Manufacturing method for piling truss structure of offshore wind power full-rotation multi-angle piling machine

Through the design of segmented structure and articulated pile trusses, the problems of low production efficiency and insufficient structural strength of offshore wind power pile drivers in the existing technology are solved, and more efficient production and safer construction processes are achieved.

CN119266220APending Publication Date: 2025-01-07NANTONG ZHENHUA HEAVY EQUIP MFG
View PDF 0 Cites 1 Cited by

Patent Information

Application Number
CN202411683070.1
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-11-22
Publication Date
2025-01-07

AI Technical Summary

Technical Problem

The production process of the existing offshore wind power pile driver is unreasonable, resulting in low working efficiency, increased rework, high construction costs, insufficient strength of the tire frame structure, and prone to component overturning accidents.

Method used

The pile truss structure of offshore wind power full-rotating multi-angle pile driver adopts a segmented structure. The pile frame is connected by articulated connection, and inspection standards are set during the production process to improve product quality and work efficiency and avoid Rework.

Benefits of technology

It improves work efficiency, reduces construction costs, enhances the structural strength and safety of the tire frame, and avoids component overturning accidents.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119266220A_ABST
    Figure CN119266220A_ABST
Patent Text Reader

Abstract

The invention relates to a manufacturing method for a piling truss structure of an offshore wind power full-rotation multi-angle piling machine. Comprising the following steps of S1, pile frame segmentation, S2, pile frame head box manufacturing, S3, pile frame main U pipe manufacturing and mounting, S4, pile frame I section sheet body manufacturing, S5, I section body forming, S6, I section body overall turning over, S7, pile frame I section forming, S8, pile frame II section and pile frame III section forming and S9, manufacturing completion. The truss structure is divided into the pile frame section I, the pile frame section II, the pile frame section III and the pile frame head box body to be manufactured, sliding shoe installation and assembly are carried out after manufacturing is completed, the manufacturing process is reasonably designed, so that the working efficiency is improved, the product quality can be improved by setting the inspection qualification standard in the manufacturing process, and the production cost is reduced. And meanwhile, the phenomena such as reworking possibly existing in the production process can be avoided, so that the construction cost can be reduced, and energy waste is avoided.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the field of offshore wind power, and in particular to a method for manufacturing a pile driving truss structure of an offshore wind power full-rotation multi-angle pile driver. Background Art

[0002] The pile frame of Sanhang's 110m pile driver has an overall dimension of 111.8m*3.27m*3.68m, and the main structure weighs about 237 tons. It is large in size and weight. The existing pile frame manufacturing process is unreasonable, resulting in low work efficiency, and rework in the production process increases construction costs and wastes energy. In addition, the tire frame layout is uneven during the production process, the tire frame structure strength is insufficient, and the tire frame center of gravity is too high, resulting in overturning of the components, which is prone to accidents caused by objects hitting. Summary of the invention

[0003] The technical problem to be solved by the present invention is to provide a method for manufacturing a pile truss structure of an offshore wind power full-rotation multi-angle pile driver.

