Overhaul performance evaluation method and device
By setting performance indicators and calculation rules for nuclear power plant overhauls, and collecting and calculating performance information in real time, the problem of excessive qualitative evaluation, insufficient quantitative evaluation, and low efficiency in the performance evaluation of nuclear power plant overhauls has been solved, and real-time display and timely evaluation of overhaul performance have been achieved.
Patent Information
- Application Number
- CN202411239433.2
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-09-05
- Publication Date
- 2025-01-10
AI Technical Summary
The performance evaluation of nuclear power plant overhauls suffers from problems such as a predominance of qualitative evaluations and a lack of quantitative evaluations, low correlation between overhaul performance targets and key positions and departments, and low timeliness and efficiency. This results in unclear management responsibilities and an inability to trace back to personnel and departments in a timely manner.
Set overhaul performance indicators and calculation rules, collect and calculate performance information in real time, realize real-time and final calculation of overhaul performance, and link performance results with positions and departments. The data processing, display and sending modules are used for real-time display and sending.
This enabled quantitative evaluation of overhaul performance, improved evaluation efficiency and timeliness, clarified management responsibilities, and ensured that all departments were informed of performance results in a timely manner.
Smart Images

Figure CN119294882A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of nuclear power plant overhaul performance evaluation, and in particular to an overhaul performance evaluation method and device. Background Art
[0002] Nuclear power plant overhaul is an important part of the production activities of nuclear power plants. It is necessary to complete the planned work within a certain time while meeting various requirements of safety, quality, progress and cost. It has the characteristics of tight time, heavy tasks, complex interfaces and strong planning.
[0003] At present, the overhaul performance evaluation has the following problems:
[0004] 1. More qualitative evaluation and less quantitative evaluation;
[0005] 2. The overhaul performance targets are not highly correlated with the main positions and departments of the overhaul. When indicators are exceeded, the management responsibilities are not clear and cannot be accurately traced back to personnel and departments;
[0006] 3. The overhaul performance evaluation is manually counted and verified and given 4 months after the overhaul, which is time-sensitive, inefficient and has a poor transparency mechanism. Departments and personnel cannot know the overhaul performance evaluation results in a timely manner and do not understand the overhaul performance appraisal items. Summary of the invention
[0007] One of the purposes of the present invention is to provide an overhaul performance evaluation method and device to solve the problem of more qualitative evaluation and less quantitative evaluation in the existing overhaul performance evaluation, and to realize quantitative evaluation of overhaul performance evaluation.
[0008] The second purpose of the present invention is to provide an overhaul performance evaluation method and device to solve the problem of low correlation between overhaul performance targets and major overhaul positions and departments in existing overhaul performance evaluation, and to achieve correlation between overhaul performance targets and major overhaul positions and departments.
[0009] The third purpose of the present invention is to provide a method and device for overhaul performance evaluation to solve the problems of low efficiency and poor timeliness of existing overhaul performance evaluation, realize automatic evaluation and display of overhaul performance, and improve the efficiency and timeliness of overhaul performance evaluation.
[0010] In order to solve the above problems, the present invention provides an overhaul performance evaluation method, comprising the following steps:
[0011] Step 101, setting overhaul performance indicators and overhaul performance calculation rules;
[0012] Step 102, associating the overhaul performance indicators with the overhaul positions and the overhaul departments respectively;
[0013] Step 103: collect the overhaul performance indicator completion information in real time, calculate the overhaul performance in real time according to the overhaul performance calculation rules, obtain the overhaul real-time performance calculation results and display them in real time;
[0014] Step 104: After the overhaul is completed, the final overhaul performance calculation is performed according to the overhaul performance calculation rules, and the final overhaul performance calculation result is obtained and displayed;
[0015] Step 105: Send the final overhaul performance calculation results to the overhaul positions and departments.
[0016] As one of the feasible ways, the overhaul performance indicators include the overall overhaul performance indicators, the overhaul position performance indicators and the overhaul department performance indicators, and the overhaul performance calculation rules include the overall overhaul performance calculation rules, the overhaul position performance calculation rules and the overhaul department performance calculation rules.
[0017] As one of the feasible methods, the calculation rule of the overall performance of overhaul is: the overall performance score of overhaul = the sum of the scores of the overall performance indicators of overhaul;
[0018] Among them, the overhaul overall performance index score = (actual number of stars of the overhaul overall performance index / optimal number of stars of the overhaul overall performance index) × the overhaul overall performance index target score;
[0019] The overhaul performance indicator completion information includes the actual number of stars for each overall performance indicator of the overhaul.
[0020] As one of the possible ways to achieve this, the overhaul position includes the overhaul executive command position and the overhaul department executive command position;
[0021] The calculation rule for the performance of the overhaul executive command position is: the performance score of the overhaul executive command position = the average performance score of each overhaul department;
[0022] The calculation rule for the performance of the overhaul department executive command position is: overhaul department executive command position performance score = overhaul department performance score.
[0023] As one of the achievable ways, the overhaul position also includes the overhaul manager position; the overhaul position performance indicators include the overhaul management indicators of the overhaul manager position;
[0024] The calculation rule for the overhaul manager's job performance is as follows: Overhaul manager's job performance score = average performance score of each overhaul department + overhaul management index score of the overhaul manager's job;
[0025] Among them, the overhaul management index score of the overhaul manager position = the overhaul management index target score of the overhaul manager position - the overhaul management index reduction score of the overhaul manager position;
[0026] Deduction of overhaul management index for overhaul manager position = the sum of deductions corresponding to each deduction item of overhaul management index for overhaul manager position;
[0027] The overhaul performance index completion information includes the various deduction items of the overhaul management index of the overhaul manager position; the lowest overhaul management index score of the overhaul manager position is 0.
[0028] As one of the achievable methods, the overhaul position also includes the overhaul department manager position; the overhaul position performance indicators also include the overhaul department manager position performance indicators;
[0029] The calculation rule for the overhaul department manager's job performance is: the overhaul department manager's job performance score = the sum of the overhaul department manager's job performance index scores;
[0030] Among them, the overhaul department manager's job performance index score = the overhaul department manager's job performance index target score + the overhaul department manager's job performance index bonus score - the overhaul department manager's job performance index deduction score; the overhaul department manager's job performance index plus or minus score = the sum of the corresponding plus or minus scores of each plus or minus score item of the overhaul department manager's job performance index;
[0031] The overhaul performance index completion information includes the various addition and subtraction items of the overhaul department manager's job performance index; the minimum score for the overhaul department manager's job performance index is 0.
[0032] As one of the feasible methods, the calculation rule of overhaul department performance is: overhaul department performance score = the sum of the scores of each performance indicator of the overhaul department;
[0033] Among them, the overhaul department performance index score = the overhaul department performance index target score + the overhaul department performance index bonus score - the overhaul department performance index deduction score; the overhaul department performance index plus or minus score = the sum of the corresponding plus or minus scores of each plus or minus score item of the overhaul department performance index;
[0034] The overhaul performance index completion information includes the various addition and subtraction items of the overhaul department performance index; the lowest overhaul department performance index score is 0.
[0035] As one of the feasible ways, the expected values of the overall overhaul performance score, overhaul position performance score and overhaul department performance score are set respectively;
[0036] When the overall overhaul performance score, overhaul position performance score or overhaul department performance score is lower than the expected value, it will be clearly marked.
[0037] As one of the feasible ways, the final overhaul performance calculation result is sent to the overhaul position and overhaul department via email.
[0038] In order to solve the above problems, the present invention provides an overhaul performance evaluation device, comprising:
[0039] The data processing module is used to set the overhaul performance index and overhaul performance calculation rules; perform overhaul performance real-time calculation according to the overhaul performance calculation rules to obtain the overhaul real-time performance calculation results; after the overhaul is completed, perform the overhaul final performance calculation according to the overhaul performance calculation rules to obtain the overhaul final performance calculation results;
[0040] The data association module is used to associate the overhaul performance indicators with the overhaul positions and overhaul departments respectively; collect the overhaul performance indicator completion information in real time;
[0041] Data display module, used to display the real-time performance calculation results of overhaul and the final performance calculation results of overhaul;
[0042] The data sending module is used to send the final overhaul performance calculation results to the overhaul position and overhaul department.
[0043] Beneficial technical effects of the present invention:
[0044] The overhaul performance evaluation method and device of the present invention set overhaul performance indicators and overhaul performance calculation rules, and associate the overhaul performance indicators with overhaul positions and overhaul departments respectively, thereby realizing real-time calculation of overhaul performance and displaying and sending overhaul performance calculation results to overhaul positions and overhaul departments in real time, thereby improving the efficiency and timeliness of overhaul performance evaluation. BRIEF DESCRIPTION OF THE DRAWINGS
[0045] Figure 1 A flowchart of an embodiment of the overhaul performance evaluation method of the present invention;
[0046] Figure 2 It is a schematic structural view of an embodiment of the overhaul performance evaluation device of the present invention. DETAILED DESCRIPTION
[0047] Unless otherwise defined, all technical and scientific terms used herein have the same meaning as commonly understood by technicians in the technical field to which this application belongs; the terms used in the specification of the application are only for the purpose of describing specific embodiments and are not intended to limit this application; the terms "including" and "having" and any variations thereof in the specification and claims of this application and the above-mentioned figure descriptions are intended to cover non-exclusive inclusions.
[0048] Reference to "embodiments" herein means that a particular feature, structure, or characteristic described in conjunction with the embodiments may be included in at least one embodiment of the present application. The appearance of the phrase in various locations in the specification does not necessarily refer to the same embodiment, nor is it an independent or alternative embodiment that is mutually exclusive with other embodiments. It is explicitly and implicitly understood by those skilled in the art that the embodiments described herein may be combined with other embodiments.
