Optimized modular structure system and installation process
By adopting a modular structure system with stacked beam shear connectors and articulated connections in the module building, the problems of poor seismic performance and increased building height of existing module buildings are solved, and the effect of improving structural safety performance and reducing construction costs is achieved.
Patent Information
- Application Number
- CN202411617474.0
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-11-13
- Publication Date
- 2025-02-07
AI Technical Summary
In the existing module building structure, the column stiffness is smaller than the strength and stiffness of the long-side bottom beam, resulting in poor seismic resistance, increased building height, uneconomical space occupied, and complex installation process, making it difficult to achieve rigid joint of columns.
Adopted an optimized module structure system, including columns, top beams and bottom beams. The top beams and bottom beams are connected by stacked beam shear connectors to make them work together. The columns of the upper and lower building modules are hinged and connected, and are installed with "drawer" type. Methods to reduce costs and construction difficulty.
It improves structural safety performance, improves product quality, reduces the structure's floor height and cost, improves earthquake resistance, and reduces construction difficulty and cost.
Smart Images

Figure CN119392943A_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of prefabricated buildings, and in particular to an optimized module structure system and installation process. Background Art
[0002] Modular construction is an emerging building structure system that uses each room as a modular unit, which is prefabricated in a factory, transported to the site, and assembled into a whole building through reliable connections.
[0003] Each module unit is a rectangular module composed of four corner columns, four bottom beams and four top beams. The upper and lower module units are connected by rigid connection of columns, and the top beams and bottom beams between the upper and lower module units work independently.
[0004] From the above-mentioned characteristics of modular buildings, it can be seen that the stiffness of the columns of modular buildings is easily caused to be significantly smaller than the strength and stiffness of the long side bottom beams. This beam-column relationship is not conducive to the seismic ductility design of the structure, because the beams in the seismic performance frame should yield before the columns, and plastic hinges appear in the beams to dissipate seismic energy. The nature of strong beams and weak columns in modular buildings will cause the columns to be destroyed first before the beams dissipate seismic energy under the action of an earthquake, which is not conducive to the seismic resistance of the structure.
[0005] The bottom beam and top beam work independently. In order to ensure the strength and rigidity of the beam, the cross-sectional size is selected to be larger, and the amount of steel and cost are both high. In addition, the top beam and bottom beam of the upper and lower module units constitute the space occupied by the module beam structure, which is significantly higher than the height of the ordinary frame structure beam. The height of each floor can differ by more than 0.18m. The height of a twenty-story building differs by 3.6m, which is equivalent to the height of one floor. The more floors there are, the greater the cumulative height, which is obviously not economical.
[0006] The upper and lower columns between floors are rigidly connected. In modular buildings, the structure that has completed some internal and external decoration reduces the operability on site, and the building modules are hoisted one by one during the installation process, further obscuring the on-site construction connection space, making it difficult to achieve rigid connection of the columns; if construction holes are left for on-site connection, the on-site work of closing the holes will reduce the quality of the finished building.
[0007] Based on the above problems, how to optimize the existing modular buildings is an urgent problem to be solved. Summary of the invention
[0008] The present invention provides an optimized module structure system and installation process, proposes an optimized design scheme for the module frame structure, so as to achieve the purpose of improving the structural safety performance and enhancing the product quality, and at the same time proposes a "drawer-type" installation method to reduce the cost and construction difficulty.
[0009] In order to solve the above technical problems, the present invention adopts the following technical solutions: The present invention discloses an optimized module structure system, comprising columns, top beams and bottom beams, wherein the beam ends of the top beams and bottom beams are provided with skeleton nodes; the top beams and bottom beams of the upper and lower building modules are connected by stacked beam shear connectors so that the top beams and bottom beams work together; the columns of the upper and lower building modules are hingedly connected.
[0010] The module structural system optimized by the present invention is further characterized in that angle steels are fixedly arranged between the top beams and the bottom beams at the inner corners of the building modules at the skeleton-like node positions.
[0011] The module structural system optimized by the present invention is further provided with cover plates at the connection between the ends of the top beam and the bottom beam and the columns, and inner partition plates are provided on the inner sides of the columns at positions corresponding to the cover plates.
