Old community outdoor pipeline construction method
Through technical means such as modular pipeline processing, drone measurement, automated excavation and intelligent backfill, traditional construction methods are solved, such as time-consuming, labor-intensive, error-free, and environmentally friendly pollution, and efficient, accurate and environmentally friendly outdoor pipeline construction is achieved, ensuring construction quality and safety.
Patent Information
- Application Number
- CN202411724430.8
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-11-28
- Publication Date
- 2025-03-07
AI Technical Summary
Traditional outdoor pipeline construction methods have problems such as time-consuming and labor-intensive, many errors, lack of intelligent management, and environmental pollution, which are difficult to effectively solve the needs of outdoor pipelines in old communities.
Technical means such as modular pipeline processing and identification, drone measurement and wiring, automated pipe groove excavation, intelligent backfill and real-time monitoring and feedback are adopted to achieve an efficient, accurate and environmentally friendly construction process.
It improves construction efficiency and quality, ensures construction safety and environmental protection, realizes intelligent and informatized management of the construction process, and ensures the traceability of the source of the pipeline and the management of the entire life cycle.
Smart Images

Figure CN119572811A_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of pipeline construction, and more specifically, to a method for outdoor pipeline construction in an old residential area. Background Art
[0002] With the acceleration of urbanization, the renovation and upgrading of old communities has become an important issue in urban development. In these old communities, there are often many problems with the outdoor pipeline system, such as aging pipelines, unreasonable layout, poor drainage, etc. These problems not only affect the normal life of residents, but also pose safety hazards. Therefore, it is particularly important to renovate the outdoor pipelines in old communities.
[0003] However, the traditional outdoor pipeline construction method has many shortcomings: 1. Traditional construction methods often rely on a large number of manual operations, such as pipe cutting, assembly, laying and trenching. These processes are not only time-consuming and labor-intensive, but also prone to errors, affecting construction quality and efficiency. At the same time, traditional construction methods lack intelligent and information-based management methods and cannot monitor and control the construction process in real time, resulting in problems and hidden dangers in the construction process that are difficult to discover and deal with in a timely manner; 2. With the increasing awareness of environmental protection, environmental issues in the construction process have also received more and more attention. Traditional construction methods often generate a lot of dust, noise and waste, causing serious pollution to the surrounding environment.
[0004] In view of the above situation, the present invention provides an outdoor pipeline construction method for old residential areas. Summary of the invention
[0005] In order to overcome the above-mentioned defects of the prior art, the present invention provides an outdoor pipeline construction method for old residential areas to solve the problems raised in the above-mentioned background technology.
[0006] To achieve the above object, the present invention provides the following technical solution: a method for outdoor pipeline construction in an old residential area, specifically comprising the following steps; S1. Modular pipe processing and identification: outdoor rainwater pipes are cut into multiple modules of standard length. The length and weight of each module are moderate, and each pipe module is quickly assembled and connected through connectors and rubber sealing rings. At the same time, a unique identification code is set for each pipe module. The identification code is read by a scanning device to record the source, installation location and usage status of the pipe module; S2. UAV measurement and line laying: Use UAVs equipped with high-precision measurement equipment to conduct aerial measurements of construction sites, obtain three-dimensional model data of outdoor terrain and pipeline layout of old residential areas, and automatically lay out lines in combination with computer control systems; S3, pipe trench excavation, using an excavator to automatically excavate the pipe trench based on the path and depth measured by the drone in S2, the excavator is equipped with sensors and a control system to monitor the excavation depth and width in real time; S4, pipeline laying and inspection well construction, laying the modular pipeline processed in S1 according to the layout position, and using concrete modular inspection wells for quality inspection and testing; S5. Pipeline water-tightness test: Conduct a water-tightness test on the completed pipeline to ensure the pipeline’s tightness; S6. Backfilling: After the pipeline installation and inspection well construction are completed, the intelligent backfilling equipment is used for backfilling. The backfilling equipment can evenly place the backfilling material and ensure the density and uniformity of the backfilling material through vibration compaction; S7. Real-time monitoring and feedback. During the construction process, sensors and monitoring systems are used to monitor the construction quality and safety status in real time, and the monitoring data is transmitted to the construction management center for analysis and processing. Once an abnormal situation is found, an alarm will be issued immediately and treatment suggestions will be provided.
