Suction barrel temporary pile shoe for deep and far sea wind power and wind power operation construction method of suction barrel temporary pile shoe
By designing temporary pile boots for suction cylinders for deep ocean wind power, the pump skid body drives the suction cylinder to sink or float, the problems of high requirements for ship staying equipment and low construction efficiency of the deep ocean offshore wind power construction platform are solved, and efficient and high-quality wind power construction is achieved.
Patent Information
- Application Number
- CN202510123297.9
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2025-01-26
- Publication Date
- 2025-03-18
AI Technical Summary
In the construction of offshore wind power in the deep sea, the stationing of the wind power construction platform ship faces the problems of high equipment requirements and low construction efficiency, especially when the pile legs are deep into the mud, high power and high torque lifting systems are required, resulting in increased costs and low construction efficiency.
A temporary pile boot for suction cylinder for deep-sea wind power is designed, including a top platform and a suction cylinder group. The suction cylinder is driven to sink or float through a pump pry body to achieve standing and displacement, avoiding high requirements for the platform ship lifting system, and reducing the time for punching piles and adjusting ballast water.
This technology improves the efficiency and quality of offshore wind power construction, reduces the construction cost of platform ships, simplifies the construction process, and reduces the requirements for platform ship lifting system.
Smart Images

Figure CN119640788A_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of deep sea wind power construction equipment, and in particular to a temporary pile shoe of a suction tube for deep sea wind power and a wind power operation construction method thereof. Background Art
[0002] In the construction of offshore wind power in the deep sea, the positioning of the ship during the lifting operation of the wind power construction platform ship faces many challenges: 1) High requirements for equipment: The water depth of the deep sea wind turbine lifting operation exceeds 70 meters. When the platform ship is stationed, the pile legs are deeply buried in the mud. The platform ship's pile insertion and extraction has high requirements for the platform ship's lifting system. The lifting system needs to have a large power and torque to achieve pile insertion and extraction, which increases the cost of ship construction; 2) Low construction efficiency: When the platform ship's pile legs are deeply buried in the mud, it is necessary to cooperate with the pile punching system to insert and extract piles. The pile punching system needs to flush the silt around the pile legs to reduce friction, but the long pile punching time leads to low construction efficiency. At the same time, the insertion and extraction requires the platform ship to adjust the ballast water to meet the mud entry requirements, and the time required to adjust the ballast water is also long. Therefore, based on the above-mentioned existing technical problems, it is necessary to design a temporary pile shoe structure for suction cylinders for deep sea. Summary of the invention
[0003] The object of the present invention is to provide a temporary pile shoe for suction tubes used in deep sea wind power that solves the above-mentioned technical problems.
[0004] Another object of the present invention is to provide a wind power construction method using a working vessel using the temporary pile shoe of the suction tube for deep sea wind power.
[0005] To this end, the technical solution of the present invention is as follows:
[0006] A temporary pile shoe for suction cylinders used for deep-sea wind power generation, comprising a top platform and a suction cylinder group arranged in sequence from top to bottom; wherein the top platform is a platform body with a groove provided in the center, and four lifting ears are evenly arranged on the top along the circumferential direction; a gravel layer is laid in the groove of the top platform; the suction cylinder group comprises N suction cylinders, which are evenly arranged along the circumferential direction and fixed to the bottom of the top platform; the delivery pipes on the tops of the N suction cylinders respectively pass through pipeline through-holes opened on the bottom surface of the top platform, and each delivery pipe end is connected to an extension pipe, and the other end of the extension pipe protrudes above the gravel layer; N pump skids are also movably arranged on the gravel layer of the top platform, which respectively cooperate with the four suction cylinders in the suction cylinder group to drive the four suction cylinders to sink to a stationary state, or float to a movable state.
[0007] Furthermore, in the above-mentioned temporary pile shoe structure of the suction tube used in the deep sea, N is a positive integer, and N≥3; in practical applications, the value of N is specifically adjusted according to the size of the top platform.
[0008] Furthermore, the depth of the groove at the center of the top platform is 4m to 5m.
[0009] Furthermore, the top platform includes a horizontally arranged platform plate, on the top surface of which two first vertical plates are vertically fixed at a group of opposite edges, and on the top surface of which two second vertical plates are vertically fixed at another group of opposite edges, and adjacent first and second vertical plates are vertically connected and fixed; two horizontal plates are symmetrically fixed on both sides of the top surfaces of the two first vertical plates, and the two horizontal plates are simultaneously connected and fixed to the top side edges of the two second vertical plates, so that a top surface platform that can be used to install four lifting ears is provided on the top of the four vertical plates.
