Hoisting method
In the construction of high-rise building corridors, the second workpiece and the first workpiece are used to simultaneously lift the different bottom wall distance design of the special-shaped curtain wall structure, the problems of high construction risks and low efficiency are solved, and an efficient and safe construction process is achieved. And reduce costs.
Patent Information
- Application Number
- CN202411467747.8
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-10-21
- Publication Date
- 2025-01-10
AI Technical Summary
In the construction of high-rise building corridors, the complex shape of the special-shaped curtain wall structure leads to problems of high construction risks and low efficiency.
During the lifting process, the second workpiece is installed on the bottom of the first workpiece, and the lifting is synchronously and installed after a preset height, the number of lifting times at high altitudes is reduced, and the aesthetics is improved by setting different bottom wall distances to avoid the use of the support device. Reduce costs.
It improves construction efficiency, reduces the risk of high-altitude operations, improves the aesthetics of the special-shaped curtain wall structure, and reduces construction costs.
Smart Images

Figure CN119288218A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of corridor construction, and in particular to a hoisting method. Background Art
[0002] Existing high-rise buildings are all equipped with corridors, which can not only strengthen the connection between multiple towers, but also serve as a safe passage. In order to improve the aesthetics of the corridor, a special-shaped curtain wall structure is arranged at the bottom of the corridor in the prior art, that is, along the extension length direction of the corridor, the height of the special-shaped curtain wall structure away from the bottom wall of the corridor is different, and the bottom wall of the special-shaped curtain wall structure is arranged in an inclined shape as a whole.
[0003] During construction, if the construction method of hoisting the special-shaped curtain wall structure after the corridor is installed is adopted, since the corridor is usually set relatively high, this will inevitably increase the number of high-altitude hoisting, greatly increasing the construction risk; and if the construction method of hoisting the corridor and the special-shaped curtain wall structure together after fixing them is adopted, then when the special-shaped curtain wall structure is fixed to the corridor on the ground, in order to ensure that the corridor and the special-shaped curtain wall structure are firmly installed and prevent them from falling off during high-altitude hoisting and causing danger, it is necessary to make a tire frame compatible with the special-shaped curtain wall structure for support, resulting in reduced construction efficiency. Summary of the invention
[0004] In view of this, the present invention provides a hoisting method to solve the problems of high construction risk and low construction efficiency when the shape of the special-shaped curtain wall structure is relatively complex.
[0005] The present invention provides a hoisting method for hoisting a first workpiece, wherein a second workpiece is disposed at the bottom of the first workpiece, and the distance between the bottom wall of the second workpiece and the bottom wall of the first workpiece is different along a direction perpendicular to the extension length of the first workpiece, comprising:
[0006] hoisting the first workpiece to a preset height, wherein the preset height is greater than a maximum distance between a bottom wall of the second workpiece and a bottom wall of the first workpiece;
[0007] installing the second workpiece on the bottom of the first workpiece;
[0008] The first workpiece is hoisted to an installation height, and the installation height is greater than the preset height.
[0009] Beneficial effects: By setting the second workpiece at the bottom of the first workpiece before hoisting the first workpiece to the installation height, the first workpiece and the second workpiece can be hoisted synchronously, thereby reducing the number of high-altitude hoisting times to improve construction efficiency and reduce the risk of high-altitude operations; by setting the bottom wall of the second workpiece to have a different distance from the bottom wall of the first workpiece, the aesthetics of the second workpiece can be improved; by hoisting the first workpiece to a preset height and then installing the second workpiece at the bottom of the first workpiece, the second workpiece can be installed in the air to avoid the influence of the shape of the bottom wall of the second workpiece on the installation, and thus there is no need to support the second workpiece, reducing the use of supporting devices during installation, reducing construction costs, and improving construction efficiency.
