Hoisting device attached to cantilever beam
By designing a lifting device attached to the cantilever beam and using the cantilever beam as a track for lifting operation, the problem of reducing the frequency of tower cranes after the construction of the main structure of the building is solved, and the effect of saving costs and improving cost-effectiveness is achieved.
Patent Information
- Application Number
- CN202411987789.4
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-12-31
- Publication Date
- 2025-03-18
AI Technical Summary
In construction sites, the frequency of tower crane usage is significantly reduced after the construction of the main structure of the building is completed, resulting in a long spare time of tower cranes and high costs.
A lifting device attached to a cantilever beam is designed, which includes an elongated substrate, a hoist, a left upright plate and a right upright plate, driven by a gear and a roller system, and the cantilever beam is used as a track for lifting operations.
After the tower crane is removed, the device can be lifted with cantilever beams to remove the tower crane in advance, saving costs and improving cost-effectiveness.
Smart Images

Figure CN119637731A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to a hoisting device attached to a cantilever beam. Background Art
[0002] Tower crane is the most commonly used lifting equipment on construction sites. It is also called "tower crane". It is connected in sections (referred to as "standard sections") to lift construction materials such as steel bars, wooden slats, concrete, and steel pipes. Tower crane is an indispensable equipment on construction sites. Tower crane is generally fixed and loaded by cantilever beams (I-beams) installed on the building body. For the structure, please refer to Chinese patent CN201710364714.4.
[0003] In construction sites, after the main structure of the building is completed, the frequency of tower crane use will be significantly reduced. Moreover, after the main structure is completed, wall masonry, exterior wall painting, external insulation construction and other operations are required before the external frame can be dismantled. The tower crane will be idle for about 4 months. During this period, each tower crane will incur a lot of expenses, and the cost performance is not high. Summary of the invention
[0004] The technical problem to be solved by the present invention is to provide a hoisting device attached to a cantilever beam, which can replace a tower crane for hoisting operations after the construction of the main structure of a building is completed, and the tower crane can be dismantled in advance to save costs.
[0005] In order to solve the above technical problems, the present invention provides a hoisting device attached to a cantilever beam;
[0006] It comprises a long strip base plate arranged horizontally and with a length direction running forward and backward, a winch arranged horizontally and with an axis direction running forward and backward is provided on the lower side of the base plate, and a left vertical plate and a right vertical plate arranged symmetrically on the left and right sides and with a length direction running forward and backward are provided on the upper side of the base plate;
[0007] The left vertical plate is provided with two first gears arranged at intervals in front and back on the right side, the two first gears are connected to the left vertical plate through the first wheel axle, and the axial directions of the two first wheel axles are both left and right. A second gear arranged at intervals in front and back is provided on the right side of the left vertical plate corresponding to the position between the two first gears, the two second gears are connected to the left vertical plate through the second wheel axle, and the axial directions of the two second wheel axles are both left and right. The second gear located at the front side is meshed with the first gear located at the front side, and the second gear located at the rear side is meshed with the first gear located at the rear side. A driving motor is provided on the left side surface of the left vertical plate corresponding to the position between the two second gears, the output shaft of the driving motor extends horizontally to the right, the right end of the output shaft of the driving motor passes through the left vertical plate and is coaxially installed with a third gear, the third gear is located between the front and rear of the two second gears and is meshed with the two second gears at the same time, and a first roller coaxially connected to the corresponding first gear is provided on the right side of the two first gears;
[0008] A second roller matching the first roller is provided on the left side of the right vertical plate and opposite to each first roller, each second roller is connected to the right vertical plate through a third wheel shaft, the axis direction of the third wheel shaft is left-right, and a gap is left-right between the first roller and the second roller opposite to each other in the left-right direction;
[0009] A power source and a controller are arranged on the left side surface of the left vertical plate or the right side surface of the right vertical plate, and the hoist and the driving motor are connected to the power source through the controller.
[0010] For the purpose of simple explanation, the hoisting device attached to the cantilever beam described in the present invention is referred to as the device below.
[0011] The use method and advantages of this device: After the tower crane is dismantled, the cantilever beam (I-beam) used to connect the tower crane still extends to the facade of the building. The web of the I-beam is vertical, and the two wing plates of the I-beam are respectively located at the upper and lower ends of the web. When the device is installed, the left plate and the right plate are respectively clamped on the left and right sides of the web, so that the two first rollers and the two second rollers are both placed on the wing plates on the lower side of the I-beam. The controller can be wirelessly remote controlled or wire controlled. At this time, the controller controls the forward and reverse rotation of the drive motor to control the device to move forward and backward along the length direction of the I-beam, connect the building materials to the winch rope, and control the winch to reel in and unreel through the controller to complete the lifting of the building materials. This device uses the cantilever beam (I-beam) remaining after the tower crane is dismantled as a track instead of the tower crane for lifting operations, so that the tower crane can be dismantled in advance to save costs. BRIEF DESCRIPTION OF THE DRAWINGS
[0012] Figure 1 This is the front view of the device.
[0013] Figure 2 It is a left side view of the device.
[0014] Figure 3 It is a right view of the left vertical plate in this device.
