Railway deep shaft retwisting and reloading construction method
By assembling temporary hanging disks at the bottom of the bearing hanging disk and using the vertical movement of the lifting device, the problem of low efficiency of vertical shaft reversing and installation in the prior art is solved, and the rapid transport of components is achieved in the well body and outside the well body. Improved the efficiency of twisting and replacing.
Patent Information
- Application Number
- CN202411568024.7
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-11-05
- Publication Date
- 2025-02-11
AI Technical Summary
In the prior art, the transport efficiency of components to be replaced and the components after the removal and adjustment of the drilling facilities is low in the well body and outside the well body, resulting in low twisting and installation efficiency of the shaft.
The temporary lifting disk is assembled to the bottom of the load-bearing suspending disk, and the vertical movement of the load-bearing suspending disk is driven through the lifting device to quickly transport the components inside and outside the well body. The temporary hanging disks are evenly distributed in the vertical direction to increase the overall load capacity of the carrying suspended disk.
Through the setting of temporary hanging disks, the load capacity of the carrying suspension disk during the movement of the well body is improved, and the components to be replaced and the components after the removal and adjustment of the well drilling facilities are quickly transported inside and outside the well body, which is improved. Replacement efficiency.
Smart Images

Figure CN119412069A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the field of railway construction, and in particular to a railway deep shaft refitting and reinstallation construction method. Background Art
[0002] The shaft refitting and refitting refers to the project of optimizing and renovating the shaft's lifting, transportation, power distribution signal, drainage, refrigeration and safety emergency systems after the shaft is constructed and the bottom construction space is formed. This project usually includes the replacement of equipment and facilities such as lifting containers to improve work efficiency and the system's collaborative linkage capabilities.
[0003] The deep vertical shaft used for railway tunnel construction generally includes a main shaft and an auxiliary shaft. During the process of refitting the vertical shaft, it is usually necessary to convert the main shaft into a slag and dirty air discharge channel, and convert the auxiliary shaft into a channel for feeding, fresh air intake, drainage, and personnel entry and exit. Among them, the refitting of the main shaft and the auxiliary shaft requires the dismantling and adjustment of the well drilling facilities and the laying of the pipelines in the well body, and finally the installation of the sealing plate at the shaft mouth to realize the refitting of the vertical shaft.
[0004] With regard to the above-mentioned prior art, the components of the equipment to be replaced and the components after the removal and adjustment of the well drilling facilities are usually placed and transported by a single lifting platform, which is not convenient for realizing the rapid transportation of the components of the equipment to be replaced and the components after the removal and adjustment of the well drilling facilities inside and outside the well body, and the efficiency of the modification and replacement of the vertical shaft is low. Summary of the invention
[0005] In order to facilitate the rapid transportation of equipment parts to be replaced and parts after dismantling and adjustment of well drilling facilities inside and outside the well body, and to improve the efficiency of shaft refitting, the present application provides a railway deep shaft refitting construction method.
[0006] The present application provides a railway deep shaft refitting and replacement construction method adopts the following technical scheme: A railway deep shaft refitting and replacement construction method, comprising the following specific steps: S1, placing the equipment parts to be replaced in the well body on the load-bearing hanging plate and vertically sending the load-bearing hanging plate into the well body through a lifting device; S2, after dismantling and adjusting the well-drilling facilities in the well body, assembling the temporary hanging plate to the bottom of the load-bearing hanging plate; S3, placing the parts to be transported out of the well body after the well-drilling facilities are dismantled and adjusted on the load-bearing hanging plate and the temporary hanging plate, and driving the load-bearing hanging plate in the vertical direction through the lifting device The movement transports the components that need to be transported outside the wellbore after the well drilling facilities are dismantled and adjusted to the outside of the wellbore; S4, repeating steps S1 and S3, after the replacement equipment components and the well drilling facilities are dismantled and adjusted, the pipes to be installed are placed on the load-bearing tray and the load-bearing tray is vertically transported into the wellbore through the lifting device, and the load-bearing tray installs the pipes on the side walls of the wellbore in sequence during the movement of the wellbore; S5, after the installation of the pipes is completed, the load-bearing tray is transported outside the wellbore through the lifting device and the temporary tray is removed; S6, installing the sealing plate at the wellhead to realize the modification and replacement of the wellbore.
[0007] By adopting the above technical scheme, under the premise that the well body is deep and the transportation rate of the carrying hoisting platform is not easy to be too fast in order to facilitate the stable transportation of components, the carrying capacity of the carrying hoisting platform when it moves in the well body is increased by setting up a temporary hoisting platform, which facilitates the movement of more components in and out of the well body at one time, that is, it facilitates the rapid transportation of equipment components to be replaced and components after dismantling and adjustment of well drilling facilities in and out of the well body, which is beneficial to improving the efficiency of shaft modification and replacement.
