Slideway beam load test device

Through the pulley set and the hoist load test device driven by the hoist, the problems of heavy manpower and deck damage in the multi-point test of the hoist beam are solved, and efficient and economical load test is achieved, which is suitable for the hoist beam of the offshore oil platform.

CN119104410APending Publication Date: 2024-12-10OFFSHORE OIL ENG QINGDAO
View PDF 0 Cites 1 Cited by

Patent Information

Application Number
CN202411048872.5
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-08-01
Publication Date
2024-12-10

AI Technical Summary

Technical Problem

The slide beam needs to be tested in the load test of the offshore oil platform. The existing reverse chain method destroys the deck sheet, which consumes a lot of manpower and is not economical, affecting efficiency.

Method used

A slide beam load test device is designed, using pulley sets and winches to replace the inverted chain and human pulling, and load tests are realized through wire ropes and counterweights, reducing tension requirements and simplifying installation and movement.

Benefits of technology

It improves the efficiency and economy of load tests, reduces the workload of deck repair, is suitable for multi-point load tests, and reduces manpower consumption.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119104410A_ABST
    Figure CN119104410A_ABST
Patent Text Reader

Abstract

The invention discloses a slideway beam load test device, which comprises a slideway beam and a slideway beam sling, the slideway beam sling is connected to the slideway beam, the slideway beam sling is connected with a tension meter through a first shackle, the tension meter is connected with a second shackle, the second shackle is connected with a first hoisting tackle, and the first hoisting tackle is connected with a second hoisting tackle. The first hoisting tackle is connected with a second hoisting tackle through a steel wire rope, the second hoisting tackle is connected with a hanging belt, the hanging belt is connected with a balancing weight, the steel wire rope is connected with a winch, and the winch drives the second hoisting tackle connected with the steel wire rope to move upwards so that the balancing weight can be hoisted. According to the slideway beam load test device provided by the invention, a slideway beam load test method of fixed chain block and manual pulling is improved, the chain block which needs to damage a deck connection fixed dead point is replaced by the pulley block, the fixed dead point is replaced by the balancing weight, and the slideway beam load test device is simple and convenient to mount, dismount and move, good in economical efficiency and high in reliability. The slide beam is suitable for a multi-point load test.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention belongs to the field of ocean engineering slideway beam load testing, and in particular relates to a slideway beam load testing device. Background Art

[0002] Electric or manual hoists are installed on the slide beam for equipment lifting. Due to the heavy weight of the inverted equipment, the slide beam is prone to bending and deformation during operation. Therefore, after the slide beam is installed, it is necessary to perform a load test to detect whether the strength of the slide beam can meet the later use requirements and safety requirements. During the construction of offshore oil platforms, a fall chain is often used to perform a slide beam load test.

[0003] The load test of the slide beam with a fall chain will destroy the deck plate, set a fixed hinge to fix the fall chain, and rely on manpower to pull to reach the test load. Offshore oil platforms usually have several slide beams, and one slide beam needs to be tested for loads at several test points, and the subsequent repair of the deck plate is a lot of work; in the case of a large load test, the manpower consumption is large and the fall chain is difficult to transport, which affects the efficiency and economy of the slide beam load test.

[0004] Therefore, it is urgent to design a slideway beam load test device to solve the above-mentioned problem of performing load tests on several test points of the slideway beam. Summary of the invention

[0005] In order to solve the technical problems mentioned in the background technology that the slideway beam needs to be subjected to load tests at several test points, and the workload of subsequent repair of the deck plate is large; in the case of large load tests, the manpower consumption is large and the reverse transportation of the fall chain is difficult, a slideway beam load testing device is provided to solve the problem of load testing on several test points of the slideway beam.