[0012] The module structure system optimized by the present invention is further characterized in that a conical latch is provided at the lower end of the column, and a socket which is spliced with the conical latch is provided on the inner partition plate at the upper end of the column.
[0013] The modular structural system optimized by the present invention further has a column side connecting plate provided at the upper and lower connections of the outer columns not covered by the building modules, bolt holes are provided on the column side connecting plate and the side walls of the columns, nuts are fixed on the inner walls of the columns, and the column side connecting plate is connected to the columns by bolts to form a hinged connection at the column base.
[0014] The module structural system optimized by the present invention is further characterized in that the stacked beam shear connector comprises a lower shear member and an upper shear member, wherein the lower shear member is fixedly mounted on the top beam of the lower building module, and the upper shear member is fixedly mounted on the bottom beam of the upper building module, and the lower shear member is provided with a slider which can slide along the width direction of the top beam flange, and the upper shear member is provided with a socket slot formed at the bottom of the bottom beam, and the slider slides into the socket slot to connect the top beam and the bottom beam, and the socket slot has upper, lower, left and right direction limit functions for the slider.
[0015] The optimized module structure system of the present invention further comprises: the lower anti-shear member comprises a fixing member fixed on the side of the top beam, the top surface of the fixing member is provided with a guide rail, and the slide block is provided with a slide groove that slidably cooperates with the guide rail; The upper shear-resistant member includes a socket block and a stiffening rib. The socket blocks are provided in two pieces and fixed on the lower flange of the bottom beam. A socket slot for inserting a sliding block is formed between the two socket blocks. The stiffening rib is fixed between the upper and lower flange plates of the bottom beam corresponding to the installation position of the socket blocks.
[0016] The module structure system optimized by the present invention is further connected between the fixing member and the slider via a spring, one end of the spring is connected to the insertion end of the slider, and the other end is connected to the fixing member, and the spring is in a stretched state after the slider slides out of the socket and is in a natural state after being inserted into the socket; A positioning hole is provided at the bottom of the slider, and a spring self-locking pin is provided on the fixing member. The spring self-locking pin is inserted into the positioning hole to fix the position of the slider.
[0017] The module structural system optimized by the present invention is further characterized in that the stacked beam shear connectors are installed at the quarter points of the ends of the top beam and the bottom beam.
[0018] The present invention provides an installation process, comprising the following steps: Step 1: Arrange a ground rail at the center of the upper flange of the top beam of the building module. The ground rail is arranged intermittently at the stacked beam shear connector. An introduction rib is provided on the inner partition plate at the upper end of the column. The introduction rib is located on both sides of the insertion hole and the top surface of the introduction rib is flush with the top surface of the column. Step 2: transport the building module and place it on the guide rail frame on the ground, align the guide rail frame with the lifting bracket, install a hydraulic lifting roller device on the lower side of the column, the hydraulic lifting roller device includes a base, a hydraulic jack and a column side sliding connector, a roller is installed under the base, and the roller has a track groove that matches the ground rail; the hydraulic jack is installed between the base and the column side sliding connector, the base and the column side sliding connector are matched along the vertical sliding, and the column side sliding connector is connected to the column; Step 3: Raise the hydraulic jack, push the building module from the guide rail frame into the lifting bracket, and lift the lifting bracket to the installation position; Step 4: Apply a mixture of iron filings and steel glue on the slider, and use the traction module to slide the building module along the ground rail into the installation position; Step 5: Use the hydraulic jack to lower the height of the column so that the tapered pin can be inserted into the socket at the top of the column; Step 6: Remove the hydraulic lifting roller device, pull out the positioning spring pin and insert it into the slider; connect the column side connecting plate on one side of the column.