[0008] Optionally, the temporary hanging plates in step S2 are multiple and evenly distributed along the vertical direction.
[0009] By adopting the above technical solution, the provision of multiple temporary lifting platforms is conducive to further improving the overall carrying capacity of the load-bearing lifting platforms, and is convenient for further improving the transportation efficiency of components inside and outside the well body.
[0010] Optionally, the temporary hanging platform in step S2 includes a bearing plate body and a connecting rod body, and a plurality of connecting rod bodies are circumferentially distributed around the axis of the bearing plate body, each connecting rod body is penetrated through the bearing plate body, and a connecting assembly for connecting to the bearing hanging plate is provided on the top of each connecting rod body, and a support seat is provided at the bottom of the connecting rod body, and the support seat includes a plate body support portion and a sleeve portion, the plate body support portion is located at the bottom of the bearing plate body and the connecting rod body is penetrated through the plate body support portion, the sleeve portion is rotatably engaged with a side of the plate body support portion away from the bearing plate body, and the connecting rod body is penetrated through the sleeve portion and threadedly engaged with the sleeve portion.
[0011] By adopting the above technical solution, after the connecting assembly is connected to the carrying hanging plate, the connection between the temporary hanging plate and the carrying hanging plate can be achieved by successively passing the connecting rod body through the carrying plate body and the support seat so that the plate body support part supports the carrying plate body. This is convenient and fast, and the height position of the plate body support part can be easily adjusted by rotating the sleeve part, thereby facilitating the adjustment of the horizontality of the plate body support part, and the applicability is strong.
[0012] Optionally, the disk body support portion is fixed to the supporting disk body by screws, the disk body support portion is fixedly connected with a sliding limit portion, the outer peripheral surface of the connecting rod body is provided with a sliding limit groove extending along its own length direction, and the sliding limit portion is slidably fitted in the sliding limit groove.
[0013] By adopting the above technical scheme, the cooperation between the sliding limit part and the sliding limit groove plays a limiting role when the support seat slides, which is convenient for ensuring the stability of the support seat when sliding, and then facilitating the disc body support part to stably move to the position where it is fixed with the supporting disc body. The setting in which the disc body support part is fixed to the supporting disc body is beneficial to further ensure the stability of the position of the supporting disc body, thereby more stably realizing the bearing of the components.
[0014] Optionally, the supporting hanging plate is provided with connecting grooves which are arranged one by one corresponding to the connecting rod bodies, and each connecting rod body is slidably fitted in each connecting groove, and the connecting assembly includes a connecting movable rod, a connecting limit rod, a connecting spring and a connecting sleeve, the connecting movable rod is coaxially penetrated and slidably fitted in the connecting rod body, the connecting limit rod is rotatably installed on the connecting movable rod, and a connecting receiving groove for accommodating the connecting movable rod is provided on the outer peripheral surface of the connecting rod body. The connecting spring is installed between the connecting movable rod and the connecting rod body and applies an elastic force to the connecting movable rod to move away from the connecting rod body. When the connecting movable rod slides in a direction close to the connecting rod body, the connecting limit rod moves in a direction close to the axis of the connecting rod body. When the connecting movable rod slides in a direction away from the connecting rod body, the connecting limit rod moves in a direction away from the axis of the connecting rod body, and the connecting sleeve is sleeved and threadedly fitted on the connecting rod body.
[0015] By adopting the above technical solution, the connecting movable rod is pressed so that the connecting limit rod is accommodated in the connecting storage groove. At this time, the connecting rod body is inserted into the connecting groove and the connecting movable rod is loosened so that the connecting limit rod passes through the connecting storage groove under the elastic force of the connecting spring. Then, the connecting sleeve is screwed so that the connecting limit rod and the connecting sleeve are respectively pressed against the two sides of the thickness direction of the supporting hanging plate to realize the connection between the connecting rod body and the supporting hanging plate, which is convenient and quick.
[0016] Optionally, a reinforcement assembly is arranged between two adjacent connecting rod bodies, and the reinforcement assembly includes a reinforcement connecting rod and a reinforcement sleeve. Two reinforcement connecting rods are provided, and the two reinforcement connecting rods are respectively passed through and threadedly engaged with the two ends of the reinforcement sleeve, and the ends of the two reinforcement connecting rods away from the reinforcement sleeve are respectively used for connection with the connecting rod body.
