Vertical wall reinforcement cage module prefabricated supporting device and construction method
By using a layered binding and step-by-step hoisting method for prefabricated support devices for vertical wall steel cage modules, the problems of complex hoisting and limited operating space in existing technologies have been solved, improving construction efficiency and the utilization rate of support devices, and meeting the schedule requirements of nuclear power projects.
Patent Information
- Application Number
- CN202411547554.3
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-11-01
- Publication Date
- 2025-01-07
AI Technical Summary
The existing vertical steel cage modules suffer from problems such as complex hoisting process, small operating space and low utilization rate of support devices during prefabrication, resulting in low construction efficiency and inability to meet the schedule requirements of nuclear power projects.
A prefabricated support device for vertical wall steel cage modules is adopted, including positioning plates, columns and control frames. By using layered binding and step-by-step hoisting methods, the steel cage modules are ensured to be operated on the outside of the columns and control frames, reducing the overall hoisting requirements and improving the utilization rate of the support device.
This method enables stable binding and rapid construction of steel cage modules, improves construction efficiency, reduces the workload of disassembling prefabricated support devices, and increases the reusability of the devices.
Smart Images

Figure CN119266461A_ABST
Abstract
Description
Technical Field
[0001] The invention belongs to the technical field of building construction, and in particular relates to a prefabricated supporting device for a vertical wall reinforcement cage module and a construction method. Background Art
[0002] The diameter of the steel bars of the walls of the powerhouses in nuclear power projects is large, the spacing is dense, the binding work is large, the construction period is long, and the construction efficiency is low, which directly affects the total construction period of nuclear power. The traditional steel bar construction process can no longer meet the requirements of the tight construction period and heavy tasks of nuclear power construction. At present, the construction method of prefabricating steel cage modules and then hoisting and connecting some wall steel bars is being explored, but the modular horizontal prefabrication method of steel cages is generally used. The construction method of this horizontal prefabricated steel cage module not only occupies a large site area, but also has great safety risks and quality risks of module deformation during the flipping of the steel cage module.
[0003] At present, existing steel cage modules are prefabricated vertically. However, the existing vertical steel cage modules have the following deficiencies during the prefabrication process: (1) During the hoisting process, the prefabricated support device and the steel cage module are hoisted together, resulting in a large amount of disassembly work after the hoisting is in place, which is not conducive to the rapid reuse of the prefabricated support device; (2) In order to ensure the overall support stability, steel bars are tied inside the prefabricated support device, resulting in a small operating space and inconvenient operation. Summary of the invention
[0004] In view of the deficiencies in the prior art, the present invention provides a prefabricated support device and a construction method for a vertical wall reinforcement cage module, which can provide stable support for reinforcement binding and facilitate binding. At the same time, there is no need to hoist the prefabricated support device and the wall reinforcement cage module at the same time, thereby improving the utilization rate of the prefabricated support device.
[0005] The present invention provides the following technical solutions:
[0006] In a first aspect, a prefabricated support device for a vertical wall reinforcement cage module is provided, comprising: a positioning plate, a column and a control frame; a plurality of the columns are arranged left and right to form a straight line; the columns include a plurality of unit section columns connected end to end; there are at least two positioning plates, which are respectively located on the front and rear sides of all the columns; the positioning plates are provided with a plurality of positioning through holes evenly distributed; a plurality of support rods are installed on each of the columns; the control frame comprises a horizontal frame and a vertical rod; the horizontal frame has a plurality of layers distributed up and down, and each layer of the horizontal frame comprises a plurality of short cross bars and two horizontal bars distributed front and back, and the short cross bars are installed across the two horizontal bars of the current layer; the horizontal bars are placed on the support rods; the two adjacent layers of the horizontal frames are connected by vertical rods.
[0007] Optionally, the column further includes a base; the base is located at the bottom of the lowest unit section column, and the cross-sectional area of the base is larger than the cross-sectional area of the column; and ears are provided on both left and right sides of the top of the unit section column.
[0008] Optionally, the unit segment column includes a main body and a connecting plate; the main body is an H-shaped steel, and the connecting plate is located at the upper and lower sides of the unit segment column; the connecting plate is provided with bolt holes so that adjacent unit segment columns can be detachably connected.