[0019] Compared with the prior art, the present invention has the following beneficial effects: 1. This application proposes an optimized design scheme for the modular frame structure to improve the structural safety performance and product quality. At the same time, it proposes a "drawer-type" installation method to reduce costs and construction difficulty; 2. The stacked beam shear connector method is adopted to make the top and bottom beams of adjacent building modules work together, reducing the cross-sectional height and cost of a single top and bottom beam, reducing the floor height and cost occupied by the structure, and effectively improving the rigidity and strength of the composite beam and reducing the deflection of the floor slab; 3. The nodes of the upper and lower columns are hinged, which can work together with the shear connectors between the beams to achieve the rigid connection effect of the columns in the overall structural performance, solving the problem of large displacement between layers under the hinged structure; 4. Weaken the flanges at the ends of the top and bottom beams to form a skeleton node. Connect the top and bottom beams through stacked beam shear connectors, which reduces the strength and stiffness of the beam section. Therefore, it is easier to form plastic hinges at the beam ends to dissipate seismic energy. It also changes the characteristics of strong beams and weak columns in modular buildings, so that the beams yield before the columns, thereby improving the seismic performance of the columns. 5. The column is hinged, which has lower requirements than rigid connection; 6. The shear connector is a self-locking connection; a module lifting and sliding installation method is provided for a "drawer-type" installation method to reduce costs and construction difficulty.
[0020] The present invention will be further described below in conjunction with the accompanying drawings. BRIEF DESCRIPTION OF THE DRAWINGS
[0021] Figure 1 It is a schematic diagram of the bone-type node of the present invention; Figure 2 It is a schematic diagram of the column bottom structure of the present invention; Figure 3 This is a schematic diagram of the installation of the column side sliding connection member of the present invention; Figure 4 This is a schematic diagram of the installation structure of the stacked beam shear connector of the present invention; Figure 5 This is a schematic diagram of the structure of the shear-resistant member of the present invention; Figure 6 This is a schematic diagram of the cooperation between the slider and the fixing member of the present invention; Figure 7 This is a schematic diagram of the structure of the spring self-locking latch of the present invention; Figure 8 This is a schematic diagram of the shear-resistant member structure of the present invention; Fig. 9 This is a schematic diagram of the floor rail installation structure of the present invention; Fig.10 This is a schematic diagram of the installation structure of the hydraulic lifting roller device of the present invention; Fig.11 It is an explosion diagram of the hydraulic lifting roller device of the present invention; Fig.12 This is a schematic diagram of the cooperation between the roller and the ground rail of the present invention; Fig.13 It is a schematic diagram of the building module of the present invention sliding from the guide rail frame into the lifting bracket; Fig.14 It is a schematic diagram of the building module of the present invention sliding from the lifting bracket into the installation position.
[0022] Reference numerals: 1. Building module; 2. Column; 3. Top beam; 4. Bottom beam; 5. Skeleton node; 6. Stacked beam shear connector; 6.1. Lower shear member; 6.1.1. Slider; 6.1.2. Fixing member; 6.1.3. Guide rail; 6.1.4. Slide; 6.1.5. Fixing plate; 6.1.6. Spring; 6.1.7. Positioning hole; 6.1.8. Spring self-locking pin; 6.2. Upper shear member; 6.2.1. Socket slot; 6.2.2. Socket block; 6.2.3. Stiffening rib; 7. Angle steel; 8. Cover plate; 9. Inner partition; 10. Steel castings; 11. Conical pins; 12. Sockets; 13. Guide ribs; 14. Column side connection plates; 15. Ground rails; 16. Guide rail frames; 17. Lifting brackets; 18. Hydraulic lifting roller device; 18.1. Base; 18.2. Hydraulic jacks; 18.3. Column side sliding connectors; 18.3.1. Side plates; 18.3.2. Horizontal cross plates; 18.3.3. Vertical plates; 18.3.4. Reinforcing ribs; 18.4. Rollers; 18.5. Rail grooves; 18.6. Mounting grooves; 18.7. Smooth bolts; 18.8. Vertical grooves. DETAILED DESCRIPTION
[0023] Reference Figure 1-14 The invention discloses an optimized module structure system and installation process.
[0024] Embodiment 1: The optimized module structure system includes columns 2, top beams 3 and bottom beams 4. Skeleton nodes 5 are provided at both ends of the top beams 3 and the bottom beams 4. The top beams 3 and the bottom beams 4 of the upper and lower building modules 1 are connected by stacked beam shear connectors 6, so that the top beams 3 and the bottom beams 4 work together, and the columns 2 of the upper and lower building modules 1 are hingedly connected.