[0015] Figure 4 It is a left view of the right vertical plate in this device. DETAILED DESCRIPTION
[0016] See also Figure 1-Figure 4 , a lifting device attached to a cantilever beam;
[0017] It comprises a long strip base plate 1 which is horizontally arranged and has a longitudinal direction running forward and backward, a hoist 2 which is horizontally arranged and has an axial direction running forward and backward is provided on the lower side of the base plate 1 (the rope on the hoist 2 is not shown), and a left vertical plate 3 and a right vertical plate 4 which are symmetrically arranged on the left and right and have a longitudinal direction running forward and backward are provided on the upper side of the base plate 1;
[0018] The right side of the left vertical plate 3 is provided with two first gears 31 arranged at intervals in front and back, and the two first gears 31 are connected to the left vertical plate 3 through a first wheel shaft 311, and the axis directions of the two first wheel shafts 311 are both left-right. A second gear 32 arranged at intervals in front and back is provided between the two first gears 31 on the right side of the left vertical plate 3, and the two second gears 32 are connected to the left vertical plate 3 through a second wheel shaft 321, and the axis directions of the two second wheel shafts 321 are both left-right. The second gear 32 located at the front side is meshed with the first gear 31 located at the front side. The second gear 32 located at the rear side is meshed with the first gear 31 located at the rear side. A driving motor 34 is provided between the two second gears 32 on the left side of the left vertical plate 3. The output shaft 341 of the driving motor 34 extends horizontally to the right. The right end of the output shaft 341 of the driving motor 34 passes through the left vertical plate 3 and is coaxially mounted with a third gear 33. The third gear 33 is located between the front and rear of the two second gears 32 and is meshed with the two second gears 32 at the same time. The right sides of the two first gears 31 are provided with first rollers 312 coaxially connected to the corresponding first gears 31.
[0019] A second roller 41 matching the first roller 312 is provided on the left side of the right vertical plate 4 and opposite to each first roller 312. Each second roller 41 is connected to the right vertical plate 4 through a third wheel shaft 2. The axis direction of the third wheel shaft 2 is left-right. A gap is left-right between the first roller 312 and the second roller 41 opposite to each other in the left-right direction.
[0020] A power supply and a controller are provided on the left side of the left vertical plate 3 or the right side of the right vertical plate 4 (the power supply, the controller and the related wiring harness are all existing mature technologies, and for the sake of simple explanation, they are not described in this embodiment and are also omitted in the drawings), and the winch 2 and the drive motor 34 are both connected to the power supply through the controller.
[0021] The use method and advantages of this device: After the tower crane is dismantled, the cantilever beam (I-beam) used to connect the tower crane still extends to the facade of the building, the web 5 of the I-beam is vertical, and the two wing plates 6 of the I-beam are respectively located at the upper and lower ends of the web. When the device is installed, the left side plate and the right side plate are respectively clamped on the left and right sides of the web, so that the two first rollers 312 and the two second rollers 41 are both placed on the wing plates 6 on the lower side of the I-beam. The controller can be wirelessly remote controlled or wire controlled. At this time, the controller controls the forward and reverse rotation of the driving motor 34 to control the device to move forward and backward along the length direction of the I-beam, connect the building materials to the rope of the winch 2, and control the winch 2 to reel in and unreel through the controller, so that the hoisting of the building materials can be completed. This device uses the cantilever beam (I-beam) remaining after the tower crane is dismantled as a track instead of the tower crane for lifting operations, so that the tower crane can be dismantled in advance and costs can be saved.
Claims
1. A hoisting device attached to a cantilever beam, characterized in that: It comprises a long strip base plate arranged horizontally and with a length direction running forward and backward, a winch arranged horizontally and with an axis direction running forward and backward is provided on the lower side of the base plate, and a left vertical plate and a right vertical plate arranged symmetrically on the left and right sides and with a length direction running forward and backward are provided on the upper side of the base plate; The left vertical plate is provided with two first gears arranged at intervals in front and back on the right side, the two first gears are connected to the left vertical plate through the first wheel axle, and the axial directions of the two first wheel axles are both left and right. A second gear arranged at intervals in front and back is provided on the right side of the left vertical plate corresponding to the position between the two first gears, the two second gears are connected to the left vertical plate through the second wheel axle, and the axial directions of the two second wheel axles are both left and right. The second gear located at the front side is meshed with the first gear located at the front side, and the second gear located at the rear side is meshed with the first gear located at the rear side. A driving motor is provided on the left side surface of the left vertical plate corresponding to the position between the two second gears, the output shaft of the driving motor extends horizontally to the right, the right end of the output shaft of the driving motor passes through the left vertical plate and is coaxially installed with a third gear, the third gear is located between the front and rear of the two second gears and is meshed with the two second gears at the same time, and a first roller coaxially connected to the corresponding first gear is provided on the right side of the two first gears; A second roller matching the first roller is provided on the left side of the right vertical plate and opposite to each first roller, each second roller is connected to the right vertical plate through a third wheel shaft, the axis direction of the third wheel shaft is left-right, and a gap is left-right between the first roller and the second roller opposite to each other in the left-right direction; A power source and a controller are arranged on the left side surface of the left vertical plate or the right side surface of the right vertical plate, and the hoist and the driving motor are connected to the power source through the controller.
Citation Information