[0009] Optionally, the short cross bar is connected to the horizontal bar via a U-shaped connector, the bottom opening of the U-shaped connector can accommodate the short cross bar to pass through; both free ends of the U-shaped connector are provided with through holes that allow the horizontal bar to pass through; the bottom of the U-shaped connector is provided with a fastening bolt, which presses the short cross bar against the surface of the horizontal bar.
[0010] Optionally, the support rod is a telescopic structure, which includes a fixed through slot, a telescopic arm and a limit piece; the fixed through slot is installed on the column, and there are two telescopic arms, which are slidably inserted from both ends of the fixed through slot; a plurality of first limit through holes are provided on the side wall of the fixed through slot, and at least one second limit through hole is provided on the telescopic arm; when the telescopic arm moves into position, at least one second limit through hole is opposite to one of the first limit through holes so that the limit piece can be inserted therein.
[0011] In a second aspect, a construction method of a vertical wall reinforcement cage module is provided, based on the prefabricated support device described in any one of the first aspects, comprising:
[0012] Assemble the prefabricated support device and fix all the columns on the ground in a straight line, and fix the two positioning plates on the ground in a front-to-back distribution;
[0013] Insert the bottom of the vertical reinforcement into the positioning through hole of the positioning plate according to the designed spacing, and tie the upper part of the vertical reinforcement to the horizontal rod of each layer to realize the vertical reinforcement tying of the prefabricated steel cage module;
[0014] Tie the horizontal reinforcement of the prefabricated reinforcement cage module;
[0015] The horizontal steel bars on the front and rear sides of the column are fixed by tensioning, and the reinforcement fixing is suspended in the area of the wall embedded parts and the area affected by the column and the support rod;
[0016] Hoist the preliminarily tied steel cage module and the uppermost horizontal frame to the designated location. Before hoisting, separate the vertical pole from the uppermost horizontal frame, and separate the support pole and the lower horizontal frame from the steel cage module;
[0017] After hoisting into place, remove the horizontal frame inside the steel cage module, fix the reinforcement in the area affected by the columns and support rods, and complete the construction of the steel cage module.
[0018] Optionally, the assembling of the prefabricated support device specifically includes:
[0019] According to the height of the steel cage module to be prefabricated, several unit section columns are selected, and the unit section columns are installed as columns in an end-to-end manner;
[0020] Install the support rods on the uprights and place the horizontal rods on the support rods;
[0021] The horizontal bars on the front and rear sides of each layer are connected by short cross bars. During the connection process, the connection position of the short cross bars and the horizontal bars is adjusted according to the distance between the front and rear sides of the wall reinforcement cage module to be prefabricated;
[0022] The horizontal racks on adjacent layers are connected into a whole through vertical poles.
[0023] Optionally, when tying the vertical reinforcement and horizontal reinforcement of the prefabricated reinforcement cage module, tying is performed simultaneously on the front and rear sides of the column and symmetry is maintained.
[0024] Optionally, among the horizontal steel bars used to bind the prefabricated steel cage module, the horizontal steel bars located at the top and bottom layers are bound with the vertical bars of the steel cage module after the hoisting is completed.
[0025] Optionally, the support rod is a telescopic structure, and the support rod is separated from the steel cage module by contracting the support rod.
[0026] Compared with the prior art, the present invention has the following beneficial effects:
[0027] The overall structure of the device of the present invention is simple, and the arrangement of the columns and the control frame can ensure that the steel cage module remains stable during the prefabrication process. Moreover, since the prefabrication of the steel cage module is carried out on the outside of the columns and the control frame, the operating space is large and the binding is convenient. In addition, when hoisting the wall steel cage module, the present invention only hoists the horizontal frame on the upper layer of the control frame together with the steel cage module, and there is no need to hoist the entire prefabricated support device, thereby improving the utilization rate of the prefabricated support device and realizing the rapid recycling of the prefabricated support device. BRIEF DESCRIPTION OF THE DRAWINGS
[0028] Figure 1 It is a schematic diagram of the overall structure of the present invention;
[0029] Figure 2 It is a structural schematic diagram of the control frame of the present invention;
[0030] Figure 3 It is a structural schematic diagram of the support rod of the present invention;
[0031] Figure 4 It is a structural schematic diagram of the U-shaped connector of the present invention.