[0017] By adopting the above technical scheme, the setting of the reinforced connecting rod is conducive to further enhancing the connection stability between the two adjacent connecting rod bodies, ensuring the stability of the position of the temporary hanging plate after installation, and the distance between the two reinforced connecting rods can be adjusted conveniently by rotating the reinforcement sleeve, so that it is convenient to adapt to connecting rod bodies at different distances, and has strong applicability.
[0018] Optionally, a reinforcement connecting seat is fixedly provided at one end of the reinforcement connecting rod away from the reinforcement sleeve, and the reinforcement connecting seat is slidably matched with two reinforcement clamping plates arranged opposite to each other. A bidirectional screw is rotatably installed on the reinforcement connecting seat, and the two ends of the bidirectional screw with opposite thread rotation directions are respectively passed through and threadedly matched with the two reinforcement clamping plates.
[0019] By adopting the above technical solution, the connection between the reinforced connecting rod and the connecting rod body can be achieved by rotating the bidirectional screw so that the two reinforcing clamping plates move towards each other until they clamp the connecting rod body, which is convenient and stable.
[0020] Optionally, in step S4, a locking mechanism for limiting the drainage pipe is provided on the side wall of the well body, the locking mechanism includes a locking fixing seat and a locking mounting seat, the locking fixing seat is fixedly installed on the side wall of the well body, the locking fixing seat is provided with a locking accommodating groove for accommodating the pipe, one end of the locking mounting seat is rotatably installed on the locking fixing seat, the other end of the locking mounting seat is fixedly connected with a locking plug block, and the locking fixing seat is provided with a locking slot corresponding to the locking plug block and plug-in-matched with the locking plug block.
[0021] By adopting the above technical solution, the setting of the positioning groove plays a role in limiting the position of the pipeline after installation, which is beneficial to ensure the stability of the position of the pipeline during operation. The cooperation between the positioning block and the positioning slot makes the connection between the positioning mounting seat and the positioning fixing seat convenient and fast.
[0022] Optionally, the locking seat is provided with a locking assembly, the locking assembly includes a locking block and a locking spring, a locking groove is opened on one side of the locking block, the locking block includes a locking portion, a locking movable portion and a locking pressing portion, the locking portion is fixedly installed on the locking movable portion, the locking portion is plug-matched with the locking groove, the locking pressing portion is fixedly installed on the locking movable portion, the locking spring is connected between the locking movable portion and the locking seat, the locking spring applies an elastic force to the locking portion to move in the direction of the locking groove, and when the locking pressing portion is pressed, the locking portion moves in the direction away from the locking groove, and a locking guide surface is provided on the side of the locking portion toward the locking block.
[0023] By adopting the above technical solution, when the locking block is inserted into the locking slot and contacts the locking guide surface, the locking part is automatically moved in the direction away from the locking block by the component force. When the locking part is directly opposite to the locking groove, the locking part is inserted into the locking groove under the elastic force of the locking spring, thereby further limiting the position of the locking block, making it convenient to fully ensure the stability of the locking block after it is inserted into the locking slot. At the same time, the locking pressing part is pressed so that the locking part is disengaged from the locking groove to release the lock of the locking block, which is convenient and quick.
[0024] Optionally, the sealing plate in step S6 includes a sealing part and a guide part, the guide part is fixedly mounted on the sealing part, the sealing part is provided with a through hole for allowing a pipeline and a supporting hanging plate to pass through, and the top of the well body is recessed with a sealing installation groove that is adapted to the outer dimensions of the sealing plate.
[0025] By adopting the above technical solution, the guide part plays a guiding role when installing the sealing disc, which makes it easy to quickly install the sealing disc to the fixed position. The setting of the through hole makes it easy to quickly realize the inspection and maintenance of the pipelines and facilities in the well body through the subsequent lifting of the carrying hoisting plate after the re-twisting and replacement is completed.
[0026] In summary, the present application includes at least one of the following beneficial technical effects: 1. The temporary hoisting platform is set up to increase the load-bearing capacity of the hoisting platform when it moves in the well body, which is convenient for the movement of more parts in and out of the well body at one time, that is, it is convenient for the parts of the equipment to be replaced and the parts of the well drilling facilities after dismantling and adjustment to be quickly transported in and out of the well body, which is beneficial to improve the efficiency of the shaft modification and replacement.
[0027] 2. After the connecting assembly is connected to the load-bearing hanging plate, the connection between the temporary hanging plate and the load-bearing hanging plate can be realized by successively passing the connecting rod body through the load-bearing plate body and the support seat so that the plate body support part supports the load-bearing plate body, which is convenient and quick.
