Tunnel water inrush test method considering disaster source material deposition-high pressure energy storage

By setting up sedimentary tanks and high-pressure water components, the high-pressure energy storage status of solid-liquid-gas three-phase hybrids in karst tunnels is simulated, and the internal parameters of the sedimentary tanks are monitored and recorded, and the existing technology cannot simulate water and mud disasters in karst tunnels are solved. The real situation problem has achieved high accuracy test simulation and provided effective reference for tunnel construction.

CN119246823APending Publication Date: 2025-01-03HENAN POLYTECHNIC UNIV
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411366948.9
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-09-29
Publication Date
2025-01-03

AI Technical Summary

Technical Problem

The existing technology cannot truly simulate the phenomenon of water bursts of disaster sources under natural deposition and high pressure under different circumstances, and cannot effectively simulate the real situation of water bursts and mud bursts in karst tunnels.

Method used

By setting up a deposition box, flow trough and high-pressure water component, the solid-liquid-gas three-phase hybrid filling under different geological conditions is simulated, and the air pressure, osmotic pressure and water pressure changes inside the deposition box are monitored and recorded, and the high pressure is simulated by sensor components. Deposition and water bursting process of mud and sand mixture in the state.

Benefits of technology

The experimental simulation of different geological deposition processes and high-pressure violent flood disasters of tunnel-filled cave disaster sources has been achieved. The test results have high true accuracy and can provide effective guidance for tunnels to pass through similar geological construction.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119246823A_ABST
    Figure CN119246823A_ABST
Patent Text Reader

Abstract

The invention belongs to the technical field of tunnel water inrush tests, and particularly relates to a tunnel water inrush test method considering disaster source material deposition-high pressure energy storage. According to the test method, the inclination angle of the launder is adjusted, so that the mud-sand mixture can flow in the launder with different gradients, and the real conditions of different flow speeds of the mud-sand mixture under different geological conditions are simulated. After deposition and solidification of the mud and sand mixture are completed, the deposition box is completely sealed, and water is injected to the set height; after water is injected, a mud-sand mixture, water and gas three-phase mixture in a high-pressure state in the deposition box can simulate a high-pressure energy storage disaster source filled with a solid-liquid-gas three-phase mixture under a real geological condition. According to the test method, test simulation of different geological deposition processes of tunnel filling type karst cave disaster source substances and high-pressure violent water burst catastrophe is implemented, and the test method has good real accuracy.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention belongs to the technical field of tunnel water inrush testing, and specifically relates to a tunnel water inrush testing method taking into account disaster source material deposition-high-pressure energy storage. Background Art

[0002] The occurrence of water and mud inrush disasters in karst tunnels mainly involves three parts: the source of disasters, the source channel of disasters, and the water-blocking mudstone. The source of disasters is the source power of water and mud inrush disasters. Different sources of disasters will inevitably lead to different mechanisms of water and mud inrush disasters in karst tunnels. The source of water and mud inrush disasters in karst tunnels is a complex medium system composed of one or more of solid mud, liquid karst water, and internally sealed gas. With the increase of the buried depth of the disaster source, its solid-liquid-gas three-phase mixing characteristics are more significant, and the gas sealed in the karst cavity is likely to be in a high-pressure state. When the tunnel construction approaches the high-pressure energy storage disaster source filled with a solid-liquid-gas three-phase mixture, once the safety thickness of the water-blocking mudstone between the disaster source and the tunnel is insufficient, it will rupture and become unstable, thereby losing its barrier function, inducing water and mud inrush disasters, and groundwater, mud, sand, and gas will gush out in large quantities.

[0003] However, in the prior art, there is no method that can truly simulate the natural deposition of disaster source materials under different conditions, and the actual situation of water inrush caused by disaster source materials under high pressure.

[0004] Therefore, it is necessary to provide an improved technical solution to address the above-mentioned deficiencies in the prior art. Invention content

[0005] The purpose of the present invention is to provide a tunnel water inrush test method taking into account the deposition of disaster source materials and high-pressure energy storage, so as to at least solve the above-mentioned problems existing in the prior art.