[0032] Figure 5 It is a left-side structural schematic diagram of the reinforcement cage module binding of the present invention.
[0033] Markings in the figure are: 1 is a positioning plate, 11 is a positioning through hole, 2 is a column, 21 is a unit section column, 211 is a main body, 212 is a connecting plate, 213 is a lifting ear, 22 is a base, 3 is a control frame, 31 is a horizontal frame, 32 is a vertical pole, 311 is a horizontal rod, 312 is a short cross bar, 313 is a U-shaped connector, 314 is a fastening bolt, 4 is a support rod, 41 is a fixed through slot, 42 is a telescopic arm, 43 is a limit piece, and 44 is a first limit through hole. DETAILED DESCRIPTION
[0034] The present invention will now be described in further detail with reference to the accompanying drawings.
[0035] It should be noted that the terms such as "upper", "lower", "left", "right", "front", "back", etc. cited in the invention are only for the convenience of description and are not used to limit the scope of implementation of the present invention. Changes or adjustments in their relative relationships should be regarded as the scope of implementation of the present invention without substantially changing the technical content.
[0036] Example 1
[0037] like Figure 1 and 2 As shown, a vertical wall reinforcement cage module prefabricated support device is provided, including: a positioning plate 1, a column 2 and a control frame 3.
[0038] A plurality of columns 2 are arranged in a straight line from left to right; the columns 2 include a plurality of unit section columns 21 connected end to end; and the plurality of unit section columns 21 are detachably connected to each other.
[0039] According to the characteristic information such as the length, cross-sectional dimensions and reinforcement information of the prefabricated wall reinforcement cage module, the number of columns 2, the use height of the columns 2, the size of the base 22 and the distance between the front and rear inner supports of the control frame 3 are determined.
[0040] In this embodiment, the unit column 21 includes a main body 211 and a connecting plate 212; the main body 211 is H-shaped steel, and the connecting plate 212 is located on the upper and lower sides of the unit column 21; the connecting plate 212 is integrally formed with the main body 211 or connected by welding; the connecting plate 212 is provided with bolt holes so that adjacent unit main bodies can be detachably connected by screws.
[0041] In some other embodiments, a base 22 is further included, and the base 22 and the unit section column 21 located at the bottom are detachably connected by screws. Of course, in some other embodiments, the base 22 and the bottom unit section column 21 are integrally formed or welded; the cross-sectional area of the base 22 is larger than the cross-sectional area of the column 2, and the base 22 is used to support the column 2 to ensure the stability of the column 2; the material of the base 22 is Q235B as an option, and the thickness of the base 22 can be selected according to actual needs. As an option, the thickness of the base 22 is 10 mm.
[0042] The left and right sides of the top of the unit section column 21 are both provided with lifting ears 213, the lifting ears 213 are made of round steel, the unit section column 21 and the lifting ears 213 are connected by welding, and the setting of the lifting ears 213 can facilitate the lifting of the column 2 into place.
[0043] In this embodiment, there are at least two positioning plates 1, which are respectively located on the front and rear sides of all the columns 2. The positioning plates 1, like the base 22, usually need to be fixed on the ground to ensure the stability of the positioning plates 1 and the columns 2; of course, in some other embodiments, there are two groups of positioning plates 1, that is, each group is respectively located on the front and rear sides of the column 2, and each group of positioning plates 1 has multiple positioning plates 1, and the ends are connected in a straight line; the spacing between the positioning plates 1 located in front and behind the column 2 is determined according to the design requirements of the steel cage module; the positioning plates 1 are provided with a plurality of evenly distributed positioning through holes 11, and the positioning through holes 11 can have one row or more rows, and the spacing between the positioning through holes 11 is determined according to the characteristic data of the steel cage module to be prefabricated, and the diameter of the positioning through holes 11 is determined according to the steel bar diameter of the steel cage module; the positioning through holes 11 are used to position the vertical bars of the steel control module to be prefabricated; as an optional option, the positioning plate 1 is made of plywood.
