Intelligent construction site project management platform
Through the smart construction site project management platform, using technologies such as the Internet of Things and BIM, the construction site equipment data is integrated and three-dimensional visual charts are generated, which solves the problem that the existing construction site management platform cannot monitor the overall construction progress and personnel status, and improves construction efficiency and safety management ability.
Patent Information
- Application Number
- CN202411227052.2
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-09-03
- Publication Date
- 2024-12-27
AI Technical Summary
The existing construction site management platform is unable to monitor the overall construction progress of the construction project and the working status of the construction personnel, resulting in low construction efficiency and safety management defects, such as not wearing a safety helmet and outsiders entering the construction site without permission.
Provide a smart construction site project management platform, including project command and dispatch center, progress visualization management system, material management system, tunnel management system, mixing station management system and beam yard management system, through the Internet of Things, BIM, GIS and AI technologies , realize data collection and analysis of hardware equipment on the construction site, generate three-dimensional visual charts, and perform remote monitoring and management.
The overall monitoring of construction projects has been achieved, the construction efficiency and intelligence level have been improved, the safety management capabilities of the construction site have been enhanced, and the real-time tracking and management of construction progress and personnel working status have been ensured.
Smart Images

Figure CN119204505A_ABST
Abstract
Description
Technical Field
[0001] The present application relates to the field of smart construction sites, and in particular to a smart construction site project management platform. Background Art
[0002] Construction sites need to have complete and strict safety construction operation specifications. Open construction sites have a large number of internal staff and transport vehicles, which makes management difficult and there are defects in personnel management. For example, construction workers do not wear safety helmets and outsiders enter the construction site without permission, which can easily cause construction site accidents.
[0003] With the continuous development of society and technology, all walks of life have carried out information reforms. In construction projects, the construction site management platform has become an indispensable and important part of construction site management. There are many large-scale equipment and testing equipment on the construction site, but the current construction site management platform generally manages each type of equipment separately, and does not integrate the various equipment and instruments on the construction site. It is impossible to manage and monitor the construction progress of the construction project and the working status of the construction personnel as a whole, resulting in low construction efficiency. Summary of the invention
[0004] The purpose of this application is to provide a smart construction site project management platform that can remotely monitor and manage the project's construction progress, materials, tunnels, mixing plants and beam yard production processes, and can overall monitor the construction progress of the construction project and the working status of construction personnel, thereby improving construction efficiency.
[0005] To achieve the above objectives, this application provides the following solutions:
[0006] This application provides a smart construction site project management platform, including:
[0007] The project command and dispatch center is connected to the business management system of the construction site, and is used to obtain the operation data of the hardware equipment on the construction site from the business management system, and generate a three-dimensional visualized project layout diagram based on the operation data of the hardware equipment on the construction site to intuitively display the basic situation of the project;
[0008] A progress visualization management system is used to obtain project construction progress information and generate a three-dimensional visualization engineering model based on the project construction progress information to display and manage the project construction progress;
[0009] The material management system uses the Internet of Things technology to automatically collect material information through hardware equipment on the construction site to remotely monitor and manage materials on the construction site;
[0010] The tunnel management system is used to obtain tunnel information involved in the project in real time and remotely monitor and manage the construction process in the tunnel based on the tunnel information;
[0011] The mixing station management system is used to automatically collect the production data of the mixing station involved in the project, and remotely monitor and manage the mixed material production process based on the production data of the mixing station; the production data of the mixing station includes the mixing time, mixing materials and project location of each batch of mixed material produced by the mixing station;
[0012] The beam yard management system is used to obtain the beam yard information involved in the project and build a three-dimensional model of the beam yard based on the beam yard information to remotely monitor and manage the production process of the beam yard.
[0013] Optionally, the project command and dispatch center uses a building information model and a geographic information system to generate a three-dimensional visualized project layout diagram.
[0014] Optionally, the project command and dispatch center is also used to determine the production plans for multiple time periods within the project construction cycle based on a pre-built project plan, obtain on-site production data at the end of each time period, and judge whether the production plan is met based on the on-site production data and the production plan for the corresponding time period. If not, adjust the production plan for the next time period.
[0015] Optionally, the project command and dispatch center is also used to visualize the space, environment, components, personnel, machines and materials on the construction site through an electronic sand table.
[0016] Optionally, a project includes multiple unit projects;
[0017] The progress visualization management system is also used to use built-in parametric modeling tools to define the type of each unit project, and build a three-dimensional visualization engineering model of each unit project based on the comprehensive parameters of each unit project. For any unit project, the project construction progress information input by the user on the client is obtained, and the project construction progress information is embedded in the three-dimensional visualization engineering model of the unit project to display and manage the construction progress of the unit project.
[0018] Optionally, the tunnel information includes: tunnel personnel labor information, tunnel personnel location information, gas information, safe step distance, monitoring video, personnel entering and exiting the tunnel, and vehicles entering and exiting the tunnel;
[0019] The process of the tunnel management system remotely monitoring and managing the construction process in the tunnel based on the tunnel information specifically includes: performing safety monitoring of personnel in the tunnel based on the labor information of the tunnel personnel, the positioning information of the tunnel personnel, the safe step distance, the monitoring video, personnel entering and exiting the tunnel, and vehicles entering and exiting the tunnel; judging whether the gas in the tunnel exceeds the safety threshold based on the gas information, and issuing an alarm when the gas in the tunnel exceeds the safety threshold.
[0020] Optionally, the mixing plant management system is also used to obtain material applications submitted by users, conduct online approval based on the material applications, and compare the cumulative signed-in quantity and the designed control quantity in real time during the mixture production process, and issue an over-consumption warning when over-consumption occurs.
[0021] Optionally, the process of remotely monitoring and managing the production process of the beam yard by the beam yard management system specifically includes: performing planning management, production site management and production process management of the beam yard according to the three-dimensional model of the beam yard.
