Blower room air gallery and air purification device
By adopting variable angle diversion vanes and multi-stage filtering structures in the air corridor of the blower, combined with variable cross-section unit and control system, the problem of excessive dust in the air intake of the blower is solved, and stable air pressure and high-efficiency air filtration are achieved, and the The device life is improved and the blower efficiency is improved.
Patent Information
- Application Number
- CN202411581418.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-11-07
- Publication Date
- 2025-02-07
AI Technical Summary
The excessive dust content in the blower intake air leads to accelerated blade wear, reduced efficiency, balance damage, corrosion and air passage blockage. The existing air corridor design and air filtration methods cannot effectively solve these problems.
A blower room air corridor and air purification device are designed, using variable angle diversion vane and multi-stage filter structure, combined with variable cross-section unit and control system to achieve stable air pressure and high-efficiency air filtration.
By dynamically adjusting the angle of the diversion blades and multi-stage filtration, the air pressure in the air corridor can be stabilized, the service life of the air filter device can be extended, and the working efficiency of the blower can be improved.
Smart Images

Figure CN119386569A_ABST
Abstract
Description
Technical Field
[0001] The invention belongs to the technical field of blower air corridors, and in particular relates to a blower room air corridor and an air purification device. Background Art
[0002] Excessive dust content in the blower intake air will have adverse effects on the air pump blades, mainly including:
[0003] 1) Accelerated wear: A large amount of dust will intensify the friction and wear on the blade surface and shorten the service life of the blade.
[0004] 2) Reduced efficiency: Dust accumulation on the blade surface will change the aerodynamic characteristics of the blade and reduce the working efficiency of the air pump.
[0005] 3) Balance destruction: Uneven dust deposition on the blades may cause the rotor to lose balance and cause vibration.
[0006] 4) Corrosion: Certain dust components may be corrosive and accelerate the degradation of blade materials.
[0007] 5) Blockage of air duct: In severe cases, it may cause blockage of air duct and affect air circulation.
[0008] In order to solve the above problems, an air filter device needs to be installed to filter the air intake of the blower. At present, the blower air corridor design method and air filtration method have the following main problems:
[0009] 1) The wind pressure inside the air corridor is unstable, which can easily affect the operation of the blower.
[0010] 2) The air filtration method is simple and cannot guarantee long-term normal operation, resulting in a large amount of dust and other impurities inside the air corridor, which wears the blades. Summary of the invention
[0011] In order to solve the above problems existing in the prior art, the purpose of the present invention is to provide an air corridor and air purification device for a blower room, which greatly improves the working efficiency of the blower and increases the service life of the air filtration device by stabilizing the wind pressure and multi-stage filtration.
[0012] The technical solution adopted by the present invention is:
[0013] A blower room air gallery and air purification device, comprising an air gallery body, one end of which is provided with an air inlet, the side of the air gallery body is connected with a plurality of blowers, a plurality of variable-angle guide blades are installed in the air gallery body, and the air inlet of the air gallery body is provided with an air purification unit and a variable-section unit for shielding the air purification unit.
[0014] The variable angle guide vane of the present invention can dynamically adjust the angle, and each variable angle guide vane can be adjusted within the range of 0° to 60°, with a response time of less than 2 seconds. The airflow direction and speed are adjusted in real time according to the current blower operating state and the required airflow distribution, thereby optimizing the airflow distribution of the entire system. The variable angle guide vane can stabilize the wind pressure inside the air corridor body and ensure the efficiency and life of the air compressor.
[0015] The air inlet of the air corridor body of the present invention is provided with an air purification unit and a variable cross-section unit for shielding the air purification unit. The variable cross-section unit can be freely unfolded and cooperate with the variable angle guide blade to shield part of the air purification unit to reduce pollution when the air intake is small.
[0016] As a preferred embodiment of the present invention, the present invention further comprises a control system, the rotating shaft of the variable angle guide vane is connected with an angle adjustment drive device, and the angle adjustment drive device is electrically connected with the control system.