[0025] The maximum length of the skeleton node 5 is 1.0hb, and the maximum cutting depth of the flange is 0.35bf, so as to increase the lateral plasticity resistance of the frame, where hb is the section height and bf is the wing plate width; angle steels 7 are fixedly welded between the top beams 3 and 3, and the bottom beams 4 and 4 at the inner corners of the building module 1 at the position of the skeleton node 5, and the angle steels 7 are connected to the middle of the webs of the top beams 3 and the bottom beams 4 to prevent the skeleton node 5 from becoming unstable out of the plane under the action of an earthquake; a cover plate 8 is arranged at the connection between the beam ends of the top beams 3 and the bottom beams 4 and the columns 2, and the cover plate 8 is located on the inner side of the column 2 and is fixed on the bottom surface of the flange plates of the top beams 3 and the bottom beams 4, and an inner partition plate 9 is arranged at the corresponding position on the inner side of the column 2 to improve the seismic performance of the node.
[0026] A thickened steel casting 10 is welded and fixed to the lower end of the column 2, and a conical pin 11 is provided at the bottom of the steel casting 10. A socket 12 is provided on the inner partition plate 9 at the upper end of the column 2. The conical pin 11 and the socket 12 are socket-fitted and used for positioning the upper and lower building modules 1. The positioning accuracy is not less than 2.0 mm; the inner partition plate 9 at the upper end of the column 2 is respectively fixed with guide ribs 13 on both sides of the socket 12. The guide ribs 13 are flush with the top surface of the column 2 and serve as a sliding introduction path for the upper building module 1.
[0027] A column side connecting plate 14 is provided at the upper and lower connections of the column 2 not covered by the building module 1. The thickness of the column side connecting plate 14 is not less than the wall thickness of the column 2 plus 4.0 mm. Bolt holes are provided on the column side connecting plate 14 and the wall of the column 2. Nuts are welded at positions corresponding to the bolt holes on the inner wall of the column 2. The column side connecting plate 14 is connected to the column 2 by bolts to form a hinged connection at the column foot.
[0028] The stacked beam shear connector 6 is installed at the four points of the ends of the top beam 3 and the bottom beam 4, and includes a lower shear member 6.1 and an upper shear member 6.2. The lower shear member 6.1 is fixedly installed on the top beam 3 of the lower building module 1, and the upper shear member 6.2 is fixedly installed on the bottom beam 4 of the upper building module 1; the lower shear member 6.1 is provided with a wedge-shaped slider 6.1.1, and the upper shear member 6.2 is provided with a wedge-shaped socket 6.2.1, and the wedge-shaped slider 6.1.1 can be inserted into the wedge-shaped socket 6.2.1 to achieve self-locking.
[0029] The lower shear member 6.1 includes a fixing member 6.1.2 and a sliding block 6.1.1. The fixing member 6.1.2 is fixedly installed on the side of the top beam 3, and a plurality of parallel guide rails 6.1.3 are arranged at intervals on the top surface thereof. In the embodiment of the present application, the cross-sectional shape of the guide rail 6.1.3 is a trapezoidal structure, and the sliding block 6.1.1 is provided with a sliding groove 6.1.4 that slides with the guide rail 6.1.3. The sliding groove 6.1.4 is clamped on the guide rail 6.1.3 to enable the sliding block 6.1.1 to slide along the fixing member 6.1.2.
[0030] A fixing plate 6.1.5 is provided at the insertion end of the slider 6.1.1, and a spring 6.1.6 is connected between the fixing plate 6.1.5 and the fixing member 6.1.2. In the embodiment of the present application, the spring 6.1.6 is in a stretched state after the slider 6.1.1 slides out of the socket slot 6.2.1, and is in a natural state after the slider 6.1.1 is inserted into the socket slot 6.2.1.