[0010] In an optional embodiment, the second workpiece includes at least a first decorative component and a second decorative component, the maximum distance between the bottom wall of the second decorative component and the bottom wall of the first workpiece is greater than the maximum distance between the bottom wall of the first decorative component and the bottom wall of the first workpiece, and the first workpiece is hoisted to a preset height and the second workpiece is installed on the bottom of the first workpiece, comprising:
[0011] hoisting the first workpiece to a first preset height, wherein the first preset height is greater than a maximum distance between a bottom wall of the first decorative component and a bottom wall of the first workpiece;
[0012] installing the first decorative component on the bottom of the first workpiece;
[0013] Hoisting the first workpiece to a second preset height, where the second preset height is greater than the maximum distance between the bottom wall of the second decorative component and the bottom wall of the first workpiece;
[0014] The second decoration component is mounted on the bottom of the first workpiece.
[0015] Beneficial effect: Since the second workpiece includes at least the first decorative component and the second decorative component, the portion with a larger distance difference between the bottom wall of the second workpiece and the bottom wall of the first workpiece can be divided, and the portion with a smaller distance difference becomes a whole. Therefore, when hoisting the first workpiece, the hoisting height of the first workpiece can be determined according to the size of each part in the second workpiece, so that the height of the first workpiece corresponds to the size of each part during installation, and the installation is more convenient.
[0016] In an optional embodiment, the second workpiece includes at least a third decorative component, and the maximum distance between the bottom wall of the third decorative component and the bottom wall of the first workpiece is greater than the maximum distance between the bottom wall of the second decorative component and the bottom wall of the first workpiece. Before hoisting the first workpiece to the installation height, the method includes:
[0017] hoisting the first workpiece to a third preset height, wherein the third preset height is greater than a maximum distance between a bottom wall of the third decorative component and a bottom wall of the first workpiece;
[0018] The third decoration component is mounted on the bottom of the first workpiece.
[0019] Beneficial effect: By providing the third decorative component, the aesthetics of the second workpiece can be improved.
[0020] In an optional embodiment, before hoisting the first workpiece to a preset height, the method includes:
[0021] Assemble the first workpiece on the ground.
[0022] Beneficial effect: By assembling the first workpiece on the ground, the assembly is simpler and more secure.
[0023] In an optional embodiment, after assembling the first workpiece on the ground, the method includes:
[0024] hoisting the first workpiece to a specified height, wherein the specified height is greater than the third preset height and less than the installation height;
[0025] Assemble the first decorative component, the second decorative component and the third decorative component on the ground.
[0026] Beneficial effect: By hoisting the first workpiece to a specified height, assembly space for the first decorative component, the second decorative component and the third decorative component can be reserved, and then they can be assembled on the ground below the first workpiece, which can reduce space occupancy and reduce construction costs.
[0027] In an optional embodiment, the cross-sections of the first decorative component, the second decorative component and the third decorative component are all U-shaped. After the first decorative component, the second decorative component and the third decorative component are assembled on the ground, the following steps are included:
[0028] A first support member is installed in the "U"-shaped opening of the first decorative component, a second support member is installed in the "U"-shaped opening of the second decorative component, and a third support member is installed in the "U"-shaped opening of the third decorative component.
[0029] Beneficial effect: By setting the first decorative component, the second decorative component and the third decorative component as a "U"-shaped structure, the lateral force of the wind load on the first workpiece can be reduced; by providing the first support member, the second support member and the third support member, the first decorative component, the second decorative component and the third decorative component can be reinforced, thereby improving the structural strength of the first decorative component, the second decorative component and the third decorative component, and preventing the first decorative component, the second decorative component and the third decorative component from being deformed during the lifting and installation process, thereby affecting the use effect.
[0030] In an optional embodiment, the second workpiece includes a first fixing member and a second fixing member, and before hoisting the first workpiece to a specified height, the process includes:
[0031] The first fixing member is installed on a first side wall of the first workpiece, and the second fixing member is installed on a second side wall opposite to the first side wall.