[0017] The control system receives the parameters of pressure and particle concentration from the main body of the air corridor, analyzes the obvious negative pressure area at the air inlet of the opened blower in the corridor, calculates the optimal variable angle guide blade angle configuration based on the inlet air volume, temperature, humidity, and air purification device wind resistance, and drives the motor to accurately adjust the angle of each variable angle guide blade according to the calculation results. The change in the angle of the blade changes the direction and speed of the airflow, thereby optimizing the airflow distribution of the entire system. The whole process is continuous, and the system can quickly respond to any changes in the operating status of the air compressor.
[0018] The variable cross-section unit cooperates with the variable angle guide vane to shield part of the air purification unit when the air intake volume is small. The specific shielding range is uniformly controlled according to the aforementioned control system.
[0019] As a preferred solution of the present invention, a high-sensitivity pressure gauge and an air particle detector are installed in the air corridor body, and both the high-sensitivity pressure gauge and the air particle detector are electrically connected to the control system.
[0020] As a preferred solution of the present invention, a dust removal grille is installed at the bottom of the air gallery body, and a dust collecting screw is installed in the dust removal grille.
[0021] As a preferred solution of the present invention, the dust collecting screw comprises a power rod, the power rod has a built-in heating device, and a dust collecting spiral is arranged on the power rod.
[0022] As a preferred embodiment of the present invention, a dust collecting surface is provided on the dust collecting spiral, an electrode grid is provided on the dust collecting surface, the electrode grid is electrically connected to a power supply system, and the power supply system is electrically connected to a voltage regulating device.
[0023] The dust collecting surface uses electric electrostatic adsorption to enhance adsorption capacity. The dust collecting surface uses conductive or semi-conductive materials such as metal grids, conductive polymers or carbon nanotube composites. An electrode grid is set on the dust collecting surface, equipped with a high-voltage DC power supply, usually between several thousand volts and tens of thousands of volts. A voltage regulator is added to adjust the electrostatic field strength as needed.
[0024] The power rod rotates counterclockwise, so that part of the desorbed dust is collected at the bottom. During the maintenance phase, the electric electrostatic adsorption device can be turned off, and the power rod has a built-in heating device. When the heating device is turned on, the temperature rises to 80°C, so that the heated desorbed dust is collected at the bottom.
[0025] As a preferred embodiment of the present invention, the air purification unit is provided with a multi-stage filtering structure from coarse to fine. The air purification unit is composed of smaller filter units, and a single filter unit has a diameter of 20 cm, which is convenient for later replacement and maintenance. The filter unit filter layer adopts gradient filtration: multi-stage filtration is set from coarse to fine, for example, a primary filter is used to remove large particles first, and then a medium filter (electrostatic precipitator: effectively removes tiny particles).
[0026] As a preferred solution of the present invention, the air inlet of the air corridor body is provided with a slide rail, and the air purification unit is arranged in the slide rail. The air purification unit can be moved into the cleaning device for cleaning via the slide rail.
[0027] As a preferred embodiment of the present invention, the variable cross-section unit includes an electric rotating device installed at the air inlet of the air corridor body, the electric rotating device is connected to a plurality of shielding plates connected in sequence, a power device is installed on the inner shielding plate, a power screw is connected to the output end of the power device, a fixing nut is connected to the outer shielding plate, the power screw is threadedly connected to the fixing nut, and the power screws on adjacent shielding plates are perpendicular to each other.
[0028] The electric rotating device can drive the entire variable cross-section unit to tilt as a whole, thereby controlling the opening and closing of the variable cross-section unit. The power device on the inner shielding plate drives the power screw to rotate, thereby driving the fixed nut on the outer shielding plate to move linearly. The outer shielding plate moves with the fixed nut to adjust the shielding area of the air purification unit and adjust the air intake in the main body of the air corridor.
[0029] As a preferred solution of the present invention, the number of the shielding plates is four, and the area of each shielding plate is one quarter of the area of the air inlet of the air corridor body. When the four shielding plates are fully unfolded, the air purification unit can be completely covered.