[0031] Two groups of positioning holes 6.1.7 are provided at the bottom of the slider 6.1.1, and a spring self-locking pin 6.1.8 is provided on the fixing piece 6.1.2. The spring self-locking pin 6.1.8 is inserted into the positioning hole 6.1.7 to fix the slider 6.1.1 in a state of sliding out of the socket slot 6.2.1 or in a state of being inserted into the socket slot 6.2.1, wherein the spring self-locking pin 6.1.8 includes a pin, a fixing plate and a reset spring 6.1.6. One end of the pin passes through the fixing piece 6.1.2 and is inserted into the positioning hole 6.1.7. The fixing plate is fixed on the pin and is located in the fixing piece 6.1.2. The reset spring 6.1.6 is sleeved on the pin and is located between the fixing plate and the fixing piece 6.1.2. Under the action of the reset spring 6.1.6, after the slider 6.1.1 slides to the designed position, the pin can be automatically inserted into the positioning hole 6.1.7 to achieve self-locking, thereby ensuring that the sliding block will not slide out of the socket slot 6.2.1.
[0032] The upper shear member 6.2 includes a socket block 6.2.2 and a stiffening rib 6.2.3. Two socket blocks 6.2.2 are provided and fixed on the lower flange of the bottom beam 4. A socket slot 6.2.1 for inserting the slider 6.1.1 is formed between the two socket blocks 6.2.2. The width of the slider 6.1.1 gradually increases from the insertion end to the insertion end. The socket slot 6.2.1 and the slider 6.1.1 are self-lockingly engaged to form a reliable stacked beam shear force path so that the top beam 3 and the bottom beam 4 of the upper and lower building modules 1 work together. In the embodiment of the present application, The cross-sectional shape of the socket block 6.2.2 is a trapezoid, and one side of its short side is fixedly mounted on the lower flange plate of the bottom beam 4; the stiffening rib 6.2.3 is fixedly arranged between the upper and lower flange plates of the bottom beam 4 corresponding to the installation position of the socket block 6.2.2, locally reinforcing the beam domain; in addition, there is a 2mm gap on the left and right sides between the slider 6.1.1 and the socket slot 6.2.1. Before the slider 6.1.1 is inserted, a 3.0mm iron filings and steel-bonding mixed caulking agent is applied on site. During the insertion process of the slider 6.1.1, the 2mm gap is filled to make it dense and reliable for force transmission.
[0033] Embodiment 2: The installation process includes the following steps: Step 1: Arrange a ground rail 15 at the center of the upper flange of the top beam 3 of the modular building. The ground rail 15 is intermittently arranged at the stacked beam shear connector 6 to avoid the upper shear member 6.2 on the bottom beam 4 of the superstructure module 1; set an introduction rib 13 on the inner partition plate 9 at the upper end of the column 2 as a path for the superstructure module 1 to slide in.
[0034] Step 2: Transport the building module 1 and place it on the guide rail 6.1.3 frame on the ground. The guide rail 6.1.3 frame is aligned with the lifting bracket 17. A hydraulic lifting roller device 18 is installed on the lower side of the column 2. The hydraulic lifting roller device 18 includes a base 18.1, a hydraulic jack 18.2 and a column side sliding connection 18.3. A roller 18.4 is installed under the base 18.1. The roller 18.4 has a track groove 18.5 that cooperates with the ground rail 15; the hydraulic jack 18.2 is installed between the base 18.1 and the column side sliding connection 18.3. The base 18.1 and the column side sliding connection 18.3 are matched along the vertical sliding, and the column side sliding connection 18.3 is connected to the column 2.
[0035] Specifically, the base 18.1 is provided with a mounting groove 18.6, the hydraulic jack 18.2 is installed in the mounting groove 18.6 and the hydraulic pipe of the hydraulic jack 18.2 passes through the groove wall; a resin roller 18.4 is installed at the lower part of the base 18.1, and a rail groove 18.5 is provided in the center of the roller 18.4, which can cooperate with the ground rail 15 on the top beam 3 to prevent the building module 1 from shifting during the insertion and sliding process.
