Road surface foundation pit enclosure structure based on road construction

By designing the guide mechanism of the inclined plate frame and the air collecting groove in the roadbed pit fence structure, the wind power is used to buffer the pressure of the fence baffle and intercept the dust through the net dust insulation mechanism, the fence in the prior art is solved. The problem of not being able to maintain stability and dust influence during wind blowing has achieved stability of the fence and protection of the construction environment.

CN119411880APending Publication Date: 2025-02-11东营金安建设工程有限公司
View PDF 1 Cites 0 Cited by

Patent Information

Application Number
CN202411960670.8
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-12-30
Publication Date
2025-02-11

AI Technical Summary

Technical Problem

The existing roadbed pit fence structure for road construction cannot effectively buffer the wind when blown, resulting in passive force on the fence plate and unable to maintain stability. At the same time, there is also a lack of barrier and interception structure for dust blown by the wind, affecting the construction environment.

Method used

A pavement foundation pit fence structure including a base, a railing frame, a guide mechanism and a partition mechanism is designed. The guide mechanism uses wind power to deflect the enclosed plate frames and air collecting grooves on both sides of the enclosed baffle, guides the air to the top and blows it out in a concentrated manner through the air guide groove, and generates a reverse air flow to buffer the pressure of the enclosed baffle. . At the same time, a net dust storage mechanism is provided on the top of the fence plate, and dust is intercepted by pulling the net through the deflected fence plate.

Benefits of technology

Through wind-guided and reverse airflow buffering, the fence can be kept stable and avoid passive wind pressure; at the same time, the net dust isolation mechanism effectively intercepts the dust in the wind and protects the construction environment.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119411880A_ABST
    Figure CN119411880A_ABST
Patent Text Reader

Abstract

The road surface foundation pit enclosure structure based on road construction comprises a base, a breast board frame is fixedly mounted at the top of the base, a guide mechanism and a partition sealing mechanism are arranged on the outer wall of the breast board frame, and the guide mechanism comprises a plurality of enclosure plates arranged on the inner wall of the breast board frame; the inclined plate frames are arranged on the two sides of the enclosure plate, so that when the enclosure plate is blown and pressed by wind, the enclosure plate deflects through wind pressure, the enclosure plate deflects through the plate frames and guides the wind to the top, the wind is blown out in a concentrated mode through the air guide grooves in the top, and in other words, airflow in the direction opposite to the blowing direction of the wind is blown out from the top of the enclosure plate; the air flow is blown out, reverse buffering pressure is conducted on the fence plate through the blown-out air flow, so that the fence plate can be kept stable, meanwhile, when the fence plate is blown to deflect, dust carried by wind passes through the top of the fence plate, the fence plate intercepts the dust through a separation net pulled by deflection at the moment, and the situation that the dust is carried by the wind and directly passes through the fence plate to affect the construction environment is avoided.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of road construction, and more specifically, to a road surface foundation pit enclosure structure based on road construction. Background Art

[0002] During the road construction process, the roadbed is not only the main body of the route, but also the foundation of the road surface and bears the vehicle load together with the road surface. The roadbed is divided into three categories according to the filling and excavation conditions of its cross-section: embankment type, cutting type and semi-filled and semi-excavated type. During the road construction process, the road foundation pit usually needs to be enclosed by a retaining structure to prevent pedestrians or vehicles from falling into the foundation pit and causing casualties.

[0003] Patent CN111636762A discloses a road foundation pit enclosure structure for road construction, which is a rectangular through hole opened by a rectangular plate, so that air can flow through the rectangular through hole to prevent the device from being blown down by wind. When there is no wind, the rectangular through hole is sealed by the rectangular plate, and warning slogans can be sprayed on the baffle plate and the rectangular plate for pedestrians to see; However, the above-mentioned patent document only has the function of setting an openable through hole on the enclosure structure to release wind pressure, but in actual use, there is no structure to buffer and utilize the wind force, which results in the enclosure plate still being passively forced by the wind and being unable to use the wind force to reversely relieve the pressure and maintain a stable state. At the same time, there is no structure to block and intercept the dust blown by the wind. During the wind blowing process, the through holes allow the wind carrying dust to pass directly, which can easily cause the construction environment to be affected by wind and sand.

[0004] In view of the above technical defects, a solution is now provided. Summary of the invention

[0005] In order to overcome the above-mentioned defects of the prior art, the present invention provides a road surface foundation pit enclosure structure based on road construction to solve the problems raised in the above-mentioned background technology.