[0049] The technical solution of the present invention is clearly and completely described below in conjunction with the accompanying drawings and specific embodiments.
[0050] refer to Figure 1 , a flow chart of an embodiment of an overhaul performance evaluation method is shown, the overhaul performance evaluation method comprising the following steps:
[0051] Step 101, setting overhaul performance indicators and overhaul performance calculation rules;
[0052] Step 102, associating the overhaul performance indicators with the overhaul positions and the overhaul departments respectively;
[0053] Step 103: collect the overhaul performance indicator completion information in real time, calculate the overhaul performance in real time according to the overhaul performance calculation rules, obtain the overhaul real-time performance calculation results and display them in real time;
[0054] Step 104: After the overhaul is completed, the final overhaul performance calculation is performed according to the overhaul performance calculation rules, and the final overhaul performance calculation result is obtained and displayed;
[0055] Step 105: Send the final overhaul performance calculation result to the overhaul position and overhaul department.
[0056] In this embodiment, as one of the achievable methods, the overhaul performance indicators include overhaul overall performance indicators, overhaul position performance indicators and overhaul department performance indicators, and the overhaul performance calculation rules include overhaul overall performance calculation rules, overhaul position performance calculation rules and overhaul department performance calculation rules; the overhaul performance indicators and overhaul performance calculation rules support modification.
[0057] In this embodiment, as one of the achievable methods, the overall overhaul performance index includes an overhaul safety performance index, an overhaul quality performance index, an overhaul progress performance index, and an overhaul cost performance index;
[0058] The calculation rule for the overall performance of overhaul is: Overall performance score of overhaul = overhaul safety performance index score + overhaul quality performance index score + overhaul progress performance index score + overhaul cost performance index score;
[0059] Among them, the overhaul safety performance index score = (actual number of stars of overhaul safety performance index / best number of stars of overhaul safety performance index) × target score of overhaul safety performance index; the overhaul safety performance index is composed of multiple safety performance indicators, and each safety performance indicator is set with a star standard and a weight according to its importance. The actual number of stars of the overhaul safety performance index = ∑ (actual number of stars of each safety performance indicator × weight of each safety performance indicator), and the best number of stars of the overhaul safety performance index = ∑ (best number of stars of each safety performance indicator × weight of each safety performance indicator);
[0060] Overhaul quality performance index score = (actual number of stars of overhaul quality performance index / best number of stars of overhaul quality performance index) × target score of overhaul quality performance index; overhaul quality performance index consists of multiple quality performance indicators, each of which has a star rating and a weight according to its importance. Actual number of stars of overhaul quality performance index = ∑ (actual number of stars of each quality performance indicator × weight of each quality performance indicator), best number of stars of overhaul quality performance index = ∑ (best number of stars of each quality performance indicator × weight of each quality performance indicator);
[0061] Overhaul progress performance index score = (actual number of stars of overhaul progress performance index / optimal number of stars of overhaul progress performance index) × target number of overhaul progress performance index; the overhaul progress performance index is composed of multiple progress performance indicators, each of which has a star rating and a weight according to its importance, the actual number of stars of the overhaul progress performance index = ∑ (actual number of stars of each progress performance indicator × weight of each progress performance indicator), the optimal number of stars of the overhaul progress performance index = ∑ (optimal number of stars of each progress performance indicator × weight of each progress performance indicator);
[0062] Overhaul cost performance index score = (actual number of stars of overhaul cost performance index / optimal number of stars of overhaul cost performance index) × target score of overhaul cost performance index; the overhaul cost performance index is composed of multiple cost performance indicators, each of which has a star rating and a weight according to its importance. Actual number of stars of overhaul cost performance index = ∑ (actual number of stars of each cost performance indicator × weight of each cost performance indicator), optimal number of stars of overhaul cost performance index = ∑ (optimal number of stars of each cost performance indicator × weight of each cost performance indicator);
[0063] The overhaul performance indicator completion information includes the actual number of stars of each overall performance indicator of the overhaul; the target points of each overall performance indicator of the overhaul are obtained through setting.
[0064] In this embodiment, as one of the achievable methods, the overhaul safety performance index target is divided into 40 points, the overhaul quality performance index target is divided into 30 points, the overhaul progress performance index target is divided into 20 points, and the overhaul cost performance index target is divided into 10 points; there are 21 overhaul safety performance indicators, 6 overhaul quality performance indicators, 6 overhaul progress performance indicators, and 2 overhaul cost performance indicators; the star standard of the indicator is set according to the peer excellence value of the indicator, including 1 star, 2 stars and 3 stars.
[0065] In this embodiment, as one of the achievable methods, the overhaul post includes an overhaul execution command post and an overhaul department execution command post;
[0066] The calculation rule for the performance of the overhaul executive command position is: the performance score of the overhaul executive command position = the average performance score of each overhaul department;
[0067] The calculation rule for the performance of the overhaul department executive command position is: overhaul department executive command position performance score = overhaul department performance score.
[0068] In this embodiment, as one of the feasible ways, the overhaul department executive command post includes the overhaul operation department executive command post, the overhaul maintenance department executive command post, the overhaul technology department executive command post and the overhaul safety and quality department executive command post.
[0069] In this embodiment, as one of the achievable methods, the overhaul position also includes an overhaul manager position; the overhaul position performance index includes an overhaul management index of the overhaul manager position;
[0070] The calculation rule for the overhaul manager's job performance is as follows: Overhaul manager's job performance score = average performance score of each overhaul department + overhaul management index score of the overhaul manager's job;
[0071] Among them, the overhaul management index score of the overhaul manager position = the target score of the overhaul management index of the overhaul manager position - the overhaul management index deduction score of the overhaul manager position; the overhaul management index deduction score of the overhaul manager position = the sum of the deduction scores corresponding to each deduction item of the overhaul management index of the overhaul manager position;
[0072] Each deduction item of the overhaul management indicator of the overhaul manager position and the corresponding deduction points of each deduction item are obtained through setting, and the target score of the overhaul management indicator of the overhaul manager position is obtained through setting; the overhaul performance indicator completion information includes each deduction item of the overhaul management indicator of the overhaul manager position; the lowest score of the overhaul management indicator of the overhaul manager position is 0.
[0073] In this embodiment, as one of the achievable methods, the overhaul management goal of the overhaul manager position is divided into 10 points;
[0074] The deduction items of the overhaul management indicators of the overhaul manager position and the corresponding deduction points for each deduction item include: personal injury accidents involving serious injuries or above, deduction of 10 points; level 1 and above operation incidents, deduction of 10 points; fire accidents, deduction of 10 points; general and above radiation accidents, deduction of 5 points for each incident; unplanned exposure incidents, deduction of 1 point for each incident; minor injuries to personnel, deduction of 3 points for each incident; if the comprehensive overhaul and maintenance quality indicators do not meet the standards, deduction of 5 points; due to poor planning and control, the delay of non-critical path projects becomes a critical path and the delay is >8 hours, deduction of 10 points.
[0075] In this embodiment, as one of the achievable methods, the overhaul position also includes the overhaul department manager position; the overhaul position performance index also includes the overhaul department manager position performance index;
[0076] The calculation rule for the overhaul department manager's job performance is: the overhaul department manager's job performance score = the sum of the overhaul department manager's job performance index scores;
[0077] Among them, the overhaul department manager's job performance index score = the overhaul department manager's job performance index target score + the overhaul department manager's job performance index bonus score - the overhaul department manager's job performance index deduction score; the overhaul department manager's job performance index plus or minus score = the sum of the corresponding plus or minus scores of each plus or minus score item of the overhaul department manager's job performance index;
[0078] Each plus or minus item of the overhaul department manager's job performance indicator and the corresponding plus or minus points of each plus or minus item are obtained through setting, and the target score of the overhaul department manager's job performance indicator is obtained through setting; the overhaul performance indicator completion information includes each plus or minus item of the overhaul department manager's job performance indicator; the minimum score of the overhaul department manager's job performance indicator is 0.
[0079] In this embodiment, as one of the achievable methods, the overhaul department manager position includes the overhaul operation manager position; the overhaul operation manager position performance indicators include the overhaul preparation indicator, overhaul risk identification and control indicator, overhaul implementation safety and quality indicator and overhaul management indicator of the overhaul operation manager position;
[0080] The calculation rule for the overhaul operation manager's job performance is as follows: Overhaul operation manager's job performance score = Overhaul operation manager's job overhaul preparation index score + Overhaul operation manager's job overhaul risk identification and control index score + Overhaul operation manager's job overhaul implementation safety and quality index score + Overhaul operation manager's job overhaul management index score;
[0081] Among them, the overhaul preparation index score of the overhaul operation manager position = the overhaul preparation index target score of the overhaul operation manager position - the overhaul preparation index deduction score of the overhaul operation manager position; the overhaul preparation index deduction score of the overhaul operation manager position = the sum of the deduction scores of each deduction item of the overhaul preparation index of the overhaul operation manager position; the minimum overhaul preparation index score of the overhaul operation manager position is 0;
[0082] Overhaul risk identification and control index score for overhaul operation manager position = target score for overhaul risk identification and control index for overhaul operation manager position - deduction score for overhaul risk identification and control index for overhaul operation manager position; deduction score for overhaul risk identification and control index for overhaul operation manager position = the sum of deduction scores corresponding to each deduction item of overhaul risk identification and control index for overhaul operation manager position; the lowest score for overhaul risk identification and control index for overhaul operation manager position is 0;
[0083] The score of the safety and quality index for overhaul implementation at the overhaul operation manager position = the target score of the safety and quality index for overhaul implementation at the overhaul operation manager position - the deduction score of the safety and quality index for overhaul implementation at the overhaul operation manager position + the addition score of the safety and quality index for overhaul implementation at the overhaul operation manager position; the addition and subtraction score of the safety and quality index for overhaul implementation at the overhaul operation manager position = the sum of the corresponding addition and subtraction scores of each addition and subtraction item of the safety and quality index for overhaul implementation at the overhaul operation manager position; the minimum score of the safety and quality index for overhaul implementation at the overhaul operation manager position is 0;
[0084] Overhaul management index score for overhaul operation manager position = target score for overhaul management index for overhaul operation manager position - deduction score for overhaul management index for overhaul operation manager position; deduction score for overhaul management index for overhaul operation manager position = sum of deduction scores for each deduction item of overhaul management index for overhaul operation manager position; the lowest overhaul management index score for overhaul operation manager position is 0;
[0085] Each plus or minus item of the overhaul operation manager's job performance indicator and the corresponding plus or minus points of each plus or minus item are obtained through setting, and the target score of the overhaul operation manager's job performance indicator is obtained through setting; the overhaul performance indicator completion information includes each plus or minus item of the overhaul operation manager's job performance indicator; the minimum score of the overhaul operation manager's job performance indicator is 0.
