Rapid construction method for water-collecting well cushion layer
Through the prefabricated water well cushion and setting the matching part, the problem of low existing construction efficiency was solved, and rapid alignment and installation were achieved, significantly saved the construction time, and improved efficiency and stability.
Patent Information
- Application Number
- CN202411575725.3
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-11-06
- Publication Date
- 2025-01-28
AI Technical Summary
The existing water collection well cushion construction methods have low construction efficiency, especially during rainy season construction, which extends the construction period and reduces efficiency.
Through the prefabricated water well cushion, set the matting part of the cushion and match the matching part of the foundation pit in the foundation pit of the water collection well to achieve rapid alignment and installation. Prefabricated reinforced mesh and hanging tendons in the prefabricated cushion to ensure stability and fast installation.
The prefabricated water well cushion method can significantly save construction time, improve construction efficiency, ensure the stability of the cushion, and apply to the construction of the rainy season, and improve the prospect of construction.
Smart Images

Figure CN119373226A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of building construction, in particular to a method for quickly constructing a water collection well cushion layer, and in particular to a method for constructing a water collection well cushion layer which can greatly improve the construction efficiency. Background Art
[0002] A water collection well is a well used to collect and store groundwater or seepage water. Modern buildings are often equipped with basements for parking. The basements are low-lying, so water collection wells are often required to facilitate drainage and avoid water seepage in the basements. At present, the cushion layers of basement water collection wells in the construction industry are all cast on site, that is, before the cushion layers are cast, the construction workers can only go down to the wells after the structural strength of the water collection wells reaches a certain requirement. This will greatly extend the construction period and reduce the construction efficiency, especially during the rainy season.
[0003] Therefore, it is of great practical significance to develop a water collection well cushion construction method with high construction efficiency. Summary of the invention
[0004] Since the prior art has the above-mentioned defects, the present invention provides a water collection well cushion layer construction method with high construction efficiency, which overcomes the defect of low construction efficiency of the current water collection well cushion layer construction method.
[0005] In order to achieve the above object, the present invention provides the following technical solutions:
[0006] A rapid construction method for a water collection well cushion layer comprises the following steps:
[0007] (1) Determine the specifications of the water collection well cushion layer according to the specifications of the water collection well foundation pit;
[0008] (2) prefabricating a water collection well cushion layer on the ground according to the specifications of the water collection well cushion layer obtained in step (1), wherein a cushion layer matching portion is provided on the prefabricated water collection well cushion layer, and a steel mesh and a suspension bar are pre-embedded in the prefabricated water collection well cushion layer;
[0009] (3) excavating a water collection well foundation pit, and setting a foundation pit matching part matching with the cushion matching part at the bottom of the water collection well foundation pit, and the position of the cushion matching part on the prefabricated water collection well cushion matches the position of the foundation pit matching part on the bottom surface of the water collection well foundation pit;
[0010] (4) placing the prefabricated water collection well cushion layer obtained in step (2) into the water collection well foundation pit from the well mouth of the water collection well, so that the cushion layer matching part on the prefabricated water collection well cushion layer fits with the foundation pit matching part of the water collection well foundation pit.
[0011] The rapid construction method for a water collection well cushion layer of the present invention prefabricates the water collection well cushion layer. When the water collection well is excavated to the bottom, the finished cushion layer can be immediately placed on the bottom of the pit, and then the workers can go down to carry out subsequent operations, which saves time and improves efficiency. At the same time, by arranging a cushion layer matching part of the prefabricated water collection well cushion layer and a foundation pit matching part in the water collection well foundation pit, rapid alignment can be achieved to ensure that the prefabricated water collection well cushion layer will not shake after being in place, has good stability and can further shorten the installation time, improve installation efficiency, and has good application prospects.
[0012] As the preferred technical solution:
[0013] In the rapid construction method of a water collection well cushion layer as described above, the foundation pit matching portion is a protrusion, and the cushion layer matching portion is a depression.
