Pile driver for highway bridge construction

By installing a mobile device on the pile device, the existing small pile driver requires two workers to hold and heavy weight, realize the convenient movement and single operation of the pile driver, and reduce the construction period and the workload of workers.

CN119373104APending Publication Date: 2025-01-28CHONGQING FENGJIE ROAD & BRIDGE CO LTD
View PDF 1 Cites 0 Cited by

Patent Information

Application Number
CN202411500636.2
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-10-25
Publication Date
2025-01-28

AI Technical Summary

Technical Problem

The existing small pile driver requires two workers to hold the hand and have a heavier weight when used, resulting in frequent manpower handling to increase the construction period and workload of workers.

Method used

A pile driver for highway bridge construction is designed, and a mobile device is installed on the pile device, including the bottom plate, the mobile wheel, the support pillar and the lifting pile device, which is convenient for the movement and use of the pile driver.

Benefits of technology

The design makes the pile driver simple and easy to handle, reduce the effects of frequent transportation equipment on the construction period, reduce the workload of workers, and only need to operate the pile device alone, which improves the convenience and efficiency of construction.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119373104A_ABST
    Figure CN119373104A_ABST
Patent Text Reader

Abstract

The invention belongs to the technical field of highway engineering, and particularly relates to a highway bridge construction pile driver which comprises a moving device and a pile driving device connected to the moving device in a liftable mode. The moving device comprises a bottom plate, moving wheels are mounted at the rear end of the bottom of the bottom plate, a notch for piling of the piling device is formed in the front end of the bottom plate, two supporting columns are connected to the rear end of the bottom plate, a top beam frame is connected between the tops of the two supporting columns, and a first holding part convenient for a worker to hold is arranged on the top beam frame. The moving device is additionally arranged on the piling device, so that the piling machine is convenient to move, the device is simple in structure and convenient to carry, the convenience degree of small construction is increased, the influence of frequent equipment carrying on the construction period is avoided, and the workload of workers is relieved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention belongs to the technical field of highway engineering, and in particular relates to a pile driver for highway bridge construction. Background Art

[0002] Pile drivers are divided into large and small types. Large pile drivers are composed of a pile hammer, a pile frame and ancillary equipment. The pile hammer is attached between two parallel vertical guide rods (commonly known as gantry) in the front of the pile frame and is lifted by a lifting hook. The pile frame is a steel structure tower with a winch at the rear to lift the pile and the pile hammer. There is a guide frame composed of two guide rods in front of the pile frame to control the direction of piling so that the pile can be accurately penetrated into the formation according to the designed direction. The basic technical parameters of a pile driver are the weight of the impact part, the impact kinetic energy and the impact frequency. Due to the large size and heavy weight of large pile drivers, they are not convenient to use in highway bridge construction, especially in highway bridge repair projects, and small pile drivers are usually used.

[0003] A Chinese patent with application number CN201820868141.9 discloses a handheld electric pile driver, comprising a main frame, a fixing box is fixedly installed on the outer surface of the upper end of the main frame, and a lamp tube is fixedly installed on the outer surface of one side of the fixing box, a shock-absorbing spring column is fixedly installed on the outer surface of one side of the main frame, a handle is fixedly installed on the outer surface of one end of the shock-absorbing spring column, an electric wire is fixedly connected to the outer surface of one side of the handle, and a plug is fixedly connected to the outer surface of one end of the electric wire away from the handle, a second connecting column is fixedly installed on the outer surface of the other side of the main frame, and a rotating ring is fixedly installed on the middle outer surface of the second connecting column.

[0004] The existing small pile driver requires two workers to hold the two ends of the top of the pile driver respectively to achieve the stability of the pile driver. Even a small pile driver is relatively heavy, and it is very difficult for one worker to carry it. During the road and bridge repair construction process, frequent manual handling of equipment affects the construction period and increases the workload of workers. For this reason, an improved pile driver for highway bridge construction has been designed. Summary of the invention

[0005] In view of the above-mentioned deficiencies in the prior art, the present invention provides a pile driver for highway bridge construction to solve the above-mentioned problems in the background technology.