[0006] In order to achieve the above object, the present invention provides the following technical solutions:

[0007] A tunnel water inrush test method considering disaster source material deposition-high pressure energy storage, the test method comprising the following steps:

[0008] Step 1, connect the sedimentation box to the perforation at the bottom of the flow channel through a hose, adjust the inclination angle of the flow channel to a set angle, and always flush water into the sedimentation box and the flow channel to make the sedimentation box and the flow channel full of water;

[0009] Step 2, fully stir the mud-sand mixture with a set particle ratio, and then flow the mud-sand mixture into the flow channel. After the mud-sand mixture is deposited in the sedimentation box to a set height, stop adding the mud-sand mixture and stop flushing;

[0010] Step 3, remove the sedimentation box from the bottom of the flow channel, and after static sedimentation, open the drain valve at the bottom of the sedimentation box to drain excess water in the sedimentation box to accelerate the sedimentation and consolidation of the mud-sand mixture in the sedimentation box;

[0011] Step 4, recording the sedimentary stratification and sedimentary morphology of the mud-sand mixture inside the sedimentation box;

[0012] Step 5, burying a sensor assembly in the sedimentation box, and monitoring the parameters of air pressure, osmotic pressure and water pressure inside the sedimentation box through the sensor assembly;

[0013] Step 6, connect the sedimentation box to the high-pressure water assembly and seal the sedimentation box;

[0014] Step 7, injecting water into the sealed sedimentation box to a set height through the high-pressure water assembly, so that the pressure in the sedimentation box gradually increases, and recording the changes in the parameters of the internal air pressure, osmotic pressure and water pressure of the sedimentation box when the internal pressure of the sedimentation box changes;

[0015] Step 8, open the water inrush valve at the bottom of the sedimentation box, and observe and record the outflow process of the three-phase mixture of mud-sand mixture, water and gas under high pressure inside the sedimentation box.

[0016] As described above, in the tunnel water inrush test method considering the deposition of disaster source materials and high-pressure energy storage, preferably, the high-pressure water assembly includes an air compressor, an air pump and a water storage tank, the air compressor is used to provide air source power for the air pump; the air pump is connected to the water storage tank, and is used to provide a stable pressure to the liquid in the water storage tank; the water storage tank is connected to the water injection port of the sedimentation box, and is used to inject water into the sedimentation box.

[0017] As described above, in the tunnel water inrush test method considering the disaster source material deposition-high pressure energy storage, preferably, the height of the water injection port on the deposition box is higher than the deposition height of the mud-sand mixture in the deposition box.

[0018] As described above, in the tunnel water inrush test method considering the deposition of disaster source materials and high-pressure energy storage, preferably, the flow channel is erected on two brackets, and the flow channel is rotatably connected to the two brackets; at least one of the brackets is a liftable bracket.

[0019] As described above, in the tunnel water inrush test method considering the deposition of disaster source materials and high-pressure energy storage, preferably, the liftable support comprises a base and a lifting frame, and the lifting frame is guided and installed in the base along the vertical direction;

[0020] A nut sleeve is fixedly mounted on the base, a screw rod is rotatably mounted on the lifting frame, and the screw rod thread is transferred to the nut sleeve;

[0021] A driven bevel gear is installed on the top of the screw rod, and a driving bevel gear is rotatably installed on the lifting frame, and the driving bevel gear is meshed with the driven bevel gear for transmission.

[0022] As described above, in the tunnel water inrush test method considering the deposition of disaster source materials and high-pressure energy storage, preferably, a sensor assembly is also provided in the deposition box; the sensor assembly signal connects the information acquisition instrument and the information processing system.

[0023] In the tunnel water inrush test method considering disaster source material deposition-high pressure energy storage as described above, preferably, the sensor assembly includes a plurality of earth pressure boxes, the plurality of earth pressure boxes are arranged in the sedimentation box along the vertical direction, and the highest arrangement height of the earth pressure boxes is lower than the height of the mud-sand mixture.

[0024] In the tunnel water inrush test method considering disaster source material deposition-high pressure energy storage as described above, preferably, the sensor assembly includes a plurality of displacement meters, the plurality of displacement meters are arranged in a sedimentation box along a vertical direction, and the highest arrangement height of the displacement meters is lower than the deposition height of the mud-sand mixture.