[0004] In order to solve the above technical problems, the technical solution of the present invention is: a method for manufacturing a pile truss structure of an offshore wind power full-rotation multi-angle pile driver, the innovation of which is that the truss structure is a segmented structure, which is sequentially composed of a pile frame head box, a pile frame section I, a pile frame section II and a pile frame section III, and the pile frame section I, the pile frame section II and the pile frame section III are all connected by hinges; The pile frame section I is arranged transversely, including a section I body, and a main frame hinge point is arranged on one side of the section I body, and the pile frame head box is arranged on the other side thereof, and a pile frame sliding shoe track is also arranged on the section I body near the pile frame head box, and a sliding shoe bracket and a pile frame sliding shoe are installed on the pile frame sliding shoe track, and two pile gripper hinge point ear plates are also arranged on the top near the main frame hinge point; The I-section body includes an upper body and a lower body, and both sides of the upper body and the lower body are four main U-tubes distributed in a rectangular shape. The upper body includes two first main U-tubes, and the first main U-tubes include a first U-shaped tube with an opening facing upward, and a top sealing plate fixed to the top of the first U-shaped tube. The lower body includes two second main U-tubes, and the second main U-tubes include a second U-shaped tube with an opening facing downward, and a bottom sealing plate fixed to the bottom of the second U-shaped tube. Branch tubes are provided between the upper body and the lower body, between the two first main U-tubes, and between the two second main U-tubes. The pile frame head box body includes a box body, which is assembled from a plurality of I-beams and is vertically arranged. A connecting portion is provided on the box body at the middle of one side close to the pile frame section I, and a plurality of single-piece lifting ears are provided on the box body below the connecting portion. A first pulley ear plate assembly and a second pulley ear plate assembly are provided on both sides of the top of the box body, respectively. A third pulley ear plate assembly and a fourth pulley ear plate assembly are also provided on the side away from the pile frame section I. The pile frame section II comprises a section II body, and the section II body has a similar structure to the section I body; The pile frame section III includes a section III body, and the section III body is similar in structure to the section I body. The preparation method comprises the following steps: S1. Pile frame segmentation: S2. Production of the pile frame head box: first, group the I-beams, then assemble them on the horizontal frame to obtain the box body, then install the first, second, third and fourth pulley ear plate assemblies at the corresponding positions on the box body, then install multiple single-piece lifting ears on the box body, and then install the connecting part on the box body; S3, production and installation of the main U-tube of the pile frame: prepare a mobile tire frame in the workshop, first prepare two bottom sealing plates on the tire frame after the plate passes the inspection, then bend the steel plate into a U-shaped tube after it passes the inspection, and then hoist and position the U-shaped tube on the top of the bottom sealing plate, and fix it on the tire frame through a U-shaped clamping plate and a wedge block, and then realize automatic welding between the bottom sealing plate and the U-shaped tube after preheating, and the preparation of the second main U-tube is completed; Then, the top sealing plate is installed on the tire frame, the U-shaped tube is hoisted and positioned on the top of the top sealing plate, and then fixed on the tire frame by U-shaped clamping plates and wedges for welding, and the preparation of the first main U-tube is completed; S4, production of the pile frame I section: two first main U-tubes are transversely and symmetrically arranged on the tire frame evenly arranged according to the weight and center of gravity of the sections. After the branch pipes between the two first main U-tubes are fixed, they are hoisted vertically and other side face branches are installed. Finally, two hinge ear plates are installed. The upper section is installed. The second main U-tube is also installed with branch pipes and side face branches in the same way. The lower section is installed. S5, forming the main body of section I: installing a branch pipe between the vertical upper sheet and the vertical lower sheet, and forming the main body of section I; S6, turning over the entirety of the I-section body: hoisting and turning over the I-section body so that the upper body and the lower body are in an upper and lower position relationship, and installing the main frame hinge point; S7, forming the pile frame section I: the pile frame sliding shoe track, the sliding shoe bracket, the pile frame sliding shoe and the pile gripper hinge point ear plate are respectively installed on the section I body, and the pile frame section I is formed as a whole; S8, forming the pile frame section II and the pile frame section III: the pile frame section II and the pile frame section III are formed by the aforementioned steps S3-S6; S9. Production completed.

[0005] Furthermore, the connecting portion includes four supporting columns distributed in a rectangular shape, and a connecting plate connected between the supporting columns; In step S2, the connecting part needs to be assembled in advance and the manufacturing accuracy of the top surfaces of the four supporting columns must be ensured. The docking accuracy between the pile frame head box and the pile frame section I is ensured by controlling the manufacturing accuracy of the four corners of the top surface section of the supporting columns. Then the connecting part is installed on the box body. After the box body is installed, four 20T lifting ears are installed on both sides of the top of the box body and on both ends of the bottom of one side of the box body close to the pile frame section I.