[0006] To achieve the above object, the present invention provides the following technical solution: a road foundation pit enclosure structure based on road construction, comprising a base, a guardrail frame is fixedly installed on the top of the base, and a guide mechanism and a sealing mechanism are arranged on the outer wall of the guardrail frame; The guide mechanism includes a plurality of enclosure plates arranged on the inner wall of the guardrail frame, the plurality of enclosure plates are arranged in a vertical state, the outer walls of the plurality of enclosure plates are in contact with the inner wall of the guardrail frame, a rotating rod is rotatably installed at the bottom of the plurality of enclosure plates, the rotating rod is fixedly installed on the inner wall of the base, a weight-pull rod is fixedly installed at the bottom of the plurality of enclosure plates, the weight-pull rod is arranged in a horizontal state, and the weight-pull rod is located inside the base.

[0007] In a preferred embodiment, a plurality of panel frames are respectively provided on both sides of the enclosure panels, and the plurality of panel frames are fixedly mounted on the outer walls of the guardrail frame, and the outer walls of the plurality of panel frames are arranged in an inclined state, and the plurality of panel frames are arranged symmetrically with each other, and the plurality of panel frames are arranged symmetrically with each other in pairs, and the outer walls of the plurality of panel frames correspond to the outer walls of the enclosure panels, and a limiting plate is fixedly mounted on one side of the plurality of panel frames, and the limiting plate and the panel frame are arranged perpendicular to each other, and the limiting plate and the enclosure panel are arranged corresponding to each other.

[0008] In a preferred embodiment, a gas collecting trough is fixedly installed on the top of the plurality of plate racks, the gas collecting trough is fixedly installed on the outer wall of the guardrail rack, the gas collecting trough is arranged in a horizontal state, one side of the gas collecting trough is connected to an air guide trough, and the air guide trough is arranged in a horizontal state.

[0009] In a preferred embodiment, the sealing mechanism includes a rubber pad fixedly mounted on the inner walls of a plurality of plate racks, the rubber pad is arranged in an L shape, and one side of the rubber pad is fixedly mounted on the outer wall of the limiting plate.

[0010] In a preferred embodiment, a plurality of the baffle plates are respectively provided with baffle plates on the top of both sides, and the plurality of the baffle plates are symmetrically arranged in pairs, and a pull rod is respectively fixedly installed on the outer walls of the two baffle plates, and the pull rod is slidably installed on the inner wall of the air collecting tank, and a limit spring is fixedly installed on one side of the pull rod, and the limit spring is fixedly installed on the outer wall of the air collecting tank.

[0011] In a preferred embodiment, a pull-net dust-isolating mechanism is provided on the top of the enclosure plate, and the pull-net dust-isolating mechanism comprises a partition net fixedly mounted on the top of the enclosure plate, the partition net is arranged in a vertical state, and the length of the partition net is the same as the length of the enclosure plate.

[0012] In a preferred embodiment, a scraper plate is provided on both sides of the partition net, and the two scrapers are fixedly mounted on the inner wall of the guardrail frame, and the outer walls of the two scrapers are in contact with the outer walls of both sides of the partition net.

[0013] In a preferred embodiment, the outer wall of the partition net is provided with a through groove, and the through groove is opened on the inner wall of the guardrail frame. A lifting plate is fixedly installed on the top of the partition net, and the lifting plate is slidably installed on the inner wall of the through groove. A supporting spring is fixedly installed on the top of the lifting plate, and the supporting spring is fixedly installed on the inner wall of the guardrail frame.

[0014] Technical effects and advantages of the present invention: 1. The present invention is to set inclined plate frames on both sides of the enclosure plate, and then when the enclosure plate is pressed by the wind, the enclosure plate is deflected by the wind pressure, and the enclosure plate is offset by the plate frame and guides the wind to the top, so that the wind is concentrated and blown out through the air guide groove on the top, that is, an airflow in the opposite direction to the wind is blown at the top of the enclosure plate, and the baffle plate is subjected to reverse buffering pressure by the blown airflow, so that the enclosure plate can remain stable.

[0015] 2. At the same time, when the enclosure plate is blown and deflected, the dust carried by the wind passes through the top of the enclosure plate. At this time, the enclosure plate is deflected and the partition net is pulled to intercept the dust, preventing the dust from being carried by the wind and passing directly through to affect the construction environment. BRIEF DESCRIPTION OF THE DRAWINGS

[0016] Figure 1 It is a schematic diagram of the overall structure of the present invention; Figure 2 is a side view of the present invention; Figure 3 It is a partial cross-sectional view of the present invention; Figure 4 It is a partial vertical cross-sectional view of the guide mechanism in the present invention; Figure 5 It is a vertical cross-sectional view of the sealing mechanism in the present invention; Figure 6 It is a vertical cross-sectional view of the dust-isolating mechanism of the present invention; Figure 7 It is a partial view of the dust-proof mechanism of the present invention.

