Water-light complementary model optimization method and device for improving water energy storage efficiency
By adjusting the output of the hydropower unit, meeting the load needs of the power grid, realizing the complementarity between hydropower and photovoltaics, the problem of inefficient energy efficiency caused by independent operation is solved and the efficiency of water storage is improved.
Patent Information
- Application Number
- CN202411494275.5
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-10-24
- Publication Date
- 2025-02-11
AI Technical Summary
In the prior art, hydropower stations and photovoltaic power stations are usually operated independently, and the complementarity of the two is not fully utilized, resulting in inefficiency in energy and waste of resources.
A water-light complementary model optimization method is proposed. By adjusting the output of each hydroelectric unit, it meets the load needs of 500kV lines and 220kV lines. The goal is to minimize the total water consumption of all hydroelectric units.
On the premise of ensuring photovoltaic power generation, reduce the water consumption of hydropower generation, improve water energy storage efficiency, make full use of water resources, and optimize the energy structure.
Smart Images

Figure CN119419942A_ABST
Abstract
Description
Technical Field
[0001] The present application relates to the technical field of water-photovoltaic complementarity, and in particular to a water-photovoltaic complementarity model optimization method and device for improving water energy storage efficiency. Background Art
[0002] The installed capacity of photovoltaic power in the current power system is getting larger and larger, and the proportion of installed capacity is increasing. The traditional power system is transforming into a new power system - with the maximization of new energy consumption as the main task, supported by the interaction of source, grid, load and storage and multi-energy complementarity. Water-photovoltaic complementarity is a major form of the new power system.
[0003] However, in the prior art, hydropower stations and photovoltaic power stations are usually operated independently, failing to fully utilize the complementarity between the two. In addition, the operation of the power station usually does not take into account the optimization of load fluctuations and water consumption, resulting in low energy efficiency and waste of resources. Summary of the invention
[0004] The present application aims to solve one of the technical problems in the related art at least to some extent.
[0005] To this end, the first purpose of the present application is to propose a water-photovoltaic complementary model optimization method for improving water energy storage efficiency.
[0006] The second object of the present application is to provide a device.
[0007] The third objective of the present application is to provide an electronic device.
[0008] A fourth objective of the present application is to provide a computer-readable storage medium.
[0009] A fifth object of the present application is to provide a computer program product.
[0010] To achieve the above-mentioned purpose, the first embodiment of the present application proposes a method for optimizing a water-photovoltaic complementary model for improving water energy storage efficiency, comprising:
[0011] Determine the application scenarios of the water-light complementary model;
[0012] In the application scenario, under the premise of ensuring that photovoltaic power generation is fully generated, the output of each hydropower unit is adjusted to meet the load demand of the 500kV line and the 220kV line, and the objective function is constructed with the minimum total water consumption of all hydropower units as the goal;
[0013] Determine boundary conditions according to stable operation areas and vibration areas of different hydropower units, and solve the objective function under the constraints of the boundary conditions to obtain an optimal dispatching solution;
[0014] Based on the optimal dispatching scheme, the output of each hydropower unit is adjusted.
[0015] The application scenario includes four hydropower units and three photovoltaic stations, among which:
[0016] The installed capacity of the first, second and third hydropower units is 250MW, and the installed capacity of the fourth hydropower unit is 120MW;
[0017] The installed capacity of the first photovoltaic station is 28MW, the installed capacity of the second photovoltaic station is 78MW, and the installed capacity of the third photovoltaic station is 425MW;
[0018] On the premise that the load demand of 220kV line is met, the excess load of the second photovoltaic station, the third photovoltaic station, the third hydropower unit and the fourth hydropower unit is stepped up from the interconnecting transformer and sent out through the 500kV line. The first hydropower unit, the second hydropower unit and the first photovoltaic station meet the 500kV load demand.