[0044] A plurality of support rods 4 are installed on each column 2; the support rods 4 are made of channel steel, and the support rods 4 at the bottom layer are usually 300 mm from the ground.
[0045] like Figure 2 As shown, the control frame 3 includes a horizontal frame 31 and a vertical pole 32; the horizontal frame 31 has several layers distributed up and down, and each layer of the horizontal frame 31 includes several short cross bars 312 and two horizontal bars 311 distributed front and back; the horizontal bar 311 is placed on the support rod 4; two adjacent layers of horizontal frames 31 are connected by the vertical pole 32, and the short cross bars 312 are installed across the two horizontal bars 311 of the current layer; the short cross bars 312 connect the two horizontal bars 311 of each layer into a whole, and can control the distance between the two horizontal bars 311 at the same time, so as to adapt to the distance between the front and rear sides of the steel bar hole module; the distance between the two horizontal bars 311 of each layer is the distance between the front and rear sides of the control frame 3.
[0046] The horizontal frame 31 usually has two layers. If the steel cage module to be prefabricated is too high, the length of the vertical pole 32 can be extended. Of course, in some other embodiments, there may be multiple layers of horizontal frames 31, that is, multiple layers of horizontal frames 31 are placed on the support rod 4. There may also be multiple layers of horizontal frames 31, some of which are placed on the support rod 4, and the remaining horizontal frames 31 are used as spares, that is, after the top horizontal frame 31 is hoisted away, the spare horizontal frames 31 are supplemented and placed on the support rod 4, so as to realize the rapid recycling of the prefabricated support device.
[0047] like Figure 4 As shown in the figure, the short cross bar 312, the horizontal bar 311 and the vertical bar 32 are all made of galvanized steel pipes. The short cross bar 312 and the horizontal bar 311 can be connected by a traditional scaffolding connection cross fastener. In this embodiment, in order to ensure the disassembly speed and the stability of the connection, the short cross bar 312 is connected to the horizontal bar 311 through a U-shaped connecting piece 313; the bottom opening of the U-shaped connecting piece 313 can accommodate the short cross bar 312 to pass through; the two free ends of the U-shaped connecting piece 313 are provided with a The through hole through which the horizontal rod 311 passes, the short cross rod 312 and the horizontal rod 311 are distributed up and down and cross each other; a fastening bolt 314 is provided at the bottom of the U-shaped connecting piece 313, and the fastening bolt 314 is threadedly connected to the U-shaped connecting piece 313. By tightening, the fastening bolt 314 can be extended into the end of the U-shaped connecting piece 313 and rest against the surface of the short cross rod 312, thereby pressing the short cross rod 312 against the surface of the horizontal rod 311 to realize the connection between the short cross rod 312 and the horizontal rod 311.
[0048] When the horizontal frame 31 has two layers, there are usually four vertical rods 32, which are respectively located at the two ends of the horizontal rod 311, and the vertical rods 32 are connected to the short cross rod 312 through cross fasteners.
[0049] like Figure 3As shown, as a further feature, in this embodiment, the support rod 4 is a telescopic structure; the support rod 4 is divided into a fixed through slot 41, a telescopic arm 42 and a stopper 43; the fixed through slot 41 is detachably mounted on the column 2, and there are two telescopic arms 42, which are slidably inserted from both ends of the fixed through slot 41; a plurality of first stopper through holes 44 are arranged on the side wall of the fixed through slot 41, and at least one second stopper through hole is arranged on the telescopic arm 42; when the telescopic arm 42 moves into position, at least one second stopper through hole is aligned with one of the first stopper through holes 44 Yes, so that the limit member 43 is inserted into the relative first limit through hole 44 and the second limit through hole; by changing the length of the telescopic arm 42 inserted into the fixed through slot 41, the length of the entire support rod 4 can be changed; when disassembling the control frame 3, the support rod 4 is contracted to achieve the control frame 3 to be detached from the support rod 4, thereby further improving the disassembly rate of the control frame 3; the limit member 43 is a latch or a spring pin, and of course it can also be a detachable structure such as a bolt. When the limit member 43 is a spring pin, its fixed part is installed on the fixed through slot 41.
