Power transmission line construction transportation scheme three-dimensional design method suitable for mountainous area, terminal equipment and storage medium
By establishing a geographical information data model for transmission line engineering in the GIS system, analyzing and selecting the optimal transportation plan, the problem of long and low efficiency of construction transportation plans in mountainous areas is solved, and fast and efficient design and analysis is achieved.
Patent Information
- Application Number
- CN202411492535.5
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-10-24
- Publication Date
- 2025-02-14
AI Technical Summary
The prior art takes a long time and is inefficient in determining the construction and transportation plan of mountain transmission lines.
By establishing a geographical information data model for transmission line engineering in the GIS system, creating a line path plan, loading road network data, analyzing the domestic, small, cableway, and road widening plans, and selecting the optimal plan through technical and economic comparison.
It significantly shortens the calculation and analysis time of construction and transportation plans, improves design quality and efficiency, and ensures the accuracy of results.
Smart Images

Figure CN119443443A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of power transmission, and is a three-dimensional design method, terminal equipment and storage medium for a power transmission line construction and transportation scheme suitable for mountainous areas. Background Art
[0002] The transportation plan for power transmission line construction includes design contents such as transportation mode selection, route planning, passability verification, engineering quantity calculation statistics, data comparison and transportation plan demonstration. In the past, there was no relevant and effective three-dimensional design method. In engineering, most of the transportation plans were determined by searching on the map and combining on-site surveys. For mountainous areas, this mode is time-consuming and inefficient.
[0003] For example, Xinjiang Uygur Autonomous Region is located in northwest China, in the hinterland of Eurasia. Its topographical features can be summarized as "three mountains and two basins", namely the Altai Mountains in the north, the Kunlun Mountains in the south, and the Tianshan Mountains running through the middle, dividing Xinjiang Uygur Autonomous Region into north and south. This topography not only shapes the unique natural landscape of Xinjiang Uygur Autonomous Region, but also has a certain impact on the local transportation development. Xinjiang Uygur Autonomous Region has a vast territory, and the transportation of construction materials for power transmission lines must be combined with the topographical characteristics of the area through which the route plan passes.
[0004] Therefore, in order to complete the calculation and analysis of the construction and transportation scheme more quickly and efficiently, a three-dimensional design method for the construction and transportation scheme of transmission lines in mountainous areas is proposed to solve the above problems. Summary of the invention
[0005] The present invention provides a three-dimensional design method, terminal equipment and storage medium for power transmission line construction and transportation schemes suitable for mountainous areas, which overcomes the deficiencies of the above-mentioned prior art and can effectively solve the problem of long time consumption and low efficiency in determining power transmission line construction and transportation schemes in mountainous areas.
[0006] One of the technical solutions of the present invention is achieved through the following measures: a three-dimensional design method for a power transmission line construction and transportation plan suitable for mountainous areas, comprising the following steps: establishing a transmission line project geographic information data model based on a GIS system; creating a line path plan in the GIS system, the line path plan including path lines and tower sites, forming several sections, and including meteorological conditions and design conditions information; loading road network data, and analyzing the large-scale transportation, small-scale transportation, cableway, and road widening plans in the project area based on the geographic information data model; and selecting the optimal plan through technical and economic comparison.
[0007] The following is a further optimization and / or improvement of one of the above-mentioned technical solutions:
[0008] The specific steps may include:
[0009] Step S1, establishing a geographic information data model in GIS, loading aerial orthophotos or online images and elevation data;
[0010] Step S2: Create a route plan, import all tower sites into the GIS system according to their coordinate positions, and form a route line;
[0011] Step S3, dividing the route into sections according to tower locations or line segments, and configuring meteorological conditions for each section to facilitate classification and statistics;
[0012] Step S4, loading road network data;
[0013] Step S5, selecting the material station location;
[0014] Step S6, selecting the unloading point position;
[0015] Step S7, calculating the transport route, wherein the transport route is the length of the road from the material station to the unloading point;
[0016] Step S8, calculating the small transport route, wherein the small transport route is the straight-line distance from the unloading point to the tower site;
[0017] Step S9, performing three-dimensional design of the cableway;
[0018] Step S10: Establish a solution library for large-scale transportation, small-scale transportation and cableway, sort and output the best solution.