[0019] The objective function is:
[0020] minH=aP1+bP2+cP3+dP4
[0021] Among them, H is the total water consumption of all hydropower units, a, b, c, d are the water consumption rates of power generation of the first hydropower unit, the second hydropower unit, the third hydropower unit, and the fourth hydropower unit, respectively, and P2, P2, P3, P4 are the real-time powers of the first hydropower unit, the second hydropower unit, the third hydropower unit, and the fourth hydropower unit, respectively.
[0022] Determining boundary conditions according to the stable operation area and vibration area of different hydropower units includes:
[0023] Assuming that the first hydropower unit and the second hydropower unit are in a stable operation zone in the 0-250MW load segment, the third hydropower unit is in a vibration zone in the 40-140MW load segment, and in a stable operation zone in the 0-40MW and 140-250MW load segments, the fourth hydropower unit is in a vibration zone in the 10-90MW load segment, and in a stable operation zone in the 0-10MW and 90-120MW load segments, the boundary conditions are:
[0024]
[0025] Among them, P 1G , P 2G , P 3G are the real-time power of the first photovoltaic station, the second photovoltaic station, and the third photovoltaic station, respectively, 220 is the real-time power of 220kV line, P 500is the real-time power of the 500kV line.
[0026] To achieve the above-mentioned purpose, the second embodiment of the present application proposes a water-photovoltaic complementary model optimization device for improving water energy storage efficiency, comprising:
[0027] A determination module, used to determine the application scenario of the water-light complementary model;
[0028] A construction module, in the application scenario, under the premise of ensuring that photovoltaic power generation is fully generated, the output of each hydropower unit is adjusted to meet the load requirements of the 500kV line and the 220kV line, and an objective function is constructed with the minimum total water consumption of all hydropower units as the goal;
[0029] A solution module, used for determining boundary conditions according to stable operation areas and vibration areas of different hydropower units, solving the objective function under the constraints of the boundary conditions, and obtaining an optimal scheduling solution;
[0030] The regulating module is used to regulate the output of each hydropower unit based on the optimal scheduling plan.
[0031] To achieve the above-mentioned purpose, the third aspect of the present application provides an electronic device, including: a processor, and a memory communicatively connected to the processor;
[0032] The memory stores computer-executable instructions;
[0033] The processor executes the computer-executable instructions stored in the memory to implement the method as described in any one of the first aspects.
[0034] To achieve the above-mentioned purpose, the fourth aspect embodiment of the present application proposes a computer-readable storage medium, in which computer-readable storage medium is stored computer execution instructions, and when the computer execution instructions are executed by a processor, they are used to implement the method as described in any one of the first aspects.
[0035] To achieve the above-mentioned purpose, the fifth aspect of the present application proposes a computer program product, which implements any method in the first aspect when executed by a processor.
[0036] The present application provides a method, device, electronic device and storage medium for optimizing a water-photovoltaic complementary model for improving water energy storage efficiency, which can make full use of the storability of water, adjust photovoltaic plants on long-term and short-term scales, and minimize the water consumption for hydropower generation while ensuring the photovoltaic power output, fully store and utilize water resources, thereby improving water energy storage efficiency.
[0037] Additional aspects and advantages of the present application will be given in part in the description below, and in part will become apparent from the description below, or will be learned through the practice of the present application. BRIEF DESCRIPTION OF THE DRAWINGS
[0038] The above and / or additional aspects and advantages of the present application will become apparent and easily understood from the following description of the embodiments in conjunction with the accompanying drawings, in which:
[0039] Figure 1 A schematic flow chart of a water-photovoltaic complementary model optimization method for improving water energy storage efficiency provided in an embodiment of the present application;
[0040] Figure 2 A schematic diagram of an application scenario of the water-light complementary model provided in an embodiment of the present application;
[0041] Figure 3 The single-day output curve of each unit obtained by MATLAB simulation provided in the embodiment of the present application;
[0042] Figure 4 A schematic diagram of the structure of a water-photovoltaic complementary model optimization device for improving water energy storage efficiency provided in an embodiment of the present application. DETAILED DESCRIPTION
[0043] Embodiments of the present application are described in detail below, and examples of the embodiments are shown in the accompanying drawings, wherein the same or similar reference numerals throughout represent the same or similar elements or elements having the same or similar functions. The embodiments described below with reference to the accompanying drawings are exemplary and are intended to be used to explain the present application, and should not be construed as limiting the present application.
