at the step-down transformer in the area where high load is likely to occur, thereby directly increasing the load of the step-down transformer at that location;
[0058] Furthermore, in extremely rainy weather, there may be leakage in the transmission lines. In this case, although it will also cause an increase in the load of the step-down transformer, since the leakage of the transmission lines is an occasional occurrence, the difference between the historically predicted load of the step-down transformer and the actual load of the step-down transformer will be very large. Therefore, it is necessary to promptly cut off the corresponding step-down transformer in the area with leakage of the transmission lines to prevent rescue workers in the area from being injured by electric shock.
[0059] In addition, at different risk levels, the grid company will allocate and dispatch resources, including manpower, materials, equipment, etc. differently. These resources will be allocated to high-risk areas first to ensure that the emergency response team and resources are on high alert and can respond quickly to possible failures or emergencies.
[0060] Furthermore, the present application can also utilize real-time data and feedback mechanisms to evaluate whether the decisions taken are effective, and make timely adjustments and optimizations; the optimization process can continuously optimize the triggering conditions of the early warning system, the formulation and execution process of response decisions based on historical data and feedback; and combine machine learning and data analysis technology to improve the accuracy and efficiency of risk prediction and decision recommendations.
[0061] In one embodiment, step 101 includes:
[0062] Step 1011: Obtain weather data for the area where the power system to be evaluated is located, and obtain weather conditions that may affect the power system based on weather data analysis.
[0063] It should be noted that weather data is generally provided by the Meteorological Bureau, and for extreme weather, the Meteorological Bureau defines it based on whether the weather data exceeds the threshold set by it. For the power system, even in the extreme weather specified by the Meteorological Bureau, if some conditions are not met, the power system will not immediately face operational risks; therefore, weather data is used to analyze weather conditions that may affect the power system, such as the impact of temperature on equipment performance or wind speed on transmission lines.
[0064] Step 1012: Obtain comprehensive operating data of each transformer in the power system to be evaluated, where the comprehensive operating data includes load data and operating data.
[0065] It should be noted that the comprehensive data includes the real-time operating data of each transformer in the power system, as well as the historical operating data, and the real-time operating data includes: the temperature of the transformer, the current load of the generator, etc., which are used to subsequently calculate the operating status and health status of the equipment; the historical operating data is the historical load data, which is usually recorded at time intervals of hours or shorter, reflecting the load changes of the step-down transformer, and after comprehensive processing and analysis of the historical operating data of multiple step-down transformers, the historical load changes of the power system can be determined; in addition, for the real-time operating data of the step-down transformer, a decentralized collection method is adopted, and then centralized acquisition and processing is adopted, which has the characteristics of overall planning, and can not only analyze the operating status of each step-down transformer, but also analyze whether the status of a step-down transformer is a special case based on the operating status of a certain step-down transformer and the equipment in its adjacent areas.
[0066] Step 1013: predict the load condition of the step-down transformer according to the load data, and evaluate the operating state of the step-down transformer according to the operating data.
[0067] In one embodiment, step 1013 includes:
[0068] According to the load data, the time series prediction model is used to predict the load condition of the step-down transformer.
[0069] It should be noted that this step is to predict the changes in the power load of each step-down transformer in the future, so as to optimize the power generation of the step-down transformers in each region, adjust the transmission scheduling, and provide a basis for the subsequent evaluation of the equipment operation status;
[0070] In addition, when predicting the load of the step-down transformer, various time series prediction models, such as ARIMA, neural network (LSTM), random forest, etc., can be used for accurate calculation and prediction;
[0071] Take ARIMA as an example:
[0072] The load forecasting model is constructed as follows:
[0073] ;
[0074] in, is the load at time t after h prediction steps, is the load data at the current moment in history, is the white noise error term;
[0075] and is the intercept term in the model, generally a constant, indicating that When it is equal to zero, the predicted value The expected value of The basic forecast level at the time of
[0076] yes The coefficient of The weight in the model that determines the Predictions for the future the extent of the impact;
[0077] is the residual term The coefficient of represents the autoregressive (AR) effect of the residuals in the model. This term allows the model to capture the temporal correlation of the residuals, that is, how the residuals at the previous moment affect the prediction at the current moment.