[0007] Preferably, in step S1, the modular pipeline adopts HDPE double-wall corrugated plastic pipe, and the length of each pipeline module is 2-5m and the weight is ≤50kg, which is convenient for manual handling and mechanical lifting during construction.
[0008] Preferably, in step S1, the unique identification code is a two-dimensional code or an RFID tag, and the scanning device is a device capable of reading a two-dimensional code or an RFID tag.
[0009] Preferably, in step S2, the measuring equipment carried by the drone includes but is not limited to high-definition cameras, lidars and infrared sensors, which are used to accurately measure the terrain and pipeline layout of the construction site and transmit the data to the construction management center in real time. The three-dimensional model data is generated based on the high-definition images and video data taken by the drone.
[0010] Preferably, in step S3, the sensors equipped on the excavator include a depth sensor, a width sensor and a tilt sensor, which are used to monitor the excavation depth and width, as well as the tilt angle of the excavator in real time to ensure excavation accuracy and safety.
[0011] Preferably, in step S6, the intelligent backfilling equipment is equipped with a vibration compaction device and a material level sensor for evenly placing the backfill material and ensuring the density and uniformity of the backfill material through vibration compaction, while monitoring the placement amount and compaction degree of the backfill material in real time.
[0012] Preferably, in step S7, the monitoring contents include soil deformation, groundwater level, pipeline displacement, construction noise and dust conditions. The monitoring data are transmitted to the construction management center in real time via a wireless network and processed and analyzed by data analysis software. Once an abnormal situation is found, an alarm is immediately issued and treatment suggestions are provided.
[0013] Preferably, it further includes S8, environmental protection construction measures, wherein the environmental protection construction measures include setting up watering and dust reduction facilities in the construction area, and regularly performing watering operations to reduce dust pollution; Classify and recycle construction waste to reduce environmental pollution; Use low-noise construction equipment to reduce the impact of construction noise on the surrounding environment.
[0014] Preferably, the environmental protection construction measures also include setting up noise monitoring equipment and dust monitoring equipment at the construction site to monitor the construction noise and dust pollution in real time, and taking corresponding control measures according to the monitoring results.
[0015] Technical effects and advantages of the present invention: 1. The present invention cuts outdoor rainwater pipes into modules of standard lengths, and uses connectors and rubber sealing rings to achieve rapid assembly and connection, significantly improving construction efficiency. At the same time, a unique identification code is set for each pipe module to facilitate tracking and management, ensuring the traceability of construction quality and pipe sources. The application of drone measurement and line laying makes the measurement and line laying work at the construction site more accurate and efficient, reducing the error and time consumption of manual measurement. The computer control system is combined to automatically lay out the line, further improving the construction accuracy and efficiency. The excavator is equipped with sensors and control systems to monitor the excavation depth and width in real time, ensuring the accuracy and safety of pipe trench excavation, and avoiding construction delays and quality problems caused by improper excavation. 2. The present invention monitors key parameters such as soil deformation, groundwater level, pipeline displacement, etc. in real time during the construction process, promptly discovers and handles potential safety hazards, ensures the life safety of construction personnel and the stability of surrounding buildings, and implements environmental protection construction measures, such as setting up water sprinkling and dust reduction facilities, classifying and recycling construction waste, and using low-noise construction equipment, which effectively reduces dust pollution, waste pollution and noise pollution during the construction process, protects the surrounding environment and the quality of life of residents, and sets up noise monitoring equipment and dust monitoring equipment to monitor construction noise and dust pollution in real time, and take corresponding control measures according to the monitoring results, which further ensures the environmental protection and compliance of the construction process; 3. The present invention utilizes sensors and monitoring systems to monitor construction quality and safety status in real time, and transmits monitoring data to the construction management center in real time for analysis and processing, thereby realizing intelligent and information management of the construction process. The application of data analysis software can deeply mine useful information and rules in monitoring data, provide scientific and accurate decision-making support for construction management personnel, and improve the scientificity and accuracy of construction management. The use of unique identification codes and scanning equipment makes the management of pipeline modules more convenient and efficient, realizing information management and tracking of the entire life cycle of pipelines, and providing strong support for subsequent maintenance and management work.