[0044] The installed capacity of photovoltaic power in the current power system is getting larger and larger, and the proportion of installed capacity is increasing. The traditional power system is transforming into a new power system - with the main task of maximizing the consumption of new energy, supported by the interaction of source, grid, load and storage and multi-energy complementarity. Hydropower complementarity is a major form in the new power system. Hydropower complementarity is to connect the photovoltaic station to the hydropower station, connect to the power grid through the transmission channel of the hydropower station, and use the regulation and storage capacity of the hydropower station reservoir and the rapid regulation capacity of the hydropower unit to bundle and send the photovoltaic power generation and hydropower unit power together to improve the utilization rate of the transmission line channel. Hydropower complementarity mainly utilizes the seasonal characteristics of the reservoir, which is divided into the flood season and the dry season. During the flood season, the hydropower unit outputs according to the incoming water and system demand, fully consumes the reservoir capacity, and the photovoltaic output tracks the hydropower output to increase the short-term peak capacity of hydropower; during the dry season, the hydropower will give way to the photovoltaic output, and the photovoltaic output is not limited. The hydropower unit plays the characteristics of flexible start and stop, providing peak and frequency regulation capacity for the system and photovoltaic.
[0045] However, in the prior art, hydropower stations and photovoltaic power stations are usually operated independently, failing to fully utilize the complementarity between the two. In addition, the operation of the power station usually does not take into account the optimization of load fluctuations and water consumption, resulting in low energy efficiency and waste of resources.
[0046] To address this problem, the present invention provides a method for optimizing a water-photovoltaic complementary model to improve water energy storage efficiency. Figure 1 A schematic diagram of a flow chart of a water-photovoltaic complementary model optimization method for improving water energy storage efficiency provided in an embodiment of the present application. Figure 1 As shown, the method comprises the following steps:
[0047] Step 101, determining the application scenario of the water-light complementary model.
[0048] In a possible embodiment, the application scenario of the water-light complementary model is as follows: Figure 2 shown.
[0049] exist Figure 2 The scenario shown includes four hydropower units and three photovoltaic stations, including:
[0050] The installed capacity of the first hydropower unit 1F, the second hydropower unit 2F, and the third hydropower unit 3F are all 250MW, and the installed capacity of the fourth hydropower unit 4F is 120MW;
[0051] The installed capacity of the first photovoltaic station 1G is 28MW, the installed capacity of the second photovoltaic station 2G is 78MW, and the installed capacity of the third photovoltaic station 3G is 425MW;
[0052] On the premise of meeting the load demand of 220kV line, the second photovoltaic station 2G, the third photovoltaic station 3G, the third hydropower unit 3F and the fourth hydropower unit 4F, the excess load is boosted from the interconnecting transformer 5G and sent out through the 500kV line. The first hydropower unit 1F, the second hydropower unit 2F and the first photovoltaic station 1G meet the 500kV load demand.
[0053] The symbol parameters involved in this application scenario are shown in the following table.
[0054] Table 1
[0055]
[0056]
[0057] Step 102, in the application scenario, under the premise of ensuring that photovoltaic power generation is fully generated, the output of each hydropower unit is adjusted to meet the load demand of the 500kV line and the 220kV line, and the objective function is constructed with the goal of minimizing the total water consumption of all hydropower units.
[0058] In the embodiment of the present application, under the premise of meeting the system load demand, meeting the forced output of hydropower, and ensuring that photovoltaic power generation is fully generated, the load demand of the 500kV line and the 220kV line is met by adjusting the output of 1F-4F. On this basis, the output of 1F-4F is reasonably arranged to achieve the goal of minimizing the total water consumption.