[0086] In this embodiment, as one of the achievable methods, the overhaul department manager position also includes the overhaul plan manager position; the overhaul plan manager position performance indicators include the overhaul preparation indicator, overhaul risk identification and control indicator, overhaul plan control indicator and overhaul management indicator of the overhaul plan manager position;
[0087] The calculation rule for the overhaul planning manager's job performance is as follows: Overhaul planning manager's job performance score = Overhaul planning manager's job overhaul preparation index score + Overhaul planning manager's job overhaul risk identification and control index score + Overhaul planning manager's job overhaul plan control index score + Overhaul planning manager's job overhaul management index score;
[0088] Among them, the overhaul preparation index score of the overhaul planning manager position = the overhaul preparation index target score of the overhaul planning manager position - the overhaul preparation index deduction score of the overhaul planning manager position; the overhaul preparation index deduction score of the overhaul planning manager position = the sum of the deduction scores of each deduction item of the overhaul preparation index of the overhaul planning manager position; the minimum overhaul preparation index score of the overhaul planning manager position is 0;
[0089] Overhaul risk identification and control index score for the overhaul planning manager position = Overhaul risk identification and control index target score for the overhaul planning manager position - Overhaul risk identification and control index deduction score for the overhaul planning manager position; Overhaul risk identification and control index deduction score for the overhaul planning manager position = the sum of deduction scores corresponding to each deduction item of the overhaul risk identification and control index for the overhaul planning manager position; The minimum overhaul risk identification and control index score for the overhaul planning manager position is 0;
[0090] Overhaul plan control index score for the overhaul plan manager position = Overhaul plan control index target score for the overhaul plan manager position - Overhaul plan control index deduction score for the overhaul plan manager position + Overhaul plan control index addition score for the overhaul plan manager position; Overhaul plan control index addition and subtraction score for the overhaul plan manager position = The sum of the corresponding addition and subtraction scores for each addition and subtraction item of the overhaul plan control index for the overhaul plan manager position; The minimum overhaul plan control index score for the overhaul plan manager position is 0;
[0091] Overhaul planning manager position overhaul management index score = overhaul planning manager position overhaul management index target score - overhaul planning manager position overhaul management index deduction score; overhaul planning manager position overhaul management index deduction score = the sum of the deduction points corresponding to each deduction item of the overhaul planning manager position overhaul management index; the minimum overhaul planning manager position overhaul management index score is 0;
[0092] Each plus or minus item of the overhaul planning manager's job performance indicator and the corresponding plus or minus points of each plus or minus item are obtained through setting, and the target score of the overhaul planning manager's job performance indicator is obtained through setting; the overhaul performance indicator completion information includes each plus or minus item of the overhaul planning manager's job performance indicator; the minimum score of the overhaul planning manager's job performance indicator is 0.
[0093] In this embodiment, as one of the achievable methods, the overhaul department manager position also includes the overhaul nuclear island manager position; the overhaul nuclear island manager position performance indicators include the overhaul preparation indicator, overhaul risk identification and control indicator, overhaul plan control indicator and overhaul management indicator of the overhaul nuclear island manager position;
[0094] The calculation rule for the overhaul nuclear island manager's job performance is as follows: Overhaul nuclear island manager's job performance score = Overhaul nuclear island manager's job overhaul preparation index score + Overhaul nuclear island manager's job overhaul risk identification and control index score + Overhaul nuclear island manager's job overhaul plan control index score + Overhaul nuclear island manager's job overhaul management index score;
[0095] Among them, the overhaul preparation index score of the overhaul nuclear island manager position = the overhaul preparation index target score of the overhaul nuclear island manager position - the overhaul preparation index deduction score of the overhaul nuclear island manager position; the overhaul preparation index deduction score of the overhaul nuclear island manager position = the sum of the deduction scores corresponding to each deduction item of the overhaul preparation index of the overhaul nuclear island manager position; the minimum overhaul preparation index score of the overhaul nuclear island manager position is 0;
[0096] Overhaul risk identification and control index score for overhaul nuclear island manager position = target score for overhaul risk identification and control index for overhaul nuclear island manager position - deduction score for overhaul risk identification and control index for overhaul nuclear island manager position; deduction score for overhaul risk identification and control index for overhaul nuclear island manager position = the sum of deduction scores corresponding to each deduction item of overhaul risk identification and control index for overhaul nuclear island manager position; the lowest score for overhaul risk identification and control index for overhaul nuclear island manager position is 0;
[0097] Overhaul plan control index score for overhaul nuclear island manager position = target score for overhaul plan control index for overhaul nuclear island manager position - deduction score for overhaul plan control index for overhaul nuclear island manager position + addition score for overhaul plan control index for overhaul nuclear island manager position; addition and subtraction score for overhaul plan control index for overhaul nuclear island manager position = the sum of the corresponding addition and subtraction scores for each addition and subtraction item of overhaul plan control index for overhaul nuclear island manager position; the minimum score for overhaul plan control index for overhaul nuclear island manager position is 0;
[0098] Overhaul management index score for overhaul nuclear island manager position = target score for overhaul management index for overhaul nuclear island manager position - deduction score for overhaul management index for overhaul nuclear island manager position; deduction score for overhaul management index for overhaul nuclear island manager position = sum of deduction scores for each deduction item of overhaul management index for overhaul nuclear island manager position; the lowest overhaul management index score for overhaul nuclear island manager position is 0;
[0099] Each plus or minus item of the overhaul nuclear island manager's job performance indicator and the corresponding plus or minus points of each plus or minus item are obtained through setting, and the target score of the overhaul nuclear island manager's job performance indicator is obtained through setting; the overhaul performance indicator completion information includes each plus or minus item of the overhaul nuclear island manager's job performance indicator; the minimum score of the overhaul nuclear island manager's job performance indicator is 0.
[0100] In this embodiment, as one of the achievable methods, the overhaul department manager position also includes the overhaul conventional island manager position; the overhaul conventional island manager position performance indicators include the overhaul preparation indicator, overhaul risk identification and control indicator, overhaul plan control indicator and overhaul management indicator of the overhaul conventional island manager position;
[0101] The calculation rule of the overhaul routine island manager's job performance is as follows: Overhaul routine island manager's job performance score = Overhaul routine island manager's job overhaul preparation index score + Overhaul routine island manager's job overhaul risk identification and control index score + Overhaul routine island manager's job overhaul plan control index score + Overhaul routine island manager's job overhaul management index score;
[0102] Among them, the overhaul preparation index score of the overhaul conventional island manager position = the overhaul preparation index target score of the overhaul conventional island manager position - the overhaul preparation index deduction score of the overhaul conventional island manager position; the overhaul preparation index deduction score of the overhaul conventional island manager position = the sum of the deduction scores of each deduction item of the overhaul preparation index of the overhaul conventional manager position; the minimum overhaul preparation index score of the overhaul conventional island manager position is 0;
[0103] Overhaul General Island Manager's Overhaul Risk Identification and Control Index Score = Overhaul General Island Manager's Overhaul Risk Identification and Control Index Target Score - Overhaul General Island Manager's Overhaul Risk Identification and Control Index Deduction Score; Overhaul General Island Manager's Overhaul Risk Identification and Control Index Deduction Score = The sum of the corresponding deduction points for each deduction item of the Overhaul Risk Identification and Control Index of the Overhaul General Island Manager's Overhaul; The lowest score for the Overhaul Risk Identification and Control Index of the Overhaul General Island Manager is 0;
[0104] Overhaul conventional island manager position overhaul plan control index score = Overhaul conventional island manager position overhaul plan control index target score - Overhaul conventional island manager position overhaul plan control index deduction score + Overhaul conventional island manager position overhaul plan control index addition score; Overhaul conventional island manager position overhaul plan control index addition and subtraction score = The sum of the corresponding addition and subtraction scores of the overhaul plan control index of the overhaul conventional island manager position; The minimum overhaul plan control index score for the overhaul conventional island manager position is 0;
[0105] Overhaul management index score of the overhaul conventional island manager position = Overhaul management index target score of the overhaul conventional island manager position - Overhaul management index deduction score of the overhaul conventional island manager position; Overhaul management index deduction score of the overhaul conventional island manager position = the sum of the deduction scores of each deduction item of the overhaul management index of the overhaul conventional island manager position; The minimum overhaul management index score of the overhaul conventional island manager position is 0;
[0106] The various plus and minus points of the overhaul routine island manager's job performance indicators and the corresponding plus and minus points of each plus and minus point item are obtained through setting, and the target score of the overhaul routine island manager's job performance indicators is obtained through setting; the overhaul performance indicator completion information includes the various plus and minus points of the overhaul routine island manager's job performance indicators; the minimum score of the overhaul routine island manager's job performance indicators is 0.