[0006] Furthermore, in step S3, the inspection qualification standard of the prepared plate of the bottom sealing plate is: Dimensions: The allowable deviation of length is ±1.5mm, the allowable deviation of width is ±1mm, and the allowable deviation of diagonal is S±2mm; Flatness: The allowable deviation is ±1mm per meter, and the allowable deviation is ±1.5mm per 3 meters; Side bending: The allowable deviation of the entire plate is 2mm; The inspection standard of the U-shaped tube after the steel plate is bent into a U-shaped tube is: Overall dimensions: The allowable deviation of length is ±2mm, the allowable deviation of width is ±2mm, and the allowable deviation of height is ±2mm; The allowable deviation of distortion is ±3mm; the allowable deviation of horizontal and vertical straightness is 2mm / 5m, and the overall allowable deviation is ≤3mm.

[0007] Furthermore, the inspection standard of the U-shaped tube after automatic welding is: Overall dimensions: the allowable deviation of length is ±3mm, the allowable deviation of width is ±2m, the allowable deviation of height is ±2m, and the allowable deviation of twisting is ±3mm; Horizontal and vertical straightness: The allowable deviation is 2mm every 5m, and the overall allowable deviation is ≤3mm.

[0008] Further, the U-shaped cardboard is opened downwards and completely covers the U-shaped tube and the bottom sealing plate, and is fixed on the tire frame in S3, and the two sides of the bottom sealing plate are clamped with cardboards between the inner walls of the two sides of the U-shaped cardboard, and the wedge is inserted between the U-shaped tube and the top inner wall of the U-shaped cardboard; After the second main U-tube is prepared, the top surface and the side surfaces need to be tested for straightness, and the overall straightness is required to be no more than 3mm.

[0009] Furthermore, the straightness detection requirements of the second main U-tube are: Overall dimensions: the allowable deviation of length is ±3mm, the allowable deviation of width is ±2mm, the allowable deviation of height is ±3mm, and the allowable deviation of distortion is ±3mm; Horizontal and vertical straightness: the allowable deviation is 2mm every 5 meters, and the overall allowable deviation is ≤3mm; The straightness detection requirements of the first main U tube are: The horizontal deviation of the extended end face is: ±1mm for every 3m; ±1.5mm for every 5m; The vertical deviation of the extended end face is: the allowable deviation is ±3mm every 3m; the allowable deviation is ±5mm every 5m.

[0010] Furthermore, the pile frame section I includes pile frame section I-1 and pile frame section I-2. Pile frame section I-1 and pile frame section I-2 are integrally manufactured in a workshop and are fixed together using card codes. After the overall manufacturing is completed, they are divided into sections in the workshop, and closing inspection marking lines are made at the same time before they are separated out of the workshop.

[0011] Further, the step of preparing two bottom sealing plates at one time: First, a rectangular structure is made of a plate, and then a pentagonal structure is made of a plate. The first pentagonal structure, the first rectangular structure, the second rectangular structure and the second pentagonal structure are tightly placed on the tire frame in sequence and then clamped. The first pentagonal structure and the first rectangular structure as well as the second rectangular structure and the second pentagonal structure are welded tightly to form two tightly arranged structural plates. The structural plates include a first vertical section, a first horizontal section, an inclined section, a second horizontal section, a second vertical section and a third horizontal section arranged in sequence, and there is an obtuse angle between the inclined section and the first horizontal section. The above two structural plates are turned over and fixed to form the bottom sealing plate shown.

[0012] The advantages of the present invention are: 1. In the present invention, the truss structure is divided into four sections, namely, pile frame section I, pile frame section II, pile frame section III and pile frame head box, and after the production is completed, the sliding shoes are installed and assembled. The present invention rationalizes the design of the preparation process, thereby improving work efficiency. By setting the inspection qualification standard in the preparation process, the product quality can be improved, and at the same time, the phenomenon of rework and the like that may exist in the production process can be avoided, thereby reducing the construction cost and avoiding the waste of energy; 2. In this structure, the tire frame is evenly arranged according to the segment weight and center of gravity, and the specifications of the tire frame are reasonably selected according to the safe bearing capacity of the tire frame, avoiding the overturning of the components due to insufficient strength of the tire frame structure and too high center of gravity of the tire frame, and avoiding accidents caused by objects hitting as much as possible. BRIEF DESCRIPTION OF THE DRAWINGS

[0013] Figure 1 It is the overall front view of the truss structure of the present invention.