[0006] To achieve the above purpose, the specific technical solution of the slideway beam load test device of the present invention is as follows: A slide beam load testing device comprises a slide beam and a slide beam sling, wherein the slide beam sling is connected to the slide beam, the slide beam sling is connected to a tension gauge via a first shackle, the tension gauge is connected to a second shackle, the second shackle is connected to a first lifting pulley, the first lifting pulley is connected to a second lifting pulley via a steel wire rope, the second lifting pulley is connected to a sling, the sling is connected to a counterweight, the steel wire rope is connected to a winch, and the winch drives the second lifting pulley connected to the steel wire rope to move upward to lift the counterweight.

[0007] Furthermore, one end of the wire rope extends out from the winch, and the wire rope passes through the second lifting pulley of the second lifting pulley and then enters the first lifting pulley of the first lifting pulley, and then passes through the first lifting pulley and then enters the second lifting pulley, so that the wire rope is evenly wound between the first lifting pulley and the second lifting pulley.

[0008] Furthermore, a fixed end of a steel wire rope is provided on the second lifting pulley, and one end of the steel wire rope passes through the first lifting pulley and is connected to the fixed end of the steel wire rope.

[0009] Furthermore, a slideway beam sling is sleeved on the slideway beam, a first shackle is sleeved on the slideway beam sling, and the first shackle is connected to the dynamometer via a first shackle pin.

[0010] Furthermore, one end of the dynamometer away from the first shackle is connected to the first lifting hook of the first lifting tackle through the second shackle.

[0011] Furthermore, the second lifting pulley is provided with a second lifting hook, the second lifting hook is hung with a sling, and one end of the sling away from the second lifting hook is connected with a counterweight block.

[0012] Furthermore, both ends of the counterweight block are provided with lifting points, and one end of the lifting belt away from the second lifting hook is sleeved on the lifting point to lift the counterweight block.

[0013] Furthermore, the winch is arranged on the deck, and a counterweight is abutted against the deck.

[0014] Further, the second lifting pulley is located below the first lifting pulley, and the first lifting pulley and the second lifting pulley are located on the same straight line.

[0015] Furthermore, the slideway beam sling can be mounted on various positions of the slideway beam to perform load tests on various positions of the slideway beam.

[0016] The slideway beam load test device of the present invention has the following advantages: The steel wire rope passes through the first lifting pulley and the second lifting pulley respectively to form a pulley block, thereby reducing the tension required to reach the test load. The load value provided by the dynamometer display device is connected to the second lifting pulley through a sling to fix the second lifting pulley. The present application improves the load test method of the slideway beam with a fixed fall chain and manual pulling. The fall chain that needs to destroy the fixed dead point of the deck connection is replaced with a pulley block, the fixed dead point is replaced with a counterweight, and the manual pulling is replaced with a winch. It is easy to install, disassemble, and move, and has good economy. It is suitable for slideway beams that require multi-point load tests. BRIEF DESCRIPTION OF THE DRAWINGS

[0017] Figure 1 It is a schematic diagram of the overall structure of the slideway beam load test device of the present invention.

[0018] Description of the markings in the figure: 1. First shackle; 2. First shackle pin; 3. Tension gauge; 4. Second shackle; 5. Second shackle pin; 6. First lifting block; 7. First lifting hook; 8. First lifting pulley; 9. Wire rope; 10. Second lifting block; 11. Second lifting hook; 12. Second lifting pulley; 13. Fixed end of wire rope; 14. Sling; 15. Counterweight; 16. Lifting point; 17. Winch; 18. Slide beam; 19. Slide beam sling; 20. Deck. DETAILED DESCRIPTION

[0019] In order to make the purpose, technical solution and advantages of the embodiments of the present invention clearer, the technical solution in the embodiments of the present invention will be clearly and completely described below in conjunction with the drawings in the embodiments of the present invention. Obviously, the described embodiments are part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by those skilled in the art without creative work are within the scope of protection of the present invention.

[0020] Those skilled in the art will appreciate that, although some embodiments herein include certain features included in other embodiments but not other features, the combination of features of different embodiments is meant to be within the scope of the present invention and form different embodiments. For example, in the claims, any one of the claimed embodiments may be used in any combination.