[0030] The beneficial effects of the present invention are:
[0031] 1. The variable angle guide vane of the present invention can dynamically adjust the angle. Each variable angle guide vane can be adjusted within the range of 0° to 60°, and the response time is less than 2s. The airflow direction and speed are adjusted in real time according to the current blower operation status and the required airflow distribution, thereby optimizing the airflow distribution of the entire system. The variable angle guide vane can stabilize the wind pressure inside the air corridor body and ensure the efficiency and life of the air compressor.
[0032] 2. The air inlet of the air corridor body of the present invention is provided with an air purification unit and a variable cross-section unit for shielding the air purification unit. The variable cross-section unit can be freely unfolded and cooperate with the variable angle guide blades. When the air intake is small, part of the air purification unit is shielded to reduce pollution. BRIEF DESCRIPTION OF THE DRAWINGS
[0033] Figure 1 It is a schematic diagram of the structure of the present invention;
[0034] Figure 2 It is a partial structural diagram of the present invention;
[0035] Figure 3 yes Figure 2 A partial enlarged view of the middle A;
[0036] Figure 4 is a structural schematic diagram of an air purification unit;
[0037] Figure 5 It is a schematic structural diagram of the air purification unit and the variable cross-section unit in the first direction;
[0038] Figure 6 It is a structural schematic diagram of the air purification unit and the variable cross-section unit in the second direction;
[0039] Figure 7 It is a structural diagram of a variable cross-section unit.
[0040] In the figure: 1-air corridor body; 2-blower; 3-variable angle guide blade; 4-air purification unit; 5-variable cross-section unit; 6-dust removal grille; 7-dust collecting screw; 8-slide rail; 51-electric rotating device; 52-shielding plate; 53-power device; 54-power screw; 55-fixing nut; 71-power rod; 72-dust collecting spiral; 73-dust collecting surface. DETAILED DESCRIPTION
[0041] In order to make the purpose, technical solutions and advantages of the embodiments of the present invention clearer, the technical solutions in the embodiments of the present invention will be clearly and completely described below in conjunction with the drawings in the embodiments of the present invention. Obviously, the described embodiments are part of the embodiments of the present invention, not all of the embodiments. Generally, the components of the embodiments of the present invention described and shown in the drawings here can be arranged and designed in various different configurations.
[0042] Therefore, the following detailed description of the embodiments of the present invention provided in the accompanying drawings is not intended to limit the scope of the claimed invention, but merely represents selected embodiments of the present invention. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in the field without creative work are within the scope of protection of the present invention. It should be noted that the embodiments of the present invention and the features in the embodiments can be combined with each other without conflict.
[0043] like Figure 1 and Figure 2 As shown, the blower room air corridor and air purification device of this embodiment include an air corridor main body 1, an air inlet is arranged at one end of the air corridor main body 1, a plurality of blowers 2 are connected to the side of the air corridor main body 1, a plurality of variable-angle guide blades 3 are installed in the air corridor main body 1, and an air purification unit 4 and a variable-section unit 5 for shielding the air purification unit 4 are arranged at the air inlet of the air corridor main body 1.
[0044] The present invention also includes a control system, the rotating shaft of the variable angle guide vane 3 is connected to an angle adjustment drive device, and the angle adjustment drive device is electrically connected to the control system. High-sensitivity pressure gauges and air particle detectors are evenly arranged in the air corridor body 1, and the high-sensitivity pressure gauges and air particle detectors are arranged at the top of the dust removal grille 6, and the high-sensitivity pressure gauges and air particle detectors are electrically connected to the control system.
[0045] The existing 2-room ventilation corridor of the blower is often difficult to meet the wind resistance requirements of air purification and multiple air compressors working at the same time. When multiple air compressors are running at the same time, the wind resistance of the ventilation corridor will increase significantly, affecting the efficiency and life of the air compressor. At the same time, traditional fixed air purification devices are difficult to maintain optimal performance under different working conditions.