[0014] Figure 2 It is a front view of pile frame section I of the present invention.

[0015] Figure 3 It is a schematic diagram of the upper segment of the pile frame I section of the present invention.

[0016] Figure 4 It is the front view of the pile frame head box of the present invention.

[0017] Figure 5 It is a top view of the pile frame head box of the present invention.

[0018] Figure 6 The present invention is a flow chart of preparing two bottom sealing plates at one time.

[0019] Figure 7 This is a diagram for preparing the second main U tube of the present invention.

[0020] Figure 8 This is a diagram for preparing the first main U-tube of the present invention.

[0021] Fig. 9 It is a vertical schematic diagram of the hoisting of the upper segment and the lower segment of the present invention.

[0022] Fig.10 It is a schematic diagram of the forming of the pile frame I section of the present invention. DETAILED DESCRIPTION

[0023] In order to further explain the technical means and effects adopted by the present invention to achieve the predetermined invention purpose, the specific implementation mode, structure, characteristics and effects of the present invention are described in detail below in combination with the accompanying drawings and preferred embodiments.

[0024] like Figure 1-5 As shown, a method for manufacturing a pile truss structure of an offshore wind power full-rotation multi-angle pile driver is shown, wherein the truss structure is a segmented structure, which comprises a pile frame head box 4, a pile frame section I 1, a pile frame section II 2 and a pile frame section III 3 in sequence, and the pile frame section I 1, the pile frame section II 2 and the pile frame section III 3 are all connected by hinges.

[0025] The pile frame section I 1 is arranged horizontally, including a section I body, and a main frame hinge point 11 is provided on one side of the section I body, and a pile frame head box body 4 is provided on the other side. A pile frame sliding shoe track 12 is also provided on the section I body near the pile frame head box body 4, and a sliding shoe bracket and a pile frame sliding shoe 5 are installed on the pile frame sliding shoe track 12. Two pile gripper hinge point ear plates 13 are also provided on the top near the main frame hinge point 11, which are used for connecting the hinge point assembly with the pile frame fork frame.

[0026] The main body of section I includes an upper body and a lower body. Both sides of the upper body and the lower body are four main U-tubes distributed in a rectangular shape. The upper body includes two first main U-tubes 14. The first main U-tubes 14 include a first U-tube with an opening facing upward and a top sealing plate 17 fixed to the top of the first U-tube. The lower body includes two second main U-tubes 15. The second main U-tubes 15 include a second U-tube with an opening facing downward and a bottom sealing plate 18 fixed to the bottom of the second U-tube. Branch tubes 16 are provided between the upper body and the lower body, between the two first main U-tubes 14, and between the two second main U-tubes 15.

[0027] The pile frame head box 4 includes an airfoil box body 41, which is assembled from a plurality of I-beams and is vertically arranged. A connecting portion 42 is provided in the middle of a side close to the pile frame section I 1, and eight 20T single-piece lifting ears 43 are provided below the connecting portion 42. A first pulley ear plate assembly 44 and a second pulley ear plate assembly 44 are provided on both sides of the top, respectively. A third pulley ear plate assembly 44 and a fourth pulley ear plate assembly 44 are also provided on the side away from the pile frame section I 1.

[0028] Each pulley lug assembly 44 includes two pulley lugs disposed opposite to each other and a shaft connected to the two pulley lugs.

[0029] The connecting portion 42 includes four supporting columns distributed in a rectangular shape and a connecting plate connected between the supporting columns.

[0030] The pile frame section II 2 comprises a section II body, and the section II body has a similar structure to the section I body.

[0031] The pile frame section III 3 includes a section III body, which has a similar structure to the section I body. The method for making a truss structure comprises the following steps: S1. Pile frame segmentation: S2. Production of the pile frame head box 4: first group the I-beams, then assemble them on a horizontal frame to obtain a box body 41, then install the first, second, third and fourth pulley ear plate assemblies 44 at corresponding positions on the box body 41, then install multiple single-piece ear plates 43 on the box body 41, and then install the connecting part 42 on the box body 41.