[0017] The accompanying drawings are marked as follows: 1. base; 2. guardrail frame; 3. guide mechanism; 31. enclosure plate; 32. rotating rod; 33. heavy pull rod; 34. plate frame; 35. limit plate; 36. air collecting groove; 37. air guide groove; 4. sealing mechanism; 41. rubber pad; 42. sealing plate; 43. pull rod; 44. limit spring; 5. pull net dust isolation mechanism; 51. partition net; 52. scraper plate; 53. through groove; 54. lifting plate; 55. support spring. DETAILED DESCRIPTION

[0018] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0019] Embodiment 1: In view of the fact that the prior art does not have a structure to buffer and utilize wind force, which results in the enclosure plate still being passively stressed by the wind and unable to relieve the pressure in the opposite direction with the help of wind force to maintain a stable state, the following technical solution is proposed to solve this problem: Refer to the instruction manual Figure 1-Figure 7 , based on the road construction pavement foundation pit enclosure structure, such as Figure 1 and Figure 2 As shown, it comprises a base 1, a guardrail frame 2 is fixedly installed on the top of the base 1, and a guide mechanism 3 and a sealing mechanism 4 are arranged on the outer wall of the guardrail frame 2; like Figure 3 As shown, the guide mechanism 3 includes a plurality of baffle plates 31 arranged on the inner wall of the guardrail frame 2, the plurality of baffle plates 31 are arranged in a vertical state, the outer walls of the plurality of baffle plates 31 are in contact with the inner wall of the guardrail frame 2, a rotating rod 32 is rotatably installed at the bottom of the plurality of baffle plates 31, the rotating rod 32 is fixedly installed on the inner wall of the base 1, a weight-pull rod 33 is fixedly installed at the bottom of the plurality of baffle plates 31, the weight-pull rod 33 is arranged in a horizontal state, the weight-pull rod 33 is located inside the base 1, and the baffle plates 31 are driven to remain vertical by the weight-pull rod 33. When the baffle plates 31 are blown by the wind, the weight-pull rod 33 is driven to rotate on the rotating rod 32 by the baffle plates 31.

[0020] like Figure 3 and Figure 4 As shown, a plurality of panel frames 34 are respectively provided on both sides of the baffle plates 31, and the plurality of panel frames 34 are fixedly mounted on the outer wall of the fence frame 2, and the outer walls of the plurality of panel frames 34 are arranged in an inclined state, and the plurality of panel frames 34 are arranged symmetrically with each other, and the plurality of panel frames 34 are arranged symmetrically with each other in pairs, and the outer walls of the plurality of panel frames 34 correspond to the outer walls of the baffle plates 31, and a limiting plate 35 is fixedly mounted on one side of the plurality of panel frames 34, and the limiting plate 35 and the panel frames 34 are arranged perpendicularly to each other, and the limiting plate 35 and the baffle plates 31 are arranged corresponding to each other, then the wind blows the baffle plates 31 to one side and approaches the panel frames 34 on the same side, and the baffle plates 31 are kept in an inclined state through the panel frames 34 and the limiting plates 35, then the wind passes through the baffle plates 31 and causes the airflow to blow upward.

[0021] like Figure 3 and Figure 5 As shown, an air collecting groove 36 is fixedly installed on the top of the multiple panel frames 34, and the air collecting groove 36 is fixedly installed on the outer wall of the guardrail frame 2. The air collecting groove 36 is arranged in a horizontal state. One side of the air collecting groove 36 is connected to an air guide groove 37, and the air guide groove 37 is arranged in a horizontal state. Then, the airflow passes through the baffle plate 31 upward into the air collecting groove 36 and is discharged from the air guide groove 37. At this time, since the direction of the airflow discharged from the air guide groove 37 is opposite to the direction of the wind, the pressure of the discharged airflow buffers the wind force.

[0022] like Figure 5As shown, the sealing mechanism 4 includes a rubber pad 41 fixedly mounted on the inner walls of multiple plate racks 34. The rubber pad 41 is arranged in an L shape, and one side of the rubber pad 41 is fixedly mounted on the outer wall of the limiting plate 35. The rubber pad 41 allows the enclosing plate 31 to fit tightly when it is close to the plate rack 34 and the limiting plate 35 to prevent airflow from escaping.