[0050] Example 2
[0051] like Figure 5 As shown, a construction method of a vertical wall reinforcement cage module is provided, comprising:
[0052] Step 1: Assemble the prefabricated support device and fix all the columns 2 on the ground in a straight line, and also fix the two positioning plates 1 on the ground in a front-to-back distribution.
[0053] Assemble the prefabricated support device, including:
[0054] Step 1.1: Select a number of unit section columns 21 according to the height of the steel cage module to be prefabricated, and install the unit section columns 21 as columns 2 in an end-to-end manner.
[0055] The unit section columns 21 are detachably connected by bolts; the number of the columns 2 can be determined according to the length of the steel cage module to be prefabricated.
[0056] Step 1.2: Install the support rod 4 on the column 2 , and place the horizontal rod 311 on the support rod 4 .
[0057] The support rod 4 is detachably mounted on the column 2 by means of screws.
[0058] Step 1.3: Connect the horizontal bars 311 on the front and rear sides of each layer through the short cross bars 312. During the connection process, adjust the connection position of the short cross bars 312 and the horizontal bars 311 according to the distance between the front and rear sides of the wall reinforcement cage module to be prefabricated.
[0059] Specifically, when the horizontal rod 311 is placed on the support rod 4, it has been penetrated by a plurality of U-shaped connectors 313, the short cross bar 312 is inserted into the opening between the U-shaped connector 313 and the horizontal rod 311, and the connection between the short cross bar 312 and the horizontal rod 311 is completed by tightening screws.
[0060] Step 1.4: Connect the horizontal racks 31 of adjacent layers into a whole through the vertical poles 32.
[0061] Step 2: Insert the bottom of the vertical reinforcement into the positioning through hole 11 of the positioning plate 1 according to the designed spacing, and tie the upper part of the vertical reinforcement to the horizontal rod 311 of each layer to realize the vertical reinforcement tying of the prefabricated steel cage module.
[0062] Tying the upper part of the vertical reinforcement to the horizontal rod 311 of each layer can ensure the verticality of the vertical reinforcement. The tying adopts 14# galvanized iron wire.
[0063] Step 3: Tie the horizontal reinforcement of the prefabricated reinforcement cage module.
[0064] Install horizontal steel bars from bottom to top in sequence according to standard spacing; each intersection of horizontal steel bars and vertical bars is bounded by binding wire, and no binding is allowed; the binding method adopts the figure-eight buckle method, and the direction of the figure-eight buckle is bounded by the middle vertical bar of the mesh, and is arranged symmetrically, and cannot be all in one direction; for walls with 4 layers of steel mesh, they should be tied in sequence from inside to outside (4L-1L), and the intersections of the 3 rows of horizontal bars and vertical bars at the top and bottom of the steel mesh should be tied and reinforced with 14# galvanized iron wire.
[0065] Step 4: The horizontal steel bars located at the front and rear sides of the column 2 are fixed by tensioning, and the tensioning and fixing of the wall embedded parts area and the area affected by the column 2 and the support rod 4 are suspended.
[0066] Step 5: hoist the preliminarily bound steel cage module and the uppermost horizontal frame 31 to the designated position. Before hoisting, separate the vertical pole 32 from the uppermost horizontal frame 31, and separate the support pole 4 and the lower horizontal frame 31 from the steel cage module.
[0067] The lifting point during hoisting is set at the top of the steel cage module, and the setting of the lifting point on the top of the steel cage module can refer to the existing technology.
[0068] When the lower horizontal frame 31 is separated from the steel cage module, loosen the fastening bolts 314 and pull the short cross bar 312 out of the U-shaped connecting piece 313; when the support rod 4 is a telescopic structure, when the support rod 4 is separated from the steel cage module, it is only necessary to retract the support rod 4.