[0022] Optionally, the progress visualization management system, the material management system, the tunnel management system, the mixing station management system and the beam yard management system are all functional modules in the project command and dispatch center.
[0023] Optionally, the project command and dispatch center is deployed in a computer device.
[0024] According to the specific embodiments provided in this application, this application discloses the following technical effects:
[0025] The present application provides a smart construction site project management platform, which generates a three-dimensional visual project layout diagram through the project command and dispatch center, and can remotely and intuitively display the basic situation of the project. Combined with the progress visualization management system, material management system, tunnel management system, mixing station management system and beam yard management system, the project's construction progress, materials, tunnels, mixing stations and beam yard production processes can be remotely monitored and managed, and the construction progress of the construction project and the working status of the construction personnel can be monitored as a whole, thereby improving the intelligence level of the construction site and thus improving construction efficiency. BRIEF DESCRIPTION OF THE DRAWINGS
[0026] In order to more clearly illustrate the embodiments of the present application or the technical solutions in the prior art, the drawings required for use in the embodiments will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the present application. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative work.
[0027] Figure 1 An overall architecture diagram of a smart construction site project management platform provided in one embodiment of the present application;
[0028] Figure 2 A development language and framework diagram of a smart construction site project management platform provided in one embodiment of the present application;
[0029] Figure 3 A functional module diagram of a smart construction site project management platform provided in one embodiment of the present application. DETAILED DESCRIPTION
[0030] The following will be combined with the drawings in the embodiments of the present application to clearly and completely describe the technical solutions in the embodiments of the present application. Obviously, the described embodiments are only part of the embodiments of the present application, not all of the embodiments. Based on the embodiments in the present application, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of this application.
[0031] In order to make the above-mentioned objects, features and advantages of the present application more obvious and easy to understand, the present application is further described in detail below with reference to the accompanying drawings and specific implementation methods.
[0032] This application takes a highway section improvement and reconstruction project as an example to build a smart construction site project management platform. Figure 1 As shown in the figure, the application data of beam yard, mixing station, vehicle positioning, production progress management, video monitoring, tunnel safety monitoring, etc. are integrated and displayed on the same platform. Through Building Information Modeling (BIM) + Geographic Information System (GIS) + Internet of Things (IOT) + Artificial Intelligence (AI) combined with a project layout diagram, the overall picture of the project can be seen and the overall project can be coordinated and dispatched; the key indicators of the project are presented in the form of intuitive charts, combined with indicators such as project production progress management and tunnel safety control, to trace the root cause of the problem, help the project to achieve digitalization, systematization, and intelligence, and create an intelligent command center for the project management team.
[0033] This application provides a set of smart construction site project management platforms that cover the information, knowledge, tools, platforms, and methods required for digital transformation. As the core function of digital projects, IOT and BIM technologies are used to integrate on-site hardware equipment into a unified platform, and the generated data is summarized and modeled in real time to form a data center, so that the project management level can fully grasp the production process, and use artificial intelligence technology to intelligently identify project risks and issue warnings, so as to build a platform for the project management level to summarize data in real time, fully grasp the production process, and effectively reduce project risks.
[0034] First, the construction process of the smart construction site project management platform is introduced, including infrastructure project decision-making design, smart Internet of Things design, system security design, database design, data generation type design, and data docking method and frequency design. The construction process of each part is introduced in detail below.
[0035] 1) Infrastructure project decision-making and design
[0036] System settings: permission management, background management, interface designer, etc.
[0037] Project Overview: Provide various indicators for project supervision and decision-making for each management level, provide a centralized management platform, and a unified entrance for functional applications.
[0038] Data accumulation: The data generated by the software and hardware of the project is stored in the data center and can be viewed and exported at any time.
[0039] Digital reports: Automatically generate digital project reports, support export and WeChat sharing.
[0040] End-to-end cloud services: mobile, web, large-screen recording + importing pictures and videos.
[0041] 2) Smart IoT Design
[0042] In view of the current situation where there are many types of hardware on construction sites, uncertain distribution areas, and unclear operating status, the on-site hardware equipment is integrated through the smart construction site platform, and the hardware usage status, operating information and warning status are presented in a digital way, and displayed uniformly on a two-dimensional rendering or three-dimensional model, so that project managers can understand: which smart hardware is arranged on site and in which areas it is distributed; the real-time operating data of the hardware; timely warnings when there are risks with the hardware; and the accumulation of big data on mechanical equipment.
[0043] System users include tenant administrators and common users.
[0044] Tenant administrators can enter the user center to view basic information, change login passwords, and change security phone numbers. To view basic information, click [User Center] - enter the User Center, locate the [Basic Information] menu, and view the basic information of the administrator account; click [User Center] - enter the User Center [Basic Information], click [Modify]; enter the employee account suffix and click [OK] to modify the employee account suffix. The employee account suffix can only be modified once, and after the modification, all user-defined accounts in this tenant will take effect at the same time. To modify the login password, click [User Center] - enter the User Center [Modify Password] menu, enter the current login password - enter the new login password - confirm the new login password, and click [OK]. To modify the security phone number, click [User Center] - enter the User Center [Mobile Phone Binding] menu, click [Modify Security Phone Number], enter the login password, new security phone number, verification code, and mobile phone verification code respectively, and complete the modification of the security phone number after verification. The bound security phone number can only be used to retrieve the password, not to log in.
[0045] Ordinary users can enter the user center to view basic information, modify avatars, modify passwords, modify bound mobile phones, and other operations. View basic information. The steps for ordinary users to view basic information and modify login passwords are the same as those for tenant administrators, so they will not be repeated here. The steps to modify the avatar are: click [User Center]-enter the User Center [Modify Avatar], click [Reselect], select a new avatar from the local, and click [Save]. The steps to modify the bound mobile phone are: click [User Center]-enter the User Center [Mobile Phone Binding] menu, click [Modify Bound Mobile Phone]. If the login account is a custom account, the security mobile phone is modified. Enter the login password, new security mobile phone, verification code, and mobile phone verification code respectively. After the verification is passed, the security mobile phone is modified. If the login account is a mobile phone account, the bound mobile phone number is modified. Enter the mobile phone number, login password, and verification code respectively. After the verification is passed, the bound mobile phone is modified. The bound security mobile phone number can only be used to retrieve the password, not to log in; the bound mobile phone account can be directly used for login, password retrieval, etc.