[0016] In summary, the outdoor pipeline construction method for old residential areas of the present invention has significant effects in improving construction efficiency and quality, ensuring construction safety and environmental protection, and promoting intelligent and information management. BRIEF DESCRIPTION OF THE DRAWINGS
[0017] Figure 1 It is the overall flow chart of the present invention. DETAILED DESCRIPTION
[0018] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0019] The present invention provides an outdoor pipeline construction method for an old residential area, which specifically comprises the following steps: S1. Modular pipeline processing and identification. HDPE double-wall corrugated plastic pipes are used as modular pipelines. The length of each pipeline module is 3m and the weight is controlled within 45kg, which is convenient for manual handling and mechanical lifting. The outdoor rainwater pipeline is cut into modules of standard length. Each module is quickly assembled and connected through connectors and rubber sealing rings. A unique QR code is set for each pipeline module as an identification code. The identification code is read by a handheld scanning device to record the source, installation location and usage status of the pipeline module; Specifically, in this step, HDPE double-wall corrugated plastic pipe is selected as the material of modular pipe because of its light weight, high strength, corrosion resistance, wear resistance, good flexibility, easy installation and other characteristics. This material not only meets the functional requirements of rainwater pipes, but also is easy to process into modules of standard length. The outdoor rainwater pipes are cut according to the predetermined length to form standardized pipe modules, which can simplify the construction process and improve construction efficiency. At the same time, it is convenient for the transportation, storage and assembly of pipe modules. Each pipe module is connected by a special connector and a rubber sealing ring. This connection method is not only simple and fast, but also can ensure the sealing between pipes and prevent rainwater leakage. A unique QR code is set for each pipe module as an identification code. The QR code contains relevant information of the pipe module, such as source, installation location and usage status. This identification method is convenient for management and tracking during the construction process. The QR code on the pipe module is read by a handheld scanning device, and the read information is entered into the construction management system or database, which can realize the full life cycle management of the pipe module, including procurement, transportation, installation, maintenance and replacement.
[0020] S2. UAV measurement and line laying: UAVs are equipped with high-definition cameras, laser radars and infrared sensors to conduct aerial measurements of construction sites. Based on the high-definition images and video data taken by the UAVs, three-dimensional model data of the outdoor terrain and pipeline layout of the old residential area are generated. Combined with a computer control system, line laying is automatically performed based on the three-dimensional model data to ensure line laying accuracy; Specifically, in this step, the high-definition camera is used to capture high-definition images and video data of the construction site. These data are the basis for generating a three-dimensional model. The laser radar achieves high-precision terrain and pipeline layout measurement by emitting laser beams and receiving reflected light signals. The laser radar can provide detailed terrain data and ground object models, which has great advantages for measuring complex terrain. The infrared sensor is used to detect potential heat sources or abnormal areas at the construction site, and assist in identifying pipeline layout and potential problems. Based on the high-definition images and video data taken by the drone, combined with the measurement data of the laser radar and infrared sensor, professional software and algorithms are used to generate three-dimensional model data of the outdoor terrain and pipeline layout of the old community. The three-dimensional model data can intuitively display the terrain, pipeline layout and surrounding environment of the construction site, providing an accurate basis for laying out the line. The generated three-dimensional model data is imported into the computer control system. The computer control system automatically plans the laying-out path according to the three-dimensional model data, and controls the laying-out equipment to lay out the line according to the planned path. The laying-out accuracy and efficiency are ensured through precise computer control and algorithm optimization.