[0069] Step 6: After the lifting is in place, the uppermost horizontal frame 31 inside the steel cage module is removed, and the reinforcement in the area affected by the columns 2 and the support rods 4 is fixed to complete the construction of the steel cage module.
[0070] When disassembling the topmost short cross bar 312 and horizontal bar 311 inside the steel cage module, loosen the fastening bolt 314 and pull the short cross bar 312 out of the U-shaped connecting piece 313.
[0071] Furthermore, in the present embodiment, when the vertical reinforcement and horizontal reinforcement of the prefabricated reinforcement cage module are being tied, the tying is performed simultaneously on the front and rear sides of the column 2 and maintained symmetric.
[0072] Furthermore, in the present embodiment, among the horizontal steel bars of the prefabricated steel cage module, the horizontal steel bars at the top and bottom layers are tied with the vertical bars of the steel cage module after the hoisting is completed.
[0073] Specifically, when tying horizontal steel bars, the horizontal steel bars at the top and bottom layers are tied on-site of the wall, that is, the prefabricated steel cage module is connected to the existing vertical bars in the wall through steel bar joints. After the connection is completed, the horizontal steel bars at the bottom layer of the steel cage module are tied to the vertical bars.
[0074] When in use, several layers of horizontal rods 311 and short cross rods 312 are configured as spares to achieve rapid recycling of the prefabricated support device. That is, after the top horizontal frame 31 and the steel cage module are hoisted away, the spare horizontal frame 31 is placed on the support rod 4, and the next prefabricated steel cage module can be made.
[0075] In order to ensure the overall stability of the steel cage, the main reinforcement is not disconnected when encountering the opening, but is cut after it is in place; however, additional reinforcement such as additional reinforcement bars at the opening, lateral structural reinforcement, U-shaped edge banding reinforcement, etc. need to be placed in advance during the prefabricated steel cage module stage. After the subsequent steel cage module is hoisted into place, the main reinforcement is cut according to the actual positioning on site, and the positioning of the additional reinforcement is adjusted.
[0076] The various embodiments in this specification are described in a progressive manner, and each embodiment focuses on the differences from other embodiments. The same or similar parts between the various embodiments can be referenced to each other.
[0077] The above are only preferred embodiments of the present invention, and the protection scope of the present invention is not limited to the above embodiments. All technical solutions under the concept of the present invention belong to the protection scope of the present invention. It should be pointed out that for ordinary technicians in this technical field, some improvements and modifications without departing from the principle of the present invention should be regarded as the protection scope of the present invention.
Claims
1. A prefabricated support device for a vertical wall reinforcement cage module, characterized in that: include: A positioning plate (1), a column (2) and a control frame (3); a plurality of the columns (2) are arranged left and right to form a straight line; the columns (2) include a plurality of unit column bodies (21) connected end to end; there are at least two positioning plates (1), which are respectively located at the front and rear sides of all the columns (2); the positioning plate (1) is provided with a plurality of evenly distributed positioning through holes (11); each of the columns (2) is installed with a plurality of support rods (4); the control frame ( 3) comprises a horizontal frame (31) and vertical bars (32); the horizontal frame (31) has a plurality of layers distributed up and down, each layer of the horizontal frame (31) comprises a plurality of short cross bars (312) and two horizontal bars (311) distributed front and back, the short cross bars (312) are installed across the two horizontal bars (311) of the current layer; the horizontal bars (311) are placed on the support bars (4); two adjacent layers of the horizontal frames (31) are connected via the vertical bars (32).
2. The prefabricated support device for vertical wall reinforcement cage modules according to claim 1 is characterized in that: The column (2) further comprises a base (22); the base (22) is located at the bottom of the lowest unit column (21), and the cross-sectional area of the base (22) is greater than the cross-sectional area of the column (2); and lifting ears (213) are provided on both left and right sides of the top of the unit column (21).
3. The prefabricated support device for vertical wall reinforcement cage modules according to claim 1 is characterized in that: The unit segment column (21) comprises a main body (211) and a connecting plate (212); the main body (211) is an H-shaped steel, and the connecting plate (212) is located at the upper and lower sides of the unit segment column (21); the connecting plate (212) is provided with bolt holes so that adjacent unit segment columns (21) can be detachably connected.