[0032] In this step, it is necessary to assemble the connecting part 42 in advance and ensure the manufacturing accuracy of the top surfaces of the four supporting columns. The docking accuracy between the pile frame head box 4 and the pile frame I section 1 is ensured by controlling the manufacturing accuracy of the four corners of the cross-section of the top surfaces of the supporting columns. Then, the connecting part 42 is installed on the box body 41. After the box body 41 is installed, four 20T lifting ears are installed on both sides of the top of the box body 41 and on both ends of the bottom of the box body 41 close to the pile frame I section 1.

[0033] S3, production and installation of the main U-tube of the pile frame: prepare a mobile tire frame 6 in the workshop, first prepare two bottom sealing plates 18 on the tire frame 6 after the plate passes the inspection, and the specific steps of preparing two bottom sealing plates 18 at a time are as follows: First, a rectangular structure is made of a plate, and then a pentagonal structure is made of a plate. The first pentagonal structure, the first rectangular structure, the second rectangular structure and the second pentagonal structure are tightly placed on the tire frame in sequence and then clamped. The first pentagonal structure and the first rectangular structure as well as the second rectangular structure and the second pentagonal structure are welded to form two tightly arranged structural plates, which include a first vertical section, a first horizontal section, an inclined section, a second horizontal section, a second vertical section and a third horizontal section arranged in sequence, and an obtuse angle is formed between the inclined section and the first horizontal section. The above two structural plates are turned over and fixed to form the bottom sealing plate 18 shown, and the bottom between the two bottom sealing plates 18 is filled with a steel plate 7 (as shown in FIG. Figure 6 as shown).

[0034] Then the steel plate is bent into a U-shaped tube after passing the inspection, and then the U-shaped tube is hoisted and positioned on the top of the bottom sealing plate 18, and fixed on the tire frame 6 through the U-shaped clamping plate 8, the wedge block 9 and the sealing plate clamping plate 10. Figure 7 As shown, after preheating, the bottom sealing plate 18 and the U-shaped tube are automatically welded, and the second main U-tube 15 is prepared.

[0035] Among them, the straightness detection requirements of the second main U-tube 15 are: Overall dimensions: The allowable deviation of length is ±3mm, the allowable deviation of width is ±2mm, the allowable deviation of height is ±3mm, and the allowable deviation of distortion is ±3mm.

[0036] Horizontal and vertical straightness: The allowable deviation is 2mm every 5 meters, and the overall allowable deviation is ≤3mm.

[0037] Then install the top sealing plate 17 on the tire frame 6, hang and position the U-shaped tube on the top of the top sealing plate 17, and then fix it on the tire frame 6 through the U-shaped clamping plate 8 and the wedge block 9 for welding. Figure 8 As shown, the first main U-tube 14 is prepared.

[0038] Straightness detection requirements for the first main U-tube 14: The allowable deviation of the extended end face in the transverse direction (direction A) is ±1mm for every 3m and ±1.5mm for every 5m.

[0039] The vertical direction (B direction) of the extended end face is: the allowable deviation is ±3mm for every 3m and ±5mm for every 5m.

[0040] S4, production of the sheet body of the pile frame I section 1: two first main U-tubes 14 are symmetrically arranged on the tire frame according to the weight and center of gravity of the sections. After the branch pipes between the two first main U-tubes 14 are fixed, they are hoisted vertically and other side face branches are installed. Finally, two hinge ear plates are installed. The upper sheet body is installed. The second main U-tube 15 is also installed with the branch pipes and side face branches in the same way. The lower sheet body is installed. Fig. 9 shown. S5. Forming of the main body of section I: installing a branch pipe between the vertical upper piece and the vertical lower piece, and forming the main body of section I. S6. Turn over the entirety of the I-section body: hoist and turn over the I-section body so that the upper and lower pieces are in an upper and lower position relationship, and install the main frame hinge 11. S7, forming of the pile frame section I 1: the pile frame sliding shoe track 12, the sliding shoe bracket, the pile frame sliding shoe 5 and the pile gripper hinge point ear plate 13 are respectively installed on the section I body, and the pile frame section I 1 is integrally formed. S8, forming of pile frame section II 2 and pile frame section III 3: the forming of pile frame section II 2 and pile frame section III 3 is carried out by adopting the aforementioned steps S3-S6.