[0107] In this embodiment, as one of the achievable methods, the overhaul department manager position also includes an overhaul technical manager position; the overhaul technical manager position performance indicators include the overhaul preparation indicator, overhaul risk identification and control indicator, overhaul implementation safety and quality indicator, and overhaul management indicator of the overhaul technical manager position;
[0108] The calculation rule for the overhaul technical manager's job performance is as follows: Overhaul technical manager's job performance score = Overhaul technical manager's job overhaul preparation index score + Overhaul technical manager's job overhaul risk identification and control index score + Overhaul technical manager's job overhaul implementation safety and quality index score + Overhaul technical manager's job overhaul management index score;
[0109] Among them, the overhaul preparation index score of the overhaul technical manager position = the overhaul preparation index target score of the overhaul technical manager position - the overhaul preparation index deduction score of the overhaul technical manager position; the overhaul preparation index deduction score of the overhaul technical manager position = the sum of the deduction scores of each deduction item of the overhaul preparation index of the overhaul technical manager position; the minimum overhaul preparation index score of the overhaul technical manager position is 0;
[0110] Overhaul technical manager position overhaul risk identification and control index score = Overhaul technical manager position overhaul risk identification and control index target score - Overhaul technical manager position overhaul risk identification and control index deduction score; Overhaul technical manager position overhaul risk identification and control index deduction score = the sum of the deduction points corresponding to each deduction item of the overhaul risk identification and control index of the overhaul technical manager position; The minimum overhaul risk identification and control index score for the overhaul technical manager position is 0;
[0111] The score of the safety and quality index for overhaul implementation at the overhaul technical manager position = the target score of the safety and quality index for overhaul implementation at the overhaul technical manager position - the deduction score of the safety and quality index for overhaul implementation at the overhaul technical manager position; the deduction score of the safety and quality index for overhaul implementation at the overhaul technical manager position = the sum of the deduction scores corresponding to each deduction item of the safety and quality index for overhaul implementation at the overhaul technical manager position; the minimum score of the safety and quality index for overhaul implementation at the overhaul technical manager position is 0;
[0112] Overhaul management index score for overhaul technical manager position = target score for overhaul management index for overhaul technical manager position - deduction score for overhaul management index for overhaul technical manager position; deduction score for overhaul management index for overhaul technical manager position = sum of deduction scores for each deduction item of overhaul management index for overhaul technical manager position; the lowest score for overhaul management index for overhaul technical manager position is 0;
[0113] Each plus or minus item of the overhaul technical manager's job performance indicator and the corresponding plus or minus points of each plus or minus item are obtained through setting, and the target score of the overhaul technical manager's job performance indicator is obtained through setting; the overhaul performance indicator completion information includes each plus or minus item of the overhaul technical manager's job performance indicator; the minimum score of the overhaul technical manager's job performance indicator is 0.
[0114] In this embodiment, as one of the achievable methods, the overhaul department manager position also includes the overhaul post-repair test manager position; the overhaul post-repair test manager position performance indicators include the overhaul preparation indicator, overhaul risk identification and control indicator, overhaul implementation safety and quality indicator, and overhaul management indicator of the overhaul post-repair test manager position;
[0115] The calculation rule for the post performance of the overhaul test manager is as follows: the post performance score of the overhaul test manager = the post overhaul preparation index score of the post overhaul test manager + the post overhaul risk identification and control index score of the post overhaul test manager + the post overhaul implementation safety and quality index score of the post overhaul test manager + the post overhaul management index score of the post overhaul test manager;
[0116] Among them, the overhaul preparation index score of the overhaul post-test manager position = the overhaul preparation index target score of the overhaul post-test manager position - the overhaul preparation index deduction score of the overhaul post-test manager position; the overhaul preparation index deduction score of the overhaul post-test manager position = the sum of the deduction scores of each deduction item of the overhaul preparation index of the overhaul post-test manager position; the minimum overhaul preparation index score of the overhaul post-test manager position is 0;
[0117] Overhaul risk identification and control index score for overhaul post-test manager position = Overhaul risk identification and control index target score for overhaul post-test manager position - Overhaul risk identification and control index deduction score for overhaul post-test manager position; Overhaul risk identification and control index deduction score for overhaul post-test manager position = the sum of deduction scores corresponding to each deduction item of overhaul risk identification and control index for overhaul post-test manager position; The minimum overhaul risk identification and control index score for overhaul post-test manager position is 0;
[0118] The score of the overhaul implementation safety and quality index of the overhaul post test manager position = the target score of the overhaul implementation safety and quality index of the overhaul post test manager position - the deduction score of the overhaul implementation safety and quality index of the overhaul post test manager position; the deduction score of the overhaul implementation safety and quality index of the overhaul post test manager position = the sum of the deduction points corresponding to each deduction item of the overhaul implementation safety and quality index of the overhaul post test manager position; the minimum score of the overhaul implementation safety and quality index of the overhaul post test manager position is 0;
[0119] Overhaul management index score of post-overhaul test manager position = target score of overhaul management index of post-overhaul test manager position - overhaul management index deduction score of post-overhaul test manager position; overhaul management index deduction score of post-overhaul test manager position = the sum of deduction scores of each deduction item of overhaul management index of post-overhaul test manager position; the minimum overhaul management index score of post-overhaul test manager position is 0;
[0120] Each plus or minus item of the overhaul test manager's job performance indicator and the corresponding plus or minus points of each plus or minus item are obtained through setting, and the target score of the overhaul test manager's job performance indicator is obtained through setting; the overhaul performance indicator completion information includes each plus or minus item of the overhaul test manager's job performance indicator; the minimum score of the overhaul test manager's job performance indicator is 0.
[0121] In this embodiment, as one of the achievable methods, the overhaul department manager position also includes the overhaul nuclear safety manager position; the overhaul nuclear safety manager position performance indicators include the overhaul preparation indicator, overhaul risk identification and control indicator, overhaul implementation safety quality indicator and overhaul management indicator of the overhaul nuclear safety manager position;
[0122] The calculation rule for the overhaul nuclear safety manager's job performance is as follows: Overhaul nuclear safety manager's job performance score = Overhaul nuclear safety manager's job overhaul preparation index score + Overhaul nuclear safety manager's job overhaul risk identification and control index score + Overhaul nuclear safety manager's job overhaul implementation safety quality index score + Overhaul nuclear safety manager's job overhaul management index score;
[0123] Among them, the overhaul preparation index score of the overhaul nuclear safety manager position = the overhaul preparation index target score of the overhaul nuclear safety manager position - the overhaul preparation index deduction score of the overhaul nuclear safety manager position; the overhaul preparation index deduction score of the overhaul nuclear safety manager position = the sum of the deduction scores corresponding to each deduction item of the overhaul preparation index of the overhaul nuclear safety manager position; the minimum overhaul preparation index score of the overhaul nuclear safety manager position is 0;
[0124] Overhaul risk identification and control index score for overhaul nuclear safety manager position = target score for overhaul risk identification and control index for overhaul nuclear safety manager position - deduction score for overhaul risk identification and control index for overhaul nuclear safety manager position; deduction score for overhaul risk identification and control index for overhaul nuclear safety manager position = the sum of deduction scores corresponding to each deduction item of overhaul risk identification and control index for overhaul nuclear safety manager position; the lowest score for overhaul risk identification and control index for overhaul nuclear safety manager position is 0;
[0125] The score of safety and quality index for overhaul implementation of overhaul nuclear safety manager post = the target score of safety and quality index for overhaul implementation of overhaul nuclear safety manager post - the deduction score of safety and quality index for overhaul implementation of overhaul nuclear safety manager post; the deduction score of safety and quality index for overhaul implementation of overhaul nuclear safety manager post = the sum of the deduction scores corresponding to each deduction item of safety and quality index for overhaul implementation of overhaul nuclear safety manager post; the minimum score of safety and quality index for overhaul implementation of overhaul nuclear safety manager post is 0;
[0126] Overhaul management index score for overhaul nuclear safety manager position = target score for overhaul management index for overhaul nuclear safety manager position - overhaul management index deduction score for overhaul nuclear safety manager position; overhaul management index deduction score for overhaul nuclear safety manager position = the sum of deduction scores corresponding to each deduction item of overhaul management index for overhaul nuclear safety manager position; the lowest overhaul management index score for overhaul nuclear safety manager position is 0;
[0127] Each plus or minus item of the overhaul nuclear safety manager's job performance indicator and the corresponding plus or minus points of each plus or minus item are obtained through setting, and the target score of the overhaul nuclear safety manager's job performance indicator is obtained through setting; the overhaul performance indicator completion information includes each plus or minus item of the overhaul nuclear safety manager's job performance indicator; the minimum score of the overhaul nuclear safety manager's job performance indicator is 0.