[0046] The variable angle guide blade 3 of the present invention can dynamically adjust the angle, and each variable angle guide blade 3 can be adjusted within the range of 0° to 60°, with a response time of less than 2 seconds. The airflow direction and speed are adjusted in real time according to the current operating state of the blower 2 and the required airflow distribution, thereby optimizing the airflow distribution of the entire system. The variable angle guide blade 3 is made of carbon fiber composite material. The variable angle guide blade 3 can stabilize the wind pressure inside the air corridor body 1 and ensure the efficiency and life of the air compressor.
[0047] Working principle of variable angle guide blade 3: The control system receives the parameters of pressure and particle concentration from the air corridor body 1, analyzes the obvious negative pressure area at the air inlet of the blower 2 in the corridor, calculates the optimal angle configuration of variable angle guide blade 3 according to the inlet air volume, temperature, humidity, and air purification device wind resistance, and drives the motor to accurately adjust the angle of each variable angle guide blade 3 according to the calculation results. The change in the angle of the blade changes the direction and speed of the airflow, thereby optimizing the airflow distribution of the entire system. The whole process continues, and the system can quickly respond to any changes in the operating status of the air compressor.
[0048] The variable cross-section unit 5 is electrically connected to the control system. The variable cross-section unit 5 cooperates with the variable angle guide vane 3 to shield part of the air purification unit 4 when the air intake is small, and the specific shielding range is uniformly controlled according to the aforementioned control system.
[0049] The air inlet of the air corridor body 1 of the present invention is provided with an air purification unit 4 and a variable cross-section unit 5 for shielding the air purification unit 4. The variable cross-section unit 5 can be freely unfolded and cooperate with the variable angle guide blade 3. When the air intake is small, part of the air purification unit 4 is shielded to reduce pollution.
[0050] like Figure 3 As shown, a dust removal grille 6 is installed at the bottom of the air gallery body 1, and a dust collecting screw 7 is installed in the dust removal grille 6. The gap of the dust removal grille 6 is 2 to 10 mm.
[0051] The dust collecting screw 7 includes a power rod 71, a heating device is built in the power rod 71, and a dust collecting spiral 72 is arranged on the power rod 71. The dust collecting spiral 72 is provided with a dust collecting surface 73, and an electrode grid is arranged on the dust collecting surface 73, and the electrode grid is electrically connected to a power supply system, and the power supply system is electrically connected to a voltage regulating device.
[0052] The dust collecting surface 73 uses electrostatic adsorption to enhance adsorption capacity. The dust collecting surface 73 uses conductive or semi-conductive materials, such as metal grids, conductive polymers or carbon nanotube composites. An electrode grid is set on the dust collecting surface 73, equipped with a high-voltage DC power supply, usually between several thousand volts and tens of thousands of volts. A voltage regulator is added to adjust the electrostatic field strength as needed.
[0053] The power rod 71 rotates counterclockwise to collect part of the desorbed dust at the bottom. During the maintenance phase, the electric electrostatic adsorption device can be turned off, and the power rod 71 has a built-in heating device. When the heating device is turned on, the temperature rises to 80° C., so that the heated desorbed dust is collected at the bottom.
[0054] The air purification unit 4 is provided with a multi-stage filtering structure from coarse to fine. The air purification unit 4 is composed of smaller filter units, and a single filter unit has a diameter of 20 cm, which is convenient for later replacement and maintenance. The filter unit filter layer adopts gradient filtration: multi-stage filtration is set from coarse to fine, for example, a primary filter is used to remove large particles first, and then a medium-efficiency filter (electrostatic precipitator: effectively removes tiny particles).
[0055] like Figure 4 As shown, the air inlet of the air corridor body 1 is provided with a slide rail 8, and the air purification unit 4 is arranged in the slide rail 8. The air purification unit 4 can be moved into the cleaning device through the slide rail 8 for cleaning.
[0056] like Figure 5 to Figure 7 As shown, the variable-section unit 5 includes an electric rotating device 51, a mounting frame is fixed outside the slide rail 8, the electric rotating device 51 is installed on the mounting frame, the electric rotating device 51 is connected to a plurality of shielding plates 52 connected in sequence, a power device 53 is installed on the inner shielding plate 52, the output end of the power device 53 is connected to a power screw 54, a fixing nut 55 is connected to the outer shielding plate 52, the power screw 54 is threadedly connected to the fixing nut 55, and the power screws 54 on adjacent shielding plates 52 are perpendicular to each other.