[0006] In order to solve the above technical problems, the present invention adopts the following technical solutions:

[0007] A pile driver for highway bridge construction comprises a moving device and a pile driving device escalably connected to the moving device;

[0008] The mobile device includes a base plate, a mobile wheel is installed at the rear end of the bottom of the base plate, a notch is opened at the front end of the base plate for a pile driving device to drive piles, two support columns are connected to the rear end of the base plate, a top beam frame is connected between the tops of the two support columns, and a first gripping portion is provided on the top beam frame for workers to hold conveniently.

[0009] By adopting the above structural design, the pile driver for highway bridge construction is a small handheld pile driver used for roadside piling. By adding a moving device to the piling device, the movement of the pile driver is facilitated. The device has a simple structure and is easy to carry, which increases the convenience of small-scale construction, avoids the impact of frequent transportation of equipment on the construction period, and reduces the workload of workers.

[0010] Furthermore, the cross-sectional shape of the top beam frame is U-shaped, a first sliding column is connected between the front end of the top beam frame and the bottom plate, a top plate is connected to the middle position of the top beam frame, a second sliding column is connected between the top plate and the bottom plate, and a spring is sleeved on the second sliding column.

[0011] Furthermore, the piling device comprises:

[0012] A base plate is slidably connected to the first sliding column and the second sliding column, a driving motor is fixedly connected to the base plate, and a spiral drill rod is connected to the driving motor.

[0013] Furthermore, first sliding sleeves are connected to both sides of the base plate, a second sliding sleeve is connected to the rear end of the base plate, the first sliding sleeve is sleeved on a first sliding column, and the second sliding sleeve is sleeved on a second sliding column.

[0014] By adopting the above structural design, a first grip is provided on the top of the moving device, which is convenient for workers to grip and push the pile driver to move. A first sliding column and a second sliding column are installed on the bottom plate of the moving device. The pile driving device is slidably connected to the first sliding column and the second sliding column. The driving motor and the spiral drill rod of the pile driving device are connected to the base plate. The base plate is slidably connected through a sliding sleeve and a sliding column, thereby facilitating the lifting and lowering activities of the pile driving device for drilling and piling. When in use, only one person needs to hold the side grip on the outside of the base plate and start the driving motor to drive the spiral drill rod to drill holes. No two people are required to operate, which is more practical.

[0015] Furthermore, side gripping parts are connected to both sides of the base plate, and the side gripping parts include two L-shaped connecting rods arranged in parallel, a gripping rod is connected between the two connecting rods, and the first sliding sleeve is located between the two connecting rods.

[0016] Furthermore, the shape of the bottom plate is an arch shape, the notch on the front end of the bottom plate is semicircular, a slot is provided at the vertex of the outer edge of the notch, a pipe sleeve column is connected below the slot, the bottom of the pipe sleeve column is connected to the chassis, and a fixing cone passing through the pipe sleeve column and the chassis is passed through the slot.

[0017] By adopting the above structural design, a pipe sleeve column is provided at the bottom of the front end of the base plate, and a triangular structure is formed between the two movable wheels at the rear end, which is more stable. At the same time, a fixed cone is installed on the pipe sleeve column. When piling, the fixed cone is inserted into the roadside land, and the side grip is held with both hands. The spiral drill rod passes through the notch to contact the soil for drilling.

[0018] Furthermore, it also includes a hydraulic cylinder for driving the piling device to move up and down, one end of the hydraulic cylinder is fixedly connected to the top beam frame, and the other end is fixedly connected to the base plate.

[0019] Furthermore, the first gripping portion is a curved flat sheet material structure.

[0020] Furthermore, a circular limiting block is arranged on the top of the fixed cone.

[0021] Compared with the prior art, the present invention has the following beneficial effects:

[0022] 1. The pile driver for highway bridge construction is a small handheld pile driver used for roadside piling. By adding a mobile device to the piling device, the movement of the pile driver is facilitated. The device has a simple structure and is easy to carry, which increases the convenience of small-scale construction, avoids the impact of frequent equipment handling on the construction period, and reduces the workload of workers;

[0023] 2. A first grip is provided on the top of the mobile device, which is convenient for workers to grip and push the pile driver to move. A first sliding column and a second sliding column are installed on the bottom plate of the mobile device. The pile driver is slidably connected to the first sliding column and the second sliding column. The driving motor and the auger rod of the pile driver are connected to the base plate. The base plate is slidably connected through the sliding sleeve and the sliding column, so as to facilitate the lifting and lowering activities of the pile driver to perform drilling and piling. When in use, only one person needs to hold the side grip on the outside of the base plate and start the driving motor to drive the auger rod to drill holes. No two people are required to operate, which is more practical.