[0128] In this embodiment, as one of the achievable methods, the overhaul department manager position also includes the overhaul industrial safety manager position; the overhaul industrial safety manager position performance indicators include the overhaul preparation indicator, overhaul risk identification and control indicator, overhaul implementation safety quality indicator and overhaul management indicator of the overhaul industrial safety manager position;
[0129] The calculation rule for the overhaul industrial safety manager's job performance is as follows: Overhaul industrial safety manager's job performance score = Overhaul industrial safety manager's job overhaul preparation index score + Overhaul industrial safety manager's job overhaul risk identification and control index score + Overhaul industrial safety manager's job overhaul implementation safety quality index score + Overhaul industrial safety manager's job overhaul management index score;
[0130] Among them, the overhaul preparation index score of the overhaul industrial safety manager position = the overhaul preparation index target score of the overhaul industrial safety manager position - the overhaul preparation index deduction score of the overhaul industrial safety manager position; the overhaul preparation index deduction score of the overhaul industrial safety manager position = the sum of the deduction scores of each deduction item of the overhaul preparation index of the overhaul industrial safety manager position; the minimum overhaul preparation index score of the overhaul industrial safety manager position is 0;
[0131] Overhaul risk identification and control index score for overhaul industrial safety manager position = Overhaul risk identification and control index target score for overhaul industrial safety manager position - Overhaul risk identification and control index deduction score for overhaul industrial safety manager position; Overhaul risk identification and control index deduction score for overhaul industrial safety manager position = the sum of deduction scores corresponding to each deduction item of overhaul risk identification and control index for overhaul industrial safety manager position; The minimum overhaul risk identification and control index score for overhaul industrial safety manager position is 0;
[0132] The score of the safety quality index for overhaul implementation of the overhaul industrial safety manager position = the target score of the safety quality index for overhaul implementation of the overhaul industrial safety manager position - the deduction score of the safety quality index for overhaul implementation of the overhaul industrial safety manager position; the deduction score of the safety quality index for overhaul implementation of the overhaul industrial safety manager position = the sum of the deduction scores corresponding to each deduction item of the safety quality index for overhaul implementation of the overhaul industrial safety manager position; the minimum score of the safety quality index for overhaul implementation of the overhaul industrial safety manager position is 0;
[0133] Overhaul management index score for overhaul industrial safety manager position = Overhaul management index target score for overhaul industrial safety manager position - Overhaul management index deduction score for overhaul industrial safety manager position; Overhaul management index deduction score for overhaul industrial safety manager position = the sum of deduction scores corresponding to each deduction item of overhaul management index for overhaul industrial safety manager position; The minimum overhaul management index score for overhaul industrial safety manager position is 0;
[0134] The various plus and minus points of the overhaul industrial safety manager's job performance indicators and the corresponding plus and minus points of each plus and minus point item are obtained through setting, and the target score of the overhaul industrial safety manager's job performance indicators is obtained through setting; the overhaul performance indicator completion information includes the various plus and minus points of the overhaul industrial safety manager's job performance indicators; the minimum score of the overhaul industrial safety manager's job performance indicator is 0.
[0135] In this embodiment, as one of the achievable methods, the overhaul department manager position also includes an overhaul radiation protection manager position; the overhaul radiation protection manager position performance indicators include the overhaul preparation indicator, overhaul risk identification and control indicator, overhaul implementation safety and quality indicator, and overhaul management indicator of the overhaul radiation protection manager position;
[0136] The calculation rule for the overhaul radiation protection manager's job performance is as follows: Overhaul radiation protection manager's job performance score = Overhaul radiation protection manager's job overhaul preparation index score + Overhaul radiation protection manager's job overhaul risk identification and control index score + Overhaul radiation protection manager's job overhaul implementation safety and quality index score + Overhaul radiation protection manager's job overhaul management index score;
[0137] Among them, the overhaul preparation index score of the overhaul radiation protection manager position = the overhaul preparation index target score of the overhaul radiation protection manager position - the overhaul preparation index deduction score of the overhaul radiation protection manager position; the overhaul preparation index deduction score of the overhaul radiation protection manager position = the sum of the deduction scores corresponding to each deduction item of the overhaul preparation index of the overhaul radiation protection manager position; the minimum overhaul preparation index score of the overhaul radiation protection manager position is 0;
[0138] Overhaul risk identification and control index score for overhaul radiation protection manager position = target score for overhaul risk identification and control index for overhaul radiation protection manager position - deduction score for overhaul risk identification and control index for overhaul radiation protection manager position; deduction score for overhaul risk identification and control index for overhaul radiation protection manager position = the sum of deduction scores corresponding to each deduction item of overhaul risk identification and control index for overhaul radiation protection manager position; the lowest score for overhaul risk identification and control index for overhaul radiation protection manager position is 0;
[0139] The score of safety and quality index for overhaul implementation of overhaul radiation protection manager post = target score of safety and quality index for overhaul implementation of overhaul radiation protection manager post - deduction score of safety and quality index for overhaul implementation of overhaul radiation protection manager post; deduction score of safety and quality index for overhaul implementation of overhaul radiation protection manager post = the sum of deduction scores corresponding to each deduction item of safety and quality index for overhaul implementation of overhaul radiation protection manager post; the minimum score of safety and quality index for overhaul implementation of overhaul radiation protection manager post is 0;
[0140] Overhaul management index score for overhaul radiation protection manager position = target score for overhaul management index for overhaul radiation protection manager position - deduction score for overhaul management index for overhaul radiation protection manager position; deduction score for overhaul management index for overhaul radiation protection manager position = sum of deduction scores for each deduction item of overhaul management index for overhaul radiation protection manager position; the lowest overhaul management index score for overhaul radiation protection manager position is 0;
[0141] The various plus and minus points of the overhaul radiation protection manager's job performance indicators and the corresponding plus and minus points of each plus and minus point item are obtained through setting, and the target score of the overhaul radiation protection manager's job performance indicators is obtained through setting; the overhaul performance indicator completion information includes the various plus and minus points of the overhaul radiation protection manager's job performance indicators; the minimum score of the overhaul radiation protection manager's job performance indicator is 0.
[0142] In this embodiment, as one of the achievable methods, the overhaul department manager position also includes the overhaul QA manager position; the overhaul QA manager position performance indicators include the overhaul preparation indicator, overhaul risk identification and control indicator, overhaul implementation safety and quality indicator and overhaul management indicator of the overhaul QA manager position;
[0143] The calculation rule for the overhaul QA manager's job performance is as follows: Overhaul QA manager's job performance score = Overhaul QA manager's job overhaul preparation index score + Overhaul QA manager's job overhaul risk identification and control index score + Overhaul QA manager's job overhaul implementation safety and quality index score + Overhaul QA manager's job overhaul management index score;
[0144] Among them, the overhaul preparation index score of the overhaul QA manager position = the overhaul preparation index target score of the overhaul QA manager position - the overhaul preparation index deduction score of the overhaul QA manager position; the overhaul preparation index deduction score of the overhaul QA manager position = the sum of the deduction scores of each deduction item of the overhaul preparation index of the overhaul QA manager position; the minimum overhaul preparation index score of the overhaul QA manager position is 0;
[0145] Overhaul risk identification and control index score for the overhaul QA manager position = Overhaul risk identification and control index target score for the overhaul QA manager position - Overhaul risk identification and control index deduction score for the overhaul QA manager position; Overhaul risk identification and control index deduction score for the overhaul QA manager position = the sum of deduction scores corresponding to each deduction item of the overhaul risk identification and control index for the overhaul QA manager position; The minimum overhaul risk identification and control index score for the overhaul QA manager position is 0;
[0146] The score of the safety and quality index for overhaul implementation at the overhaul QA manager position = the target score of the safety and quality index for overhaul implementation at the overhaul QA manager position - the deduction score of the safety and quality index for overhaul implementation at the overhaul QA manager position; the deduction score of the safety and quality index for overhaul implementation at the overhaul QA manager position = the sum of the deduction scores corresponding to each deduction item of the safety and quality index for overhaul implementation at the overhaul QA manager position; the minimum score of the safety and quality index for overhaul implementation at the overhaul QA manager position is 0;
[0147] Overhaul QA manager position overhaul management index score = Overhaul QA manager position overhaul management index target score - Overhaul QA manager position overhaul management index deduction score; Overhaul QA manager position overhaul management index deduction score = the sum of the deduction points corresponding to each deduction item of the overhaul QA manager position overhaul management index; The lowest overhaul management index score for the overhaul QA manager position is 0;
[0148] The various plus and minus points of the overhaul QA manager's job performance indicators and the corresponding plus and minus points of each plus and minus point item are obtained through setting, and the target score of the overhaul QA manager's job performance indicators is obtained through setting; the overhaul performance indicator completion information includes the various plus and minus points of the overhaul QA manager's job performance indicators; the minimum score of the overhaul QA manager's job performance indicator is 0.
[0149] In this embodiment, as one of the achievable methods, the overhaul preparation index target of the overhaul operation manager position is 35 points; the deduction items of the overhaul preparation index of the overhaul operation manager position and the deduction points corresponding to each deduction item include: failure to organize and complete the planned preparation work according to the overhaul preparation work requirements, each item is deducted 1-5 points;
[0150] The target of the overhaul risk identification and control index for the overhaul operation manager position is 15 points; the deduction items of the overhaul risk identification and control index for the overhaul operation manager position and the deduction points corresponding to each deduction item include: due to inadequate identification of operational risks, non-critical path or sub-critical path projects become critical path projects, and the delay is ≥4 hours, 15 points will be deducted;
[0151] The target score of safety and quality index for overhaul implementation in the overhaul operation manager position is 40 points; the plus and minus points for safety and quality index for overhaul implementation in the overhaul operation manager position and the plus and minus points corresponding to each plus and minus point item include: if the operation period is at least 10% ahead of the target period, add 10 points; if the operation period is at least 10% behind the target period, subtract 10 points; if the safety measures are implemented incorrectly, 3 points will be subtracted for each item; if the isolation is not implemented or lifted as planned, 3 points will be subtracted for each item;
[0152] The target score of the overhaul management index for the overhaul operation manager position is 10 points; the deduction items of the overhaul management index for the overhaul operation manager position include: the overhaul operation manager position performance index score is lower than the target score of the overhaul operation manager position performance index.