[0059] Among them, the objective function constructed with the minimum total water consumption of all hydropower units can be expressed as:
[0060] minH=aP1+bP2+cP3+dP4
[0061] Among them, H is the total water consumption of all hydropower units, a, b, c, d are the water consumption rates of the first, second, third and fourth hydropower units respectively, and P2, P2, P3, P4 are the real-time powers of the first, second, third and fourth hydropower units respectively.
[0062] In a possible embodiment, [a bcd] = [0.20.250.220.6].
[0063] Step 103, determining boundary conditions according to the stable operation areas and vibration areas of different hydropower units, solving the objective function under the constraints of the boundary conditions, and obtaining the optimal scheduling solution.
[0064] In a possible embodiment, it is assumed that 1F and 2F are in a stable operation zone in the 0-250MW load range; 3F is in a vibration zone in the 40-140MW load range, and the unit should not be operated in this load range, and the 0-40MW and 140-250MW load ranges are in a stable operation zone, and the unit can be operated stably for a long time in this load range; 4F is in a vibration zone in the 10-90MW load range, and the unit should not be operated in this load range, and the 0-10MW and 90-120MW load ranges are in a stable operation zone, and the unit can be operated stably for a long time in this load range. The above boundary conditions are as follows:
[0065]
[0066] Among them, P 1G , P 2G , P 3G are the real-time power of the first photovoltaic station, the second photovoltaic station, and the third photovoltaic station, P 220 is the real-time power of 220kV line, P 500 is the real-time power of the 500kV line.
[0067] It can be understood that after determining the constraints and the objective function, solving the model is well known to those skilled in the art, and this application does not specifically limit the solution method.
[0068] As an implementation method, use linear programming, nonlinear programming or other optimization algorithms to solve the model, and consider using tools such as MATLAB and Python for numerical simulation and optimization.
[0069] It can be understood that the water-photovoltaic complementary model proposed in this application uses a connecting transformer to connect the three voltage levels of 500kV, 220kV, and 35kV. Photovoltaic stations are connected to the three voltage level buses, which is generally representative of the water-photovoltaic complementary mode. Moreover, most photovoltaic stations are currently connected to hydropower stations at a single voltage level. Therefore, the actual part of the model can be extracted to establish a model and solve it.
[0070] Step 104: Adjust the output of each hydropower unit based on the optimal scheduling plan.
[0071] In a possible embodiment, after adjusting the output of each hydropower unit based on the optimal scheduling scheme, the single-day output curve obtained by MATLAB simulation is as follows: Figure 3 shown.
[0072] It can be understood that the water-photovoltaic complementary operation model proposed in this application has the following effects:
[0073] 1. Hydropower and photovoltaic complementary peak-shifting power generation enhances peak capacity. In the hydropower and photovoltaic complementary model, photovoltaic output increases during the day, hydropower output decreases under normal circumstances, and reservoirs store water; during peak electricity consumption periods, hydropower increases its output, forming a reasonable staggered system demand for photovoltaic and hydropower output.
[0074] 2. "Store water in low seasons and consume water in high seasons" on an annual scale to effectively optimize the energy structure of the power grid. The water inflow of hydropower is divided into the flood season and the dry season. In the flood season, the upstream water inflow is large. In order to avoid water abandonment, a certain hydropower output needs to be guaranteed. During the flood season, when the sunlight is good and the channel capacity is limited, the hydropower units reduce the output to give up the channel and form a short-term water storage, giving priority to photovoltaic power generation. The hydropower units adjust the output according to the needs of the system, and the hydropower output tracks the photovoltaic output during the day. When the sunlight is not ideal, the hydropower output is increased according to the water inflow and system needs to fully absorb the reservoir capacity; during the dry season, the upstream water inflow is small. While ensuring the minimum forced output of hydropower, the delivery channel can be given to photovoltaic power generation as much as possible, and the reservoir can store water. The hydropower units play the characteristics of flexible start and stop, providing peak and frequency regulation capacity for the system and new energy.