[0078] The transformer's temperature rise, real-time current data, real-time power load, and historical failure rate are calculated based on the operating data to evaluate the operating status of the step-down transformer.
[0079] It should be noted that this step is used to evaluate the operating status of key equipment in the power system, namely the step-down transformer, to ensure the normal operation of the equipment and to detect potential faults in a timely manner;
[0080] Specifically, the health status of the device can be evaluated by analyzing indicators such as the device's temperature, current load, or historical failure rate.
[0081] Among them, the following formula can be used to evaluate the temperature rise of the transformer:
[0082] ;
[0083] in, is the temperature rise, is the current load, is the equivalent resistance of the transformer;
[0084] The current load can be evaluated through the real-time current data of the device, that is;
[0085] ;
[0086] in, is the real-time power load of the transformer, is the voltage;
[0087] The historical failure rate usually refers to the frequency of equipment failures in the past period of time, which can be estimated by the following formula:
[0088] ;
[0089] in, is the number of times a device fails within a certain period of time. It is the total number of times the device has run in the same time period.
[0090] Step 1014: Conduct a risk assessment on the safe operation of the power system to be assessed based on the load condition and operating status of the step-down transformer and weather conditions.
[0091] In one embodiment, step 1014 includes:
[0092] Compare the predicted load conditions with the actual load values to obtain the load prediction error, determine the equipment health status indicator based on the step-down transformer operating status, and determine the impact of weather conditions based on weather conditions;
[0093] Based on the weighted comprehensive score calculation formula, the risk index is calculated according to the load forecast error and equipment health status indicators, as well as the impact of weather conditions, and the safe operation of the power system to be evaluated is risk assessed based on the risk index;
[0094] The weighted comprehensive score calculation formula is:
[0095] ;
[0096] in, is a risk indicator, is the load forecast error, An indicator of the health status of the device. Due to the influence of weather conditions, , , is the weight of each factor.
[0097] It should be noted that is the load forecast error, which is the difference between the predicted load value and the actual load value;
[0098] It is an indicator of the health status of the step-down transformer, obtained by comparing the current status of the device with historical operating data;
[0099] Is the impact of weather conditions, if extreme weather conditions occur, and or The larger the value of becomes, the greater the impact of weather conditions on the safe operation of the power system becomes.
[0100] The following is an example of step 101:
[0101] If the city encounters extreme heavy rain, the method of step 101 will run as follows:
[0102] First, based on the current weather data and forecast weather data in the urban area, it can be determined that the city is currently experiencing extreme heavy rain weather. Then, it can be concluded that under such weather conditions, the power system may experience a short circuit failure of the step-down transformer due to water exposure, or the transmission line may be exposed.
[0103] Afterwards, if the load forecast error increases, it means that the step-down transformer has a short circuit due to water or the transmission line is exposed. The value of becomes larger accordingly;
[0104] If the transmission line is exposed, the current load of the step-down transformer will increase, and the health status index of the step-down transformer will also increase. The value of becomes larger accordingly;
[0105] And in and If the values of and increase, it means that the weather conditions have a great impact on the safe operation of the power system. The value of becomes larger accordingly;
[0106] Finally, when The value of exceeds 3, indicating that the operation of the power system is high risk;
[0107] when The value of is 2-3, indicating that the operation of the power system is at medium risk;
[0108] when The value of is 1-2, indicating that the operation of the power system is low risk;
[0109] when The value of is less than 1, indicating that the operation of the power system is risk-free.
[0110] If the city encounters extremely high temperature weather or extremely low temperature weather, the method of step 101 will operate as follows:
[0111] First, based on the current weather data and forecast weather data of the urban area, it can be determined that the city is currently in extremely high temperature weather or extremely low temperature weather. Then, it can be concluded that under such weather conditions, the power system may experience an increase in user power consumption.