[0046] like Figure 2 As shown, the execution entities of the smart construction site project management platform provided by this application include browsers, applications, personal computers and third parties, and the development languages and frameworks used include load balancing, reverse proxy, site, service gateway and application interface gateway. The service part includes service governance, basic business services and public services. Among them, service governance includes discovery (Eureka) service, configuration service, fuse monitoring and link tracking; basic business services include login service, user service, tenant service, organization service, role service, permission service, tenant product authorization service, authorization file generation service, project extension information service, product service, sales service and project configuration service; public services include push (PUSH) service, sequence (Sequence) service, SMS gateway service, SMS address service, data synchronization service and report printing service. The designed underlying database includes relational database management system (MySQL), remote dictionary service (Redis), object storage service (Object Storage Service, OSS), distributed database service (Table Store, OTS) and message queue (Message queue, MQ).
[0047] This application adopts a unified cloud platform to make the data of the internal system highly consistent, running through the entire software and hardware data system, so that scalability and consistency can be guaranteed. A high-performance Internet of Things platform is used to make hardware access safe and stable. The overall architecture is centered on microservices to achieve unified platform microservice governance. This architectural approach achieves large-scale support, reduces duplicate development, and facilitates expansion and maintenance. The platform splits the system business into components and services, splitting them into independent microservices, which are uniformly managed by the service governance center. Each microservice is an independent container, and the communication between microservices is completed through remote procedure calls (RPC), representational state transfer (REST) or message queues to achieve maximum decoupling and reuse. The deployment method uses K8S containerized deployment to reduce the service's dependency on infrastructure.
[0048] This architecture has the following advantages:
[0049] ① Complexity is controllable. While decomposing the application, the endless accumulation of complexity is avoided. Each microservice focuses on a single function and clearly expresses the service boundary through a well-defined interface. Due to its small size and low complexity, each microservice can be fully controlled by a small development team, making it easy to maintain high maintainability and development efficiency.
[0050] ② Independent deployment. Since microservices have independent running processes, each microservice can also be deployed independently. When a microservice changes, there is no need to compile and deploy the entire application. An application composed of microservices is equivalent to having a series of parallel release processes, making release more efficient, while reducing the risks to the production environment, and ultimately shortening the application delivery cycle.
[0051] ③ Flexible technology selection. Under the microservice architecture, technology selection is decentralized. Each team can freely choose the most suitable technology stack based on its own service needs and the current status of industry development. Since each microservice is relatively simple, the risk of upgrading the technology stack is low, and it is even feasible to completely reconstruct a microservice.
[0052] ④ High fault tolerance. When a component fails, in the traditional architecture of a single process, the fault is likely to spread within the process, causing the application to be globally unavailable. In the microservice architecture, the fault will be isolated in a single service. Other services can achieve application-level fault tolerance through mechanisms such as retries and smooth degradation.
[0053] ⑤ Scalability. Monolithic applications can also be expanded horizontally, that is, the entire application is completely copied to different nodes. When different components of the application have different expansion requirements, the microservice architecture will show its flexibility, because each service can be expanded independently according to actual needs.
[0054] 3) System security design
[0055] The data security of users is the lifeline of users and is also one of the most important concrete manifestations of the overall security capabilities of the smart construction site project management platform. The requirements for data security can be summarized by the three basic elements of information security: confidentiality, integrity, and availability. Confidentiality specifically refers to the fact that protected data can only be accessed by legitimate (or expected) users. Its main implementation methods include data access control, data leakage prevention, data encryption, and key management. Integrity is to ensure that only legitimate (or expected) users can modify data, which is mainly achieved through access control. At the same time, the integrity of user data can be guaranteed by verification algorithms during data transmission and storage. The availability of data is mainly reflected in the overall security capabilities, disaster recovery capabilities, and reliability of the cloud environment, as well as the normal operation of various related systems on the cloud (storage systems, network paths, identity authentication mechanisms, and permission verification mechanisms, etc.). This application stores all data on the Huawei cloud platform to improve data security.
[0056] 4) Database design
[0057] The database design should follow the following principles:
[0058] ① Standardized naming. All database names, table names, and domain names must follow unified naming rules and provide necessary explanations to facilitate design, maintenance, and query.
[0059] ② Control the reference of fields. When designing, you can choose appropriate database design management tools to facilitate the distributed design of developers and the centralized review and management of data teams. Use a unified naming rule. If the designed field already exists, it can be directly referenced; otherwise, it should be redesigned.
[0060] ③ Library table duplication control. During the design process, if it is found that most of the fields already exist, the developer should doubt whether the library table designed already exists. By querying the library table where the field is located and the corresponding designer, it can be confirmed whether the library table is indeed duplicated.
[0061] ④ Concurrency control. Concurrency control should be implemented in the design, that is, for the same database table, only one person has control at the same time, and others can only query.
[0062] ⑤Header file processing. After each data modification, the corresponding header file needs to be modified and the relevant developers need to be notified so that the corresponding program modifications can be made.
[0063] 5) Design of generated data types
[0064] The types of data generated include real-time equipment data, equipment alarm data, equipment image data, equipment business data, business data of each business module, etc.
[0065] 6) Data connection method and frequency design
[0066] This application supports data push of protocols such as Hypertext Transfer Protocol (HTTP), Transmission Control Protocol (TCP), Message Queuing Telemetry Transport (MQTT), etc.; push according to standard protocols; push according to the docking party format; support historical data query. Dynamic docking frequency is adopted, and the frequency can be dynamically set according to the docking party interface definition. There is no frequency limit by default.