[0021] Please refer to the attached Figure 1 The slide beam load test apparatus of the present invention is described.

[0022] like Figure 1As shown, the slide beam load test device in the present invention includes a slide beam 18 and a slide beam sling 19, the slide beam sling 19 is connected to the slide beam 18, the slide beam sling 19 is connected to the slide beam 18, the slide beam sling 19 is connected to the tension gauge 3 through the first shackle 1, the tension gauge 3 is connected to the second shackle 4, the second shackle 4 is connected to the first lifting pulley 6, the first lifting pulley 6 is connected to the second lifting pulley 10 through the wire rope 9, the second lifting pulley 10 is connected to the sling 14, the sling 14 is connected to the counterweight 15, the wire rope 9 is connected to the winch 17, the winch 17 drives the second lifting pulley 10 connected to the wire rope 9 to move upward to lift the counterweight 15. The steel wire rope 15 passes through the first lifting pulley 6 and the second lifting pulley 10 to form a pulley block, thereby reducing the tension required to reach the test load. The load value provided by the dynamometer 3 display device is connected to the second lifting pulley 10 through a sling to fix the second lifting pulley 10. The present application improves the load test method of the slideway beam 18 with a fixed fall chain and manual pulling, and replaces the fall chain that needs to destroy the fixed dead point of the deck 20 with a pulley block, replaces the fixed dead point with a counterweight 15, and replaces the manual pulling with a winch 17. It is easy to install, disassemble, and move, and has good economy. It is suitable for slideway beams that need to undergo multi-point load tests.

[0023] Further, if Figure 1 As shown, one end of the wire rope 9 extends out from the winch 17, and the wire rope 9 passes through the second lifting pulley 12 of the second lifting pulley 10 and then passes into the first lifting pulley 8 of the first lifting pulley 6, and then passes through the first lifting pulley 8 and then passes into the second lifting pulley 12, so that the wire rope 9 is evenly wound between the first lifting pulley 8 and the second lifting pulley 12; a wire rope fixed end 13 is provided on the second lifting pulley 10, and one end of the wire rope 9 passing through the first lifting pulley 8 is connected to the wire rope fixed end 13; a slide beam sling 19 is provided on the slide beam 18, and a first shackle 1 is provided on the slide beam sling 19, and the first shackle 1 is connected to the dynamometer 3 through the first shackle pin 2.

[0024] In this embodiment, the wire rope 9 is wound on the winch 17, one end of the wire rope 9 extends from the winch 17, passes through the second lifting pulley 12 and then passes upward through the first lifting pulley 8. Preferably, the wire rope 9 passes upward from one end of the second lifting pulley 12, penetrates into the corresponding end of the first lifting pulley 8, and then goes around the first lifting pulley 8 back to the second lifting pulley 12, and so on, so that the wire rope 9 is evenly wound between the first lifting pulley 8 and the second lifting pulley 12.

[0025] Preferably, the second lifting pulley 10 is away from the end of the wire rope 9 that passes through the second lifting pulley 12 for the first time. The second lifting pulley 12 is provided with a wire rope fixed end 13. The wire rope 9 is connected to the wire rope fixed end 13 after finally passing through the first lifting pulley 8, so that the first lifting pulley 6 and the second lifting pulley 10 form a pulley group, reducing the tension required to reach the test load.

[0026] Preferably, the slide beam 18 is an I-beam, a slide beam sling 19 is sleeved on the slide beam 18, a first shackle 1 is connected below the slide beam sling 19, the first shackle 1 is connected to a dynamometer 3 at one end away from the slide beam sling 19 through a first shackle pin 2, and the dynamometer 3 displays the load value provided by the device.