[0036] The column side sliding connection 18.3 includes a pair of side plates 18.3.1, a horizontal cross plate 18.3.2 is fixedly arranged between the side plates 18.3.1 in the horizontal direction, and a vertical plate 18.3.3 is fixedly arranged in the vertical direction. A reinforcing rib 18.3.4 is arranged between the vertical plate 18.3.3 and the horizontal cross plate 18.3.2 to transmit the gravity of the building module 1 transmitted from the column wall. The hydraulic jack 18.2 is supported on the horizontal cross plate 18.3.2 and can be lifted up and down under the action of the hydraulic jack 18.2. Bolt holes are opened on the vertical plate 18.3.3 and the column 2, and three bolt holes are arranged at intervals along the vertical direction. Nuts are fixedly arranged on the inner wall of the column 2, and the vertical plate 18.3.3 and the column 2 are fixed by bolts.
[0037] Two smooth bolts 18.7 are respectively arranged on the two side walls of the base 18.1, and a vertical groove 18.8 is opened on the side plate 18.3.1, and the smooth bolts 18.7 are slidably arranged in the vertical groove 18.8, wherein the double vertical groove 18.8 is arranged to prevent the column side sliding connector 18.3 from always turning over during the jacking or transportation process of the building module 1.
[0038] Step 3: Raise the hydraulic jack 18.2 by about 30 mm, push the building module 1 from the guide rail 6.1.3 frame into the lifting bracket 17, and lift the lifting bracket 17 to the installation position. During the lifting process, use wind-resistant cables to resist the wind load during the lifting process.
[0039] Step 4: Apply a 3.0 mm thick mixture of iron filings and steel glue on the slider 6.1.1, and use the servo motor to pull the module to slide the building module 1 along the ground rail 15 into the installation position.
[0040] Step 5: Lower the height of the column 2 by means of the hydraulic jack 18.2 so that the conical latch 11 is inserted into the insertion hole 12 at the top of the column 2.
[0041] Step 6: Remove the hydraulic lifting roller device 18, pull out the positioning spring 6.1.6 pin and insert it into the slider 6.1.1; connect the column side connecting plate 14 on one side of the column 2.
[0042] The embodiments described above are merely descriptions of preferred implementation modes of the present invention and are not intended to limit the scope of the present invention. Without departing from the design spirit of the present invention, various modifications and improvements made to the technical solutions of the present invention by ordinary technicians in this field should all fall within the protection scope determined by the claims of the present invention.
Claims
1. An optimized modular structural system, comprising columns (2), top beams (3) and bottom beams (4), characterized in that: The beam ends of the top beam (3) and the bottom beam (4) are provided with skeleton nodes (5); the top beam (3) and the bottom beam (4) of the upper and lower building modules (1) are connected via a stacked beam shear connector (6) so that the top beam (3) and the bottom beam (4) work together; and the columns (2) of the upper and lower building modules (1) are hingedly connected.
2. The optimized modular structure system according to claim 1, characterized in that: Angle steels (7) are fixedly arranged between the top beams (3) and the bottom beams (4) at the inner corners of the building module (1) at the positions of the skeleton nodes (5).
3. The optimized modular structure system according to claim 1, characterized in that: A cover plate (8) is provided at the connection between the beam ends of the top beam (3) and the bottom beam (4) and the column (2), and an inner partition plate (9) is provided on the inner side of the column (2) at a position corresponding to the cover plate (8).
4. The optimized modular structure system according to claim 1, characterized in that: A conical plug pin (11) is provided at the lower end of the column (2), and a socket (12) which is spliced with the conical plug pin (11) is provided on the inner partition plate (9) at the upper end of the column (2).
5. The optimized modular structure system according to claim 1, characterized in that: A column side connection plate (14) is provided at the upper and lower connection points of the outer column (2) not covered by the building module (1), bolt holes are provided on the column side connection plate (14) and the side wall of the column (2), nuts are fixed on the inner wall of the column (2), and the column side connection plate (14) is connected to the column (2) by bolts to form a hinged connection at the column foot.