[0025] In the tunnel water inrush test method considering disaster source material deposition-high pressure energy storage as described above, preferably, the sensor assembly includes a plurality of piezometers, the plurality of piezometers are arranged in a sedimentation box along a vertical direction, and the highest arrangement height of the piezometers is lower than the sedimentation height of the mud-sand mixture.

[0026] In the tunnel water inrush test method considering the disaster source material deposition-high pressure energy storage as described above, preferably, the sensor assembly further includes at least one water pressure gauge and at least one air pressure gauge;

[0027] The water pressure gauge is arranged at a height higher than the sedimentation height of the mud-sand mixture and lower than the water injection height;

[0028] The arrangement height of the barometer is higher than the water injection height.

[0029] Beneficial effects:

[0030] In this test method, when the inclination angle of the flow channel needs to be adjusted, one of the liftable brackets is lifted and lowered in the vertical direction, so that one end of the flow channel rises or falls, thereby changing the inclination angle of the entire flow channel, so that the mud-sand mixture can flow in flow channels with different slopes, thereby simulating the actual situation of mud-sand mixture exhibiting different flow velocities under different geological conditions.

[0031] At the same time, after the sedimentation and consolidation of the mud-sand mixture, the sedimentation box is completely sealed and water is injected to a set height, where the water injection port is higher than the sedimentation height of the mud-sand mixture, so as to avoid the direct impact of the injected water on the mud-sand mixture; after the water injection, the mud-sand mixture, water, and gas three-phase mixture in the sedimentation box is in a high-pressure state to simulate the high-pressure energy storage disaster source filled with a solid-liquid-gas three-phase mixture under real geological conditions.

[0032] That is, the test method implemented experimental simulations of different geological sedimentation processes of tunnel-filling karst cave disaster source materials and high-pressure violent water inrush disasters. The test method is closer to the actual geological conditions, and the test results have good real accuracy, which can provide better reference and guidance for tunnel construction through similar geological conditions. BRIEF DESCRIPTION OF THE DRAWINGS

[0033] The drawings constituting part of the present application are used to provide a further understanding of the invention. The exemplary embodiments and descriptions of the invention are used to explain the invention and do not constitute an improper limitation on the invention. Among them:

[0034] Figure 1 A schematic diagram of the connection between a sedimentation box and a high-pressure water assembly is created for one embodiment of the present invention;

[0035] Figure 2 A schematic diagram of the connection between a sedimentation box, a flow trough and a liftable support according to an embodiment of the present invention;

[0036] Figure 3 A schematic diagram of a structure of a liftable bracket according to an embodiment of the present invention;

[0037] Figure 4 A diagram of the actual construction of the components in a test method for creating an embodiment of the present invention.

[0038] In the figure: 1. Sedimentation box; 11. Water inlet; 12. Drain valve; 13. Water inrush valve; 21. Earth pressure box; 22. Displacement meter; 23. Osmometer; 24. Water pressure gauge; 25. Barometer; 3. Water storage tank; 4. Air pump; 5. Air compressor; 6. Information collector; 7. Information processing system; 8. Flow chute; 9. Liftable bracket; 91. Base; 92. Lifting frame; 93. Nut sleeve; 94. Screw; 95. Driven bevel gear; 96. Driving bevel gear; 97. Rotating shaft; 98. Turntable; 10. Mixer; 20. Mixing barrel; 30. Flow meter. DETAILED DESCRIPTION

[0039] The technical solutions in the embodiments of the present invention are described clearly and completely below. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of them. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field belong to the scope of protection of the present invention.

[0040] In the description of the present invention, the terms "longitudinal", "lateral", "upper", "lower", "front", "back", "left", "right", "vertical", "horizontal", "top", "bottom" and the like indicate directions or positional relationships based on the directions or positional relationships shown in the accompanying drawings. They are only for the convenience of describing the present invention and do not require that the present invention must be constructed and operated in a specific direction. Therefore, they cannot be understood as limitations on the present invention. The terms "connected" and "connected" used in the present invention should be understood in a broad sense. For example, they can be fixedly connected or detachably connected; they can be directly connected or indirectly connected through intermediate components. For ordinary technicians in this field, the specific meanings of the above terms can be understood according to specific circumstances.