[0075] 3. Hydropower regulation can smooth out the fluctuation of new energy load on a daily scale. Photovoltaic power generation has the obvious characteristics of large installed capacity and small power output, and is easily affected by weather, temperature, solar radiation intensity, etc. For the problem of large fluctuations in photovoltaic output during the day, the hydropower regulation capacity in water-photovoltaic complementarity can be fully utilized to smooth it out. The rapid and flexible response capabilities of hydropower units can cope with extreme situations such as instantaneous decline in photovoltaic output caused by extreme weather and partial photovoltaic matrix disconnection caused by collector line failure.
[0076] 4. The regulation characteristics of hydropower units strongly support the consumption of new energy. The water-photovoltaic complementary operation model is photovoltaic power to hydropower power. As a large power source, the hydropower unit has the characteristics of rapid regulation and can provide effective frequency regulation technology support for the surrounding photovoltaic power generation operation. At the same time, the power-to-power characteristics of the water-photovoltaic complementary model, through the rotating standby of the hydropower unit, the response of the synchronous generator is increased, providing regional inertia response capability.
[0077] In order to implement the above-mentioned embodiments, the present application also proposes a water-photovoltaic complementary model optimization device for improving water energy storage efficiency. Figure 4 This is a schematic diagram of the structure of a water-light complementary model optimization device 10 for improving water energy storage efficiency provided in an embodiment of the present application. Figure 4 As shown, the device comprises:
[0078] A determination module 100 is used to determine an application scenario of the water-light complementary model;
[0079] Building module 200, in the application scenario, under the premise of ensuring that photovoltaic power generation is fully generated, the output of each hydropower unit is adjusted to meet the load demand of the 500kV line and the 220kV line, and the objective function is constructed with the minimum total water consumption of all hydropower units as the goal;
[0080] The solution module 300 is used to determine the boundary conditions according to the stable operation area and vibration area of different hydropower units, and solve the objective function under the constraint of the boundary conditions to obtain the optimal scheduling plan;
[0081] The regulating module 400 is used to regulate the output of each hydropower unit based on the optimal scheduling solution.
[0082] In order to implement the above embodiments, the present application also proposes an electronic device, comprising: a processor, and a memory communicatively connected to the processor; the memory stores computer-executable instructions; the processor executes the computer-executable instructions stored in the memory to implement the method provided by the above embodiments.
[0083] In order to implement the above embodiments, the present application also proposes a computer-readable storage medium, in which computer-executable instructions are stored. When the computer-executable instructions are executed by a processor, they are used to implement the methods provided by the above embodiments.
[0084] In order to implement the above embodiments, the present application also proposes a computer program product, including a computer program, which implements the methods provided by the above embodiments when executed by a processor.
[0085] The collection, storage, use, processing, transmission, provision and disclosure of user personal information involved in this application are in compliance with relevant laws and regulations and do not violate public order and good morals.
[0086] It should be noted that personal information from users should be collected for legitimate and reasonable purposes and should not be shared or sold outside of these legitimate uses. In addition, such collection / sharing should be carried out after receiving the user's informed consent, including but not limited to notifying the user to read the user agreement / user notice and sign the agreement / authorization including authorization of relevant user information before the user uses the function. In addition, any necessary steps should be taken to protect and safeguard access to such personal information data and ensure that others who have access to personal information data comply with its privacy policy and procedures.
[0087] The present application is expected to provide an implementation scheme for users to selectively block the use or access of personal information data. That is, the present disclosure is expected to provide hardware and / or software to prevent or block access to such personal information data. Once the personal information data is no longer needed, the risk can be minimized by limiting data collection and deleting the data. In addition, when applicable, such personal information is de-identified to protect the privacy of the user.