[0019] The above step S5 may specifically include the following steps:
[0020] Step S51: Arrange the material station in the middle of the route according to the on-site transportation conditions and close to the transportation road or the designed access road;
[0021] Step S52, analyzing the terrain slope of the area where the material station is located;
[0022] Step S53: Perform manual adjustments, combine three-dimensional geographic information and road traffic data to comprehensively consider the impact of land area, surrounding traffic, and land use properties, conduct comparisons, and select the optimal layout location.
[0023] The above step S6 may specifically include the following steps:
[0024] Step S61, setting the unloading point close to the road and the tower, wherein the software initially selects the point with the shortest distance between the road and the tower;
[0025] Step S62: The site should meet the requirements for temporary stacking of materials and layout of lifting equipment;
[0026] Step S63: The line connecting the unloading point and the tower position should avoid crossing power lines, communication lines, roads, railways, residential areas, and densely vegetated areas. The site location is determined by combining the three-dimensional geographic information data, the comprehensive leveling engineering volume, and the height difference.
[0027] When solving the minimum distance from the tower site to the road, a vector algorithm can be used.
[0028] The above step S7 may specifically include the following steps:
[0029] Step S71, the software calculates the route of the Grand Canal based on the loaded road kml file;
[0030] Step S72: Analyze the road capacity. If the existing road width reaches 3.5m or more, it is suitable for mechanical transportation. Otherwise, consider building a temporary road.
[0031] Step S73, manually adjusting the temporary road;
[0032] Step S74: Based on the temporary road construction model, the size of the material transportation equipment and the amount of materials transported, the software completes the verification design of the road size, turning radius, and spatial collision transportation capacity in the three-dimensional scene one by one, and outputs the corresponding calculation results.
[0033] The second technical solution of the present invention is achieved through the following measures: a terminal device includes a memory and a processor, the memory stores a program that can be run on the processor, and when the processor executes the program, the above-mentioned three-dimensional design method for power transmission line construction and transportation scheme suitable for mountainous areas is implemented.
[0034] The third technical solution of the present invention is achieved through the following measures: a storage medium, the storage medium stores one or more programs, and the one or more programs can be executed by one or more processors to realize the above-mentioned three-dimensional design method for power transmission line construction and transportation scheme suitable for mountainous areas.
[0035] The present invention establishes a geographic information data model and path plan for the power transmission line project in the GIS system, analyzes the large-scale transportation, small-scale transportation, cableway, and road widening plans in the project area based on the road network data, and selects the optimal plan through technical and economic comparison. By establishing a geographic information data model for the power transmission line project, automatic calculation and analysis of transportation conditions can be achieved, which can significantly shorten working time and greatly promote the improvement of design quality and efficiency. The present invention carries out modeling and transportation plan calculation and analysis based on the GIS system, reduces the energy consumed by manual analysis, improves production efficiency through programmed and automated operations, and ensures the accuracy of the results. BRIEF DESCRIPTION OF THE DRAWINGS
[0036] Figure 1It is a schematic flow chart of a three-dimensional design method for a transmission line construction transportation plan applicable to mountainous areas in an embodiment of the present invention.
[0037] Figure 2 It is a schematic calculation diagram for solving the minimum distance from a tower site to a road (when 0 < r < 1) in an embodiment of the present invention.
[0038] Figure 3 It is a schematic calculation diagram for solving the minimum distance from a tower site to a road (when r ≥ 1) in an embodiment of the present invention.
[0039] Figure 4 It is a schematic calculation diagram for solving the minimum distance from a tower site to a road (when r ≤ 0) in an embodiment of the present invention. Specific embodiments
[0040] The present invention is not limited by the following embodiments, and specific implementation manners can be determined according to the technical solutions of the present invention and actual situations.
[0041] The present invention will be further described below in conjunction with embodiments:
[0042] Embodiment 1: As shown in Appendix Figure 1 to Appendix Figure 4 The three-dimensional design method for a transmission line construction transportation plan applicable to mountainous areas includes the following steps: establishing a geographical information data model for the transmission line project based on the GIS system; creating a line path plan in the GIS system, where the line path plan includes path lines and tower sites, forming several sections, and containing meteorological conditions and design condition information; loading road network data, and analyzing the large transport, small transport, cableway, and road widening plans in the project area based on the geographical information data model; selecting the optimal plan through technical and economic comparison.