[0041] S9. Production completed.

[0042] Among them, in step S3, the inspection qualification standard of the prepared plate of the bottom sealing plate 18 is: Overall dimensions: The allowable deviation of length is ±1.5mm, the allowable deviation of width is ±1mm, and the allowable deviation of diagonal is S±2mm.

[0043] Flatness: The allowable deviation is ±1mm per meter, and the allowable deviation is ±1.5mm per 3 meters.

[0044] Side bend: The allowable deviation of the entire plate is 2mm.

[0045] The inspection standards for U-shaped tubes after the steel plate is bent into U-shaped tubes are: Overall dimensions: The allowable deviation of length is ±2mm, the allowable deviation of width is ±2mm, and the allowable deviation of height is ±2mm.

[0046] The permissible deviation of distortion is ±3mm. The permissible deviation of horizontal and vertical straightness is 2mm / 5m, and the overall permissible deviation is ≤3mm.

[0047] Among them, the inspection standards for U-shaped tubes after automatic welding are: Overall dimensions: The allowable deviation of length is ±3mm, the allowable deviation of width is ±2m, the allowable deviation of height is ±2m, and the allowable deviation of twisting is ±3mm.

[0048] Horizontal and vertical straightness: The allowable deviation is 2mm every 5m, and the overall allowable deviation is ≤3mm.

[0049] The U-shaped pallet 8 is opened downwards and completely covers the U-shaped tube and the bottom sealing plate 18, and is fixed on the tire frame in S3. A pallet is clamped between the two sides of the bottom sealing plate 18 and the inner walls of the two sides of the U-shaped pallet 8, and a wedge 9 is inserted between the U-shaped tube and the top inner wall of the U-shaped pallet 8.

[0050] After the second main U-tube 15 is prepared, the top surface and the side surfaces need to be tested for straightness, and the overall straightness is required to be no more than 3 mm.

[0051] Pile frame section 1 includes pile frame section 1-1 and pile frame section 1-2. Pile frame section 1-1 and pile frame section 1-2 are manufactured as a whole in the workshop and fixed together with card codes. After the overall manufacturing is completed, they are divided into sections in the workshop, and the closing inspection marking lines are made at the same time, and then they are separated out of the workshop.

[0052] The above description is only a preferred embodiment of the present invention and does not limit the present invention in any form. Although the present invention has been disclosed as a preferred embodiment as above, it is not used to limit the present invention. Any technical personnel in this field can make some changes or modify the technical contents disclosed above into equivalent embodiments without departing from the scope of the technical solution of the present invention. However, any brief modifications, equivalent changes and modifications made to the above embodiments based on the technical essence of the present invention without departing from the content of the technical solution of the present invention are still within the scope of the technical solution of the present invention.