[0153] In this embodiment, as one of the achievable methods, the overhaul preparation index target of the overhaul planning manager position is divided into 35 points; the deduction items of the overhaul preparation index of the overhaul planning manager position and the deduction points corresponding to each deduction item include: failure to organize and complete the planning preparation work according to the overhaul preparation work requirements, each item is deducted 1-5 points;
[0154] The target of the overhaul risk identification and control index of the overhaul planning manager position is 15 points; the deduction items of the overhaul risk identification and control index of the overhaul planning manager position and the corresponding deductions include: due to inadequate identification of plan risks, incorrect judgment of the main line logic, non-critical path or sub-critical path items become critical path items, and the delay is ≥4 hours, 15 points will be deducted;
[0155] The overhaul plan control index target of the overhaul plan manager position is 40 points; the plus and minus points of the overhaul plan control index of the overhaul plan manager position and the plus and minus points corresponding to each plus and minus point include: if the construction period is at least 10% ahead of the target construction period, add 10 points; if the construction period lags behind the target construction period by at least 10%, subtract 10 points; if the critical path operation is delayed by ≥8 hours due to poor plan control, subtract 5 points each time; if the construction period deviation is greater than 3, subtract 5 points;
[0156] The target score of the overhaul management index for the overhaul planning manager position is 10 points; the deduction items for the overhaul management index for the overhaul planning manager position include: the overhaul planning manager position performance index score is lower than the overhaul planning manager position performance index target score.
[0157] In this embodiment, as one of the achievable methods, the target of the overhaul preparation index of the overhaul nuclear island manager position is 35 points; the deduction items of the overhaul preparation index of the overhaul nuclear island manager position and the deduction points corresponding to each deduction item include: failure to organize and complete the planned preparation work according to the overhaul preparation work requirements, each item is deducted 1-5 points;
[0158] The target of the overhaul risk identification and control index of the overhaul nuclear island manager position is 15 points; the deduction items of the overhaul risk identification and control index of the overhaul nuclear island manager position and the deduction points corresponding to each deduction item include: due to poor identification of nuclear island special risks, non-critical path or sub-critical path special items become critical path special items, and the delay is ≥4 hours, 15 points will be deducted;
[0159] The target score of the overhaul plan control index of the overhaul nuclear island manager position is 40 points; the plus and minus points of the overhaul plan control index of the overhaul nuclear island manager position and the plus and minus points corresponding to each plus and minus point item include: if the nuclear island construction period is at least 10% ahead of the target construction period, add 10 points; if the nuclear island construction period lags behind the target construction period by at least 10%, subtract 10 points; if the non-critical path and sub-critical path special work order are delayed due to poor management and control and become critical paths, 5 points will be subtracted each time;
[0160] The target score of the overhaul management index for the overhaul nuclear island manager position is 10 points; the deduction items of the overhaul management index for the overhaul nuclear island manager position include: the overhaul nuclear island manager position performance index score is lower than the target score of the overhaul nuclear island manager position performance index.
[0161] In this embodiment, as one of the achievable methods, the overhaul preparation index target of the overhaul routine island manager position is 35 points; the deduction items of the overhaul preparation index of the overhaul routine island manager position and the deduction points corresponding to each deduction item include: failure to organize and complete the planned preparation work according to the overhaul preparation work requirements, each item is deducted 1-5 points;
[0162] The target of the overhaul risk identification and control index of the overhaul conventional island manager position is 15 points; the deduction items of the overhaul risk identification and control index of the overhaul conventional island manager position and the deduction points corresponding to each deduction item include: due to poor identification of the risks of the conventional island special project, the non-critical path or sub-critical path special project becomes the critical path special project, and the delay is ≥4 hours, 15 points will be deducted;
[0163] The overhaul plan control index target of the overhaul conventional island manager position is 40 points; the plus and minus points of the overhaul plan control index of the overhaul conventional island manager position and the plus and minus points corresponding to each plus and minus point item include: if the conventional island construction period is at least 10% ahead of the target construction period, add 10 points; if the conventional island construction period lags behind the target construction period by at least 10%, subtract 10 points; if the non-critical path and sub-critical path special work order are delayed due to poor management and control and become critical paths, 5 points will be deducted each time;
[0164] The target score of the overhaul management index for the overhaul routine island manager position is 10 points; the deduction items of the overhaul management index for the overhaul routine island manager position include: the performance index score of the overhaul routine island manager position is lower than the target score of the performance index of the overhaul routine island manager position.
[0165] In this embodiment, as one of the achievable methods, the overhaul preparation index target of the overhaul technical manager position is 35 points; the deduction items of the overhaul preparation index of the overhaul technical manager position and the deduction points corresponding to each deduction item include: failure to organize and complete the planned preparation work according to the overhaul preparation work requirements, each item is deducted 1-5 points;
[0166] The target of the overhaul risk identification and control index for the overhaul technical manager position is 15 points; the deduction items of the overhaul risk identification and control index for the overhaul technical manager position and the corresponding deductions include: due to inadequate risk identification, non-critical path or sub-critical path projects become critical path projects, and the delay is ≥4 hours, 15 points will be deducted;
[0167] The target of safety and quality indicators for overhaul implementation of overhaul technical manager position is 40 points; the deduction items and corresponding deduction items of safety and quality indicators for overhaul implementation of overhaul technical manager position include: 5 points for each event that affects the overhaul critical path due to the QDR plan determination and approval process; 5 points for each event that affects the overhaul critical path plan due to spare parts other than Class B; 5 points for each event that causes delays in the critical path due to the new change and modification approval process; 5 points for each event that causes overrun events or other quality control events due to QC organizational reasons;
[0168] The target score of the overhaul management index for the overhaul technical manager position is 10 points; the deduction items of the overhaul management index for the overhaul technical manager position include: the overhaul technical manager position performance index score is lower than the target score of the overhaul technical manager position performance index.
[0169] In this embodiment, as one of the achievable methods, the overhaul preparation index target of the overhaul post-test manager position is 35 points; the deduction items of the overhaul preparation index of the overhaul post-test manager position and the deduction points corresponding to each deduction item include: failure to organize and complete the planned preparation work according to the overhaul preparation work requirements, each item is deducted 1-5 points;
[0170] The target of the overhaul risk identification and control index of the overhaul post-test manager position is 15 points; the deduction items of the overhaul risk identification and control index of the overhaul post-test manager position and the deduction points corresponding to each deduction item include: due to inadequate risk identification, if a non-critical path or sub-critical path project becomes a critical path project and the delay is ≥4 hours, 15 points will be deducted;
[0171] The target of the safety and quality index of overhaul implementation for the overhaul post test manager position is 40 points; the deduction items of the safety and quality index of overhaul implementation for the overhaul post test manager position and the deduction points corresponding to each deduction item include: 5 points will be deducted for each case where the critical path or sub-critical path is affected due to poor work organization and arrangement; 5 points will be deducted for each case where the critical path or sub-critical path is affected due to poor work organization and arrangement;
[0172] The target score of the overhaul management index for the post-overhaul test manager position is 10 points; the deduction items of the overhaul management index for the post-overhaul test manager position include: the post-overhaul test manager position performance index score is lower than the post-overhaul test manager position performance index target score.
[0173] In this embodiment, as one of the achievable methods, the target of the overhaul preparation index of the overhaul nuclear safety manager position is 35 points; the deduction items of the overhaul preparation index of the overhaul nuclear safety manager position and the deduction points corresponding to each deduction item include: failure to organize and complete the planned preparation work according to the overhaul preparation work requirements, each item is deducted 1-5 points;
[0174] The target of the overhaul risk identification and control index for the overhaul nuclear safety manager position is 15 points; the deduction items of the overhaul risk identification and control index for the overhaul nuclear safety manager position and the corresponding deductions include: 15 points for delays in critical path projects due to inadequate nuclear safety risk identification; 10 points for non-critical path or sub-critical path projects becoming critical path projects and the delay is ≥4 hours;
[0175] The target of safety and quality index for overhaul implementation of overhaul nuclear safety manager position is 40 points; the deduction items and corresponding deduction items of safety and quality index for overhaul implementation of overhaul nuclear safety manager position include: due to poor coordination, the pre-criticality inspection is not carried out as planned, resulting in delays in the critical path, 5 points are deducted for each case; due to poor coordination, nuclear safety-related projects are not witnessed in time, resulting in delays in the critical path, 5 points are deducted for each case; due to poor coordination, nuclear safety-related control points are not issued in time, resulting in delays in the critical path, 5 points are deducted for each case;
[0176] The target score of the overhaul management index for the overhaul nuclear safety manager position is 10 points; the deduction items of the overhaul management index for the overhaul nuclear safety manager position include: the overhaul nuclear safety manager position performance index score is lower than the target score of the overhaul nuclear safety manager position performance index.