[0088] In the description of the aforementioned embodiments, the description with reference to the terms "one embodiment", "some embodiments", "example", "specific example", or "some examples" etc. means that the specific features, structures, materials or characteristics described in conjunction with the embodiment or example are included in at least one embodiment or example of the present application. In this specification, the schematic representations of the above terms do not necessarily refer to the same embodiment or example. Moreover, the specific features, structures, materials or characteristics described may be combined in any one or more embodiments or examples in a suitable manner. In addition, those skilled in the art may combine and combine the different embodiments or examples described in this specification and the features of the different embodiments or examples, without contradiction.
[0089] In addition, the terms "first" and "second" are used for descriptive purposes only and should not be understood as indicating or implying relative importance or implicitly indicating the number of the indicated technical features. Therefore, the features defined as "first" and "second" may explicitly or implicitly include at least one of the features. In the description of this application, the meaning of "plurality" is at least two, such as two, three, etc., unless otherwise clearly and specifically defined.
[0090] Any process or method description in a flowchart or otherwise described herein may be understood to represent a module, fragment or portion of code comprising one or more executable instructions for implementing the steps of a custom logical function or process, and the scope of the preferred embodiments of the present application includes alternative implementations in which functions may not be performed in the order shown or discussed, including performing functions in a substantially simultaneous manner or in the reverse order depending on the functions involved, which should be understood by technicians in the technical field to which the embodiments of the present application belong.
[0091] The logic and / or steps represented in the flowchart or otherwise described herein, for example, can be considered as an ordered list of executable instructions for implementing logical functions, and can be embodied in any computer-readable medium for use by an instruction execution system, device or apparatus (such as a computer-based system, a system including a processor, or other system that can fetch instructions from an instruction execution system, device or apparatus and execute the instructions), or in combination with these instruction execution systems, devices or apparatuses. For the purpose of this specification, "computer-readable medium" can be any device that can contain, store, communicate, propagate or transmit a program for use by an instruction execution system, device or apparatus, or in combination with these instruction execution systems, devices or apparatuses. More specific examples of computer-readable media (a non-exhaustive list) include the following: an electrical connection with one or more wires (electronic device), a portable computer disk box (magnetic device), a random access memory (RAM), a read-only memory (ROM), an erasable and programmable read-only memory (EPROM or flash memory), a fiber optic device, and a portable compact disk read-only memory (CDROM). In addition, the computer-readable medium may even be paper or other suitable medium on which the program is printed, since the program may be obtained electronically, for example, by optically scanning the paper or other medium and then editing, interpreting or processing in other suitable ways if necessary, and then stored in a computer memory.
[0092] It should be understood that the various parts of the present application can be implemented by hardware, software, firmware or a combination thereof. In the above-mentioned embodiments, multiple steps or methods can be implemented by software or firmware stored in a memory and executed by a suitable instruction execution system. For example, if implemented by hardware, as in another embodiment, it can be implemented by any one of the following technologies known in the art or their combination: a discrete logic circuit having a logic gate circuit for implementing a logic function for a data signal, a dedicated integrated circuit having a suitable combination of logic gate circuits, a programmable gate array (PGA), a field programmable gate array (FPGA), etc.
[0093] A person skilled in the art may understand that all or part of the steps in the method for implementing the above-mentioned embodiment may be completed by instructing related hardware through a program, and the program may be stored in a computer-readable storage medium, which, when executed, includes one or a combination of the steps of the method embodiment.
[0094] In addition, each functional unit in each embodiment of the present application may be integrated into a processing module, or each unit may exist physically separately, or two or more units may be integrated into one module. The above-mentioned integrated module may be implemented in the form of hardware or in the form of a software functional module. If the integrated module is implemented in the form of a software functional module and sold or used as an independent product, it may also be stored in a computer-readable storage medium.
[0095] The storage medium mentioned above may be a read-only memory, a magnetic disk or an optical disk, etc. Although the embodiments of the present application have been shown and described above, it can be understood that the above embodiments are exemplary and cannot be understood as limiting the present application. A person of ordinary skill in the art may change, modify, replace and modify the above embodiments within the scope of the present application.