[0032] Beneficial effect: By setting the first fixing member and the second fixing member, a position for fixed installation can be provided for the first decorative component, the second decorative component and the third decorative component, and the connection is tight and not easy to fall during high-altitude hoisting.
[0033] In an optional embodiment, the first decoration component, the second decoration component and the third decoration component are all installed between the first fixing member and the second fixing member.
[0034] In an optional embodiment, the first decoration component, the second decoration component and the third decoration component are arranged in sequence along the extension length direction of the first workpiece.
[0035] In an optional embodiment, the first decoration component, the second decoration component and the third decoration component are all surrounded by at least two decoration modules.
[0036] Beneficial effect: By enclosing the first decorative component by at least two decorative modules, the weight of the first decorative component can be dispersed, thereby facilitating transportation and lifting; by enclosing the second decorative component by at least two decorative modules, the weight of the second decorative component can be dispersed, thereby facilitating transportation and lifting; by enclosing the third decorative component by at least two decorative modules, the weight of the third decorative component can be dispersed, thereby facilitating transportation and lifting. BRIEF DESCRIPTION OF THE DRAWINGS
[0037] In order to more clearly illustrate the specific implementation methods of the present invention or the technical solutions in the prior art, the drawings required for use in the specific implementation methods or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are some implementation methods of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative work.
[0038] Figure 1 A schematic diagram of the steps of a hoisting method according to an embodiment of the present invention (I);
[0039] Figure 2 for Figure 1 Schematic diagram of the steps of the hoisting method shown (II);
[0040] Figure 3 for Figure 1 Schematic diagram of the steps of the lifting method shown (III);
[0041] Figure 4 for Figure 1 Schematic diagram of the steps of the hoisting method shown (IV);
[0042] Figure 5 for Figure 1 Schematic diagram of the steps of the lifting method shown (V);
[0043] Figure 6 for Figure 1 Schematic diagram of the steps of the lifting method shown (VI);
[0044] Figure 7 for Figure 6 A cross-sectional view of the first workpiece and the second workpiece shown (a);
[0045] Figure 8 for Figure 6 The cross-sectional view (II) of the first workpiece and the second workpiece shown;
[0046] Fig. 9 for Figure 6 The cross-sectional view of the first workpiece and the second workpiece is shown in (iii).
[0047] Description of reference numerals:
[0048] 1. First workpiece; 2. First decorative component; 21. First decorative piece; 22. Second decorative piece; 23. Third decorative piece; 3. Second decorative component; 31. Fourth decorative piece; 32. Fifth decorative piece; 33. Sixth decorative piece; 4. Third decorative component; 41. Seventh decorative piece; 42. Eighth decorative piece; 43. Ninth decorative piece; 5. First fixing piece; 6. Second fixing piece; 7. First supporting piece; 8. Second supporting piece; 9. Third supporting piece. DETAILED DESCRIPTION
[0049] In order to make the purpose, technical solution and advantages of the embodiments of the present invention clearer, the technical solution in the embodiments of the present invention will be clearly and completely described below in conjunction with the drawings in the embodiments of the present invention. Obviously, the described embodiments are part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by those skilled in the art without creative work are within the scope of protection of the present invention.
[0050] Combine the following Figures 1 to 9 , describing an embodiment of the present invention.
[0051] According to an embodiment of the present invention, a hoisting method is provided for hoisting a first workpiece 1, wherein a second workpiece is provided at the bottom of the first workpiece 1, and along a direction of extension length perpendicular to the first workpiece 1, the distances between the bottom walls of the second workpiece and the bottom walls of the first workpiece 1 are different, comprising: hoisting the first workpiece 1 to a preset height, the preset height being greater than the maximum distance between the bottom walls of the second workpiece and the bottom walls of the first workpiece 1; installing the second workpiece at the bottom of the first workpiece 1; hoisting the first workpiece 1 to an installation height, the installation height being greater than the preset height.