Claims

1. A method for manufacturing a pile truss structure of an offshore wind power full-rotation multi-angle pile driver, characterized in that: The truss structure is a segmented structure, which is composed of a pile frame head box, pile frame section I, pile frame section II and pile frame section III in sequence, and the pile frame section I, pile frame section II and pile frame section III are all connected by hinges; The pile frame section I is arranged transversely, including a section I body, and a main frame hinge point is arranged on one side of the section I body, and the pile frame head box is arranged on the other side thereof, and a pile frame sliding shoe track is also arranged on the section I body near the pile frame head box, and a sliding shoe bracket and a pile frame sliding shoe are installed on the pile frame sliding shoe track, and two pile gripper hinge point ear plates are also arranged on the top near the main frame hinge point; The I-section body includes an upper body and a lower body, and both sides of the upper body and the lower body are four main U-tubes distributed in a rectangular shape. The upper body includes two first main U-tubes, and the first main U-tubes include a first U-shaped tube with an opening facing upward, and a top sealing plate fixed to the top of the first U-shaped tube. The lower body includes two second main U-tubes, and the second main U-tubes include a second U-shaped tube with an opening facing downward, and a bottom sealing plate fixed to the bottom of the second U-shaped tube. Branch tubes are provided between the upper body and the lower body, between the two first main U-tubes, and between the two second main U-tubes. The pile frame head box body includes a box body, which is assembled from a plurality of I-beams and is vertically arranged. A connecting portion is provided on the box body at the middle of one side close to the pile frame section I, and a plurality of single-piece lifting ears are provided on the box body below the connecting portion. A first pulley ear plate assembly and a second pulley ear plate assembly are provided on both sides of the top of the box body, respectively. A third pulley ear plate assembly and a fourth pulley ear plate assembly are also provided on the side away from the pile frame section I. The pile frame section II comprises a section II body, and the section II body has a similar structure to the section I body; The pile frame section III includes a section III body, and the section III body is similar in structure to the section I body. The preparation method comprises the following steps: S1. Pile frame segmentation: S2. Production of the pile frame head box: first, group the I-beams, then assemble them on the horizontal frame to obtain the box body, then install the first, second, third and fourth pulley ear plate assemblies at the corresponding positions on the box body, then install multiple single-piece lifting ears on the box body, and then install the connecting part on the box body; S3, production and installation of the main U-tube of the pile frame: prepare a mobile tire frame in the workshop, first prepare two bottom sealing plates on the tire frame after the plate passes the inspection, then bend the steel plate into a U-shaped tube after it passes the inspection, and then hoist and position the U-shaped tube on the top of the bottom sealing plate, and fix it on the tire frame through a U-shaped clamping plate and a wedge block, and then realize automatic welding between the bottom sealing plate and the U-shaped tube after preheating, and the preparation of the second main U-tube is completed; Then, the top sealing plate is installed on the tire frame, the U-shaped tube is hoisted and positioned on the top of the top sealing plate, and then fixed on the tire frame by U-shaped clamping plates and wedges for welding, and the preparation of the first main U-tube is completed; S4, production of the pile frame I section: two first main U-tubes are transversely and symmetrically arranged on the tire frame evenly arranged according to the weight and center of gravity of the sections. After the branch pipes between the two first main U-tubes are fixed, they are hoisted vertically and other side face branches are installed. Finally, two hinge ear plates are installed. The upper section is installed. The second main U-tube is also installed with branch pipes and side face branches in the same way. The lower section is installed. S5, forming the main body of section I: installing a branch pipe between the vertical upper sheet and the vertical lower sheet, and forming the main body of section I; S6, turning over the entirety of the I-section body: hoisting and turning over the I-section body so that the upper body and the lower body are in an upper and lower position relationship, and installing the main frame hinge point; S7, forming the pile frame section I: the pile frame sliding shoe track, the sliding shoe bracket, the pile frame sliding shoe and the pile gripper hinge point ear plate are respectively installed on the section I body, and the pile frame section I is formed as a whole; S8, forming the pile frame section II and the pile frame section III: the pile frame section II and the pile frame section III are formed by the aforementioned steps S3-S6; S9. Production completed.

2. The method for manufacturing a pile truss structure of an offshore wind power full-rotation multi-angle pile driver according to claim 1, characterized in that: The connecting portion includes four supporting columns distributed in a rectangular shape, and a connecting plate connected between the supporting columns; In step S2, it is necessary to assemble the connection part in advance and ensure the manufacturing accuracy of the top surfaces of the four support columns, and then install the connection part on the box body. After the box body is installed, four 20T lifting ears are installed on both sides of the top of the box body and on both ends of the bottom of one side of the box body close to the pile frame I section.