Claims
1. A water-photovoltaic complementary model optimization method for improving water energy storage efficiency, characterized in that: The following steps are involved: Determine the application scenarios of the water-light complementary model; In the application scenario, under the premise of ensuring that photovoltaic power generation is fully generated, the output of each hydropower unit is adjusted to meet the load demand of the 500kV line and the 220kV line, and the objective function is constructed with the minimum total water consumption of all hydropower units as the goal; Determine boundary conditions according to stable operation areas and vibration areas of different hydropower units, and solve the objective function under the constraints of the boundary conditions to obtain an optimal dispatching solution; Based on the optimal dispatching scheme, the output of each hydropower unit is adjusted.
2. The method according to claim 1, characterized in that The application scenario includes four hydropower units and three photovoltaic stations, among which: The installed capacity of the first, second and third hydropower units is 250MW, and the installed capacity of the fourth hydropower unit is 120MW; The installed capacity of the first photovoltaic station is 28MW, the installed capacity of the second photovoltaic station is 78MW, and the installed capacity of the third photovoltaic station is 425MW; On the premise that the load demand of 220kV line is met, the excess load of the second photovoltaic station, the third photovoltaic station, the third hydropower unit and the fourth hydropower unit is stepped up from the interconnecting transformer and sent out through the 500kV line. The first hydropower unit, the second hydropower unit and the first photovoltaic station meet the 500kV load demand.
3. The method according to claim 2, characterized in that The objective function is: minH=aP1+bP2+cP3+dP4 Among them, H is the total water consumption of all hydropower units, a, b, c, d are the water consumption rates of power generation of the first hydropower unit, the second hydropower unit, the third hydropower unit, and the fourth hydropower unit, respectively, and P2, P2, P3, P4 are the real-time powers of the first hydropower unit, the second hydropower unit, the third hydropower unit, and the fourth hydropower unit, respectively.
4. The method according to claim 3, characterized in that Determining boundary conditions according to the stable operation area and vibration area of different hydropower units includes: Assuming that the first hydropower unit and the second hydropower unit are in a stable operation zone in the 0-250MW load segment, the third hydropower unit is in a vibration zone in the 40-140MW load segment, and in a stable operation zone in the 0-40MW and 140-250MW load segments, the fourth hydropower unit is in a vibration zone in the 10-90MW load segment, and in a stable operation zone in the 0-10MW and 90-120MW load segments, the boundary conditions are: Among them, P 1G , P 2G , P 3G are the real-time power of the first photovoltaic station, the second photovoltaic station, and the third photovoltaic station, respectively, 220 is the real-time power of 220kV line, P 500 is the real-time power of the 500kV line.
5. A water-photovoltaic complementary model optimization device for improving water energy storage efficiency, characterized in that: include: A determination module, used to determine the application scenario of the water-light complementary model; A construction module, in the application scenario, under the premise of ensuring that photovoltaic power generation is fully generated, the output of each hydropower unit is adjusted to meet the load requirements of the 500kV line and the 220kV line, and an objective function is constructed with the minimum total water consumption of all hydropower units as the goal; A solution module, used for determining boundary conditions according to stable operation areas and vibration areas of different hydropower units, solving the objective function under the constraints of the boundary conditions, and obtaining an optimal scheduling solution; The regulating module is used to regulate the output of each hydropower unit based on the optimal scheduling plan.
6. An electronic device, characterized in that: include: A processor, and a memory communicatively connected to the processor; The memory stores computer-executable instructions; The processor executes the computer-executable instructions stored in the memory to implement the method according to any one of claims 1 to 4.
7. A computer-readable storage medium, characterized in that: The computer-readable storage medium stores computer-executable instructions, which are used to implement the method according to any one of claims 1 to 4 when executed by a processor.
8. A computer program product, characterized in that The invention comprises a computer program, which implements the method according to any one of claims 1 to 4 when being executed by a processor.