[0067] In an exemplary embodiment, Figure 3 As shown, a smart construction site project management platform is provided, including: a project command and dispatch center 301, a progress visualization management system 302, a material management system 303, a tunnel management system 304, a mixing station management system 305 and a beam yard management system 306.
[0068] In this application, the project command and dispatch center 301, the progress visualization management system 302, the material management system 303, the tunnel management system 304, the mixing station management system 305 and the beam yard management system 306 are used for different business departments, and their basic data and results are shared, and interconnection is achieved through the data middle platform.
[0069] In a specific example, the progress visualization management system 302, the material management system 303, the tunnel management system 304, the mixing station management system 305 and the beam yard management system 306 are all functional modules in the project command and dispatch center 301. The project command and dispatch center 301 is deployed in a computer device.
[0070] The functions of each system are introduced below.
[0071] (1) Project Command and Dispatch Center 301
[0072] The project command and dispatch center 301 is connected to the business management system of the construction site to obtain the operating data of the hardware equipment on the construction site from the business management system, and generate a three-dimensional visual project layout diagram based on the operating data of the hardware equipment on the construction site to intuitively display the basic situation of the project.
[0073] The hardware equipment on the construction site includes sensors, access control, cameras, high-definition scanners, video hosts, mobile terminals, printers, industrial control desks, weighbridges and infrared beamforming devices. The hardware equipment on the construction site is connected to the mobile application and data analysis platform through the Internet.
[0074] In a specific example, the project command and dispatch center 301 uses building information modeling and geographic information system to generate a three-dimensional visualized project layout diagram. That is, the project command and dispatch center 301 forms a three-dimensional visualized project layout diagram by superimposing GIS maps through BIM modeling to replace the traditional project floor plan and project overview board, thereby intuitively displaying the basic situation of the project through a real-time online digital project panorama, allowing the management to quickly and intuitively understand the project overview and operation status.
[0075] In another exemplary embodiment, the project command and dispatch center 301 is also used to determine the production plans for multiple time periods within the project construction cycle based on a pre-built project plan, obtain on-site production data at the end of each time period, and determine whether the production plan is met based on the on-site production data and the production plan for the corresponding time period. If not, adjust the production plan for the next time period.
[0076] In another exemplary embodiment, the project command and dispatch center 301 is also used to visualize the space, environment, components, personnel, machines and materials of the construction site through an electronic sand table. The on-site image progress and construction deviation can also be visualized through the electronic sand table. At the same time, roaming videos can be quickly produced based on the electronic sand table, which has a very good application effect in image display. The maps in the electronic sand table are divided into oblique photography and purchased Baidu maps.
[0077] The project command and dispatch center 301 is connected to the business management system of the construction site through the Internet of Things equipment, collects data such as labor, materials, progress, videos, etc. on the construction site, and assists on-site management through pre-designed internal management logic. For example, when managing the production progress, first upload the overall project plan, and the project command and dispatch center 301 automatically generates a weekly plan (including the number of people required, the number of machines required, the amount of materials required, etc.) according to the overall project plan, and compares the weekly plan with the data collected on site to determine whether it meets the production plan.
[0078] This application integrates, analyzes, processes and stores the data of smart construction site related applications by establishing a project command and dispatch center 301. Project managers can quickly understand the core data of project management through the data analysis platform of the project command and dispatch center 301, including safety and quality warning conditions, distribution of man-machine materials, real-time progress status, on-site video, etc., to assist in scientific management of the project and improve the level of project management. The project command and dispatch center 301 can also be used to achieve unified management of project camps, beam yards, steel bar processing plants and other sites, and realize dynamic management of major production factors such as labor personnel, machinery and equipment, materials, and environment. Through labor management, the labor management needs of infrastructure projects such as roads, railways, roads and bridges, tunnels, and closed and non-closed scenarios are met, and information management is used to help enterprises avoid labor risks, improve project progress, and reduce labor costs.
[0079] This application has created a project command and dispatch center 301 that can be observed, commanded, and moved. The command center uses a digital construction platform for project management and adopts modern scientific and technological equipment to combine the BIM model with on-site construction briefing, production, safety, and quality. At the same time, the on-site equipment is intelligently monitored through the smart construction site system to create an integrated platform for digital command. Specifically, the digital exhibition hall was built from three aspects: digital operation, digital command, and intelligent experience. Among them, the BIM model is combined with on-site construction briefing, production, safety, and quality to lead a new generation of construction mode with visual management and digital operation; digital command provides data visualization dashboards, presents the status and key data of various elements of the construction site as a whole, remotely grasps risks and hidden dangers, and conducts remote command and dispatch; uses augmented reality / virtual reality / hybrid display and other forms of intelligent experience, so that visitors can have an immersive experience and achieve efficient technical briefing and production management.
[0080] (2) Progress visualization management system 302
[0081] The progress visualization management system 302 is used to obtain project construction progress information and generate a three-dimensional visualization engineering model based on the project construction progress information to display and manage the project construction progress.
[0082] Specifically, a project includes multiple unit projects. Visual progress is the core indicator of infrastructure project control and management progress, and the visual progress wall chart that has been used for decades is also the most popular and commonly used tool for visual progress. Visual progress wall charts usually draw and display the components of unit projects such as bridges, tunnels, and culverts in two dimensions, and then mark the progress completion status of each component by coloring according to the actual progress. The visual progress wall chart can be used to view and understand the overall progress of the entire project at a glance, and can also be used to introduce or report on the progress completion of the project. Visual progress wall charts Figure 1It is usually hung on the walls of the project manager's office, other project leaders' offices, project meeting rooms and other indoor places where needed.
[0083] The three-dimensional visualization engineering model constructed in this application displays the visual progress through the color difference of the model, and can also compare the design quantity and the actual quantity, that is, the loss quantity.