[0052] By setting the second workpiece at the bottom of the first workpiece 1 before hoisting the first workpiece 1 to the installation height, the first workpiece 1 and the second workpiece can be hoisted synchronously, thereby reducing the number of high-altitude hoisting times, improving construction efficiency, and reducing the risk of high-altitude operations; by setting the bottom wall of the second workpiece to have a different distance from the bottom wall of the first workpiece 1, the aesthetics of the second workpiece can be improved; by hoisting the first workpiece 1 to a preset height and then installing the second workpiece at the bottom of the first workpiece 1, the second workpiece can be installed in the air to avoid the influence of the shape of the bottom wall of the second workpiece on the installation, and thus there is no need to support the second workpiece, reducing the use of supporting devices during installation, reducing construction costs, and improving construction efficiency.
[0053] In one embodiment, the first workpiece 1 is a corridor, and the second workpiece is a special-shaped curtain wall structure. As a convertible implementation, the first workpiece 1 can also be a connecting beam or other connecting structure, which is not limited here. As a convertible implementation, the second workpiece can also be other types of decorative structures, which are not limited here.
[0054] like Figure 2-Figure 4As shown, in one embodiment, the special-shaped curtain wall structure includes a first decorative component 2 and a second decorative component 3, the maximum distance between the bottom wall of the second decorative component 3 and the bottom wall of the corridor is greater than the maximum distance between the bottom wall of the first decorative component 2 and the bottom wall of the corridor, and the corridor is hoisted to a preset height, and the special-shaped curtain wall structure is installed at the bottom of the corridor, including: hoisting the corridor to a first preset height, the first preset height is greater than the maximum distance between the bottom wall of the first decorative component 2 and the bottom wall of the corridor; installing the first decorative component 2 at the bottom of the corridor; hoisting the corridor to a second preset height, the second preset height is greater than the maximum distance between the bottom wall of the second decorative component 3 and the bottom wall of the corridor; installing the second decorative component 3 at the bottom of the corridor. Specifically, in actual setting, the first preset height can be set to be slightly greater than the maximum distance between the bottom wall of the first decorative component 2 and the bottom wall of the corridor, and the second preset height can be set to be slightly greater than the maximum distance between the bottom wall of the second decorative component 3 and the bottom wall of the corridor. By having the special-shaped curtain wall structure include the first decorative component 2 and the second decorative component 3, the portion with a larger distance difference between the bottom wall of the special-shaped curtain wall structure and the bottom wall of the corridor can be divided, and the portion with a smaller distance difference can be made into a whole, and then when the corridor is hoisted, the hoisting height of the corridor can be determined according to the size of each part in the special-shaped curtain wall structure, so that the height of the corridor corresponds to the size of each part during installation, and the installation is more convenient. As a convertible implementation, it is also possible that when the distance difference between the bottom wall of the special-shaped curtain wall structure and the bottom wall of the corridor is small, the special-shaped curtain wall structure is not divided, that is, the special-shaped curtain wall structure is an integral structure.
[0055] like Figure 5 As shown, the special-shaped curtain wall structure also includes a third decorative component 4, and the maximum distance between the bottom wall of the third decorative component 4 and the bottom wall of the corridor is greater than the maximum distance between the bottom wall of the second decorative component 3 and the bottom wall of the corridor. Before hoisting the corridor to the installation height, it includes: hoisting the corridor to a third preset height, and the third preset height is greater than the maximum distance between the bottom wall of the third decorative component 4 and the bottom wall of the corridor; installing the third decorative component 4 at the bottom of the corridor. Specifically, in actual setting, the third preset height is set to be slightly greater than the maximum distance between the bottom wall of the third decorative component 4 and the bottom wall of the corridor. By setting the third decorative component 4, the aesthetics of the special-shaped curtain wall structure can be improved. As a convertible embodiment, the third decorative component 4 may not be set, or a fourth decorative component may also be set, and no excessive restrictions are made here.