[0028] 3. The setting of the reinforced connecting rod is conducive to further enhancing the connection stability between the two adjacent connecting rod bodies and ensuring the stability of the position of the temporary hanging plate after installation. At the same time, by rotating the reinforcement sleeve, it is convenient to adjust the distance between the two reinforced connecting rods, so that it is easy to adapt to connecting rod bodies at different distances, and has strong applicability. BRIEF DESCRIPTION OF THE DRAWINGS
[0029] Figure 1 It is a schematic diagram of the overall structure of an embodiment of the present application.
[0030] Figure 2 It is a schematic cross-sectional front view of the load-bearing hanging plate in the embodiment of the present application.
[0031] Figure 3 yes Figure 2 A partial enlarged schematic diagram of part A.
[0032] Figure 4 It is a schematic diagram of the bottom structure of the supporting plate in the embodiment of the present application.
[0033] Figure 5 It is a schematic diagram of the main structure of the reinforcement component in the embodiment of the present application.
[0034] Figure 6 yes Figure 5 A partial enlarged schematic diagram of part B.
[0035] Figure 7 It is a cross-sectional schematic diagram of the locking mechanism in the embodiment of the present application.
[0036] Description of reference numerals: 1. Lifting frame; 2. Lifting wheel; 3. Lifting rope; 4. Winch; 5. Well body; 6. Load-bearing lifting plate; 7. Temporary lifting plate; 701. Load-bearing plate body; 702. Connecting rod body; 8. Support seat; 801. Plate body support part; 802. Sleeve part; 9. Sliding limit part; 10. Sliding limit groove; 11. Connecting groove; 12. Connecting movable rod; 13. Connecting limit rod; 14. Connecting spring; 15. Connecting sleeve; 16. Connecting storage groove; 17. Reinforced connecting rod; 18. Reinforced sleeve; 19. Reinforced connection Seat; 20, reinforcement slide groove; 21, reinforcement clamping plate; 22, bidirectional screw; 23, rotating handle; 24, connecting clamping groove; 25, card-position fixing seat; 26, card-position mounting seat; 27, card-position accommodating groove; 28, card-position plug-in block; 29, card-position slot; 30, locking block; 301, locking part; 302, locking movable part; 303, locking pressing part; 31, locking spring; 32, locking groove; 33, sealing disk; 331, sealing part; 332, guide part; 34, sealing mounting groove; 35, through hole. DETAILED DESCRIPTION
[0037] The following is combined with Figure 1-7This application is described in further detail.
[0038] The present application embodiment discloses a railway deep shaft refitting and reinstallation construction method. Figure 1 The railway deep shaft refitting and refitting construction method includes the following specific steps: S1, placing the equipment parts to be transported to the shaft body 5 on the load-bearing hanging plate 6 and vertically transporting the load-bearing hanging plate 6 into the shaft body 5 through the lifting device, wherein, with reference to Figure 1 and Figure 2 The lifting device includes a lifting frame 1, a lifting wheel 2, a lifting rope 3 and a winch 4. The lifting frame 1 is arranged at the top of the well body 5, the lifting wheel 2 is rotatably installed on the lifting frame 1, the lifting rope 3 is wound around the lifting wheel 2, and one end of the lifting wheel 2 is connected to the winch and the other end is connected to the supporting hanging plate 6, so that the vertical movement of the supporting hanging plate 6 in the well body 5 can be realized by driving the lifting rope 3 to be reeled in by the winch.
[0039] S2, after dismantling and adjusting the well drilling facilities in the well body 5, assembling the temporary hanging platform 7 to the bottom of the supporting hanging platform 6.
[0040] S3, the components that need to be transported to the outside of the well body 5 after the well drilling facilities are dismantled and adjusted are placed on the load-bearing hoisting plate 6 and the temporary hoisting plate 7, and the components that need to be transported to the outside of the well body 5 after the well drilling facilities are dismantled and adjusted are transported to the outside of the well body 5 by driving the load-bearing hoisting plate 6 to move vertically through the lifting device, wherein, with reference to Figure 2 There are multiple temporary hanging plates 7 evenly distributed along the vertical direction to fully improve the overall carrying capacity of the carrying hanging plate 6.
[0041] Specifically, refer to Figure 3 and Figure 4 The temporary hanging plate 7 includes a bearing plate body 701 and a connecting rod body 702. There are multiple connecting rod bodies 702 distributed in a rectangular circumferential direction around the axis of the bearing plate body 701. A support seat 8 is arranged at the bottom of each connecting rod body 702. The support seat 8 includes a plate body support portion 801 and a sleeve portion 802. The plate body support portion 801 is located at the bottom of the bearing plate body 701 and the connecting rod body 702 is penetrated through the plate body support portion 801. The sleeve portion 802 is rotatably matched with the side of the plate body support portion 801 away from the bearing plate body 701. The connecting rod body 702 is penetrated through the sleeve portion 802 and is threadedly matched with the sleeve portion 802. When the sleeve portion 802 is rotated to make the plate body support portion 801 contact the bearing plate body 701, the support seat 8 can achieve stable support for the bearing plate body 701.