[0043] Specifically, it includes the following steps:
[0044] Step S1: Establish a geographical information data model in the GIS, and load aerial orthophoto images or online images and elevation data;
[0045] Step S2: Create a line path plan, and import all tower sites into the GIS system according to their coordinate positions, and form path lines;
[0046] Step S3: Divide sections, divide the path lines into several sections according to tower sites or line segments, and configure the meteorological conditions for each section for classification and statistics;
[0047] Step S4: Load road network data; in this embodiment, the road network data should include national roads, provincial roads, county roads, township roads, village-level roads, near-tower paths, and bridge holes near the line path, and the object information should include length, height, width, surface layer material, foundation bearing capacity, and height limit control; in this embodiment, the format of the road network data is kml;
[0048] Step S5, select the material station location; in this embodiment, the naming rule may be CL1, CL2...CLn.
[0049] In this embodiment, step S5 specifically includes the following steps:
[0050] Step S51: According to the on-site transportation conditions, the material station is arranged in the middle of the route and close to the transportation road or the designed access road; in this embodiment, the distance limit is set to 10m; the average distance between two material stations is generally 40km / station, so in this embodiment, if the average distance is less than 40km, the material station setting location should be reduced, otherwise it should be increased;
[0051] Step S52, analyzing the terrain slope of the area where the material station is located. In this embodiment, a flat area is selected, where the slope is less than 10 degrees;
[0052] Step S53: Perform manual adjustments, combine three-dimensional geographic information and road traffic data to comprehensively consider the impact of land area, surrounding traffic, and land use properties, conduct comparisons, and select the optimal layout location.
[0053] Step S6, selecting the unloading point location; in this embodiment, the naming rule may be XL1, XL2...XLn;
[0054] In this embodiment, step S6 specifically includes the following steps:
[0055] Step S61, setting the unloading point close to the road and the tower, wherein the software initially selects the point with the shortest distance between the road and the tower;
[0056] Step S62: The site should meet the requirements for temporary storage of materials and layout of lifting equipment; in this embodiment, the site is automatically selected according to the area of about 5×5m;
[0057] Step S63: The line connecting the unloading point and the tower position should avoid crossing power lines, communication lines, roads, railways, residential areas, and densely vegetated areas. The site location is determined by combining the three-dimensional geographic information data, the comprehensive leveling engineering volume, and the height difference.
[0058] In this embodiment, a vector algorithm is used to solve the minimum distance from the tower site to the road. The vector algorithm process is clear. When the amount of data to be calculated is large, this method has obvious advantages. Its principle is:
[0059] like Figure 2 , 3 , as shown in 4, first find the vector In the direction The projection on
[0060]
[0061] The above is the unit vector in the direction whose meaning is to determine the direction of the vector to be found. is the inner product of two vectors, and where θ is the included angle between the vector AP and AB. is the vector length. Then is namely Figure 2 the length value of the line segment AC in without directionality. This value and the above-mentioned that characterizes the direction in the direction together form a new vector with magnitude and direction
[0062] According to the obtained From the directionality of the vector, it can be known that: if the situation is Figure 2 as shown, then 0 < r < 1; if it is the situation Figure 3 as shown, then r ≥ 1; if it is the situation Figure 4 as shown, then r ≤ 0; special situations such as a point on a line segment, a point at an endpoint, a point on the extension of a line segment, etc. all apply to this formula.
[0063] Therefore, according to different r values, the shortest distance can be calculated as:
[0064]
[0065] Step S7, calculate the large transport route, where the large transport route is the road length from the material station to the unloading point; in this embodiment, its naming rule can be DY1, DY2... DYn.
[0066] In this embodiment, step S7 specifically includes the following steps:
[0067] Step S71, the software calculates the large transport route based on the loaded road kml file, maximizing the use of the existing roads on the project site, thereby reducing the length of the temporary road construction;
[0068] Step S72, analyze the road passing capacity. In this embodiment, if the width of the existing road reaches more than 3.5m, it has the condition for mechanical transportation, otherwise, a temporary road should be considered for construction;
[0069] Step S73, manually adjust the temporary road; in this embodiment, the main data information such as the construction size, road material, reinforcement range, and channel cleaning of the temporary road should be able to be marked and reflected in the 3D model, and the construction, cleaning, and compensation engineering quantities involved can be statistically calculated and output to meet the conditions for multi - scheme comparison of material transportation;
[0070] Step S74: Based on the temporary road construction model, the size of the material transportation equipment and the amount of materials transported, the software completes the verification design of the road size, turning radius, and space collision transportation capacity in the three-dimensional scene, and outputs the corresponding calculation results. The large-scale transportation plan is shown in Table 1.