[0112] Afterwards, if the load forecast error increases, it means that the user's power consumption has increased. The value of becomes larger accordingly;
[0113] If the user's power consumption increases, the temperature rise and current load of the step-down transformer will also increase. At the same time, combined with the historical failure rate, it can be judged whether the step-down transformer is prone to failure at the current time in the past. If it is prone to failure, the health status index of the transformer will increase. The value of will become larger accordingly; if it is not easy to fail, and the temperature rise and current load of the step-down transformer do not reach the critical value, the health index of the step-down transformer will remain unchanged;
[0114] And in and If the values of and increase, it means that the weather conditions have a great impact on the safe operation of the power system. The value of becomes larger accordingly;
[0115] Finally, when The value of exceeds 3, indicating that the operation of the power system is high risk;
[0116] when The value of is 2-3, indicating that the operation of the power system is at medium risk;
[0117] when The value of is 1-2, indicating that the operation of the power system is low risk;
[0118] when The value of is less than 1, indicating that the operation of the power system is risk-free.
[0119] The present application provides a method for assisting decision-making in the safe operation of an electric power system under weather conditions. The method combines weather data in the area where the electric power system is located and the comprehensive operating data of each transformer to evaluate the operating risk of the electric power system, obtains risk assessment results, and adopts different control decisions for electric power systems with different operating risk levels, which can effectively reduce the amount of calculations and thus improve calculation efficiency; and gives corresponding decisions on the power consumption side of the electric power system, which can accurately predict the risks of the urban power system and make more accurate corresponding decisions. This solves the problem that the existing technology is prone to prediction errors in the failure rate of the electric power system due to the lack of analysis conditions on the user side, which leads to errors in the corresponding decisions.
[0120] The above is a method for assisting decision-making in the safe operation of an electric power system under certain weather conditions provided in an embodiment of the present application. The following is a system for assisting decision-making in the safe operation of an electric power system under certain weather conditions provided in an embodiment of the present application.
[0121] See also Figure 3 , an auxiliary decision-making system for safe operation of a power system under weather conditions provided in an embodiment of the present application includes:
[0122] The analysis unit 201 is used to evaluate the operation risk of the power system in combination with the weather data of the area where the power system is located and the comprehensive operation data of each transformer to obtain a risk assessment result, which includes: low risk, medium risk and high risk.
[0123] The first auxiliary decision unit 202 is used to shorten the time interval for tracking the step-down transformers in the power system when the risk assessment result of the power system is low risk.
[0124] The second auxiliary decision unit 203 is used to reduce the load of the step-down transformer by adjusting the operating parameters of the step-down transformer when the risk assessment result of the power system is medium risk.
[0125] The third auxiliary decision unit 204 is used to make a decision to start the standby step-down transformer when the risk assessment result of the power system is high risk, wherein the standby transformer is in parallel with the main transformer.
[0126] Furthermore, an embodiment of the present application also provides a safe operation decision-making auxiliary device for a power system under extreme weather conditions, the device comprising a processor and a memory:
[0127] The memory is used to store program codes and transmit the program codes to the processor;
[0128] The processor is used to execute the steps of the method for auxiliary decision-making for safe operation of the power system under extreme weather conditions as described in the above method embodiment according to the instructions in the program code.
[0129] Furthermore, a computer-readable storage medium is provided in an embodiment of the present application, and the computer-readable storage medium is used to store program code, and the program code is used to execute the method for auxiliary decision-making for safe operation of the power system under extreme weather conditions as described in the above method embodiment.
[0130] Those skilled in the art can clearly understand that, for the convenience and brevity of description, the specific working processes of the systems and units described above can refer to the corresponding processes in the aforementioned method embodiments, and will not be repeated here.
[0131] The terms "first", "second", "third", "fourth", etc. (if any) in the specification of the present application and the above-mentioned drawings are used to distinguish similar objects, and are not necessarily used to describe a specific order or sequence. It should be understood that the data used in this way can be interchangeable where appropriate, so that the embodiments of the present application described herein can be implemented in an order other than those illustrated or described herein, for example. In addition, the terms "including" and "having" and any of their variations are intended to cover non-exclusive inclusions, for example, a process, method, system, product or device that includes a series of steps or units is not necessarily limited to those steps or units that are clearly listed, but may include other steps or units that are not clearly listed or inherent to these processes, methods, products or devices.