[0177] In this embodiment, as one of the achievable methods, the overhaul preparation index target of the overhaul industrial safety manager position is 35 points; the deduction items of the overhaul preparation index of the overhaul industrial safety manager position and the deduction points corresponding to each deduction item include: failure to organize and complete the planned preparation work according to the overhaul preparation work requirements, each item is deducted 1-5 points;
[0178] The target of the overhaul risk identification and control index for the overhaul industrial safety manager position is 15 points; the deduction items of the overhaul risk identification and control index for the overhaul industrial safety manager position and the corresponding deductions include: 15 points for delays in critical path projects due to inadequate industrial safety risk identification; 10 points for non-critical path or sub-critical path projects becoming critical path projects and delayed by ≥4 hours;
[0179] The target of the safety and quality index for overhaul implementation of the overhaul industrial safety manager position is 40 points; the deduction items for the safety and quality index for overhaul implementation of the overhaul industrial safety manager position and the deduction points corresponding to each deduction item include: serious injury or above personal injury accident, each of which is deducted 10 points; minor injury to personnel, each of which is deducted 5 points; minor injury to personnel due to inadequate control, each of which is deducted 5 points; critical path delay due to poor coordination, each of which is deducted 5 points;
[0180] The target score of the overhaul management index for the overhaul industrial safety manager position is 10 points; the deduction items of the overhaul management index for the overhaul industrial safety manager position include: the overhaul industrial safety manager position performance index score is lower than the overhaul industrial safety manager position performance index target score.
[0181] In this embodiment, as one of the achievable methods, the overhaul preparation index target of the overhaul radiation protection manager position is 35 points; the deduction items of the overhaul preparation index of the overhaul radiation protection manager position and the deduction points corresponding to each deduction item include: failure to organize and complete the planned preparation work according to the overhaul preparation work requirements, wherein each item is deducted 1-5 points;
[0182] The target of the overhaul risk identification and control index of the overhaul radiation protection manager position is 15 points; the deduction items of the overhaul risk identification and control index of the overhaul radiation protection manager position and the deduction points corresponding to each deduction item include: if the critical path project is delayed due to inadequate radiation protection risk identification, 15 points will be deducted; if a non-critical path or sub-critical path project becomes a critical path project and the delay is ≥4 hours, 10 points will be deducted;
[0183] The target of safety and quality indicators for overhaul implementation of the overhaul radiation protection manager position is 40 points; the deduction items for safety and quality indicators for overhaul implementation of the overhaul radiation protection manager position and the deduction points corresponding to each deduction item include: general and above radiation accidents, 10 points for each incident; collective doses less than three stars, 3 points for each incident; unplanned exposure incidents, 3 points for each incident; maximum personal doses less than three stars, 3 points for each incident; radioactive solid waste generation less than three stars, 3 points for each incident;
[0184] The target score of the overhaul management index for the overhaul radiation protection manager position is 10 points; the deduction items of the overhaul management index for the overhaul radiation protection manager position include: the performance index score of the overhaul radiation protection manager position is lower than the target score of the overhaul radiation protection manager position performance index.
[0185] In this embodiment, as one of the achievable methods, the overhaul preparation index target of the overhaul QA manager position is 35 points; the deduction items of the overhaul preparation index of the overhaul QA manager position and the deduction points corresponding to each deduction item include: failure to organize and complete the planned preparation work according to the overhaul preparation work requirements, each item is deducted 1-5 points;
[0186] The target of the overhaul risk identification and control index for the overhaul QA manager position is 15 points; the deduction items of the overhaul risk identification and control index for the overhaul QA manager position and the deduction points corresponding to each deduction item include: 15 points will be deducted if the critical path project is delayed due to inadequate QA quality risk identification; 10 points will be deducted if a non-critical path or sub-critical path project becomes a critical path project and the delay is ≥4 hours;
[0187] The target score of safety and quality index for overhaul implementation in the overhaul QA manager position is 40 points; the deduction items for safety and quality index for overhaul implementation in the overhaul QA manager position and the deduction points corresponding to each deduction item include: 5 points will be deducted for each delay in the critical path due to poor coordination;
[0188] The target score of the overhaul management index for the overhaul QA manager position is 10 points; the deduction items for the overhaul management index for the overhaul QA manager position include: the overhaul QA manager position performance index score is lower than the target score of the overhaul QA manager position performance index.
[0189] In this embodiment, as one of the achievable methods, the overhaul department performance calculation rule is: overhaul department performance score = the sum of the overhaul department's performance index scores;
[0190] Among them, the overhaul department performance index score = the overhaul department performance index target score + the overhaul department performance index bonus score - the overhaul department performance index deduction score; the overhaul department performance index plus or minus score = the sum of the corresponding plus or minus scores of each plus or minus score item of the overhaul department performance index;
[0191] Each plus or minus item of the overhaul department performance indicator and the corresponding plus or minus points of each plus or minus item are obtained through setting, and the target score of the overhaul department performance indicator is obtained through setting; the overhaul performance indicator completion information includes each plus or minus item of the overhaul department performance indicator; the minimum score of the overhaul department performance indicator is 0.
[0192] In this embodiment, as one of the achievable methods, the overhaul department includes an overhaul operation department, an overhaul maintenance department, an overhaul technical department and an overhaul safety and quality department; the overhaul department performance indicators include the overhaul preparation indicators, overhaul implementation safety and quality indicators, overhaul plan control indicators, overhaul summary indicators and overhaul management indicators of the overhaul department;
[0193] The calculation rule of overhaul department performance is: overhaul department performance score = overhaul department overhaul preparation index score + overhaul department overhaul implementation safety and quality index score + overhaul department overhaul plan control index score + overhaul department overhaul summary index score + overhaul department overhaul management index score;
[0194] Among them, the overhaul preparation index score of the overhaul department = the overhaul preparation index target score of the overhaul department - the overhaul preparation index deduction score of the overhaul department; the overhaul preparation index deduction score of the overhaul department = the sum of the deduction scores of each deduction item of the overhaul preparation index of the overhaul department; the minimum overhaul preparation index score of the overhaul department is 0;
[0195] The overhaul department's overhaul implementation safety and quality index score = the overhaul department's overhaul implementation safety and quality index target score - the overhaul department's overhaul implementation safety and quality index deduction score; the overhaul department's overhaul implementation safety and quality index deduction score = the sum of the deduction scores corresponding to each deduction item of the overhaul department's overhaul implementation safety and quality index; the overhaul department's overhaul implementation safety and quality index score is the lowest 0;
[0196] Overhaul plan control index score of overhaul department = target score of overhaul plan control index of overhaul department + bonus score of overhaul plan control index of overhaul department - minus score of overhaul plan control index of overhaul department; plus or minus score of overhaul plan control index of overhaul department = the sum of the plus or minus scores of each plus or minus score item of overhaul plan control index of overhaul department; the lowest score of overhaul plan control index of overhaul department is 0;
[0197] Overhaul summary index score of overhaul department = target score of overhaul summary index of overhaul department - deduction score of overhaul summary index of overhaul department; deduction score of overhaul summary index of overhaul department = sum of deduction scores corresponding to each deduction item of overhaul summary index of overhaul department; the lowest score of overhaul summary index of overhaul department is 0;
[0198] Overhaul management index score of overhaul department = target score of overhaul management index of overhaul department + bonus score of overhaul management index of overhaul department - minus score of overhaul management index of overhaul department; minus score of overhaul management index of overhaul department = sum of the corresponding plus and minus scores of each plus and minus score item of overhaul management index of overhaul department; the lowest score of overhaul management index of overhaul department is 0;
[0199] Each plus or minus item of the overhaul department performance indicator and the corresponding plus or minus points of each plus or minus item are obtained through setting, and the target score of the overhaul department performance indicator is obtained through setting; the overhaul performance indicator completion information includes each plus or minus item of the overhaul department performance indicator; the minimum score of the overhaul department performance indicator is 0.
[0200] In this embodiment, as one of the achievable ways, the overhaul preparation index target of the overhaul department is divided into 30 points; the deduction items of the overhaul preparation index of the overhaul department and the corresponding deduction items include: if the execution rate of overhaul preparation work as planned is less than 100%, 0.2 points will be deducted for each item; if the completion rate of overhaul work package preparation is less than 95%, 1 point will be deducted; one month before the overhaul, the success rate of work order material reservation is less than 95%, and 1 point will be deducted for every 1% decrease; one month before the overhaul, the contract signing rate of the outsourcing project proposed 10 months ago is less than 100%, and 1 point will be deducted for every 1% decrease; if insufficient preparation is found during the implementation of the overhaul, 1-5 points will be deducted.
[0201] In this embodiment, as one of the achievable ways, the overhaul department's overhaul implementation safety and quality index target is divided into 25 points; the deduction items of the overhaul department's overhaul implementation safety and quality index and the corresponding deduction items include: Level 1 and above operation events, each of which is deducted 25 points; serious injury and above personal injury accidents, each of which is deducted 25 points; fire accidents, each of which is deducted 25 points; general and above radiation accidents, each of which is deducted 25 points; Level 0 operation events caused by human factors, each of which is deducted 10 points; minor injuries to personnel, each of which is deducted 10 points; the number of serious damages to major equipment, each of which is deducted 10 points; unplanned irradiation events, each of which is deducted 10 points; Level 1 shutdown orders during overhaul, each of which is deducted 10 points; Class A status reports due to human factors during overhaul, each of which is deducted 10 points; attempted industrial safety incidents, each of which is deducted 5 points; fire risk incidents, each of which is deducted 5 points; violations, each of which is deducted 5 points; and Class B status reports due to human factors during overhaul, each of which is deducted 5 points.
[0202] In this embodiment, as one of the feasible ways, the overhaul plan control index target of the overhaul department is divided into 10 points; the plus and minus points of the overhaul plan control index of the overhaul department and the plus and minus points corresponding to each plus and minus point item include: critical path work control ≤ excellent construction period, add 1 point for every hour less, up to 10 points; overhaul critical path delay, subtract 1 point for every hour, up to 10 points.
[0203] In this embodiment, as one of the achievable methods, the overhaul summary index target of the overhaul department is divided into 5 points; the deduction items of the overhaul summary index of the overhaul department and the corresponding deduction items include: failure to complete the overhaul summary as required, deduction of 0.2 points for each item; defects within 100 days of overhaul of the maintenance equipment lead to Class A or Class B status reports, deduction of 2 points for each item; human factors cause the overhaul index to fail to reach the three-star value, deduction of 1 point for each item.