[0084] In another exemplary embodiment, the progress visualization management system 302 is also used to use a built-in parametric modeling tool to define the type of each unit project, and construct a three-dimensional visualization engineering model of each unit project based on the comprehensive parameters of each unit project. For any unit project, the project construction progress information input by the user on the client is obtained, and the project construction progress information is embedded in the three-dimensional visualization engineering model of the unit project to display and manage the construction progress of the unit project.
[0085] The progress visualization management system 302 has a built-in standard component library that meets the common types of infrastructure projects. The standard component library is mainly used to meet the needs of visual progress display and expression. For example, the bridge component library contains common bridge foundation types, piers and beam models. The standard component library supports the addition of component types according to the actual needs of the project to form an enterprise component asset library. At the same time, the progress visualization management system 302 also supports the import of existing BIM models of the project.
[0086] This application mainly uses the built-in parametric modeling tool. By defining the unit project type and then entering the comprehensive parameters of the unit project, a three-dimensional visual engineering model that meets the requirements of project image progress display and management can be quickly built. For example, the parametric modeling of the bridge image progress model only needs to define the type of bridge (simply supported beam, continuous beam, continuous T-structure or other types), and then enter the starting and ending mileage of the bridge location, the number of spans, the length of the span, the number of beams arranged per span and the cross-sectional form of the beam body, the type of bridge foundation, the arrangement of pile foundations, the type of piers, and other core parameters, and the overall bridge model can be produced with one click.
[0087] Users can report progress completion status in a timely manner through mobile applications or mini-programs. This application can further preview the visual progress of all unit projects or view detailed progress information through the "Visual Progress" menu on page 301 of the project command and dispatch center. On the "Visual Progress" homepage, you can identify the progress status of each unit project, and use a flashing red light to prompt the unit project with lagging progress. You can also switch to the visual progress chart of a specific unit project to view detailed component progress information.
[0088] (3) Material Management System 303
[0089] The material management system 303 is used to adopt the Internet of Things technology to automatically collect material information through hardware equipment on the construction site, so as to remotely monitor and manage the materials on the construction site.
[0090] This application realizes all-round lean management of materials entering and leaving the site through the material management system 303, and adopts the Internet of Things technology to intelligently and automatically collect material information through peripheral hardware equipment such as weighbridges. Data integration and cloud computing technologies are used to timely grasp first-hand data, effectively accumulate, preserve and increase the value of material data assets. The Internet and big data technologies are used for multi-project data monitoring and full-dimensional intelligent analysis. Mobile Internet technology is used to control the site and identify risks anytime and anywhere, and realize zero-distance intensive management and control and visual decision-making.
[0091] In a specific example, the material management system 303 can be connected to the scale at the construction site, and the materials can be automatically weighed through the scale, and the material information can be sent to the material management system 303, ensuring that no one can modify the weighing data, ensuring the authenticity and accuracy from the source of the data, avoiding the existence of human factors such as manual errors, and ensuring that the materials are actually weighed and put into storage. Through the automatic association between the material management system 303 and the scale, it can be traced when problems arise in the material management process. In addition, the material management system 303 can also analyze and organize the material information and export reports.
[0092] The material management system 303 can also analyze the details and summary of material delivery and receipt, and update them dynamically in real time to objectively, truly and accurately reflect the situation of material delivery and receipt. It can combine and analyze multiple perspectives such as time, material supplier, source, deviation, etc. to support actual procurement, actual arrival and actual material delivery analysis, and provide accurate data support for procurement plans, funding plans, material arrangements, project progress, etc.
[0093] (4) Tunnel Management System 304
[0094] The tunnel management system 304 is used to obtain tunnel information involved in the project in real time, and to remotely monitor and manage the construction process in the tunnel based on the tunnel information.
[0095] In a specific example, the tunnel information includes: tunnel personnel labor information, tunnel personnel location information, gas information, safe step distance, monitoring video, personnel entering and exiting the tunnel, and vehicles entering and exiting the tunnel.
[0096] Gas information includes gas detection and non-gas detection. The safety step distance uses laser radar to measure distance accurately.
[0097] The process by which the tunnel management system 304 remotely monitors and manages the construction process in the tunnel based on the tunnel information specifically includes: performing safety monitoring of personnel in the tunnel based on the tunnel personnel labor information, the tunnel personnel positioning information, the safe step distance, the monitoring video, personnel entering and exiting the tunnel, and vehicles entering and exiting the tunnel; determining whether the gas in the tunnel exceeds the safety threshold based on the gas information, and issuing an alarm when the gas in the tunnel exceeds the safety threshold.
[0098] The tunnel management system 304 of the present application displays data such as tunnel personnel labor information, tunnel personnel positioning information, gas information, safe step distance, monitoring video, etc. through a billboard, and can also monitor the personnel and vehicles entering and leaving the tunnel in real time. It further counts attendance and various labor warnings in different dimensions, and alarms are issued in combination with real-time personnel positioning. When the gas in the tunnel exceeds the standard, an alarm is issued to ensure the safety of on-site workers. In addition, the tunnel management system 304 has its own calibration function, which can be compared and calibrated with the tile inspector.
[0099] (5) Mixing station management system 305
[0100] The mixing station management system 305 is used to automatically collect the production data of the mixing station involved in the project, and remotely monitor and manage the mixed material production process according to the production data of the mixing station. The production data of the mixing station includes the mixing time, mixing materials and project location of each batch of mixed material produced by the mixing station.
[0101] This application aims at the management pain points of mixing stations, adopts new technologies such as the Internet of Things, cloud computing, big data analysis, 5G, etc., uses the method of dynamic quality management, and adopts a combination of software and hardware to automatically collect and analyze the production data of mixing stations. It also makes error judgments on the production data of mixing stations according to the set standards, and promptly issues alarms when abnormal data is found, thus realizing remote monitoring and management of mixed material production, achieving pre-control of mixed material quality, and ensuring the quality and safety of the main structure of the project.
[0102] In another exemplary embodiment, the mixing station management system 305 is also used to obtain material applications submitted by users, perform online approval based on the material applications, and compare the cumulative signed-in quantity and the designed control quantity in real time during the mixture production process, and issue an over-consumption warning when over-consumption occurs.