[0027] Further, if Figure 1 As shown, the end of the dynamometer 3 away from the first shackle 1 is connected to the first lifting hook 7 of the first lifting pulley 6 through the second shackle 4; the second lifting pulley 10 is provided with a second lifting hook 11, and a sling 14 is hung on the second lifting hook 11, and a counterweight 15 is connected to the end of the sling 14 away from the second lifting hook 11; both ends of the counterweight 15 are provided with lifting points 16, and the end of the sling 14 away from the second lifting hook 11 is mounted on the lifting points 16 to lift the counterweight 15.

[0028] In this embodiment, the end of the dynamometer 3 away from the first shackle 1 is connected to the first lifting hook 7 of the first lifting pulley 6 through the second shackle 4, so that the first lifting pulley 6 is hung on the dynamometer 3; a second lifting hook 11 is provided under the second lifting pulley 10, and a sling 14 is connected to the second lifting hook 11. The end of the sling 14 away from the second lifting hook 11 is connected to the counterweight block 15, thereby realizing the connection of the counterweight block 15 in the load test for lifting.

[0029] Preferably, fixed lifting points 16 are symmetrically provided at both ends of the counterweight block 15 , and one end of the lifting belt 14 away from the second lifting hook 11 is respectively sleeved on the lifting points 16 to achieve stable lifting of the counterweight block 15 .

[0030] Further, if Figure 1 As shown, the winch 17 is arranged on the deck 20, and the counterweight block 15 is abutted on the deck 20; the second lifting pulley 10 is located below the first lifting pulley 6, and the first lifting pulley 6 and the second lifting pulley 10 are located on the same straight line; the slide beam sling 19 can be mounted on various positions of the slide beam 18 to perform load tests on various positions of the slide beam 18.

[0031] In this embodiment, the winch 17 provides tension for the wire rope 9, tightens the wire rope 9, and makes the reading of the dynamometer 3 reach the test load. Preferably, the winch 17 is fixedly mounted on the deck 20. Before the lifting begins, the counterweight 15 is also abutted against the deck 20, and the counterweight 15 and the winch 17 are on the same horizontal line.

[0032] Preferably, the second lifting block 10 is located below the first lifting block 6, and the first lifting block 6, the second lifting block 10 and the counterweight block 15 are arranged on the same straight line.

[0033] Preferably, the slide beam sling 19 can be mounted on any position of the slide beam 18 , and a load test can be performed on any position of the slide beam 18 through the first lifting pulley 6 , the second lifting pulley 10 , the winch 17 and the counterweight 15 .

[0034] The working steps of the slideway beam load test device of this application are as follows: First, the first shackle 1 is connected to the slide beam sling 19 on the slide beam 18, the upper hinge point of the dynamometer 3 is matched with the first shackle pin 2, and the dynamometer 3 is fixed below the test point of the slide beam 18; Then, the first lifting hook 7 is turned sideways upward, connected to the lower hinge point of the tension gauge 3 through the second shackle 4, and the first lifting tackle 6 is fixed directly below the tension gauge 3; Then, the counterweight 15 is arranged on the deck 20 just below the test point of the slide beam 18, and two equal-length slings 14 are used to wrap around the rear ends of the sling points 16 on both sides of the counterweight 15 and hang them on the second lifting hook 11. The second lifting pulley 10 is connected to the counterweight 15 and fixed just below the first lifting pulley 6; Then, the wire rope 9 is led out from the drum of the winch 17, passed through the first lifting pulley 8 and the second lifting pulley 12 of the first lifting pulley 6 and the second lifting pulley 10 in sequence, and the end is fixed to the wire rope fixed end 13 at the latch of the second lifting pulley 10, so that the first lifting pulley 6 and the second lifting pulley 10 form a pulley block; Then, when the load test of the slideway beam 18 is carried out, the hoist 17 is started, the wire rope 9 is tightened, and after the reading of the dynamometer 3 reaches the required test load, the hoist 17 is stopped and kept in this state for a period of time. After the test is completed, the load test of the next point is carried out; Finally, when transporting the slide beam load test device in reverse, take out the end of the wire rope 9 from the fixed end 13 of the wire rope, and lead out the wire rope 9 from the first lifting pulley 8 and the second lifting pulley 12 in turn, remove the first shackle 1 from the slide beam sling 19, use a trolley to transport the device to the next load test point, and repeat the above steps to install it.