[0024] 3. A pipe sleeve column is set at the bottom of the front end of the base plate, forming a triangular structure with the two moving wheels at the rear end, which is more stable. At the same time, a fixed cone is installed on the pipe sleeve column. When piling, the fixed cone is inserted into the roadside land, and the side grip is held with both hands. The spiral drill rod passes through the notch to contact the soil for drilling. BRIEF DESCRIPTION OF THE DRAWINGS

[0025] Figure 1 A schematic diagram of the three-dimensional structure of an embodiment of a pile driver for highway bridge construction according to the present invention (viewing angle 1);

[0026] Figure 2 A schematic diagram of the three-dimensional structure of an embodiment of a pile driver for highway bridge construction according to the present invention (viewing angle 2);

[0027] Figure 3It is a schematic diagram of the three-dimensional structure of a moving device in an embodiment of a pile driver for highway bridge construction of the present invention;

[0028] Figure 4 A schematic diagram of the three-dimensional structure of a pile driving device in an embodiment of a pile driver for highway bridge construction of the present invention (viewing angle 1);

[0029] Figure 5 A schematic diagram of the three-dimensional structure of a pile driving device in an embodiment of a pile driver for highway bridge construction of the present invention (viewing angle 2);

[0030] Figure 6 A schematic diagram of the three-dimensional structure of an embodiment of a pile driver for highway bridge construction according to the present invention;

[0031] The reference numerals in the drawings of the specification include:

[0032] A moving device (1), a pile driving device (2), a fixed cone (3), a bottom plate (11), a notch (12), a moving wheel (13), a support column (14), a top beam frame (15), a first gripping portion (151), a top plate (16), a first sliding column (17), a second sliding column (18), a spring (19), a base plate (21), a driving motor (22), an auger rod (23), a side gripping portion (24), a connecting rod (241), a gripping rod (242), a first sliding sleeve (25), a second sliding sleeve (26), a slot (101), a pipe sleeve column (102), a chassis (103), and a hydraulic cylinder (4). DETAILED DESCRIPTION

[0033] In order to enable those skilled in the art to better understand the present invention, the technical solution of the present invention is further described below in conjunction with the accompanying drawings and embodiments.

[0034] Among them, the drawings are only used for illustrative explanations, and they only represent schematic diagrams rather than actual pictures, and should not be understood as limitations on this patent; in order to better illustrate the embodiments of the present invention, some parts of the drawings may be omitted, enlarged or reduced, and do not represent the size of the actual product; for those skilled in the art, it is understandable that some well-known structures and their descriptions in the drawings may be omitted.

[0035] The same or similar numbers in the drawings of the embodiments of the present invention correspond to the same or similar parts; in the description of the present invention, it should be understood that if the terms "upper", "lower", "left", "right", "inner", "outer", etc. appear, the orientation or position relationship indicated is based on the orientation or position relationship shown in the drawings, which is only for the convenience of describing the present invention and simplifying the description, rather than indicating or implying that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation. Therefore, the terms describing the position relationship in the drawings are only used for illustrative purposes and cannot be understood as a limitation on this patent. For ordinary technicians in this field, the specific meanings of the above terms can be understood according to specific circumstances.

[0036] In the description of the present invention, unless otherwise clearly specified and limited, if the term "connection" or the like appears to indicate the connection relationship between components, the term should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection or an indirect connection through an intermediate medium, it can be the internal connection of two components or the interaction relationship between two components. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.

[0037] Embodiment 1:

[0038] like Figure 1-5 Specifically, a pile driver for highway bridge construction includes a mobile device 1 and a pile driver 2 connected to the mobile device 1 in a liftable manner; the mobile device 1 includes a bottom plate 11, a moving wheel 13 is installed at the bottom rear end of the bottom plate 11, a notch 12 for the pile driver 2 to pile is opened at the front end of the bottom plate 11, two support columns 14 are connected to the rear end of the bottom plate 11, a top beam 15 is connected between the tops of the two support columns 14, and a first gripping portion 151 is provided on the top beam 15 for workers to hold.