[0014] In the rapid construction method of a water collection well cushion layer as described above, the foundation pit matching portion is a depression, and the cushion layer matching portion is a protrusion.
[0015] The above-mentioned method for rapid construction of a water collection well cushion layer, the operation steps of the prefabricated water collection well cushion layer are as follows:
[0016] 1) Processing steel mesh and suspension bars;
[0017] 2) Tie the steel mesh pieces together in series through the hanging bars;
[0018] 3) Support external formwork;
[0019] 4) Pour concrete into the outer formwork;
[0020] 5) Cure the concrete and set it aside after it reaches a certain strength.
[0021] According to the quick construction method of a water collection well cushion layer as described above, the prefabricated water collection well cushion layer is placed into the water collection well foundation pit from the well mouth of the water collection well by hoisting.
[0022] In the rapid construction method of a water collection well cushion layer as described above, the specification of the water collection well cushion layer is smaller than the bottom surface of the water collection well foundation pit to ensure that the water collection well cushion layer can be conveniently placed in the water collection well foundation pit.
[0023] The above technical solution is only a feasible technical solution of the present invention, and the protection scope of the present invention is not limited thereto. Those skilled in the art can reasonably adjust the specific design according to actual needs.
[0024] The above invention has the following advantages or beneficial effects:
[0025] (1) The rapid construction method of the water collection well cushion layer of the present invention prefabricates the water collection well cushion layer. When the water collection well is excavated to the bottom, the finished cushion layer can be immediately placed at the bottom of the pit, and then the workers can go down to carry out subsequent operations, which saves time and improves efficiency;
[0026] (2) The rapid construction method of the water collection well cushion layer of the present invention can realize rapid alignment by setting the cushion layer matching part of the prefabricated water collection well cushion layer and the foundation pit matching part in the water collection well foundation pit, ensuring that the prefabricated water collection well cushion layer will not shake after being in place, having good stability and being able to further shorten the installation time, thereby improving the installation efficiency and having good application prospects. BRIEF DESCRIPTION OF THE DRAWINGS
[0027] The present invention and its features, appearance and advantages will become more apparent by reading the detailed description of non-limiting embodiments with reference to the following drawings. The same reference numerals indicate the same parts in all the drawings. The drawings are not drawn to scale, and emphasis is placed on illustrating the subject matter of the present invention.
[0028] Figure 1 It is a step sequence diagram of the rapid construction method of the water collection well cushion layer of the present invention. DETAILED DESCRIPTION
[0029] The structure of the present invention is further described below in conjunction with the accompanying drawings and specific embodiments, but is not intended to limit the present invention.
[0030] Example 1
[0031] A method for quickly constructing a water collection well cushion layer comprises the following steps (such as Figure 1 shown):
[0032] (1) The specifications of the water collection well cushion layer are determined according to the specifications of the water collection well foundation pit. The specifications of the water collection well cushion layer are smaller than the bottom surface of the water collection well foundation pit;
[0033] (2) prefabricating a water collection well cushion layer on the ground according to the specifications of the water collection well cushion layer obtained in step (1), wherein a cushion layer matching portion is provided on the prefabricated water collection well cushion layer, and a steel mesh and a suspension bar are pre-embedded in the prefabricated water collection well cushion layer;
[0034] The operation steps of prefabricated water collection well cushion are as follows:
[0035] 1) Processing steel mesh and suspension bars;
[0036] 2) Tie the steel mesh pieces together in series through the hanging bars;
[0037] 3) Support external formwork;
[0038] 4) Pour concrete into the outer formwork;
[0039] 5) Cure the concrete and keep it ready for use after it reaches the required strength;
[0040] (3) excavating a water collection well foundation pit, and setting a foundation pit matching part that matches the cushion matching part at the bottom of the water collection well foundation pit (the cushion matching part and the foundation pit matching part are matched through a concave-convex structure), and the position of the cushion matching part on the prefabricated water collection well cushion is matched with the position of the foundation pit matching part on the bottom surface of the water collection well foundation pit;
[0041] (4) The prefabricated water collection well cushion layer obtained in step (2) is placed from the well mouth of the water collection well into the water collection well foundation pit by hoisting, so that the cushion layer matching part on the prefabricated water collection well cushion layer fits with the foundation pit matching part of the water collection well foundation pit.