[0021] S3, pipe trench excavation, according to the data measured by the drone, the excavation path and depth are mined, and the excavator equipped with depth sensors, width sensors and tilt sensors is used to automatically excavate the pipe trench. The sensors monitor the excavation depth and width, as well as the tilt angle of the excavator in real time to ensure the excavation accuracy and safety; Specifically, in this step, a drone is used to take aerial photos of the excavation area and collect terrain data. Through data analysis, the optimal path and depth of the trench are determined to ensure that the excavation of the trench meets the engineering requirements and avoids underground obstacles. The depth sensor is installed on the excavator to monitor the excavation depth in real time to ensure that the excavation depth meets the design requirements and avoids over-excavation or under-excavation. The width sensor monitors the excavation width to ensure that the width of the trench meets the requirements for laying pipelines. The tilt sensor monitors the inclination angle of the excavator to ensure that the excavator remains stable during operation and prevents safety accidents caused by excessive inclination angles. The excavator performs automated operations based on the data measured by the drone and the information monitored in real time by the sensor. The driver can clearly see the excavation depth and excavation direction through the display and control terminal in the cab, thereby controlling the operation of the excavator more accurately.
[0022] S4. Pipeline laying and inspection well construction: Lay the processed modular pipelines according to the layout position to ensure that the pipelines are tightly connected and accurately positioned. Use concrete modular inspection wells for construction and conduct quality inspections and tests to ensure the strength and sealing of the inspection wells. Specifically, in this step, the processed modular pipes are laid one by one according to the layout position to ensure the accuracy of the position of the pipes on the predetermined path. The pipes need to be tightly connected to ensure the smooth flow of the fluid in the pipes and prevent leakage. Concrete modular inspection wells are used for construction. Concrete modular inspection wells have the advantages of high strength and convenient construction, and can adapt to various complex construction environments. During the construction process, operations must be carried out in accordance with relevant specifications and standards to ensure the quality and safety of the inspection wells. Quality inspection and testing are carried out on the laid pipes and constructed inspection wells to verify whether the key performance of the pipes and inspection wells, such as strength and sealing, meet the design requirements. Quality inspection and testing usually include appearance inspection, dimension measurement, and pressure testing.
[0023] S5. Pipeline water-tightness test: Conduct a water-tightness test on the completed pipelines. Inject water into the pipelines and observe whether there is leakage to ensure the pipeline tightness. Record the test results, mark the leakage parts and repair them. Specifically, in this step, the principle of the pipeline water-tightness test is based on the Pascal principle, that is, the pressure of the liquid in a closed container on the container wall and the immersed object is proportional to the liquid depth and has nothing to do with the shape of the container. In the water-tightness test, a certain amount of water is injected into the laid pipeline and a certain hydrostatic pressure is applied. If there is a leak in the pipeline, the water at the leak will seep out due to the pressure difference, forming a visible leakage mark, or causing the water level to drop. By observing the leakage phenomenon, the sealing performance of the pipeline can be judged; Specifically, fill the test pipe section with water, and the water level should reach a certain height above the top of the upstream pipe of the test section (such as 2 meters), and soak for a period of time (such as 1-2 days) to fully check the sealing of the pipeline and the interface. After the pipeline is filled with water, start recording the test data. Start timing when the test water head reaches the specified water head, observe the water seepage in the pipeline, and the water seepage observation time must not be less than the specified time (such as 30 minutes). During this period, water should be continuously added to the test pipeline to keep the test water head constant. The seepage amount is calculated according to the drop value of the water level in the well, and compared with the specified allowable seepage amount. When the measured seepage amount is less than or equal to the allowable seepage amount, the test is qualified; otherwise, the test is unqualified.