[0042] Reference Figure 4In order to further ensure the stability of the position of the bearing plate 701 when it is loaded, the plate support part 801 is fixed to the bearing plate 701 by screws. In order to facilitate the rapid and stable movement of the plate support part 801 to the position where it is fixed with the bearing plate 701, a sliding limit part 9 is fixedly connected to the inner side of the plate support part 801. A sliding limit groove 10 extending along the length direction of the connecting rod body 702 is provided on the outer peripheral surface of the connecting rod body 702. The sliding limit groove 10 extends to the bottom of the connecting rod body 702. The sliding limit part 9 slides in the sliding limit groove 10 to limit the plate support part 801 when it slides.
[0043] Reference Figure 2 and Figure 3 , each connecting rod body 702 is provided with a connecting assembly at the top thereof, so as to be connected with the supporting tray body 701 of the supporting hanging tray 6 or another temporary hanging tray 7. Specifically, the supporting tray body 701 of the supporting hanging tray 6 and the temporary hanging tray 7 are provided with connecting grooves 11 corresponding to the connecting rod bodies 702 one by one, and each connecting rod body 702 is respectively slidably matched in each connecting groove 11, and the connecting rod bodies 702 of two adjacent temporary hanging trays 7 are staggered.
[0044] Reference Figure 3 The connection assembly includes a connection movable rod 12, a connection limit rod 13, a connection spring 14 and a connection sleeve 15, wherein the connection movable rod 12 is coaxially arranged and slidably matched with the connection rod body 702. In the embodiment of the present application, there are two connection limit rods 13 distributed circumferentially around the axis of the connection movable rod 12, and the two connection limit rods 13 are both rotatably mounted on the connection movable rod 12. The outer circumferential surface of the connection rod body 702 is provided with two connection receiving grooves 16 corresponding to the connection limit rods 13, so as to realize the storage and accommodation of the connection limit rods 13.
[0045] Continue to refer to Figure 2 and Figure 3The connecting spring 14 is installed between the connecting movable rod 12 and the connecting rod body 702. Specifically, the connecting spring 14 is sleeved outside the connecting movable rod 12. One end of the connecting spring 14 is connected to the connecting rod body 702, and the other end is connected to the connecting movable rod 12. The connecting spring 14 applies an elastic force to the connecting movable rod 12 to move away from the connecting rod body 702. When the connecting movable rod 12 slides toward the direction close to the connecting rod body 702, the connecting limit rod 13 moves toward the direction close to the axis of the connecting rod body 702, so that the connecting limit rod 13 can be stored in the connecting storage groove 16. When the connecting movable rod 12 slides toward the direction away from the connecting rod body 702, the connecting limit rod 13 moves toward the direction away from the axis of the connecting rod body 702. The connecting sleeve 15 is sleeved and threadedly engaged with the connecting rod body 702. When the connecting sleeve 15 is screwed so that the connecting limit rod 13 and the connecting sleeve 15 respectively contact the two sides of the supporting hanging plate 6 or the supporting plate body 701, the connecting rod body 702 and the supporting hanging plate 6 or the supporting plate body 701 are firmly fixed.
[0046] Reference Figure 5 and Figure 6 In order to further ensure the connection stability between the two adjacent connecting rod bodies 702, a reinforcement component is arranged between the two adjacent connecting rod bodies 702 on the same side. The reinforcement component includes a reinforcement connecting rod 17 and a reinforcement sleeve 18. There are two reinforcement connecting rods 17. The two reinforcement connecting rods 17 are respectively penetrated and threadedly engaged with the two ends of the reinforcement sleeve 18, and the threads of the two reinforcement connecting rods 17 are rotated in opposite directions, so that when the two reinforcement connecting rods 17 are limited in the rotation direction, by screwing the reinforcement sleeve 18, the two reinforcement connecting rods 17 can be synchronously moved in the direction of approaching or moving away from each other, thereby facilitating the fixation of the connecting rod bodies 702 with different spacings.
[0047] Reference Figure 6 , a reinforced connecting seat 19 is fixedly provided at one end of the two reinforced connecting rods 17 away from the reinforced sleeve 18, and a reinforced slide groove 20 is opened on the side of the reinforced connecting seat 19 away from the reinforced sleeve 18, and two reinforced clamping plates 21 arranged opposite to each other are slidably matched in the reinforced slide groove 20, and a bidirectional screw 22 is rotatably installed on the reinforced connecting seat 19, and the two ends of the bidirectional screw 22 with opposite thread rotation directions are respectively penetrated and threadedly matched with the two reinforced clamping plates 21, so that when the bidirectional screw 22 rotates, the two reinforced clamping plates 21 move in the direction of approaching or moving away from each other, and when the two reinforced clamping plates 21 clamp the connecting rod body 702, the fixation between the reinforced connecting rod 17 and the connecting rod body 702 is achieved.