[0132] It should be understood that in this application, "at least one (item)" means one or more, and "plurality" means two or more. "And / or" is used to describe the association relationship of associated objects, indicating that three relationships may exist. For example, "A and / or B" can mean: only A exists, only B exists, and A and B exist at the same time, where A and B can be singular or plural. The character " / " generally indicates that the objects associated before and after are in an "or" relationship. "At least one of the following" or similar expressions refers to any combination of these items, including any combination of single or plural items. For example, at least one of a, b or c can mean: a, b, c, "a and b", "a and c", "b and c", or "a and b and c", where a, b, c can be single or multiple.
[0133] In the several embodiments provided in the present application, it should be understood that the disclosed systems, devices and methods can be implemented in other ways. For example, the device embodiments described above are only schematic. For example, the division of the units is only a logical function division. There may be other division methods in actual implementation, such as multiple units or components can be combined or integrated into another system, or some features can be ignored or not executed. Another point is that the mutual coupling or direct coupling or communication connection shown or discussed can be an indirect coupling or communication connection through some interfaces, devices or units, which can be electrical, mechanical or other forms.
[0134] The units described as separate components may or may not be physically separated, and the components shown as units may or may not be physical units, that is, they may be located in one place or distributed on multiple network units. Some or all of the units may be selected according to actual needs to achieve the purpose of the solution of this embodiment.
[0135] In addition, each functional unit in each embodiment of the present application may be integrated into one processing unit, or each unit may exist physically separately, or two or more units may be integrated into one unit. The above-mentioned integrated unit may be implemented in the form of hardware or in the form of software functional units.
[0136] If the integrated unit is implemented in the form of a software functional unit and sold or used as an independent product, it can be stored in a computer-readable storage medium. Based on this understanding, the technical solution of the present application is essentially or the part that contributes to the prior art or all or part of the technical solution can be embodied in the form of a software product. The computer software product is stored in a storage medium, including several instructions to enable a computer device (which can be a personal computer, server, or network device, etc.) to execute all or part of the steps of the method described in each embodiment of the present application. The aforementioned storage medium includes: U disk, mobile hard disk, read-only memory (full name in English: Read-Only Memory, English abbreviation: ROM), random access memory (full name in English: Random Access Memory, English abbreviation: RAM), disk or optical disk and other media that can store program codes.
[0137] As described above, the above embodiments are only used to illustrate the technical solutions of the present application, rather than to limit them. Although the present application has been described in detail with reference to the aforementioned embodiments, those skilled in the art should understand that they can still modify the technical solutions described in the aforementioned embodiments, or make equivalent replacements for some of the technical features therein. However, these modifications or replacements do not deviate the essence of the corresponding technical solutions from the spirit and scope of the technical solutions of the embodiments of the present application.
Claims
1. A method for assisting decision-making in safe operation of power systems under extreme weather conditions, characterized in that: include: Combine weather data of the area where the power system is located and comprehensive operation data of each transformer to evaluate the operation risk of the power system and obtain risk assessment results, which include: low risk, medium risk and high risk; When the risk assessment result of the power system is low risk, shortening the time interval for tracking the step-down transformers in the power system; When the risk assessment result of the power system is medium risk, reducing the load of the step-down transformer by adjusting the operating parameters of the step-down transformer; When the risk assessment result of the power system is high risk, a decision is made to start a standby step-down transformer, wherein the standby transformer is connected in parallel with the main transformer.
2. The method for auxiliary decision-making for safe operation of power system under extreme weather conditions according to claim 1 is characterized in that: The operation risk assessment of the power system is performed by combining the weather data of the area where the power system is located and the comprehensive operation data of each transformer to obtain the risk assessment results, including: Obtain weather data for the area where the power system to be evaluated is located, and obtain weather conditions that may affect the power system based on the weather data; Obtaining comprehensive operating data of each transformer in the power system to be evaluated, wherein the comprehensive operating data includes: load data and operating data; Predicting the load condition of the step-down transformer according to the load data, and evaluating the operating state of the step-down transformer according to the operating data; In combination with the load condition and the operating status of the step-down transformer, as well as the weather conditions, a risk assessment is performed on the safe operation of the power system to be assessed.