[0071] Table 1 List of Grand Canal Plans
[0072]
[0073] Step S8, calculate the small transport route, wherein the small transport route is the straight-line distance from the unloading point to the tower site; in this embodiment, the naming rule can be XY1, XY2...XYn; the small transport plan is shown in Table 2.
[0074] Table 2 List of small transport plans
[0075]
[0076]
[0077] Step S9, perform three-dimensional design of the cableway; in this embodiment, when the XL point overlaps, generally when more than three towers overlap, the small transport XY is marked as SD, that is, the cableway design is switched; the three-dimensional design of the cableway should include parametric modeling, line design, ranking arrangement, load-bearing cable sag calculation, cross-span verification, engineering quantity and cleanup quantity statistics, etc. The cableway scheme is shown in Table 3.
[0078] Table 3 List of ropeway solutions
[0079]
[0080] Step S10, establish a scheme library for large-scale transportation, small-scale transportation and cableway and sort and output the best scheme. In this embodiment, the transportation three-dimensional design result file should include the transportation scheme layout, road horizontal and vertical section drawings, engineering material list, etc. The relevant projects should be reflected in the mechanized construction unit basic planning table. The scheme comparison result table is shown in Table 4.
[0081] Table 4 Scheme comparison results
[0082]
[0083] Compared with the prior art, the three-dimensional design method for the construction and transportation scheme of power transmission lines in mountainous areas establishes a geographic information data model and path scheme for power transmission line projects in the GIS system, analyzes the large-scale transportation, small-scale transportation, cableway, and road widening schemes in the project area based on the road network data, and selects the optimal scheme through technical and economic comparison. By establishing a geographic information data model for power transmission line projects, automatic calculation and analysis of transportation conditions can be achieved, which can significantly shorten working time and greatly promote the improvement of design quality and efficiency. The present invention carries out modeling and transportation scheme calculation and analysis based on the GIS system, reduces the energy consumed by manual analysis, improves production efficiency through programmed and automated operations, and ensures the accuracy of the results.
[0084] Embodiment 2: This embodiment provides a terminal device, which includes a memory, a processor, a communication interface and a communication bus. The memory stores a program that can be run on the processor. When the processor executes the program, the three-dimensional design method of the transmission line construction and transportation plan applicable to mountainous areas in the above embodiment is implemented.
[0085] The processor may be a central processing unit, or other general-purpose processors, digital signal processors, application-specific integrated circuits, field programmable gate arrays or other programmable logic devices, discrete gate or transistor logic devices, discrete hardware components, or a combination of the above chips.
[0086] The memory, as a non-transient computer-readable storage medium, can be used to store non-transient software programs, non-transient computer executable programs and units, such as the corresponding program units in the above method embodiments of the present invention. The processor executes various functional applications and data processing of the processor by running the non-transient software programs, instructions and modules stored in the memory, thereby realizing the three-dimensional design method for the construction and transportation scheme of power transmission lines in mountainous areas in the above embodiment.
[0087] The memory may include a program storage area and a data storage area, wherein the program storage area may store an operating system, an application required by at least one function; the data storage area may store data created by the processor, etc. In addition, the memory may include a high-speed random access memory, and may also include a non-volatile memory, such as at least one disk storage device, a flash memory device, or other non-volatile solid-state storage device. The memory may optionally include a memory remotely disposed relative to the processor, and these remote memories may be connected to the processor via a network. One or more programs are stored in the memory, and when executed by the processor, the three-dimensional design method for the construction and transportation scheme of the power transmission line applicable to mountainous areas in the above-mentioned embodiment is executed.
[0088] Embodiment 3: This embodiment provides a storage medium for computer-readable storage, the storage medium stores one or more programs, and the one or more programs can be executed by one or more processors to implement the three-dimensional design method of power transmission line construction and transportation scheme applicable to mountainous areas as in the above embodiment.