[0048] Continue to refer to Figure 6In order to facilitate the application of force to rotate the bidirectional screw 22, a rotating handle 23 is fixedly connected to one end of the bidirectional screw 22. In order to fully ensure the stability of the reinforcing clamping plate 21 when clamping the connecting rod body 702, the two reinforcing clamping plates 21 are both provided with a connecting clamping groove 24 that matches the shape of the connecting rod body 702 on one side facing each other.
[0049] S4, repeating steps S1 and S3, after the replacement equipment parts and the well drilling facilities are transported after dismantling and adjustment, the pipe to be installed is placed on the load-bearing hanging plate 6 and the load-bearing hanging plate 6 is vertically transported into the well body 5 through the lifting device, and the load-bearing hanging plate 6 installs the pipe on the side wall of the well body 5 in sequence during the movement of the well body 5. Specifically, refer to Figure 5 The side wall of the well body 5 is also provided with a positioning mechanism for limiting the drainage pipe, and a plurality of positioning mechanisms are arranged along the vertical direction.
[0050] Reference Figure 5 and Figure 7 The locking mechanism includes a locking fixing seat 25 and a locking mounting seat 26. The locking fixing seat 25 is fixedly installed on the side wall of the well body 5 by bolts. A vertically penetrating locking accommodating groove 27 is provided on the side of the locking fixing seat 25 away from the side wall of the well body 5 for accommodating the pipeline. One end of the locking mounting seat 26 is rotatably installed on the locking fixing seat 25, and a locking plug block 28 is fixedly connected to the other end of the locking mounting seat 26. The locking fixing seat 25 is provided with a locking slot 29 corresponding to the locking plug block 28 and plugged with the locking plug block 28. When the locking plug block 28 is inserted into the locking slot 29, the locking mounting seat 26 closes the notch of the locking accommodating groove 27 away from the side wall of the well body 5, thereby playing a role in limiting the position of the pipeline, which is conducive to ensuring the stability of the pipeline during operation.
[0051] Reference Figure 7 In order to further ensure the stability of the card insertion block 28 when it is inserted into the card slot 29, that is, to further ensure the connection stability between the card installation seat 26 and the card fixing seat 25, the card fixing seat 25 is provided with a locking assembly. The locking assembly includes a locking block 30 and a locking spring 31. The locking block 30 includes a locking portion 301, a locking movable portion 302 and a locking pressing portion 303. The locking movable portion 302 is vertically arranged and slidably matched with the card fixing seat 25. The locking pressing portion 303 is fixedly installed at the bottom of the locking movable portion 302 and is located outside the card fixing seat 25, so as to realize the pressing of the locking block 30 as a whole.
[0052] Continue to refer to Figure 7The top of the locking block 30 is provided with a locking groove 32, and the locking portion 301 is fixedly mounted on the locking movable portion 302. One end of the locking portion 301 extends into the locking slot 29 and is plugged into the locking groove 32. The locking spring 31 is sleeved outside the locking movable portion 302, and one end of the locking spring 31 is connected to the locking movable portion 302, and the other end is connected to the locking fixed seat 25. The locking spring 31 applies an elastic force to the locking portion 301 to move in the direction of the locking groove 32. When the locking portion 301 is snapped into the locking groove 32 under the elastic force of the locking spring 31, the locking block 28 is further fixed. When the locking pressing portion 303 is pressed, the locking portion 301 moves in a direction away from the locking groove 32, so as to unlock the locking block 28. To further facilitate the locking of the locking block 28, a locking guide surface is further provided on the side of the locking portion 301 facing the locking block 28, so that the locking block 28 can abut against the locking guide surface of the locking portion 301, and the locking portion 301 automatically moves away from the locking block 28 under the action of the component force. When the locking portion 301 is opposite to the locking groove 32, the locking portion 301 is snapped into the locking groove 32 under the elastic force of the locking spring 31.
[0053] S5, after the pipeline is installed, the carrying suspension plate 6 is transported to the outside of the well body 5 by the lifting device and the temporary suspension plate 7 is removed.