[0041] The present invention will be described in detail below with reference to the accompanying drawings and in combination with the embodiments. It should be noted that the embodiments and features in the embodiments of the present invention can be combined with each other without conflict.

[0042] According to the specific embodiments of the present invention, Figure 1-3 As shown, the present invention provides a tunnel water inrush test method considering the disaster source material deposition-high pressure energy storage, and the test method comprises the following steps:

[0043] Step 1, connect the sedimentation box 1 to the perforation at the bottom of the flow channel 8 through a hose, adjust the inclination angle of the flow channel 8 to a set angle, and always flush water into the sedimentation box 1 and the flow channel 8, so that the sedimentation box 1 and the flow channel 8 are in a state of being filled with water;

[0044] Step 2, fully stir the mud-sand mixture with a set particle ratio, and then flow the mud-sand mixture into the flow channel 8. After the mud-sand mixture is deposited to a set height in the sedimentation box 1, stop adding the mud-sand mixture and stop flushing;

[0045] Step 3, remove the sedimentation box 1 from the bottom of the flow channel 8, and after the static sedimentation setting design, open the drain valve 12 at the bottom of the sedimentation box 1 to discharge the excess water in the sedimentation box 1 to accelerate the sedimentation and consolidation of the mud and sand mixture in the sedimentation box 1; in this embodiment, a filtering structure is arranged at the position of the sedimentation box 1 corresponding to the drain valve 12, and the filtering structure can be a drainage stone or a filter element or a filter paper and other structures to prevent the mud and sand mixture from flowing out of the drain valve 12, and can prevent the mud and sand mixture from clogging the drain valve 12.

[0046] Step 4, recording the sedimentary stratification and sedimentary morphology of the mud-sand mixture inside the sedimentation box 1;

[0047] Step 5, burying a sensor assembly in the sedimentation box 1, and monitoring the parameters of the air pressure, osmotic pressure and water pressure inside the sedimentation box 1 through the sensor assembly;

[0048] Step 6, connecting the sedimentation box 1 to the high-pressure water assembly and sealing the sedimentation box 1;

[0049] Step 7, water is injected into the sealed sedimentation box 1 to a set height through a high-pressure water assembly, and the water level continues to rise to squeeze the gas at the top, so that the pressure in the sedimentation box 1 gradually increases, and the changes in the internal air pressure, osmotic pressure and water pressure of the sedimentation box 1 are recorded when the internal pressure of the sedimentation box 1 changes;

[0050] Step 8, open the water inrush valve 13 at the bottom of the sedimentation box 1, and observe and record the outflow process of the three-phase mixture of mud-sand mixture, water and gas under high pressure inside the sedimentation box 1.

[0051] In this test method, the inclination angle of the flow channel 8 is adjusted so that the mud-sand mixture can flow in the flow channel 8 with different slopes, so as to simulate the actual situation of different flow rates of the mud-sand mixture under different geological conditions; at the same time, after the mud-sand mixture is deposited and consolidated, the sedimentation box 1 is completely sealed and water is injected to a set height to make the mud-sand mixture, water and gas three-phase mixture in the sedimentation box 1 in a high-pressure state to simulate the high-pressure energy storage disaster source filled with solid-liquid-gas three-phase mixture under real geological conditions; that is, the test method implements the experimental simulation of different geological deposition processes of tunnel filling type cave disaster source materials and high-pressure violent water inrush disasters. The test method is closer to the real geological conditions, and the test results have good real accuracy, which can provide better reference and guidance for tunnel crossing similar geological construction.

[0052] The high-pressure water assembly includes an air compressor 5, an air pump 4 and a water tank 3. The air compressor 5 is used to provide air source power for the air pump 4; the air pump 4 is connected to the water tank 3 to provide stable pressure for the liquid in the water tank 3; the water tank 3 is connected to the water injection port 11 of the sedimentation box 1 to inject water into the sedimentation box 1.