[0035] Based on the slideway beam load test device, the steel wire rope 9 passes through the first lifting pulley 8 and the second lifting pulley 12 respectively, forming a pulley block, reducing the tension required to reach the test load, and the load value provided by the dynamometer 3 display device, and the lifting points 16 at both ends of the counterweight block 15 are connected to the second lifting hook 11 of the second lifting pulley 10 through the sling 14 to fix the second lifting pulley 10. The present application improves the slideway beam load test method with fixed fall chain and manual pulling, and replaces the fall chain that needs to destroy the fixed dead point of the deck 20 with a pulley block, replaces the fixed dead point with a counterweight block 15, and replaces the manual pulling with a winch 17. It is easy to install, disassemble, and move, and has good economy. It is suitable for slideway beams that need to undergo multi-point load tests.

[0036] Obviously, the above embodiments of the present invention are merely examples for clearly illustrating the present invention, and are not intended to limit the embodiments of the present invention. For those skilled in the art, other different forms of changes or modifications can be made based on the above description. It is not necessary and impossible to list all the embodiments here. Any modifications, equivalent substitutions and improvements made within the spirit and principles of the present invention should be included in the protection scope of the claims of the present invention.

Claims

1. A slide beam load test device, characterized in that: It includes a slideway beam and a slideway beam sling, the slideway beam sling is connected to the slideway beam, the slideway beam sling is connected to a tension gauge through a first shackle, the tension gauge is connected to a second shackle, the second shackle is connected to a first lifting pulley, the first lifting pulley is connected to a second lifting pulley through a wire rope, the second lifting pulley is connected to a sling, the sling is connected to a counterweight, the wire rope is connected to a winch, and the winch drives the second lifting pulley connected to the wire rope to move upward to lift the counterweight.

2. The slideway beam load test device according to claim 1, characterized in that: One end of the wire rope extends out from the winch, and the wire rope passes through the second lifting pulley of the second lifting pulley and then enters the first lifting pulley of the first lifting pulley, and then passes through the first lifting pulley and then enters the second lifting pulley, so that the wire rope is evenly wound between the first lifting pulley and the second lifting pulley.

3. The slideway beam load test device according to claim 2, characterized in that: The second lifting pulley is provided with a fixed end of a steel wire rope, and one end of the steel wire rope passes through the first lifting pulley and is connected with the fixed end of the steel wire rope.

4. The slideway beam load test device according to claim 1, characterized in that: A slideway beam sling is sleeved on the slideway beam, a first shackle is sleeved on the slideway beam sling, and the first shackle is connected with the dynamometer through a first shackle pin shaft.

5. The slideway beam load test device according to claim 5, characterized in that: One end of the dynamometer away from the first shackle is connected to the first lifting hook of the first lifting tackle through the second shackle.

6. The slideway beam load test device according to claim 2, characterized in that: The second lifting pulley is provided with a second lifting hook, the second lifting hook is hung with a sling, and one end of the sling away from the second lifting hook is connected with a counterweight block.

7. The slideway beam load test device according to claim 6, characterized in that: Both ends of the counterweight block are provided with lifting points, and one end of the lifting belt away from the second lifting hook is sleeved on the lifting point to lift the counterweight block.

8. The slideway beam load test device according to claim 2, characterized in that: The winch is arranged on the deck, and a counterweight is abutted against the deck.

9. The slideway beam load test device according to claim 1, characterized in that: The second lifting pulley is located below the first lifting pulley, and the first lifting pulley and the second lifting pulley are located on the same straight line.

10. The slideway beam load testing device according to claim 4, characterized in that: The slideway beam sling can be mounted on various positions of the slideway beam to perform load tests on various positions of the slideway beam.

Citation Information

Cited By

  • Mooring seat tension test device and method

    CN120651651A