[0054] S6, install the sealing plate 33 at the wellhead to realize the refitting of the well body 5. Figure 1 and Figure 2 The sealing plate 33 includes a sealing portion 331 and a guide portion 332. The cross section of the sealing portion 331 is circular. The guide portion 332 is fixedly mounted on the outer peripheral surface of the sealing portion 331. A sealing installation groove 34 matching the outer dimensions of the sealing plate 33 is recessed on the top of the well body 5, so that the guide portion 332 plays a guiding role in the installation of the sealing plate 33, and facilitates the rapid installation of the sealing plate 33 to the position at the time of sealing. The sealing portion 331 is provided with a through hole 35 for the pipeline and the supporting hanging plate 6 to pass through, so as to ensure the stable operation of the pipeline and facilitate the subsequent maintenance of the pipeline in the well body 5.
[0055] The implementation principle of a railway deep shaft reconstruction and replacement construction method in an embodiment of the present application is as follows: when the shaft body 5 is relatively deep and in order to facilitate the stable transportation of components, the transportation rate of the load-bearing hoisting platform 6 is not easy to be too fast, the provision of a temporary hoisting platform 7 increases the load-bearing capacity of the load-bearing hoisting platform 6 when the shaft body 5 moves, which facilitates the movement of more components in and outside the shaft body 5 at one time, that is, it facilitates the rapid transportation of equipment components to be replaced and components after dismantling and adjustment of the well drilling facilities in and outside the shaft body 5, which is beneficial to improving the efficiency of shaft reconstruction and replacement.
[0056] The above are all preferred embodiments of the present application, and the protection scope of the present application is not limited thereto. Therefore, any equivalent changes made according to the structure, shape, and principle of the present application should be included in the protection scope of the present application.
Claims
1. A railway deep shaft refitting and reinstallation construction method, characterized in that: The method comprises the following specific steps: S1, placing the equipment component to be replaced and to be transported into the well body (5) on a load-bearing hanging plate (6) and vertically transporting the load-bearing hanging plate (6) into the well body (5) by means of a lifting device; S2, after dismantling and adjusting the well drilling facilities in the well body (5), assembling the temporary hanging plate (7) to the bottom of the load-bearing hanging plate (6); S3, placing the components that need to be transported outside the well body (5) after the well drilling facilities are dismantled and adjusted on the load-bearing hoisting platform (6) and the temporary hoisting platform (7), and driving the load-bearing hoisting platform (6) to move vertically by the hoisting device to transport the components that need to be transported outside the well body (5) after the well drilling facilities are dismantled and adjusted to the outside of the well body (5); S4, repeating steps S1 and S3, after the replacement equipment parts and the well drilling facilities are transported after dismantling and adjustment, the pipe to be installed is placed on the load-bearing hanging plate (6) and the load-bearing hanging plate (6) is vertically transported into the well body (5) by a lifting device, and the load-bearing hanging plate (6) installs the pipe on the side wall of the well body (5) in sequence during the movement of the well body (5); S5, after the pipeline is installed, the carrying hoisting plate (6) is transported to the outside of the well body (5) by a hoisting device and the temporary hoisting plate (7) is removed; S6, installing a sealing plate (33) at the wellhead to achieve the refitting of the well body (5).
2. A railway deep shaft refitting and reinstallation construction method according to claim 1, characterized in that: The temporary hanging plates (7) in step S2 are evenly distributed in a plurality along the vertical direction.
3. A railway deep shaft refitting and reinstallation construction method according to claim 1, characterized in that: The temporary hanging plate (7) in step S2 comprises a bearing plate body (701) and a connecting rod body (702), wherein a plurality of connecting rod bodies (702) are circumferentially distributed around the axis of the bearing plate body (701), each of the connecting rod bodies (702) is penetrated through the bearing plate body (701), and a connecting assembly for connecting to the bearing hanging plate (6) is arranged at the top of each connecting rod body (702), and a supporting seat (8) is arranged at the bottom of the connecting rod body (702). The support seat (8) comprises a disc support portion (801) and a sleeve portion (802), wherein the disc support portion (801) is located at the bottom of the bearing disc (701) and the connecting rod (702) is passed through the disc support portion (801), the sleeve portion (802) is rotatably engaged with a side of the disc support portion (801) away from the bearing disc (701), and the connecting rod (702) is passed through the sleeve portion (802) and threadedly engaged with the sleeve portion (802).
4. A railway deep shaft refitting and reinstallation construction method according to claim 3, characterized in that: The disc body support portion (801) is fixed to the supporting disc body (701) by means of screws, the disc body support portion (801) is fixedly connected with a sliding limit portion (9), the outer peripheral surface of the connecting rod body (702) is provided with a sliding limit groove (10) extending along its own length direction, and the sliding limit portion (9) is slidably fitted in the sliding limit groove (10).