3. The method for manufacturing a pile truss structure of an offshore wind power full-rotation multi-angle pile driver according to claim 2, characterized in that: In step S3, The inspection qualification standard of the prepared plate of the bottom sealing plate is: Dimensions: The allowable deviation of length is ±1.5mm, the allowable deviation of width is ±1mm, and the allowable deviation of diagonal is S±2mm; Flatness: The allowable deviation is ±1mm per meter, and the allowable deviation is ±1.5mm per 3 meters; Side bending: The allowable deviation of the entire plate is 2mm; The inspection standard of the U-shaped tube after the steel plate is bent into a U-shaped tube is: Overall dimensions: The allowable deviation of length is ±2mm, the allowable deviation of width is ±2mm, and the allowable deviation of height is ±2mm; The allowable deviation of distortion is ±3mm; the allowable deviation of horizontal and vertical straightness is 2mm / 5m, and the overall allowable deviation is ≤3mm.

4. The method for manufacturing a pile truss structure of an offshore wind power full-rotation multi-angle pile driver according to claim 3, characterized in that: The inspection standards for the U-shaped tube after automatic welding are: Overall dimensions: the allowable deviation of length is ±3mm, the allowable deviation of width is ±2m, the allowable deviation of height is ±2m, and the allowable deviation of twisting is ±3mm; Horizontal and vertical straightness: The allowable deviation is 2mm every 5m, and the overall allowable deviation is ≤3mm.

5. The method for manufacturing a pile truss structure of an offshore wind power full-rotation multi-angle pile driver according to claim 1, characterized in that: The U-shaped cardboard is opened downwards and completely covers the U-shaped tube and the bottom sealing plate, and is fixed on the tire frame in S3, and the two sides of the bottom sealing plate are clamped with cardboards between the inner walls of the two sides of the U-shaped cardboard, and the wedge is inserted between the U-shaped tube and the top inner wall of the U-shaped cardboard; After the second main U-tube is prepared, the top surface and the side surfaces need to be tested for straightness, and the overall straightness is required to be no more than 3mm.

6. The method for manufacturing a pile truss structure of an offshore wind power full-rotation multi-angle pile driver according to claim 5, characterized in that: The straightness detection requirements of the second main U tube are: Overall dimensions: the allowable deviation of length is ±3mm, the allowable deviation of width is ±2mm, the allowable deviation of height is ±3mm, and the allowable deviation of distortion is ±3mm; Horizontal and vertical straightness: the allowable deviation is 2mm every 5 meters, and the overall allowable deviation is ≤3mm; The straightness detection requirements of the first main U tube are: The horizontal deviation of the extended end face is: ±1mm for every 3m; ±1.5mm for every 5m; The vertical deviation of the extended end face is: the allowable deviation is ±3mm every 3m; the allowable deviation is ±5mm every 5m.

7. The method for manufacturing a pile truss structure of an offshore wind power full-rotation multi-angle pile driver according to claim 1, characterized in that: The pile frame section I includes pile frame section I-1 and pile frame section I-2. Pile frame section I-1 and pile frame section I-2 are integrally manufactured in a workshop and fixed together with card codes. After the overall manufacturing is completed, they are divided into sections in the workshop, and the closing inspection marking lines are made at the same time, and then they are separated out of the workshop.

8. The method for manufacturing a pile truss structure of an offshore wind power full-rotation multi-angle pile driver according to claim 1, characterized in that: Steps for preparing two bottom sealing plates at one time: First, a rectangular structure is made of a plate, and then a pentagonal structure is made of a plate. The first pentagonal structure, the first rectangular structure, the second rectangular structure and the second pentagonal structure are tightly placed on the tire frame in sequence and then clamped. The first pentagonal structure and the first rectangular structure as well as the second rectangular structure and the second pentagonal structure are welded tightly to form two tightly arranged structural plates. The structural plates include a first vertical section, a first horizontal section, an inclined section, a second horizontal section, a second vertical section and a third horizontal section arranged in sequence, and there is an obtuse angle between the inclined section and the first horizontal section. The above two structural plates are turned over and fixed to form the bottom sealing plate shown.

Citation Information

Cited By

  • Preparation process of offshore wind power full-rotation multi-angle pile driver fork frame