[0056] like Figure 7As shown, in one embodiment, the first decorative component 2 is surrounded by three decorative modules. The first decorative component 2 includes: a first decorative piece 21, which is arranged on the first side wall of the corridor and extends out of the bottom wall of the corridor; a second decorative piece 22, which is arranged on the second side wall opposite to the first side wall and extends out of the bottom wall of the corridor; and a third decorative piece 23, which is arranged between the first decorative piece 21 and the second decorative piece 22. By surrounding the first decorative component 2 with three decorative modules, the weight of the first decorative component 2 can be dispersed, thereby facilitating transportation and hoisting. As a convertible embodiment, the first decorative component 2 can also be surrounded by two or four decorative modules, and there is no excessive restriction here.
[0057] Likewise, if Figure 8 As shown, the second decorative component 3 is surrounded by three decorative modules. The second decorative component 3 includes: a fourth decorative piece 31, which is arranged on the first side wall of the corridor and extends out of the bottom wall of the corridor; a fifth decorative piece 32, which is arranged on the second side wall opposite to the first side wall and extends out of the bottom wall of the corridor; and a sixth decorative piece 33, which is arranged between the fourth decorative piece 31 and the fifth decorative piece 32. By surrounding the second decorative component 3 with three decorative modules, the weight of the second decorative component 3 can be dispersed, thereby facilitating transportation and hoisting. As a convertible embodiment, the second decorative component 3 can also be surrounded by two or four decorative modules, and there is no excessive restriction here.
[0058] like Fig. 9 As shown, the third decorative component 4 is surrounded by three decorative modules. Among them, the third decorative component 4 includes: a seventh decorative piece 41, which is arranged on the first side wall of the corridor and extends out of the bottom wall of the corridor; an eighth decorative piece 42, which is arranged on the second side wall opposite to the first side wall and extends out of the bottom wall of the corridor; and a ninth decorative piece 43, which is arranged between the seventh decorative piece 41 and the eighth decorative piece 42. By surrounding the third decorative component 4 with three decorative modules, the weight of the third decorative component 4 can be dispersed, thereby facilitating transportation and hoisting. As a convertible embodiment, the third decorative component 4 can also be surrounded by two or four decorative modules, and there is no excessive restriction here.
[0059] like Figure 6As shown, in one embodiment, along the extension length direction of the corridor, the first decorative component 2, the second decorative component 3 and the third decorative component 4 are arranged in sequence. Furthermore, the bottom walls of the first decorative component 2, the second decorative component 3 and the third decorative component 4 are arranged in a generally inclined straight line as a whole. As a convertible embodiment, the second decorative component 3, the first decorative component 2 and the third decorative component 4 may also be arranged in sequence, or the first decorative component 2, the third decorative component 4 and the second decorative component 3 may be arranged in sequence, without making too many restrictions here. As a convertible embodiment, the bottom walls of the first decorative component 2, the second decorative component 3 and the third decorative component 4 may also be arranged in an inclined arc or other curve as a whole, without making too many restrictions here.
[0060] like Figure 1 As shown, in one embodiment, before hoisting the corridor to a preset height, the method includes: assembling the corridor on the ground. Specifically, a support frame is set up on the ground, and the corridor is assembled on the support frame. By assembling the corridor on the ground, the assembly is simpler and more secure. As a convertible implementation, the corridor can also be assembled in the air, so that the support frame does not need to be used, and there is no excessive restriction here.