[0023] like Figure 2 and Figure 5 As shown, sealing plates 42 are respectively provided on the tops of both sides of the multiple baffle plates 31, and the multiple baffle plates 42 are symmetrically arranged in pairs. Pull rods 43 are respectively fixedly installed on the outer walls of the two baffle plates 42, and the pull rods 43 are slidably installed on the inner wall of the air collecting groove 36. A limiting spring 44 is fixedly installed on one side of the pull rod 43, and the limit spring 44 is fixedly installed on the outer wall of the air collecting groove 36. The baffle plates 42 are driven by the deflection of the baffle plates 31 to squeeze and drive them, and then the baffle plates 42 squeeze the pull rods 43 to stretch the limit springs 44, so that the baffle plates 42 are always in contact with the tops of the baffle plates 31, so that the gap between the baffle plates 31 and the air collecting groove 36 is connected through the baffle plates 42 to avoid air leakage.

[0024] The wind blows the airflow upward through the enclosing plate 31, and the airflow passes through the enclosing plate 31 and enters the air collecting groove 36 and is discharged from the air guide groove 37. At this time, the direction of the airflow discharged from the air guide groove 37 is opposite to the direction of the wind, and the pressure of the discharged airflow buffers the wind force.

[0025] Embodiment 2: There is no structure to block and intercept the dust blown by the wind. In the process of wind blowing, the wind carrying dust passes directly through the through hole, resulting in the construction environment being affected by the wind and sand. To solve this problem, the following technical solution is proposed: like Figure 6 and Figure 7 As shown, a pull-net dust-isolating mechanism 5 is provided on the top of the enclosing plate 31. The pull-net dust-isolating mechanism 5 includes a partition net 51 fixedly installed on the top of the enclosing plate 31. The partition net 51 is arranged in a vertical state. The length of the partition net 51 is the same as the length of the enclosing plate 31. The partition net 51 is pulled out by the deflection of the enclosing plate 31, and then the wind passing through the top of the enclosing plate 31 carries the dust through the partition net 51.

[0026] like Figure 6 and Figure 7 As shown, scraper plates 52 are respectively provided on both sides of the partition net 51. The two scraper plates 52 are fixedly installed on the inner wall of the guardrail frame 2. The outer walls of the two scraper plates 52 are in contact with the outer walls on both sides of the partition net 51. The outer wall of the moving partition net 51 is scraped by the scraper plates 52, so that the dust intercepted by the partition net 51 can be scraped off.

[0027] like Figure 6 and Figure 7 As shown, the outer wall of the partition net 51 is provided with a through groove 53, and the through groove 53 is opened on the inner wall of the guardrail frame 2. A lifting plate 54 is fixedly installed on the top of the partition net 51, and the lifting plate 54 is slidably installed on the inner wall of the through groove 53. A supporting spring 55 is fixedly installed on the top of the lifting plate 54, and the supporting spring 55 is fixedly installed on the inner wall of the guardrail frame 2. The partition net 51 is pulled by the enclosure plate 31, and then the partition net 51 moves downward, so that the lifting plate 54 moves downward in the through groove 53 synchronously, that is, the lifting plate 54 moves downward to pull the supporting spring 55 to extend.

[0028] In specific implementation, the partition net 51 is pulled out by the deflection of the enclosure plate 31, and then the partition net 51 moves downward, causing the lifting plate 54 to move downward in the through groove 53 synchronously, that is, the lifting plate 54 moves downward to pull the supporting spring 55 to extend. At this time, the wind passing through the top of the enclosure plate 31 carries the dust and passes through the partition net 51 and is blocked. After the wind stops, the supporting spring 55 on the lifting plate 54 retracts the partition net 51 and drives the enclosure plate 31 to return to the normal state, and then the outer wall of the upwardly moved partition net 51 is scraped off by the scraper plate 52, so as to facilitate the scraping off of the dust intercepted by the partition net 51.

[0029] Finally, a few points should be explained: First, in the description of this application, it should be noted that, unless otherwise specified and limited, the terms "installed", "connected", and "connected" should be understood in a broad sense, which may refer to mechanical connection or electrical connection, or internal communication between two components, or direct connection. "upper", "lower", "left", "right", etc. are only used to indicate relative positional relationships. When the absolute position of the object being described changes, the relative positional relationship may change; Secondly: In the drawings of the embodiments disclosed in the present invention, only the structures related to the embodiments disclosed in the present invention are involved, and other structures can refer to the general design. In the absence of conflict, the same embodiment and different embodiments of the present invention can be combined with each other; Finally: The above description is only a preferred embodiment of the present invention and is not intended to limit the present invention. Any modifications, equivalent substitutions, improvements, etc. made within the spirit and principles of the present invention should be included in the protection scope of the present invention.