5. A railway deep shaft refitting and reinstallation construction method according to claim 4, characterized in that: The supporting hanging plate (6) is provided with connecting grooves (11) which are arranged one by one with the connecting rod bodies (702), and each of the connecting rod bodies (702) is slidably fitted in each of the connecting grooves (11). The connecting assembly comprises a connecting movable rod (12), a connecting limit rod (13), a connecting spring (14) and a connecting sleeve (15). The connecting movable rod (12) is coaxially penetrated and slidably fitted in the connecting rod body (702), and the connecting limit rod (13) is rotatably installed on the connecting movable rod (12). The outer peripheral surface of the connecting rod body (702) is provided with a connecting receiving groove (16) for accommodating the connecting movable rod (12). The connecting spring (14) is installed between the connecting movable rod (12) and the connecting rod body (702) and applies an elastic force to the connecting movable rod (12) to move in a direction away from the connecting rod body (702). When the connecting movable rod (12) slides in a direction close to the connecting rod body (702), the connecting limit rod (13) moves in a direction close to the axis of the connecting rod body (702). When the connecting movable rod (12) slides in a direction away from the connecting rod body (702), the connecting limit rod (13) moves in a direction away from the axis of the connecting rod body (702). The connecting sleeve (15) is sleeved and threadedly engaged with the connecting rod body (702).
6. A railway deep shaft refitting and reinstallation construction method according to claim 3, characterized in that: A reinforcement component is arranged between two adjacent connecting rod bodies (702), and the reinforcement component includes a reinforcement connecting rod (17) and a reinforcement sleeve (18). Two reinforcement connecting rods (17) are arranged, and the two reinforcement connecting rods (17) are respectively passed through and threadedly engaged with the two ends of the reinforcement sleeve (18), and the ends of the two reinforcement connecting rods (17) away from the reinforcement sleeve (18) are respectively used for connecting with the connecting rod body (702).
7. A railway deep shaft refitting and reinstallation construction method according to claim 6, characterized in that: A reinforcing connection seat (19) is fixedly provided at one end of the reinforcing connection rod (17) away from the reinforcing sleeve (18), and the reinforcing connection seat (19) is slidably matched with two reinforcing clamping plates (21) arranged opposite to each other. A bidirectional screw (22) is rotatably installed on the reinforcing connection seat (19), and the two ends of the bidirectional screw (22) with opposite thread rotation directions are respectively penetrated and threadedly matched with the two reinforcing clamping plates (21).
8. The railway deep shaft refitting and reinstallation construction method according to claim 1 is characterized by: In step S4, a positioning mechanism for limiting the position of the drainage pipe is provided on the side wall of the well body (5), the positioning mechanism comprising a positioning fixing seat (25) and a positioning mounting seat (26), the positioning fixing seat (25) being fixedly mounted on the side wall of the well body (5), the positioning fixing seat (25) being provided with a positioning accommodating groove (27) for accommodating the pipe, one end of the positioning mounting seat (26) being rotatably mounted on the positioning fixing seat (25), the other end of the positioning mounting seat (26) being fixedly connected with a positioning plug-in block (28), the positioning fixing seat (25) being provided with a positioning slot (29) corresponding to the positioning plug-in block (28) and pluggably matched with the positioning plug-in block (28).
9. A railway deep shaft refitting and reinstallation construction method according to claim 8, characterized in that: The locking seat (25) is provided with a locking assembly, the locking assembly comprising a locking block (30) and a locking spring (31); a locking groove (32) is provided on one side of the locking block (28); the locking block (30) comprises a locking portion (301), a locking movable portion (302) and a locking pressing portion (303); the locking portion (301) is fixedly mounted on the locking movable portion (302); the locking portion (301) is plugged into and matched with the locking groove (32); the locking pressing portion (303) is The locking portion (303) is fixedly mounted on the locking movable portion (302), the locking spring (31) is connected between the locking movable portion (302) and the locking fixed seat (25), the locking spring (31) applies an elastic force to the locking portion (301) to move in the direction of the locking groove (32), when the locking pressing portion (303) is pressed, the locking portion (301) moves in the direction away from the locking groove (32), and a locking guide surface is provided on the side of the locking portion (301) facing the locking plug block (28).
10. A railway deep shaft refitting and reinstallation construction method according to claim 1, characterized in that: The sealing plate (33) in step S6 includes a sealing portion (331) and a guiding portion (332), wherein the guiding portion (332) is fixedly mounted on the sealing portion (331), and the sealing portion (331) is provided with a through hole (35) for allowing a pipeline and a supporting hanging plate (6) to pass through, and a sealing mounting groove (34) adapted to the outer dimensions of the sealing plate (33) is recessed on the top of the well body (5).