[0089] The storage medium may be an internal storage unit of the terminal device, such as a hard disk or memory of the terminal device. The storage medium may also be an external storage device of the terminal device, such as a plug-in hard disk, smart memory card, secure digital card, flash memory card, etc. equipped on the terminal device.
[0090] The above technical features constitute the embodiments of the present invention, which have strong adaptability and implementation effect. Non-essential technical features can be added or reduced according to actual needs to meet the requirements of different situations.
Claims
1. A three-dimensional design method for power transmission line construction and transportation scheme suitable for mountainous areas, characterized in that The following steps are involved: Establish a geographic information data model for the power transmission line project based on the GIS system; create a line path plan in the GIS system, which includes path lines and tower sites, forming several sections, and contains information on meteorological conditions and design conditions; load road network data, and analyze the large-scale, small-scale, cableway, and road widening plans in the project area based on the geographic information data model; select the optimal plan through technical and economic comparison.
2. The three-dimensional design method for power transmission line construction and transportation scheme suitable for mountainous areas according to claim 1 is characterized in that The specific steps include: Step S1, establishing a geographic information data model in GIS, loading aerial orthophotos or online images and elevation data; Step S2: Create a route plan, import all tower sites into the GIS system according to their coordinate positions, and form a route line; Step S3, dividing the route into sections according to tower locations or line segments, and configuring meteorological conditions for each section to facilitate classification and statistics; Step S4, loading road network data; Step S5, selecting the material station location; Step S6, selecting the unloading point position; Step S7, calculating the transport route, wherein the transport route is the length of the road from the material station to the unloading point; Step S8, calculating the small transport route, wherein the small transport route is the straight-line distance from the unloading point to the tower site; Step S9, performing three-dimensional design of the cableway; Step S10: Establish a solution library for large-scale transportation, small-scale transportation and cableway, sort and output the best solution.
3. The three-dimensional design method for power transmission line construction and transportation scheme suitable for mountainous areas according to claim 2 is characterized in that Step S5 specifically includes the following steps: Step S51: Arrange the material station in the middle of the route according to the on-site transportation conditions and close to the transportation road or the designed access road; Step S52, analyzing the terrain slope of the area where the material station is located; Step S53: Perform manual adjustments, combine three-dimensional geographic information and road traffic data to comprehensively consider the impact of land area, surrounding traffic, and land use properties, conduct comparisons, and select the optimal layout location.
4. The three-dimensional design method for power transmission line construction and transportation scheme applicable to mountainous areas according to claim 2 or 3, characterized in that Step S6 specifically includes the following steps: Step S61, setting the unloading point close to the road and the tower, wherein the software initially selects the point with the shortest distance between the road and the tower; Step S62: The site should meet the requirements for temporary stacking of materials and layout of lifting equipment; Step S63: The line connecting the unloading point and the tower position should avoid crossing power lines, communication lines, roads, railways, residential areas, and densely vegetated areas. The site location is determined by combining the three-dimensional geographic information data, the comprehensive leveling engineering volume, and the height difference.
5. The three-dimensional design method for power transmission line construction and transportation scheme applicable to mountainous areas according to claim 2 or 3, characterized in that When solving the minimum distance from the tower site to the road, a vector algorithm is used.
6. The three-dimensional design method for power transmission line construction and transportation scheme applicable to mountainous areas according to claim 2 or 3, characterized in that Step S7 specifically includes the following steps: Step S71, the software calculates the route of the Grand Canal based on the loaded road kml file; Step S72: Analyze the road capacity. If the existing road width reaches 3.5m or more, it is suitable for mechanical transportation. Otherwise, consider building a temporary road. Step S73, manually adjusting the temporary road; Step S74: Based on the temporary road construction model, the size of the material transportation equipment and the amount of materials transported, the software completes the verification design of the road size, turning radius, and spatial collision transportation capacity in the three-dimensional scene one by one, and outputs the corresponding calculation results.
7. A terminal device, comprising a memory and a processor, wherein the memory stores a program that can be run on the processor, characterized in that: When the processor executes the program, the three-dimensional design method for the construction and transportation plan of the power transmission line applicable to the mountainous area is implemented as described in any one of claims 1 to 6.
8. A storage medium, characterized in that: The storage medium stores one or more programs, and the one or more programs can be executed by one or more processors to implement the three-dimensional design method for transmission line construction and transportation scheme applicable to mountainous areas as described in any one of claims 1 to 6.