[0039] By adopting the above structural design, the pile driver for highway bridge construction is a small handheld pile driver used for roadside piling. By adding a moving device 1 to the piling device 2, the movement of the pile driver is facilitated. The device has a simple structure and is easy to carry, which increases the convenience of small-scale construction, avoids the impact of frequent transportation of equipment on the construction period, and reduces the workload of workers.

[0040] In this embodiment, the cross-sectional shape of the top beam frame 15 is U-shaped, a first slide column 17 is connected between the front end of the top beam frame 15 and the bottom plate 11, a top plate 16 is connected to the middle position of the top beam frame 15, a second slide column 18 is connected between the top plate 16 and the bottom plate 11, and a spring 19 is sleeved on the second slide column 18.

[0041] In this embodiment, the piling device 2 comprises:

[0042] A base plate 21 slidably connected to the first sliding column 17 and the second sliding column 18 , a driving motor 22 fixedly connected to the base plate 21 , and a spiral drill rod 23 connected to the driving motor 22 .

[0043] The first sliding sleeves 25 are connected to both sides of the base plate 21 , and the second sliding sleeve 26 is connected to the rear end of the base plate 21 . The first sliding sleeve 25 is sleeved on the first sliding post 17 , and the second sliding sleeve 26 is sleeved on the second sliding post 18 .

[0044] By adopting the above structural design, a first gripping portion 151 is provided on the top of the mobile device 1, which is convenient for workers to hold and push the pile driver to move. A first sliding column 17 and a second sliding column 18 are installed on the bottom plate 11 of the mobile device 1. The pile driving device 2 is slidably connected to the first sliding column 17 and the second sliding column 18. The driving motor 22 and the auger rod 23 of the pile driving device 2 are connected to the base plate 21. The base plate 21 is slidably connected through a sliding sleeve and a sliding column, so as to facilitate the lifting and lowering activities of the pile driving device 2 for drilling and piling. When in use, only one person needs to hold the side gripping portion 24 on the outside of the base plate 21, start the driving motor 22 to drive the auger rod 23 to drill holes, and no two people are required to operate, which is more practical.

[0045] In this embodiment, side grips 24 are connected to both sides of the base plate 21 . The side grips 24 include two L-shaped connecting rods 241 arranged in parallel. A gripping rod 242 is connected between the two connecting rods 241 . The first sliding sleeve 25 is located between the two connecting rods 241 .

[0046] In this embodiment, the bottom plate 11 is in an arch shape, the notch 12 on the front end of the bottom plate 11 is semicircular, a slot 101 is provided at the vertex of the outer edge of the notch 12, a sleeve column 102 is connected below the slot 101, a bottom of the sleeve column 102 is connected to a chassis 103, and a fixing cone 3 passing through the sleeve column 102 and the chassis 103 is passed through the slot 101.

[0047] By adopting the above structural design, a pipe sleeve column 102 is provided at the bottom of the front end of the base plate 11, and a triangular structure is formed between the two moving wheels 13 at the rear end, which is more stable. At the same time, a fixed cone 3 is installed on the pipe sleeve column 102. When piling, the fixed cone 3 is inserted into the roadside soil, and the side gripping part 24 is held with both hands. The spiral drill rod 23 passes through the notch 12 to contact the soil for drilling.

[0048] In this embodiment, the first gripping portion 151 is a curved flat sheet structure.

[0049] In this embodiment, a circular limiting block is arranged on the top of the fixed cone 3 .

[0050] Working principle: When moving the pile driver, the moving wheel 13 at the rear end of the mobile device 1 is placed on the ground, the front end is tilted up, the first gripping part 151 is held, and the pile driver is pulled or pushed. When piling, the fixing cone 3 is stepped into the soil to fix it, and then both hands are held on the side gripping part 24 of the pile driver 2, and the driving motor 22 is started to drive the spiral drill rod 23 to pass through the notch 12 of the base plate 21 to contact the soil for drilling. The device has a simple structure and is easy to carry, which increases the convenience of small-scale construction, avoids the impact of frequent equipment handling on the construction period, and reduces the workload of workers;

[0051] like Figure 6 As shown, in order to save more manpower, the piling device 2 can also be driven by a hydraulic cylinder 4, thereby saving more manpower. Specifically, one end of the hydraulic cylinder 4 is fixedly connected to the top beam frame 15, and the other end is fixedly connected to the base plate 21.