[0103] Specifically, users can submit material applications through mobile applications. The mixing station management system 305 sets up an approval process according to management requirements, and conducts real-time online convenient approval, replacing the original telephone, paper document signing and other methods. The approval process is efficient and traceable. Users sign for materials on site through mobile applications, compare the cumulative signed quantity with the design control quantity in real time, and promptly remind the signatory of over-consumption or expected over-consumption. At the same time, over-consumption warning messages are pushed to management personnel, realizing real-time control of on-site material consumption. This application uses mobile applications to collect data from mixing stations, and realizes refined management by analyzing and processing the data, such as order distribution, mix ratio supervision, and capacity management.
[0104] Furthermore, the mixing station management system 305 is also used to calculate the material consumption of each part in real time, and intuitively display the construction progress of each part on the part tree in the form of a progress bar. The material savings and capital profits and losses of each part are calculated through real-time and accurate data. The construction team dimension is calculated in real time, and the overall material savings and capital profits and losses are analyzed in real time, and the consumption of each material and each part of the construction team can be drilled down.
[0105] (6) Beam yard management system 306
[0106] The beam yard management system 306 is used to obtain beam yard information involved in the project and construct a three-dimensional model of the beam yard based on the beam yard information to remotely monitor and manage the production process of the beam yard.
[0107] In a specific example, the process of remote monitoring and management of the production process of the beam yard by the beam yard management system 306 specifically includes: planning management, production site management and production process management of the beam yard according to the three-dimensional model of the beam yard.
[0108] In another exemplary embodiment, the beam yard management system 306 includes a C / S terminal, a B / S terminal and an M / S terminal. Among them, the C / S terminal mainly performs complex business operations, the B / S terminal can conveniently query various information and statistical reports, and the M / S terminal is used to fill in data on site and query information in real time.
[0109] The beam yard management system 306 is based on the Internet of Things platform and supports the access to third-party systems such as the on-site intelligent production system, such as the intelligent tensioning system, the intelligent grouting system, and the intelligent maintenance system, to achieve the integrated display and management of the production system. The beam yard management system 306 also provides a large visual digital screen to comprehensively display all aspects of beam yard production information, and users can easily browse beam yard information and three-dimensional models.
[0110] In this application, the construction of the beam yard management system 306 is based on the 4D+BIM cloud platform. The cloud service provides the application end with a BIM data engine, a graphics engine, and an IoT engine, supporting cross-platform business data integration and collaboration. On the upper layer of the cloud platform, the beam yard management system 306 provides general functions for the construction stage.
[0111] On the basis of general functions, the beam yard management system 306 provides beam yard professional functions for the actual needs of the prefabricated beam yard, including planning management functions such as beam erection plan, beam manufacturing plan, and line deployment, on-site management functions such as process management, beam management, and pedestal management, and production management functions such as progress management, production status, production ledgers, and production reports. At the same time, the beam yard management system 306 provides on-site display of three-dimensional models and a large screen for beam yard production management and command.
[0112] In another exemplary embodiment, the smart construction site project management platform also includes: a technical management system 307, a standard curing room specimen management system 308, a testing machine data acquisition and monitoring system 309, a pile driving monitoring system 310, a pile driver construction intelligent monitoring system 311 and an earthwork continuous compaction quality intelligent control system 312.
[0113] (7) Technical management system 307 includes drawing management, change management, program management and briefing management.
[0114] ① The business scenario of drawing management is: the construction project site needs to check the latest version of drawings anytime and anywhere; the general contractor's drawings are not issued in time, resulting in rework of the subcontractor according to the old version of the drawings, causing disputes between the general contractor and the subcontractor; it is difficult to find the changes in the drawing packages issued by the design institute and the updated drawings, and it is easy to miss the change information, resulting in the risk of rework. The solution is to view the drawings online anytime and anywhere, issue and sign the drawing ledger online, and the packaged version and drawing changes are clear at a glance. In this way, the drawings can be stored in an orderly manner and managed as a whole, which is convenient for project personnel to find and view; the drawing update version, the issuance and receipt management, ensure the timeliness and accuracy of the drawing viewing by all parties; drawing comparison and drawing package version comparison make it easier for project personnel to understand the updated content of each version of the drawings.
[0115] ②The business scenario of change management is: due to inadequate change management in a certain project, the subcontractor implemented the old changes, resulting in a demolition and modification cost of 230,000 and a delay of 10 days in the construction period; due to the loss of visa record information in a certain project, the settlement loss was 134,000; due to the inadequate implementation of the subcontractor in a certain project, the subcontractor claimed improper supervision, and the general contractor ultimately assumed part of the responsibility and construction period loss. The solution is to view the change drawings in a linked manner, and provide SMS early warning reminders to reduce omissions, change review and other records, and export them online with one click. View relevant change and review records through drawings to avoid missing changes and rework; remind drawing review and change content according to the progress of the project to avoid unclear responsibilities; electronically archive change and visa documents to support settlement and avoid settlement losses.
[0116] ③Business scenarios of solution management are: a project solution was not submitted for review in time, resulting in construction without a solution, and the government inspection resulted in a one-week suspension of work; a project solution was not fully disclosed, and the actual construction was inconsistent with the solution requirements, resulting in disputes between technical personnel and production personnel; a project did not recognize the content of a hidden process mentioned in the solution during settlement, and required on-site photos to provide evidence. The solution is to assign responsibility for the solution plan to individuals, provide early warning reminders, and record the entire process of solution disclosure and review. Then form a solution preparation plan, assign responsibilities to individuals, and issue early warnings according to the planned time to prevent delays in preparation; manage the entire process from solution approval to demonstration disclosure and review, forming a closed management loop to reduce the risk of inadequate solution implementation and incomplete information.