[0057] The electric rotating device 51 can drive the entire variable cross-section unit 5 to tilt as a whole, thereby controlling the opening and closing of the variable cross-section unit 5. The power device 53 on the inner shielding plate 52 drives the power screw 54 to rotate, thereby driving the fixing nut 55 on the outer shielding plate 52 to move linearly, and the outer shielding plate 52 moves with the fixing nut 55 to adjust the shielding area of the air purification unit 4, and the air intake in the air corridor body 1 is adjusted.
[0058] Specifically, there are four shielding plates 52, and the area of each shielding plate 52 is one quarter of the area of the air inlet of the air corridor body 1. When the four shielding plates 52 are fully unfolded, the air purification unit 4 can be completely covered.
[0059] The present invention is not limited to the above-mentioned optional implementation modes. Anyone can derive other various forms of products under the inspiration of the present invention. However, no matter what changes are made in the shape or structure, all technical solutions that fall within the scope defined by the claims of the present invention fall within the protection scope of the present invention.
Claims
1. An air corridor and air purification device for a blower room, characterized in that: The invention comprises an air corridor body (1), one end of which is provided with an air inlet, a plurality of blowers (2) are connected to the side of the air corridor body (1), a plurality of variable-angle guide blades (3) are installed in the air corridor body (1), and an air purification unit (4) and a variable-section unit (5) for shielding the air purification unit (4) are provided at the air inlet of the air corridor body (1).
2. The air corridor and air purification device for a blower room according to claim 1, characterized in that: It also comprises a control system, the rotating shaft of the variable angle guide blade (3) is connected to an angle adjustment drive device, and the angle adjustment drive device is electrically connected to the control system.
3. The air corridor and air purification device for a blower room according to claim 2, characterized in that: A high-sensitivity pressure gauge and an air particle detector are installed in the air gallery body (1), and both the high-sensitivity pressure gauge and the air particle detector are electrically connected to the control system.
4. The air corridor and air purification device for a blower room according to claim 1, characterized in that: A dust removal grille (6) is installed at the bottom of the air gallery body (1), and a dust collection screw (7) is installed inside the dust removal grille (6).
5. The air corridor and air purification device for a blower room according to claim 4, characterized in that: The dust collecting screw (7) comprises a power rod (71), the power rod (71) has a built-in heating device, and a dust collecting spiral (72) is arranged on the power rod (71).
6. The air corridor and air purification device for a blower room according to claim 5, characterized in that: The dust collecting spiral (72) is provided with a dust collecting surface (73), the dust collecting surface (73) is provided with an electrode grid, the electrode grid is electrically connected to a power supply system, and the power supply system is electrically connected to a voltage regulating device.
7. The air corridor and air purification device for a blower room according to claim 1, characterized in that: The air purification unit (4) is provided with a multi-stage filtering structure from coarse to fine.
8. The air corridor and air purification device for a blower room according to claim 1, characterized in that: The air inlet of the air corridor body (1) is provided with a slide rail (8), and the air purification unit (4) is arranged inside the slide rail (8).
9. The air corridor and air purification device for a blower room according to claim 1, characterized in that: The variable cross-section unit (5) comprises an electric rotating device (51) installed at the air inlet of the air corridor body (1); the electric rotating device (51) is connected to a plurality of shielding plates (52) connected in sequence; a power device (53) is installed on the inner shielding plate (52); the output end of the power device (53) is connected to a power screw (54); the outer shielding plate (52) is connected to a fixing nut (55); the power screw (54) is threadedly connected to the fixing nut (55); and the power screws (54) on adjacent shielding plates (52) are perpendicular to each other.
10. The air corridor and air purification device for a blower room according to claim 9, characterized in that: The number of the shielding plates (52) is four, and the area of each shielding plate (52) is one quarter of the area of the air inlet of the air corridor body (1).