[0061] In one embodiment, after assembling the corridor on the ground, the following steps are included: hoisting the corridor to a specified height, the specified height being greater than the third preset height and less than the installation height; and assembling the first decorative component 2, the second decorative component 3, and the third decorative component 4 on the ground. In actual setting, the specified height can be set to be slightly greater than the third preset height, that is, the specified height can be sufficient as long as it can meet the requirements of assembling the first decorative component 2, the second decorative component 3, and the third decorative component 4 below the corridor. By hoisting the corridor to the specified height, it is possible to reserve space for assembling the first decorative component 2, the second decorative component 3, and the third decorative component 4, so that they can be assembled on the ground below the corridor, which can reduce space occupation and construction costs. As a convertible implementation, it is also possible to assemble the first decorative component 2, the second decorative component 3, and the third decorative component 4 at a position away from the ground below the corridor, so that it is not necessary to hoist the corridor to the specified height and then assemble the first decorative component 2, the second decorative component 3, and the third decorative component 4 on the ground.
[0062] like Figure 1 , Figure 7-Figure 9As shown, in one embodiment, the special-shaped curtain wall structure includes a first fixing member 5 and a second fixing member 6. Before hoisting the corridor to a specified height, the structure includes: installing the first fixing member 5 on the first side wall of the corridor, and installing the second fixing member 6 on the second side wall opposite to the first side wall. Furthermore, the first decorative component 2, the second decorative component 3 and the third decorative component 4 are all installed between the first fixing member 5 and the second fixing member 6. Among them, the first fixing member 5 and the second fixing member 6 are both steel structures. By providing the first fixing member 5 and the second fixing member 6, a position for fixed installation can be provided for the first decorative component 2, the second decorative component 3 and the third decorative component 4, and the connection is tight and not easy to fall during high-altitude hoisting. As a convertible embodiment, it can also be that a special installation position is provided on the corridor, and the first fixing member 5 and the second fixing member 6 do not need to be provided.
[0063] like Figure 7-Figure 9 As shown, in one embodiment, the cross-sections of the first decorative component 2, the second decorative component 3 and the third decorative component 4 are all "U"-shaped. After the first decorative component 2, the second decorative component 3 and the third decorative component 4 are assembled on the ground, the following steps are included: installing the first support member 7 in the "U"-shaped opening of the first decorative component 2, installing the second support member 8 in the "U"-shaped opening of the second decorative component 3, and installing the third support member 9 in the "U"-shaped opening of the third decorative component 4. Among them, the first decorative component 2, the second decorative component 3 and the third decorative component 4 are all flexible sheet trusses, and the first support member 7, the second support member 8 and the third support member 9 are all truss structures; the first support member 7 is arranged between the bottom of the corridor and the first decorative component 2, the second support member 8 is arranged between the bottom of the corridor and the second decorative component 3, and the third support member 9 is arranged between the bottom of the corridor and the third decorative component 4. By setting the first decorative component 2, the second decorative component 3 and the third decorative component 4 as a "U"-shaped structure, the lateral force of the wind load on the corridor can be reduced; by setting the first support member 7, the second support member 8 and the third support member 9, the first decorative component 2, the second decorative component 3 and the third decorative component 4 can be reinforced, thereby improving the structural strength of the first decorative component 2, the second decorative component 3 and the third decorative component 4, and preventing the first decorative component 2, the second decorative component 3 and the third decorative component 4 from being deformed during the hoisting and installation process, thereby affecting the use effect. As a convertible embodiment, the cross-section of the first decorative component 2, the second decorative component 3 and the third decorative component 4 can also be "V"-shaped, or other shapes, without making too many restrictions here.
[0064] After hoisting the corridor to the installation height, the following steps are performed: connecting and fixing the corridor to the towers on both sides.
[0065] Although the embodiments of the present invention have been described in conjunction with the accompanying drawings, those skilled in the art may make various modifications and variations without departing from the spirit and scope of the present invention, and such modifications and variations are all within the scope defined by the appended claims.