[0117] ④ The business scenarios of briefing management are: sharing of briefing materials is not easy to use, shared materials on social software are easy to expire, have size restrictions, and viewing without records can easily lead to disputes; the text briefing requirements for key parts and difficult nodes are difficult to understand, which can easily lead to on-site problems; the briefing process is not closed-loop, and the responsibility is not clear after problems occur. The solution is WeChat applet + QR code to search for materials, 3D node + process animation briefing, and briefing notification sharing, assessment and signing full process records. This makes it more convenient and quick to send and search project materials; 3D briefing is more intuitive, which improves the learning speed of front-line operators, thereby accelerating construction progress; the entire briefing process is recorded online to reduce later disputes.
[0118] (8) Standard curing room specimen management system 308
[0119] The current standard maintenance room temperature and humidity monitoring is not timely and there are no early warning prompts; the manual entry of the management ledger of ten standard samples is inefficient, and it is troublesome to query the expiration of the test blocks; the standard maintenance data is difficult to statistically analyze and cannot form a basis for decision-making.
[0120] The standard curing room specimen management system 308 provided in the present application adopts the Internet of Things method, and uses sensors to sense changes in the temperature and humidity of the standard curing room for real-time viewing. The alarm threshold can also be set for over-temperature alarms; a digital method is used to enter the test block information through a mobile phone or computer, which is convenient for recording and querying, and active warnings are issued for test block expiration; and the relevant data are displayed in an all-round manner on a large screen to assist management decisions.
[0121] (9) Testing machine data acquisition and monitoring system 309
[0122] The testing machine data acquisition and monitoring system 309 conducts digital transformation and upgrading of asphalt testing instruments and equipment, and uses information technology such as network communication to complete the third-party background collection of test data during the test process, and upload it to the monitoring platform to ensure the authenticity of the test data from the source; at the same time, data analysis is performed according to the test inspection standards to achieve the control of unqualified data. Specifically, management personnel monitor the on-site experimental data in real time through mobile phones and computer backends, and check the test completion status and past experimental data at any time, providing first-hand information for quality analysis control and construction ledger improvement. When it is found that the test results exceed the limit, the early warning information is sent to the manager's mobile phone in time to facilitate timely rectification and timely adjustment of the backstage. According to the test data, feedback is given to the background in the form of charts, making data viewing more intuitive and providing comprehensive statistical data.
[0123] (10) Pile monitoring system 310
[0124] The pile pouring monitoring system 310 monitors the concrete pouring status in real time by installing a sensing module at the top elevation of the steel cage pile in advance. The front-end host provides real-time feedback on the monitoring status of the sensing module to remind on-site construction personnel that the concrete has been poured in place. Managers can also view the on-site pile pouring status in real time through a computer or mobile phone background and form a cloud chart for quality and progress analysis.
[0125] (11) Intelligent monitoring system for pile driver construction 311
[0126] Traditional pile foundation construction has the following defects: it is a hidden project and the process is difficult to control; personnel are required to supervise the whole process; it is affected by the on-site environment and measurements are not timely; process connection wastes time; there is a lot of data to record on-site construction; and there is no data traceability for quality issues.
[0127] The pile driver construction intelligent monitoring system 311 provided in this application performs intelligent pile foundation construction: 1. Real-time monitoring, timely warning of problems, and timely correction; 2. A navigation tablet is set up in the cab to guide the driver in construction; 2. High-precision positioning, only the points need to be imported, no on-site layout is required; 3. Save measurement time and smoothly connect the processes; 4. Monitoring records are exported as reports, and the data is true and valid; 5. Data is saved for a long time and can be queried and exported for use according to conditions. By adopting Beidou satellite positioning technology, the Internet of Things, cloud computing, big data and other means, the method of mechanically adding Internet of Things sensor equipment can solve the problems of time-consuming and labor-intensive layout, difficult construction quality and progress control, and complex quality traceability during pile foundation construction, and effectively achieve process control.
[0128] Specifically, the intelligent monitoring system 311 for pile driver construction includes: monitoring of dynamic compaction machines, monitoring of hammer piles, monitoring of long spiral drills, monitoring of mixing piles and monitoring of rotary drilling machines.
[0129] ① Dynamic compaction machine monitoring: display foundation construction information, start and end node information, centimeter-level positioning of the rammer and the horizontal position, elevation and direction of the machine body; accurately and automatically record the number of ramming times, rammer drop distance, ramming energy, and ramming sinking amount.
[0130] ② Hammer pile monitoring: display foundation construction information and start and end node information; provide on-site prompts when the penetration reaches the stop hammer standard; perform background calculations on the amount of concrete poured before the inner pipe expansion and provide real-time feedback; display the verticality of the pile body, real-time on-site wind speed, soil pressure at the pile end, and graphically guide the position of the pile point.
[0131] ③Long spiral drilling rig monitoring: display foundation construction information, start and end node information, feed data, hole depth, pile verticality, on-site real-time wind speed, pile end bearing pressure and graphic guidance of pile point location.
[0132] ④ Mixing pile monitoring: Display foundation construction information, start and end node information, centimeter-level positioning rammer and horizontal position, elevation and direction of the fuselage; display pile foundation point positioning, pile drilling depth, pile drilling speed, inner drill rod current, outer drill rod current, inclination, cement slurry flow, and material usage. Pile point design files are imported into the onboard tablet; alarm is triggered when the set value is exceeded; construction data is transmitted back to the foundation processing construction management platform in real time; monitoring data is automatically stored and supports breakpoint continuation.
[0133] ⑤ Rotary drilling rig monitoring: display foundation construction information, start and end node information, centimeter-level positioning rammer and horizontal position, elevation and direction of the machine body; pile foundation point positioning; display pile drilling depth and inclination.
[0134] (12) Earthwork continuous compaction quality intelligent control system 312
[0135] The earthwork continuous compaction quality intelligent control system 312 is used to monitor the compaction process, over-limit warning and correction, historical data tracing and on-site construction guidance.