[0024] S6. Backfilling: Use intelligent backfilling equipment equipped with a vibration compaction device and a material level sensor to evenly place the backfill material, and ensure the density and uniformity of the backfill material through vibration compaction. Monitor the amount of backfill material placed and the degree of compaction in real time to ensure the quality of backfilling; Specifically, in this step, the backfilling equipment integrates a vibration compaction device and a material level sensor, which can achieve uniform delivery and compaction of the backfill material. The material level sensor is used to monitor the delivery amount of the backfill material in real time to ensure that the supply of the backfill material is sufficient and not excessive. The vibration compaction device generates high-frequency vibrations to cause relative displacement and rearrangement between the backfill material particles. Under the action of the vibration force, the gaps between the backfill material particles are gradually reduced, thereby achieving a compaction effect. The intelligent backfilling equipment monitors the delivery amount of the backfill material in real time through the material level sensor to ensure the continuity and stability of the backfilling operation. At the same time, the equipment also monitors the degree of compaction in real time through the control system of the vibration compaction device to ensure that the density and uniformity of the backfill material meet the design requirements.
[0025] S7. Real-time monitoring and feedback, including soil deformation, groundwater level, pipeline displacement, construction noise and dust. Sensors and monitoring systems are used to monitor construction quality and safety status in real time. Monitoring data is transmitted to the construction management center in real time via wireless networks and processed and analyzed by data analysis software. Once an abnormal situation is found, an alarm is immediately issued and treatment suggestions are provided; Specifically, in this structure, a variety of sensors are arranged at the construction site, such as soil deformation sensors, groundwater level sensors, pipeline displacement sensors, noise monitoring sensors and dust monitoring sensors. These sensors can monitor the key parameters of soil deformation, groundwater level changes, pipeline displacement, construction noise and dust concentration at the construction site in real time. The monitoring data is transmitted to the construction management center in real time through wireless networks (such as 4G / 5G, Wi-Fi, etc.). The monitoring data received by the construction management center is processed and analyzed by data analysis software. The data analysis software can use various algorithms and models to deeply mine and interpret the data, and extract useful information and rules. The data analysis software can set thresholds and early warning conditions, and perform real-time monitoring and anomaly detection of monitoring data. Once an abnormal situation is found, such as excessive soil deformation, abnormal increase in groundwater level, pipeline displacement out of range, construction noise or dust exceeding the standard, the data analysis software will immediately issue an alarm and provide corresponding processing suggestions.
[0026] S8. Environmental protection construction measures: install watering and dust reduction facilities in the construction area, carry out watering operations regularly to reduce dust pollution, classify and recycle construction waste to reduce waste pollution to the environment, use low-noise construction equipment to reduce the impact of construction noise on the surrounding environment, install noise monitoring equipment and dust monitoring equipment at the construction site to monitor construction noise and dust pollution in real time, and take corresponding control measures based on the monitoring results; Specifically, in this step, watering and dust reduction facilities are set up in the construction area. Through regular watering operations, the air humidity is increased, and the suspended particles in the air are moistened and settled, thereby reducing dust pollution. Construction waste is classified to distinguish between recyclables, hazardous waste, wet waste and dry waste. Recyclables are recycled, such as scrap steel, waste wood, and waste paper. Hazardous waste is specially treated to prevent it from polluting the environment. Wet and dry waste are properly handled to reduce their negative impact on the environment. Low-noise construction equipment is used, such as excavators and loaders with less noise, and the equipment is cleaned and emptied. Noise reduction devices such as silencers and shock absorbers are installed to reduce the generation and spread of construction noise. Noise monitoring equipment and dust monitoring equipment are set up at the construction site to monitor construction noise and dust pollution in real time. The noise monitoring equipment calculates the noise level by measuring the propagation speed and amplitude of sound waves in the air. The dust monitoring equipment measures the scattered light intensity of particulate matter in the air to calculate the dust concentration. According to the noise and dust monitoring results, corresponding control measures are taken. For example, when the noise or dust exceeds the standard, the construction equipment is adjusted in time, the frequency of watering is increased, and waste management is strengthened to reduce noise and dust pollution.
[0027] The above description is only a preferred embodiment of the present invention and is not intended to limit the present invention. Any modifications, equivalent substitutions, improvements, etc. made within the spirit and principle of the present invention should be included in the protection scope of the present invention.