4. The prefabricated support device for vertical wall reinforcement cage modules according to claim 1, characterized in that: The short cross bar (312) is connected to the horizontal bar (311) via a U-shaped connecting piece (313); the bottom opening of the U-shaped connecting piece (313) can accommodate the short cross bar (312) to pass through; both free ends of the U-shaped connecting piece (313) are provided with through holes that allow the horizontal bar (311) to pass through; and the bottom of the U-shaped connecting piece (313) is provided with a fastening bolt (314), and the fastening bolt (314) presses the short cross bar (312) against the surface of the horizontal bar (311).
5. The prefabricated support device for vertical wall reinforcement cage modules according to claim 1, characterized in that: The support rod (4) is a telescopic structure, and the support rod (4) comprises a fixed through slot (41), a telescopic arm (42) and a limiting member (43); the fixed through slot (41) is installed on the column (2), and there are two telescopic arms (42), which are slidably inserted from both ends of the fixed through slot (41); a plurality of first limiting through holes (44) are arranged on the side wall of the fixed through slot (41), and at least one second limiting through hole is arranged on the telescopic arm (42); when the telescopic arm (42) moves into position, at least one second limiting through hole is opposite to one of the first limiting through holes (44), so that the limiting member (43) is inserted therein.
6. A construction method for a vertical wall reinforcement cage module, based on the prefabricated support device according to any one of claims 1 to 5, characterized in that: include: Assemble the prefabricated support device, and fix all the columns (2) on the ground in a straight line arrangement, and also fix the two positioning plates (1) on the ground in a front-to-back distribution manner; Inserting the bottom of the vertical reinforcement into the positioning through hole (11) of the positioning plate (1) according to the designed spacing, and tying the upper part of the vertical reinforcement to the horizontal rod (311) of each layer, so as to realize the tying of the vertical reinforcement of the prefabricated steel cage module; Tie the horizontal reinforcement of the prefabricated reinforcement cage module; The horizontal steel bars located at the front and rear sides of the column (2) are fixed by tensioning, and the tensioning and fixing of the embedded wall parts area and the area affected by the column (2) and the support rod (4) are suspended; The preliminarily tied steel cage module and the uppermost horizontal frame (31) are hoisted to a designated position. Before hoisting, the vertical pole (32) is separated from the uppermost horizontal frame (31), and the support pole (4) and the lower horizontal frame (31) are separated from the steel cage module; After the lifting is in place, the horizontal frame (31) inside the steel cage module is removed, and the reinforcement in the area affected by the columns (2) and the support rods (4) is fixed to complete the construction of the steel cage module.
7. The construction method of the vertical wall reinforcement cage module according to claim 6 is characterized in that: The assembling prefabricated support device specifically comprises: According to the height of the steel cage module to be prefabricated, a number of unit section columns (21) are selected, and the unit section columns (21) are installed as columns (2) in an end-to-end manner; Install the support rod (4) on the column (2), and place the horizontal rod (311) on the support rod (4); The horizontal bars (311) on both sides of each layer are connected by short cross bars (312). During the connection process, the connection position of the short cross bars (312) and the horizontal bars (311) is adjusted according to the distance between the front and rear sides of the wall reinforcement cage module to be prefabricated; The horizontal frames (31) of adjacent layers are connected into a whole through vertical poles (32).
8. The construction method of the vertical wall reinforcement cage module according to claim 6, characterized in that: When tying the vertical reinforcement and horizontal reinforcement of the prefabricated reinforcement cage module, tying is performed simultaneously on the front and rear sides of the column (2) while maintaining symmetry.
9. The construction method of the vertical wall reinforcement cage module according to claim 6, characterized in that: Among the horizontal steel bars of the prefabricated steel cage module, the horizontal steel bars at the top and bottom layers are tied with the vertical bars of the steel cage module after the hoisting is completed.
10. The construction method of the vertical wall reinforcement cage module according to claim 6, characterized in that: The support rod (4) is a telescopic structure, and the support rod (4) can be separated from the steel cage module by contracting the support rod (4).