Claims
1. A method for hoisting a first workpiece (1), wherein: A second workpiece is provided at the bottom of the first workpiece (1), and along a direction perpendicular to the extension length of the first workpiece (1), the distance between the bottom wall of the second workpiece and the bottom wall of the first workpiece (1) is different, and the invention is characterized in that: hoisting the first workpiece (1) to a preset height, wherein the preset height is greater than the maximum distance between the bottom wall of the second workpiece and the bottom wall of the first workpiece (1); Installing the second workpiece on the bottom of the first workpiece (1); The first workpiece (1) is hoisted to an installation height, wherein the installation height is greater than the preset height.
2. The hoisting method according to claim 1, characterized in that: The second workpiece comprises at least a first decorative component (2) and a second decorative component (3), the maximum distance between the bottom wall of the second decorative component (3) and the bottom wall of the first workpiece (1) is greater than the maximum distance between the bottom wall of the first decorative component (2) and the bottom wall of the first workpiece (1), and the first workpiece (1) is hoisted to a preset height and the second workpiece is installed on the bottom of the first workpiece (1), comprising: hoisting the first workpiece (1) to a first preset height, wherein the first preset height is greater than the maximum distance between the bottom wall of the first decorative component (2) and the bottom wall of the first workpiece (1); Installing the first decorative component (2) on the bottom of the first workpiece (1); hoisting the first workpiece (1) to a second preset height, wherein the second preset height is greater than the maximum distance between the bottom wall of the second decorative component (3) and the bottom wall of the first workpiece (1); The second decorative component (3) is mounted on the bottom of the first workpiece (1).
3. The hoisting method according to claim 2, characterized in that: The second workpiece at least comprises a third decorative component (4), the maximum distance between the bottom wall of the third decorative component (4) and the bottom wall of the first workpiece (1) being greater than the maximum distance between the bottom wall of the second decorative component (3) and the bottom wall of the first workpiece (1), and before hoisting the first workpiece (1) to the installation height, comprising: hoisting the first workpiece (1) to a third preset height, wherein the third preset height is greater than the maximum distance between the bottom wall of the third decorative component (4) and the bottom wall of the first workpiece (1); The third decorative component (4) is mounted on the bottom of the first workpiece (1).
4. The hoisting method according to claim 3, characterized in that: Before hoisting the first workpiece (1) to a preset height, the method comprises: Assembling the first workpiece (1) on the ground.
5. The hoisting method according to claim 4, characterized in that: After assembling the first workpiece (1) on the ground, the method comprises: hoisting the first workpiece (1) to a specified height, wherein the specified height is greater than the third preset height and less than the installation height; The first decorative component (2), the second decorative component (3) and the third decorative component (4) are assembled on the ground.
6. The hoisting method according to claim 5, characterized in that: The cross-sections of the first decorative component (2), the second decorative component (3) and the third decorative component (4) are all U-shaped. After the first decorative component (2), the second decorative component (3) and the third decorative component (4) are assembled on the ground, they include: A first support member (7) is installed in the "U"-shaped opening of the first decorative component (2), a second support member (8) is installed in the "U"-shaped opening of the second decorative component (3), and a third support member (9) is installed in the "U"-shaped opening of the third decorative component (4).
7. The hoisting method according to claim 6, characterized in that: The second workpiece comprises a first fixing member (5) and a second fixing member (6), and before the first workpiece (1) is hoisted to a specified height, comprises: The first fixing member (5) is mounted on a first side wall of the first workpiece (1), and the second fixing member (6) is mounted on a second side wall opposite to the first side wall.
8. The hoisting method according to claim 7, characterized in that: The first decorative component (2), the second decorative component (3) and the third decorative component (4) are all installed between the first fixing member (5) and the second fixing member (6).
9. The hoisting method according to any one of claims 3 to 8, characterized in that: Along the extending length direction of the first workpiece (1), the first decorative component (2), the second decorative component (3) and the third decorative component (4) are arranged in sequence.
10. The hoisting method according to any one of claims 3 to 8, characterized in that: The first decorative component (2), the second decorative component (3) and the third decorative component (4) are all surrounded by at least two decorative modules.