[0204] In this embodiment, as one of the achievable ways, the overhaul management index target of the overhaul department is divided into 30 points; the deduction items and the corresponding addition and subtraction items of the overhaul management index of the overhaul department include: level 1 and above operation events, the management department deducts 3 points for each event; serious injury and above personal injury accidents, the management department deducts 3 points for each event; fire accidents, the management department deducts 3 points for each event; general and above radiation accidents, the management department deducts 3 points for each event; safety measures error license, deduct 3 points; uncontrolled transfer of radioactive materials, deduct 3 points for each event; collective dose does not reach three stars, the management department deducts 3 points; collective dose exceeds the target value of the management department, the management department deducts 1 point; collective dose exceeds the target value of non-management departments, the non-management departments deduct 1 point; equipment is tested once after maintenance If the qualification rate is less than 97%, 3 points will be deducted; if the equipment re-maintenance rate is greater than 0.5, 3 points will be deducted; if the comprehensive indicators of overhaul and maintenance quality do not meet the standards, 3 points will be deducted; if the increase or decrease rate of projects after the overhaul project is frozen is greater than 4, 3 points will be deducted; if the overhaul schedule deviation is greater than the target value, 3 points will be deducted; if the projects that should be implemented during the overhaul are not implemented, 3 points will be deducted; if the number of existing defects on the tenth day after grid connection is greater than 40, 3 points will be deducted; if the unit efficiency change base is less than the benchmark value or the pre-maintenance value, 3 points will be deducted; if the isolation is not implemented or lifted as planned, 3 points will be deducted; if the change project preparation affects the critical path, 3 points will be deducted; if the in-service inspection of important and key equipment is not completed as planned, 3 points will be deducted; for every 10 points deducted from the overhaul special project, 1 point will be deducted from the corresponding department, and a maximum of 3 points will be deducted from 1 special project; if it is approved by the overhaul execution command, it will contribute to the safety and quality progress of the overhaul, and a maximum of 3 points will be added.
[0205] In this embodiment, as one of the achievable methods, expected values of the overall overhaul performance score, the overhaul position performance score, and the overhaul department performance score are set respectively;
[0206] When the overall overhaul performance score, overhaul position performance score or overhaul department performance score is lower than the expected value, it will be clearly marked.
[0207] In this embodiment, as one of the feasible ways, the final overhaul performance calculation result is sent to the overhaul position and the overhaul department via email.
[0208] refer to Figure 2 As an implementation of the above method, the present invention provides an embodiment of an overhaul performance evaluation device. The embodiment of the device corresponds to the embodiment of the above overhaul performance evaluation method. The device can be specifically applied to various electronic devices.
[0209] The overhaul performance evaluation device described in this embodiment includes:
[0210] The data processing module 201 is used to set the overhaul performance index and the overhaul performance calculation rules; perform the overhaul performance real-time calculation according to the overhaul performance calculation rules to obtain the overhaul real-time performance calculation results; after the overhaul is completed, perform the overhaul final performance calculation according to the overhaul performance calculation rules to obtain the overhaul final performance calculation results;
[0211] The data association module 202 is used to associate the overhaul performance indicators with the overhaul positions and overhaul departments respectively; and collect the overhaul performance indicator completion information in real time;
[0212] Data display module 203, used to display the overhaul real-time performance calculation results and the overhaul final performance calculation results;
[0213] The data sending module 204 is used to send the final overhaul performance calculation result to the overhaul position and overhaul department.
[0214] In this embodiment, as one of the achievable methods, the data display module 203 sets the expected values of the overall overhaul performance score, the overhaul position performance score and the overhaul department performance score respectively;
[0215] When the overall overhaul performance score, the overhaul position performance score or the overhaul department performance score is lower than the expected value, the data display module 203 makes a prominent mark.
[0216] The above-mentioned embodiments only express several implementation methods of the present invention, and the description thereof is relatively specific and detailed, but it cannot be understood as limiting the scope of the patent of the present invention. It should be pointed out that, for ordinary technicians in this field, several variations and improvements can be made without departing from the concept of the present invention, which all belong to the protection scope of the present invention. Therefore, the protection scope of the patent of the present invention shall be subject to the attached claims.
Claims
1. A method for evaluating overhaul performance, characterized in that: The steps include: Step 101, setting overhaul performance indicators and overhaul performance calculation rules; Step 102, associating the overhaul performance indicators with the overhaul positions and the overhaul departments respectively; Step 103: collect the overhaul performance indicator completion information in real time, calculate the overhaul performance in real time according to the overhaul performance calculation rules, obtain the overhaul real-time performance calculation results and display them in real time; Step 104: After the overhaul is completed, the final overhaul performance calculation is performed according to the overhaul performance calculation rules, and the final overhaul performance calculation result is obtained and displayed; Step 105: Send the final overhaul performance calculation results to the overhaul positions and departments.
2. The overhaul performance evaluation method according to claim 1, characterized in that: The overhaul performance indicators include the overall overhaul performance indicators, overhaul position performance indicators and overhaul department performance indicators. The overhaul performance calculation rules include the overall overhaul performance calculation rules, overhaul position performance calculation rules and overhaul department performance calculation rules.
3. The overhaul performance evaluation method according to claim 2, characterized in that: The calculation rule for the overall performance of overhaul is: the overall performance score of overhaul = the sum of the scores of each overall performance index of overhaul; Among them, the overhaul overall performance index score = (actual number of stars of the overhaul overall performance index / optimal number of stars of the overhaul overall performance index) × the overhaul overall performance index target score; The overhaul performance indicator completion information includes the actual number of stars for each overall performance indicator of the overhaul.
4. The overhaul performance evaluation method according to claim 2, characterized in that: Overhaul positions include overhaul executive command positions and overhaul department executive command positions; The calculation rule for the performance of the overhaul executive command position is: the performance score of the overhaul executive command position = the average performance score of each overhaul department; The calculation rule for the performance of the overhaul department executive command position is: overhaul department executive command position performance score = overhaul department performance score.
5. The overhaul performance evaluation method according to claim 4, characterized in that: Overhaul positions also include overhaul manager positions; overhaul position performance indicators include overhaul management indicators for overhaul manager positions; The calculation rule for the overhaul manager's job performance is as follows: Overhaul manager's job performance score = average performance score of each overhaul department + overhaul management index score of the overhaul manager's job; Among them, the overhaul management index score of the overhaul manager position = the overhaul management index target score of the overhaul manager position - the overhaul management index reduction score of the overhaul manager position; Deduction of overhaul management index for overhaul manager position = the sum of deductions corresponding to each deduction item of overhaul management index for overhaul manager position; The overhaul performance index completion information includes the various deduction items of the overhaul management index of the overhaul manager position; the lowest overhaul management index score of the overhaul manager position is 0.
6. The overhaul performance evaluation method according to claim 4, characterized in that: Overhaul positions also include overhaul department manager positions; overhaul position performance indicators also include overhaul department manager position performance indicators; The calculation rule for the overhaul department manager's job performance is: the overhaul department manager's job performance score = the sum of the overhaul department manager's job performance index scores; Among them, the overhaul department manager's job performance index score = the overhaul department manager's job performance index target score + the overhaul department manager's job performance index bonus score - the overhaul department manager's job performance index deduction score; the overhaul department manager's job performance index plus or minus score = the sum of the corresponding plus or minus scores of each plus or minus score item of the overhaul department manager's job performance index; The overhaul performance index completion information includes the various addition and subtraction items of the overhaul department manager's job performance index; the minimum score for the overhaul department manager's job performance index is 0.
7. The overhaul performance evaluation method according to claim 2, characterized in that: The calculation rule for overhaul department performance is: overhaul department performance score = the sum of the scores of each performance indicator of the overhaul department; Among them, the overhaul department performance index score = the overhaul department performance index target score + the overhaul department performance index bonus score - the overhaul department performance index deduction score; the overhaul department performance index plus or minus score = the sum of the corresponding plus or minus scores of each plus or minus score item of the overhaul department performance index; The overhaul performance index completion information includes the various addition and subtraction items of the overhaul department performance index; the lowest overhaul department performance index score is 0.
8. The overhaul performance evaluation method according to claim 2, characterized in that: Set the expected values for the overall overhaul performance score, overhaul position performance score and overhaul department performance score respectively; When the overall overhaul performance score, overhaul position performance score or overhaul department performance score is lower than the expected value, it will be clearly marked.
9. The overhaul performance evaluation method according to claim 1, characterized in that: The final overhaul performance calculation results will be sent to the overhaul position and overhaul department via email.
10. An overhaul performance evaluation device, characterized in that: include: A data processing module (201) is used to set overhaul performance indicators and overhaul performance calculation rules; perform overhaul performance real-time calculation according to the overhaul performance calculation rules to obtain overhaul real-time performance calculation results; After the overhaul is completed, the final overhaul performance calculation is performed according to the overhaul performance calculation rules to obtain the final overhaul performance calculation result; A data association module (202) is used to associate the overhaul performance indicators with the overhaul positions and overhaul departments respectively; Collect overhaul performance indicator completion information in real time; A data display module (203) is used to display the overhaul real-time performance calculation results and the overhaul final performance calculation results; The data sending module (204) is used to send the final overhaul performance calculation result to the overhaul position and the overhaul department.
Citation Information
Patent Citations
Performance assessment management system in comprehensive energy field, computer equipment and storage medium
CN114997570A
Engineering project comprehensive control and evaluation method based on information system
CN117436755A