6. The optimized modular structure system according to claim 1, characterized in that: The stacked beam shear connector (6) comprises a lower shear member (6.1) and an upper shear member (6.2); the lower shear member (6.1) is fixedly mounted on the top beam (3) of the lower building module (1); the upper shear member (6.2) is fixedly mounted on the bottom beam (4) of the upper building module (1); the lower shear member (6.1) is provided with a slider (6.1.1) which can slide along the width direction of the flange of the top beam (3); the upper shear member (6.2) is provided with a socket (6.2.1) at the bottom of the bottom beam (4); the slider (6.1.1) slides into the socket (6.2.1) to connect the top beam (3) and the bottom beam (4); the socket (6.2.1) has upper, lower, left and right limit positions for the slider (6.1.1).
7. The optimized modular structure system according to claim 6, characterized in that: The lower anti-shear member (6.1) comprises a fixing member (6.1.2) fixed on the side of the top beam (3), a guide rail (6.1.3) is provided on the top surface of the fixing member (6.1.2), and a sliding groove (6.1.4) slidably matched with the guide rail (6.1.3) is provided on the sliding block (6.1.1); The upper shear member (6.2) comprises a socket block (6.2.2) and a stiffening rib (6.2.3); two socket blocks (6.2.2) are provided and fixedly mounted on the lower flange of the bottom beam (4); a socket slot (6.2.1) for inserting a sliding block (6.1.1) is formed between the two socket blocks (6.2.2); and the stiffening rib (6.2.3) is fixedly mounted between the upper and lower flange plates of the bottom beam (4) corresponding to the mounting positions of the socket blocks (6.2.2).
8. The optimized modular structure system according to claim 7, characterized in that: The fixing member (6.1.2) and the slider (6.1.1) are connected via a spring (6.1.6), one end of the spring (6.1.6) is connected to the insertion end of the slider (6.1.1), and the other end is connected to the fixing member (6.1.2), the spring (6.1.6) is in a stretched state after the slider (6.1.1) slides out of the socket (6.2.1), and is in a natural state after being inserted into the socket (6.2.1); A positioning hole (6.1.7) is provided at the bottom of the slider (6.1.1), and a spring self-locking pin (6.1.8) is provided on the fixing member (6.1.2). The spring self-locking pin (6.1.8) is inserted into the positioning hole (6.1.7) to fix the position of the slider (6.1.1).
9. The optimized modular structure system according to claim 1, characterized in that: The stacked beam shear connector (6) is installed at the quarter points of the ends of the top beam (3) and the bottom beam (4).
10. An installation process, comprising the optimized module structure system according to any one of claims 1 to 9, characterized in that: The following steps are involved: Step 1: a ground rail (15) is arranged at the center of the upper flange of the top beam (3) of the building module (1), and the ground rail (15) is arranged intermittently at the stacked beam shear connector (6). An introduction rib (13) is provided on the inner partition (9) at the upper end of the column (2), and the introduction rib (13) is respectively located on both sides of the insertion hole (12) and the top surface of the introduction rib (13) is flush with the top surface of the column (2); Step 2: transport the building module (1) and place it on the guide rail (6.1.3) frame on the ground, align the guide rail (6.1.3) frame with the lifting bracket (17), install a hydraulic lifting roller device (18) on the lower side of the column (2), the hydraulic lifting roller device (18) includes a base (18.1), a hydraulic jack (18.2) and a column side sliding connection (18.3), a roller (18.4) is installed under the base (18.1), and the roller (18.4) has a track groove (18.5) that matches the ground rail (15); the hydraulic jack (18.2) is installed between the base (18.1) and the column side sliding connection (18.3), the base (18.1) and the column side sliding connection (18.3) are slidably matched in the vertical direction, and the column side sliding connection (18.3) is connected to the column (2); Step 3: Raise the hydraulic jack (18.2), push the building module (1) from the guide rail (6.1.3) frame into the lifting bracket (17), and lift the lifting bracket (17) to the installation position; Step 4: Apply a mixture of iron filings and steel glue on the slider (6.1.1), and use the traction module to slide the building module (1) along the ground rail (15) into the installation position; Step 5: Lower the height of the column (2) by means of a hydraulic jack (18.2) so that the conical pin (11) is inserted into the insertion hole (12) at the top of the column (2); Step 6: Remove the hydraulic lifting roller device (18), pull out the positioning spring (6.1.6) latch and insert it into the slide block (6.1.1); connect the column side connecting plate (14) to one side of the column (2).