[0136] ① Compaction process monitoring: Change the traditional result detection method, control the continuous compaction value during the process, truly record the entire compaction process (speed, density, number of passes, compaction trajectory), and view all summary data in real time, and support mobile phone viewing.
[0137] ② Over-limit warning and correction: If the compaction quality exceeds the limit value, multiple forms of alarms will be provided in time according to customer standards to remind on-site problems to be corrected in time.
[0138] ③ Historical data traceability: Truthfully record and consolidate the data of the entire process, provide support for quality control with the most comprehensive and authentic data, realize accurate backtracking of construction data, and customize work statistical reports and analysis reports according to needs.
[0139] ④ On-site construction guidance: The analysis data is fed back to the navigation tablet in real time. The driver can adjust the mechanical operation in time according to the data displayed on the tablet to achieve in-process control.
[0140] This application implants high-tech technologies such as artificial intelligence, sensing technology, virtual reality, etc. into various objects such as buildings, machinery, personnel wearable facilities, site entry and exit checkpoints, and generally interconnects them to form the Internet of Things, which is then integrated with the Internet to achieve the integration of engineering management personnel and engineering construction sites, ensure the safe progress of the project, ensure the safety of construction personnel based on linkage information, and improve construction efficiency.
[0141] It should be noted that the user information (including but not limited to user device information, user personal information, etc.) and data (including but not limited to data used for analysis, stored data, displayed data, etc.) involved in this application are all information and data authorized by the user or fully authorized by all parties, and the collection, use and processing of relevant data must comply with relevant regulations.
[0142] The technical features of the above embodiments may be arbitrarily combined. To make the description concise, not all possible combinations of the technical features in the above embodiments are described. However, as long as there is no contradiction in the combination of these technical features, they should be considered to be within the scope of this specification.
[0143] This article uses specific examples to illustrate the principles and implementation methods of this application. The description of the above embodiments is only used to help understand the method and core ideas of this application. At the same time, for those skilled in the art, according to the ideas of this application, there will be changes in the specific implementation methods and application scope. In summary, the content of this specification should not be understood as limiting this application.
Claims
1. A smart construction site project management platform, characterized in that: The smart construction site project management platform includes: The project command and dispatch center is connected to the business management system of the construction site, and is used to obtain the operation data of the hardware equipment on the construction site from the business management system, and generate a three-dimensional visualized project layout diagram based on the operation data of the hardware equipment on the construction site to intuitively display the basic situation of the project; A progress visualization management system is used to obtain project construction progress information and generate a three-dimensional visualization engineering model based on the project construction progress information to display and manage the project construction progress; The material management system uses the Internet of Things technology to automatically collect material information through hardware equipment on the construction site to remotely monitor and manage materials on the construction site; The tunnel management system is used to obtain tunnel information involved in the project in real time and remotely monitor and manage the construction process in the tunnel based on the tunnel information; The mixing station management system is used to automatically collect the production data of the mixing station involved in the project, and remotely monitor and manage the mixed material production process based on the production data of the mixing station; the production data of the mixing station includes the mixing time, mixing materials and project location of each batch of mixed material produced by the mixing station; The beam yard management system is used to obtain the beam yard information involved in the project and build a three-dimensional model of the beam yard based on the beam yard information to remotely monitor and manage the production process of the beam yard.
2. The smart construction site project management platform according to claim 1, characterized in that: The project command and dispatch center uses building information modeling and geographic information system to generate a three-dimensional visualized project layout diagram.
3. The smart construction site project management platform according to claim 1, characterized in that: The project command and dispatch center is also used to determine the production plans for multiple time periods within the project construction cycle based on the pre-built project plan, obtain on-site production data at the end of each time period, and judge whether the production plan is met based on the on-site production data and the production plan for the corresponding time period. If not, adjust the production plan for the next time period.
4. The smart construction site project management platform according to claim 1, characterized in that: The project command and dispatch center is also used to visualize the space, environment, components, personnel, machines and materials on the construction site through an electronic sand table.
5. The smart construction site project management platform according to claim 1, characterized in that: A project includes multiple unit projects; The progress visualization management system is also used to use built-in parametric modeling tools to define the type of each unit project, and build a three-dimensional visualization engineering model of each unit project based on the comprehensive parameters of each unit project. For any unit project, the project construction progress information input by the user on the client is obtained, and the project construction progress information is embedded in the three-dimensional visualization engineering model of the unit project to display and manage the construction progress of the unit project.
6. The smart construction site project management platform according to claim 1, characterized in that: The tunnel information includes: tunnel personnel labor information, tunnel personnel location information, gas information, safe step distance, monitoring video, personnel entering and exiting the tunnel, and vehicles entering and exiting the tunnel; The process of the tunnel management system remotely monitoring and managing the construction process in the tunnel based on the tunnel information specifically includes: performing safety monitoring of personnel in the tunnel based on the labor information of the tunnel personnel, the positioning information of the tunnel personnel, the safe step distance, the monitoring video, personnel entering and exiting the tunnel, and vehicles entering and exiting the tunnel; judging whether the gas in the tunnel exceeds the safety threshold based on the gas information, and issuing an alarm when the gas in the tunnel exceeds the safety threshold.
7. The smart construction site project management platform according to claim 1, characterized in that: The mixing station management system is also used to obtain material applications submitted by users, conduct online approval based on the material applications, and compare the cumulative signed-in quantity and the designed control quantity in real time during the mixture production process, and issue an over-consumption warning when over-consumption occurs.
8. The smart construction site project management platform according to claim 1, characterized in that: The process of remote monitoring and management of the production process of the beam yard by the beam yard management system specifically includes: planning management, production site management and production process management of the beam yard according to the three-dimensional model of the beam yard.
9. The smart construction site project management platform according to claim 1, characterized in that: The progress visualization management system, the material management system, the tunnel management system, the mixing station management system and the beam yard management system are all functional modules in the project command and dispatch center.
10. The smart construction site project management platform according to claim 9, characterized in that: The project command and dispatch center is deployed in computer equipment.
Citation Information