Claims
1. A method for outdoor pipeline construction in old residential areas, characterized by: The specific steps include: S1. Modular pipe processing and identification: outdoor rainwater pipes are cut into multiple modules of standard length. The length and weight of each module are moderate, and each pipe module is quickly assembled and connected through connectors and rubber sealing rings. At the same time, a unique identification code is set for each pipe module. The identification code is read by a scanning device to record the source, installation location and usage status of the pipe module; S2. UAV measurement and line laying: Use UAVs equipped with high-precision measurement equipment to conduct aerial measurements of construction sites, obtain three-dimensional model data of outdoor terrain and pipeline layout of old residential areas, and automatically lay out lines in combination with computer control systems; S3, pipe trench excavation, using an excavator to automatically excavate the pipe trench based on the path and depth measured by the drone in S2, the excavator is equipped with sensors and a control system to monitor the excavation depth and width in real time; S4, pipeline laying and inspection well construction, laying the modular pipeline processed in S1 according to the layout position, and using concrete modular inspection wells for quality inspection and testing; S5. Pipeline water-tightness test: Conduct a water-tightness test on the completed pipeline to ensure the pipeline’s tightness; S6. Backfilling: After the pipeline installation and inspection well construction are completed, the intelligent backfilling equipment is used for backfilling. The backfilling equipment can evenly place the backfilling material and ensure the density and uniformity of the backfilling material through vibration compaction; S7. Real-time monitoring and feedback. During the construction process, sensors and monitoring systems are used to monitor the construction quality and safety status in real time, and the monitoring data is transmitted to the construction management center for analysis and processing. Once an abnormal situation is found, an alarm will be issued immediately and treatment suggestions will be provided.
2. The outdoor pipeline construction method for old residential areas according to claim 1 is characterized in that: In step S1, the modular pipeline adopts HDPE double-wall corrugated plastic pipe, and the length of each pipeline module is 2-5m and the weight is ≤50kg, which is convenient for manual handling and mechanical lifting during construction.
3. The outdoor pipeline construction method for old residential areas according to claim 1 is characterized in that: In step S1, the unique identification code is a two-dimensional code or an RFID tag, and the scanning device is a device capable of reading a two-dimensional code or an RFID tag.
4. The outdoor pipeline construction method for old residential areas according to claim 1 is characterized in that: In step S2, the measurement equipment carried by the drone includes but is not limited to high-definition cameras, lidars and infrared sensors, which are used to accurately measure the terrain and pipeline layout of the construction site and transmit the data to the construction management center in real time. The three-dimensional model data is generated based on the high-definition images and video data taken by the drone.
5. The outdoor pipeline construction method for old residential areas according to claim 1 is characterized by: In step S3, the excavator is equipped with sensors including depth sensors, width sensors and tilt sensors, which are used to monitor the excavation depth and width, as well as the tilt angle of the excavator in real time to ensure excavation accuracy and safety.
6. The outdoor pipeline construction method for old residential areas according to claim 1 is characterized by: In step S6, the intelligent backfilling equipment is equipped with a vibration compaction device and a material level sensor to evenly place the backfill material and ensure the density and uniformity of the backfill material through vibration compaction, while monitoring the amount of backfill material placed and the degree of compaction in real time.
7. The outdoor pipeline construction method for old residential areas according to claim 1 is characterized by: In step S7, the monitoring contents include soil deformation, groundwater level, pipeline displacement, construction noise and dust. The monitoring data is transmitted to the construction management center in real time via the wireless network, and processed and analyzed by data analysis software. Once an abnormal situation is found, an alarm will be issued immediately and treatment suggestions will be provided.
8. The outdoor pipeline construction method for old residential areas according to claim 1 is characterized by: It also includes S8, environmental protection construction measures, which include setting up watering and dust reduction facilities in the construction area, and regularly performing watering operations to reduce dust pollution; Classify and recycle construction waste to reduce environmental pollution; Use low-noise construction equipment to reduce the impact of construction noise on the surrounding environment.
9. The outdoor pipeline construction method for old residential areas according to claim 8 is characterized by: The environmental protection construction measures also include setting up noise monitoring equipment and dust monitoring equipment at the construction site to monitor the construction noise and dust pollution in real time, and taking corresponding control measures based on the monitoring results.