3. The method for auxiliary decision-making for safe operation of power system under extreme weather conditions according to claim 2 is characterized in that: The predicting the load condition of the step-down transformer according to the load data, and evaluating the operating state of the step-down transformer according to the operating data, includes: According to the load data, a time series prediction model is used to predict the load condition of the step-down transformer; The temperature rise, real-time current data, real-time power load and historical failure rate of the transformer are calculated based on the operating data to evaluate the operating status of the step-down transformer.
4. The method for auxiliary decision-making for safe operation of power system under extreme weather conditions according to claim 2 is characterized in that: The risk assessment of the safe operation of the power system to be assessed is performed in combination with the load condition and the operating state of the step-down transformer and the weather conditions, including: Comparing the predicted load condition with the actual load value to obtain a load prediction error, determining an indicator of the equipment health status according to the operating status of the step-down transformer, and determining the impact of weather conditions according to the weather conditions; Based on a weighted comprehensive score calculation formula, a risk index is calculated according to the load forecast error and the equipment health status index, as well as the influence of weather conditions, and a risk assessment is performed on the safe operation of the power system to be assessed according to the risk index; The weighted comprehensive score calculation formula is: ; in, is a risk indicator, is the load forecast error, An indicator of the health status of the device. Due to the influence of weather conditions, , , is the weight of each factor.
5. The method for auxiliary decision-making for safe operation of power system under extreme weather conditions according to claim 2 is characterized in that: The weather data includes: current weather data and forecast weather data; the weather conditions include: extreme heavy rain weather, extremely high temperature weather and extremely low temperature weather.
6. The method for auxiliary decision-making for safe operation of power system under extreme weather conditions according to claim 1, characterized in that: When the risk assessment result of the power system is medium risk, reducing the load of the step-down transformer by adjusting the operating parameters of the step-down transformer includes: When the risk assessment result of the power system is medium risk, the load on the transformer is reduced so that the transformer operates within the rated capacity, and the step-down transformer in the adjacent area is connected in parallel to the step-down transformer.
7. The method for auxiliary decision-making for safe operation of power system under extreme weather conditions according to claim 2, characterized in that: When the risk assessment result of the power system is high risk, the decision to start the standby step-down transformer, wherein the standby transformer is connected in parallel with the main transformer, includes: According to the load condition of the step-down transformer, a standby transformer is arranged at the step-down transformer in the area where high load is likely to occur, wherein the standby transformer is connected in parallel with the main transformer; When the risk assessment result of the power system is high risk, a decision is made to start the backup step-down transformer.
8. A safe operation decision support system for power systems under extreme weather conditions, characterized in that: include: An analysis unit, used to evaluate the operation risk of the power system by combining weather data of the area where the power system is located and comprehensive operation data of each transformer, and obtain a risk assessment result, wherein the risk assessment result includes: low risk, medium risk and high risk; A first auxiliary decision-making unit, configured to shorten a time interval for tracking a step-down transformer in the power system when the risk assessment result of the power system is low risk; a second auxiliary decision-making unit, configured to reduce the load of the step-down transformer by adjusting the operating parameters of the step-down transformer when the risk assessment result of the power system is medium risk; The third auxiliary decision unit is used to make a decision to start a standby step-down transformer when the risk assessment result of the power system is high risk, wherein the standby transformer is connected in parallel with the main transformer.
9. A safe operation decision-making auxiliary device for power systems under extreme weather conditions, characterized in that: The device comprises a processor and a memory: The memory is used to store program code and transmit the program code to the processor; The processor is used to execute the method for auxiliary decision-making for safe operation of the power system under extreme weather conditions as described in any one of claims 1-7 according to the instructions in the program code.
10. A computer-readable storage medium, characterized in that: The computer-readable storage medium is used to store program code, and the program code is used to execute the method for auxiliary decision-making for safe operation of the power system under extreme weather conditions as described in any one of claims 1-7.