[0042] It has been verified that the rapid construction method for a water collection well cushion layer of the present invention can prefabricate the water collection well cushion layer. When the water collection well is excavated to the bottom, the finished cushion layer can be immediately placed at the bottom of the pit, and then the workers can go down to carry out subsequent operations, which saves time and improves efficiency. By arranging a cushion layer matching part of the prefabricated water collection well cushion layer and a foundation pit matching part in the water collection well foundation pit, rapid alignment can be achieved to ensure that the prefabricated water collection well cushion layer will not shake after being in place, has good stability and can further shorten the installation time, improve installation efficiency, and has good application prospects.
[0043] Those skilled in the art should understand that those skilled in the art can implement variations by combining the prior art and the above embodiments, which will not be described in detail here. Such variations do not affect the essential content of the present invention, and will not be described in detail here.
[0044] The above describes the preferred embodiments of the present invention. It should be understood that the present invention is not limited to the above-mentioned specific embodiments, and the devices and structures that are not described in detail should be understood to be implemented in a common manner in the art; any technician familiar with the art can use the above-disclosed methods and technical contents to make many possible changes and modifications to the technical solutions of the present invention without departing from the scope of the technical solutions of the present invention, or modify them into equivalent embodiments of equivalent changes, which does not affect the essential content of the present invention. Therefore, any simple modifications, equivalent changes and modifications made to the above embodiments based on the technical essence of the present invention without departing from the content of the technical solutions of the present invention are still within the scope of protection of the technical solutions of the present invention.
Claims
1. A rapid construction method for a water collection well cushion layer, characterized in that: The following steps are involved: (1) Determine the specifications of the water collection well cushion layer according to the specifications of the water collection well foundation pit; (2) prefabricating a water collection well cushion layer on the ground according to the specifications of the water collection well cushion layer obtained in step (1), wherein a cushion layer matching portion is provided on the prefabricated water collection well cushion layer, and a steel mesh and a suspension bar are pre-embedded in the prefabricated water collection well cushion layer; (3) excavating a water collection well foundation pit, and setting a foundation pit matching part matching with the cushion matching part at the bottom of the water collection well foundation pit, and the position of the cushion matching part on the prefabricated water collection well cushion matches the position of the foundation pit matching part on the bottom surface of the water collection well foundation pit; (4) placing the prefabricated water collection well cushion layer obtained in step (2) into the water collection well foundation pit from the well mouth of the water collection well, so that the cushion layer matching part on the prefabricated water collection well cushion layer fits with the foundation pit matching part of the water collection well foundation pit.
2. A rapid construction method for a water collection well cushion layer according to claim 1, characterized in that: The foundation pit matching portion is a protrusion, and the cushion layer matching portion is a depression.
3. A rapid construction method for a water collection well cushion layer according to claim 1, characterized in that: The foundation pit matching portion is a depression, and the cushion layer matching portion is a protrusion.
4. A rapid construction method for a water collection well cushion layer according to claim 1, characterized in that: The operation steps of the prefabricated water collection well cushion are as follows: 1) Processing steel mesh and suspension bars; 2) Tie the steel mesh pieces together in series through the hanging bars; 3) Support external formwork; 4) Pour concrete into the outer formwork; 5) Cure the concrete and set it aside after it reaches a certain strength.
5. A rapid construction method for a water collection well cushion layer according to claim 1, characterized in that: The prefabricated water collection well cushion layer is placed into the water collection well foundation pit from the water collection well mouth by hoisting.
6. A rapid construction method for a water collection well cushion layer according to claim 1, characterized in that: The specification of the water collection well cushion layer is smaller than the bottom surface of the water collection well foundation pit.