[0052] The above are only embodiments of the present invention, and the circuits, electronic components and modules involved are all prior art, which can be fully implemented by those skilled in the art. It is needless to say that the content protected by this application does not involve improvements to software and methods. The common sense such as the known specific structures and characteristics in the scheme is not described in detail here. Ordinary technicians in the relevant field know all the common technical knowledge in the technical field of the invention before the application date or priority date, can obtain all the prior art in the field, and have the ability to apply conventional experimental means before that date. Ordinary technicians in the relevant field can improve and implement this scheme in combination with their own abilities under the enlightenment given by this application. Some typical known structures or known methods should not become obstacles for ordinary technicians in the relevant field to implement this application. It should be pointed out that for those skilled in the art, without departing from the structure of the present invention, several deformations and improvements can be made, which should also be regarded as the scope of protection of the present invention, and these will not affect the effect of the implementation of the present invention and the practicality of the patent.

Claims

1. A pile driver for highway bridge construction, characterized in that: It comprises a moving device (1) and a piling device (2) which is liftably connected to the moving device (1); The mobile device (1) comprises a base plate (11), a mobile wheel (13) is installed at the rear end of the bottom of the base plate (11), a notch (12) is provided at the front end of the base plate (11) for a pile driving device (2) to drive a pile, the rear end of the base plate (11) is connected to two support columns (14), a top beam frame (15) is connected between the tops of the two support columns (14), and a first gripping portion (151) is provided on the top beam frame (15) for workers to hold.

2. A pile driver for highway bridge construction as claimed in claim 1, characterized in that: The cross-sectional shape of the top beam frame (15) is U-shaped, a first sliding column (17) is connected between the front end of the top beam frame (15) and the bottom plate (11), a top plate (16) is connected to the middle position of the top beam frame (15), a second sliding column (18) is connected between the top plate (16) and the bottom plate (11), and a spring (19) is sleeved on the second sliding column (18).

3. A pile driver for highway bridge construction as claimed in claim 2, characterized in that: The piling device (2) comprises: A base plate (21) slidably connected to the first sliding column (17) and the second sliding column (18), a driving motor (22) fixedly connected to the base plate (21), and a spiral drill rod (23) connected to the driving motor (22).

4. A pile driver for highway bridge construction as claimed in claim 3, characterized in that: The two sides of the base plate (21) are connected to a first sliding sleeve (25), the rear end of the base plate (21) is connected to a second sliding sleeve (26), the first sliding sleeve (25) is sleeved on a first sliding column (17), and the second sliding sleeve (26) is sleeved on a second sliding column (18).

5. A pile driver for highway bridge construction as claimed in claim 4, characterized in that: Side gripping portions (24) are also connected to both sides of the base plate (21), and the side gripping portions (24) include two L-shaped connecting rods (241) arranged in parallel, a gripping rod (242) is connected between the two connecting rods (241), and the first sliding sleeve (25) is located between the two connecting rods (241).

6. A pile driver for highway bridge construction as claimed in claim 1, characterized in that: The bottom plate (11) is in an arch shape, the notch (12) on the front end of the bottom plate (11) is in a semicircular shape, a slot (101) is provided at the vertex of the outer edge of the notch (12), a pipe sleeve column (102) is connected below the slot (101), the bottom of the pipe sleeve column (102) is connected to a chassis (103), and a fixing cone (3) is provided in the slot (101) and passes through the pipe sleeve column (102) and the chassis (103).

7. A pile driver for highway bridge construction as claimed in claim 5, characterized in that: It also includes a hydraulic cylinder (4) for driving the pile driving device (2) to move up and down, wherein one end of the hydraulic cylinder (4) is fixedly connected to the top beam frame (15), and the other end is fixedly connected to the base plate (21).

8. A pile driver for highway bridge construction as claimed in claim 1, characterized in that: The first gripping portion (151) is a curved flat sheet metal structure.

9. A pile driver for highway bridge construction as claimed in claim 6, characterized in that: A circular limiting block is arranged on the top of the fixed cone (3).

Citation Information

Patent Citations

  • Electronic pile driver of hand -held type

    CN208533527U