[0053] In one embodiment of the present application, a more uniform pressure can be applied to the water storage tank 3 through the air pump 4, ensuring that the high-pressure component maintains a more uniform pressure to inject water into the sedimentation box 1; in other embodiments, the high-pressure water component can also use a pressure-stabilizing water pump, in which case water is directly added to the sedimentation box 1 through the pressure-stabilizing water pump.

[0054] In one embodiment of the present application, the air pump 4 is connected to the upper part of the sedimentation box 1, and the pressure in the sedimentation box 1 is adjusted by the air pump 4 to change the air pressure environment in the sedimentation box 1, thereby simulating different high-pressure environments of the solid-liquid-gas three-phase mixture.

[0055] In this embodiment, a mixer 10, a mixing barrel 20 and a flow meter 30 are also provided upstream of the flow chute 8, wherein the mixer 10 extends into the mixing barrel 20, and the mud-sand mixture is evenly stirred by the mixer 10 in the mixing barrel 20; a flow meter 30 is provided at the flow outlet of the mixing barrel 20 for detecting the outflow flow rate of the mud-sand mixture, and the stirred mud-sand mixture is transported to the flow chute 8.

[0056] In this embodiment, a material receiving bucket is further provided at the position of the water bursting valve 13 of the sedimentation box 1, and a measuring scale is provided below the material receiving bucket for measuring the mass of the water bursting material.

[0057] The height of the water injection port 11 on the sedimentation box 1 is higher than the sedimentation height of the mud-sand mixture in the sedimentation box 1. In this embodiment, the water injection port 11 is higher than the sedimentation height of the mud-sand mixture, so as to avoid the direct impact of the injected water on the mud-sand mixture; specifically, the water injection port 11 can be set in the middle and upper part of the sedimentation box 1, and the mud-sand mixture is deposited in the middle and lower part of the sedimentation box 1.

[0058] In this embodiment, when sealing the sedimentation box 1, first close all valve bodies connected to the sedimentation box 1, then cover the opening on the top of the sedimentation box 1 with a sealing cover, pass multiple bolts between the sedimentation box 1 and the sealing cover, and tighten the nuts to seal.

[0059] The flow channel 8 is mounted on two brackets, and the flow channel 8 is rotatably connected to the two brackets; at least one of the brackets is a liftable bracket 9.

[0060] In one embodiment of the present application, a pair of rotating seats are arranged on the bracket, a rotating shaft is arranged between the pair of rotating seats, and the bottom of the flow channel 8 is fixed on the rotating shaft, so that the flow channel 8 can rotate relative to the bracket to facilitate the adjustment of the angle of the flow channel 8; specifically, when the inclination angle of the flow channel 8 needs to be adjusted, one of the liftable brackets 9 is lifted and displaced in the vertical direction, so that one end of the flow channel 8 rises or falls, thereby changing the inclination angle of the entire flow channel 8.

[0061] The liftable bracket 9 includes a base 91 and a lifting frame 92. The lifting frame 92 is installed in the base 91 along the vertical direction. A nut sleeve 93 is fixedly installed on the base 91, and a screw rod 94 is rotatably installed on the lifting frame 92. The screw rod 94 is threadedly transferred in the nut sleeve 93. A driven bevel gear 95 is installed on the top of the screw rod 94, and a driving bevel gear 96 is rotatably installed on the lifting frame 92. The driving bevel gear 96 is meshed with the driven bevel gear 95 for transmission.

[0062] In one embodiment of the present application, the screw rod 94 and the nut sleeve 93 both extend in the vertical direction, and the screw rod 94 and the nut sleeve 93 are both located in the middle of the liftable bracket 9, so that the liftable bracket 9 is subjected to more uniform force during the lifting movement; the active bevel gear 96 is connected to a rotating shaft 97, and the rotating shaft 97 is rotatably set on the lifting frame 92. The end of the rotating shaft 97 extending out of the lifting frame 92 is connected to a turntable 98, and the active bevel gear 96 is driven by rotating the turntable 98, and the active bevel gear 96 drives the driven bevel gear 95 and the screw rod 94 to select. Under the cooperation of the screw rod 94 and the nut sleeve 93, the screw rod 94 performs a vertical displacement movement along the nut sleeve 93, so that the lifting frame 92 performs a vertical lifting movement along the base 91, thereby realizing the adjustment of the inclination angle of the convection trough 8.