Claims

1. A road foundation pit enclosure structure for road construction, comprising a base (1), a guardrail frame (2) being fixedly mounted on the top of the base (1), characterized in that: The outer wall of the guardrail frame (2) is provided with a guide mechanism (3) and a sealing mechanism (4); The guide mechanism (3) comprises a plurality of enclosure plates (31) arranged on the inner wall of the fence frame (2), the plurality of enclosure plates (31) being arranged in a vertical state, the outer walls of the plurality of enclosure plates (31) being in contact with the inner wall of the fence frame (2), a rotating rod (32) being rotatably mounted at the bottom of the plurality of enclosure plates (31), the rotating rod (32) being fixedly mounted on the inner wall of the base (1), a weight pull rod (33) being fixedly mounted at the bottom of the plurality of enclosure plates (31), the weight pull rod (33) being arranged in a horizontal state, and the weight pull rod (33) being located inside the base (1).

2. The road foundation pit enclosure structure based on road construction according to claim 1 is characterized in that: A plate frame (34) is provided on both sides of the plurality of enclosure plates (31), the plurality of plate frames (34) are fixedly mounted on the outer wall of the fence frame (2), the outer walls of the plurality of plate frames (34) are arranged in an inclined state, the plurality of plate frames (34) are arranged symmetrically to each other, the plurality of plate frames (34) are arranged symmetrically to each other, the outer walls of the plurality of plate frames (34) correspond to the outer walls of the enclosure plates (31), a limiting plate (35) is fixedly mounted on one side of the plurality of plate frames (34), the limiting plate (35) and the plate frame (34) are arranged perpendicularly to each other, and the limiting plate (35) and the enclosure plates (31) are arranged corresponding to each other.

3. The road foundation pit enclosure structure based on road construction according to claim 2 is characterized in that: An air collecting groove (36) is fixedly mounted on the top of the plurality of plate racks (34), the air collecting groove (36) is fixedly mounted on the outer wall of the guardrail rack (2), the air collecting groove (36) is arranged in a horizontal state, one side of the air collecting groove (36) is connected to an air guide groove (37), and the air guide groove (37) is arranged in a horizontal state.

4. The road foundation pit enclosure structure based on road construction according to claim 3 is characterized in that: The sealing mechanism (4) comprises a rubber pad (41) fixedly mounted on the inner walls of a plurality of plate racks (34); the rubber pad (41) is arranged in an L shape, and one side of the rubber pad (41) is fixedly mounted on the outer wall of the limiting plate (35).

5. The road foundation pit enclosure structure based on road construction according to claim 4 is characterized in that: A plurality of baffle plates (42) are respectively provided on the top of both sides of the baffle plates (31), and the plurality of baffle plates (42) are symmetrically arranged in pairs, and a pull rod (43) is fixedly installed on the outer walls of the two baffle plates (42), and the pull rod (43) is slidably installed on the inner wall of the air collecting groove (36), and a limit spring (44) is fixedly installed on one side of the pull rod (43), and the limit spring (44) is fixedly installed on the outer wall of the air collecting groove (36).

6. The road foundation pit enclosure structure based on road construction according to claim 1 is characterized in that: A net-pulling dust-isolating mechanism (5) is provided on the top of the enclosure plate (31), the net-pulling dust-isolating mechanism (5) comprising a partition net (51) fixedly mounted on the top of the enclosure plate (31), the partition net (51) being arranged in a vertical state, and the length of the partition net (51) being the same as the length of the enclosure plate (31).

7. The road foundation pit enclosure structure based on road construction according to claim 6 is characterized in that: Scraping plates (52) are respectively provided on both sides of the partition net (51), and the two scraping plates (52) are fixedly mounted on the inner wall of the fence frame (2), and the outer walls of the two scraping plates (52) are in contact with the outer walls of both sides of the partition net (51).

8. The road foundation pit enclosure structure based on road construction according to claim 7 is characterized in that: The outer wall of the partition net (51) is provided with a through groove (53), and the through groove (53) is opened on the inner wall of the fence frame (2). A lifting plate (54) is fixedly installed on the top of the partition net (51), and the lifting plate (54) is slidably installed on the inner wall of the through groove (53). A supporting spring (55) is fixedly installed on the top of the lifting plate (54), and the supporting spring (55) is fixedly installed on the inner wall of the fence frame (2).

Citation Information

Patent Citations

  • Road foundation pit fencing structure for road construction

    CN111636762A