[0063] A sensor assembly is also provided in the sedimentation box 1; the sensor assembly signal connects the information collector 6 and the information processing system 7. In one embodiment of the present application, the sensor assembly monitors the changes in the air pressure, osmotic pressure and water pressure parameters inside the sedimentation box 1, and transmits the monitored signals to the information collector 6. All signals collected by the information collector 6 are transmitted to the information processing system 7, and the information processing system 7 performs comprehensive processing on the signals.

[0064] The sensor assembly includes a plurality of earth pressure boxes 21, which are arranged in the sedimentation box 1 in the vertical direction, and the highest arrangement height of the earth pressure boxes 21 is lower than the height of the mud-sand mixture. In one embodiment of the present application, the plurality of earth pressure boxes 21 are used to detect the earth pressure conditions at different heights of the mud-sand mixture, and the highest arrangement height of the earth pressure boxes 21 is set to be lower than the mud-sand mixture, so that after the mud-sand mixture is deposited and consolidated, the plurality of earth pressure boxes 21 are pre-buried in the mud-sand mixture.

[0065] The sensor assembly includes a plurality of displacement meters 22, which are arranged in the sedimentation box 1 along a vertical direction, and the highest arrangement height of the displacement meters 22 is lower than the sedimentation height of the mud-sand mixture.

[0066] In one embodiment of the present application, multiple displacement meters 22 are used to detect the displacement of the mud-sand mixture. The highest arrangement height of the displacement meter 22 is set lower than the mud-sand mixture so that the multiple displacement meters 22 are pre-buried in the mud-sand mixture after the mud-sand mixture is deposited and consolidated.

[0067] The sensor assembly includes a plurality of osmometers 23, which are arranged in the sedimentation box 1 along a vertical direction, and the highest arrangement height of the osmometers 23 is lower than the sedimentation height of the mud-sand mixture.

[0068] In one embodiment of the present application, multiple piezometers 23 are used to detect the seepage pressure in the mud-sand mixture. The highest arrangement height of the piezometers 23 is set lower than the mud-sand mixture so that the multiple piezometers 23 are pre-buried in the mud-sand mixture after the mud-sand mixture is deposited and consolidated.

[0069] The sensor assembly further includes at least one water pressure gauge 24 and at least one air pressure gauge 25; the water pressure gauge 24 is arranged at a height higher than the sedimentation height of the mud-sand mixture and lower than the water injection height; the air pressure gauge 25 is arranged at a height higher than the water injection height.

[0070] In one embodiment of the present application, the water pressure gauge 24 is located in the middle of the sedimentation box 1, in the water injected into the sedimentation box 1, and the water pressure gauge 24 is used to detect the pressure of the water injected into the sedimentation box 1; the barometer 25 is located at the top of the sedimentation box 1, in the gas part at the top of the sedimentation box 1, and the barometer 25 is used to detect the pressure of the gas in the sedimentation box 1; so that the sensor assembly can better monitor the solid-liquid-gas three-phase mixture in the sedimentation box 1 in a high-pressure state, as well as the solid-liquid-gas three-phase mixture in the sedimentation box 1 during the water inrush process.

[0071] It should be understood that the above description is merely exemplary and the embodiments of the present application do not limit this.

[0072] The above description is only a preferred embodiment of the present invention and is not intended to limit the present invention. Any modifications, equivalent substitutions, improvements, etc. made within the spirit and principle of the present invention are within the scope of protection of the pending claims of the present invention.

Claims

1. A tunnel water inrush test method considering disaster source material deposition-high pressure energy storage, characterized in that: The test method comprises the following steps: Step 1, connect the sedimentation box to the perforation at the bottom of the flow channel through a hose, adjust the inclination angle of the flow channel to a set angle, and always flush water into the sedimentation box and the flow channel to make the sedimentation box and the flow channel full of water; Step 2, fully stir the mud-sand mixture with a set particle ratio, and then flow the mud-sand mixture into the flow channel. After the mud-sand mixture is deposited in the sedimentation box to a set height, stop adding the mud-sand mixture and stop flushing; Step 3, remove the sedimentation box from the bottom of the flow channel, and after static sedimentation, open the drain valve at the bottom of the sedimentation box to drain excess water in the sedimentation box to accelerate the sedimentation and consolidation of the mud-sand mixture in the sedimentation box; Step 4, recording the sedimentary stratification and sedimentary morphology of the mud-sand mixture inside the sedimentation box; Step 5, burying a sensor assembly in the sedimentation box, and monitoring the parameters of air pressure, osmotic pressure and water pressure inside the sedimentation box through the sensor assembly; Step 6, connect the sedimentation box to the high-pressure water assembly and seal the sedimentation box; Step 7, injecting water into the sealed sedimentation box to a set height through the high-pressure water assembly, so that the pressure in the sedimentation box gradually increases, and recording the changes in the parameters of the internal air pressure, osmotic pressure and water pressure of the sedimentation box when the internal pressure of the sedimentation box changes; Step 8, open the water inrush valve at the bottom of the sedimentation box, and observe and record the outflow process of the three-phase mixture of mud-sand mixture, water and gas under high pressure inside the sedimentation box.

2. The tunnel water inrush test method considering disaster source material deposition-high pressure energy storage according to claim 1 is characterized in that: The high-pressure water assembly includes an air compressor, an air pump and a water tank. The air compressor is used to provide air source power for the air pump; the air pump is connected to the water tank to provide stable pressure for the liquid in the water tank; the water tank is connected to the water inlet of the sedimentation box to inject water into the sedimentation box.

3. The tunnel water inrush test method considering disaster source material deposition-high pressure energy storage according to claim 2 is characterized in that: The height of the water injection port on the sedimentation box is higher than the sedimentation height of the mud-sand mixture in the sedimentation box.

4. The tunnel water inrush test method considering disaster source material deposition-high pressure energy storage according to claim 2 is characterized in that: The flow channel is mounted on two brackets, and the flow channel is rotatably connected to the two brackets; at least one of the brackets is a liftable bracket.

5. The tunnel water inrush test method considering disaster source material deposition-high pressure energy storage according to claim 4 is characterized in that: The liftable support comprises a base and a lifting frame, wherein the lifting frame is guided and installed in the base along a vertical direction; A nut sleeve is fixedly mounted on the base, a screw rod is rotatably mounted on the lifting frame, and the screw rod thread is transferred to the nut sleeve; A driven bevel gear is installed on the top of the screw rod, and a driving bevel gear is rotatably installed on the lifting frame, and the driving bevel gear is meshed with the driven bevel gear for transmission.

6. The tunnel water inrush test method considering disaster source material deposition-high pressure energy storage according to claim 2 is characterized in that: A sensor component is also provided in the deposition box; the sensor component signal connects the information acquisition instrument and the information processing system.

7. The tunnel water inrush test method considering disaster source material deposition-high pressure energy storage according to claim 6 is characterized in that: The sensor assembly comprises a plurality of earth pressure boxes, which are arranged in a vertical direction in a sedimentation box, and the highest arrangement height of the earth pressure boxes is lower than the height of the mud-sand mixture.

8. The tunnel water inrush test method considering disaster source material deposition-high pressure energy storage according to claim 6 is characterized in that: The sensor assembly comprises a plurality of displacement meters which are arranged in a sedimentation box along a vertical direction, and the highest arrangement height of the displacement meters is lower than the sedimentation height of the mud-sand mixture.

9. The tunnel water inrush test method considering disaster source material deposition-high pressure energy storage according to claim 6 is characterized in that: The sensor assembly comprises a plurality of piezometers which are arranged in a sedimentation box along a vertical direction, and the highest arrangement height of the piezometers is lower than the sedimentation height of the mud-sand mixture.

10. The tunnel water inrush test method considering disaster source material deposition-high pressure energy storage according to claim 6, characterized in that: The sensor assembly also includes at least one water pressure gauge and at least one air pressure gauge; The water pressure gauge is arranged at a height higher than the sedimentation height of the mud-sand mixture and lower than the water injection height; The arrangement height of the barometer is higher than the water injection height.