[0010] Furthermore, an inverted trapezoidal notch is centrally opened on the top sides of the two first vertical plates, and the width of the inverted trapezoidal notch is adapted to the width of the barge, so that an embedding groove is formed on the top side of the top platform.
[0011] Furthermore, the thickness of the debris accumulation layer is 2.5m to 3.5m, and it is formed by the accumulation of crushed stones or flexible debris with a diameter of 10mm to 50mm; the flexible debris can be but is not limited to rubber blocks, water-resistant wood blocks, etc.
[0012] Furthermore, each pump skid comprises a submersible pump, an air compressor and a generator arranged in a box; wherein the generator is electrically connected to the submersible pump and the air compressor respectively.
[0013] Furthermore, the pump skid also includes a PLC controller; the water inlet end of the submersible pump is connected to the other end of the extension pipe through the first delivery pipe, and the water inlet end of the submersible pump is also connected to the sea through the second delivery pipe; the water outlet end of the submersible pump is connected to the other end of the extension pipe through the third delivery pipe, and the water outlet end of the submersible pump is also connected to the sea through the fourth delivery pipe; the air outlet end of the air compressor is connected to the other end of the extension pipe through the fifth delivery pipe; the first delivery pipe is provided with a first electrically-controlled valve, the second delivery pipe is provided with a second electrically-controlled valve, the third delivery pipe is provided with a third electrically-controlled valve, the fourth delivery pipe is provided with a fourth electrically-controlled valve, and the fifth delivery pipe is provided with a fifth electrically-controlled valve; each electrically-controlled valve is electrically connected to the PLC controller respectively.
[0014] Furthermore, two lifting ears are symmetrically arranged on the outer side of the box body of each pump skid.
[0015] Furthermore, a barge wind power construction method using the above-mentioned suction tube temporary pile shoe for deep sea wind power is implemented, and the steps are as follows:
[0016] S1. According to the requirement of configuring two temporary pile shoes of suction cylinders at both ends of the bottom side of the platform ship, the transport ship transports four temporary pile shoes of suction cylinders and their connecting beams to the designated machine position, and hoists the four temporary piles of suction cylinders to the designated sinking point by the crane ship to adapt to the stationing position of the platform ship;
[0017] S2. Two connection beams spaced apart along the width direction of the platform ship 10 are hingedly connected between the two temporary pile shoes of the suction cylinder at the same end of the corresponding platform ship, and two connection beams spaced apart along the length direction of the platform ship are hingedly connected between the two temporary pile shoes of the suction cylinder at the same side of the corresponding platform ship; the transport ship and the crane ship leave the site;
[0018] S3. The four temporary pile shoes of the suction cylinders use the pump skids on them to drive the suction cylinder group to sink to the specified depth, and then recover the pump skids to the ship;
[0019] S4. The platform ship enters the site and sails to the top of the temporary pile shoes of the four suction cylinders. Through its own positioning system, it lowers the four pile legs and inserts them into the gravel layers of the temporary pile shoes of the four suction cylinders respectively. After the platform ship is stable, the wind power operation at the position can be carried out;
[0020] S5. After the platform ship completes the operation task at the position, it transports the pump skid to the top surface platform of the temporary pile shoes of each suction cylinder, so as to use multiple pump skids to float the suction cylinder group to a movable state;
[0021] S6. A total of eight winches are arranged on both sides of the platform ship, corresponding to the positions of the four temporary pile shoes of the suction cylinders. The eight winches lower steel wire ropes and are respectively connected to the two lifting ears on the temporary pile shoes of the four suction cylinders located on one side of the ship's side, so that the platform ship and the four temporary pile shoes of the suction cylinders are connected as one; the platform ship is used to synchronously drive the four temporary pile shoes of the suction cylinders to move to the next construction position, and the connection between the eight winches and the lifting ears on the temporary pile shoes of the four suction cylinders is released;
[0022] S7, repeating the above steps S3 to S6, the platform ship completes the wind power installation work at all construction positions by repeatedly stationing and shifting;
[0023] S8. After completing the wind power installation work at the last construction site, the platform ship leaves the site and removes the connecting beams between the temporary pile shoes of the suction cylinders; the transport ship and the crane ship enter the site, and the crane ship lifts the four temporary pile shoes of the suction cylinders onto the transport ship for transportation back to the dock.
[0024] Furthermore, a platform wind power construction method using the above-mentioned suction tube temporary pile shoe for deep sea wind power is implemented, and the steps are as follows:
[0025] S1. According to the requirement of configuring two temporary pile shoes of suction cylinders at both ends of the bottom side of the platform ship, the transport ship transports four temporary pile shoes of suction cylinders and their connecting beams to the designated machine position, and hoists the four temporary piles of suction cylinders to the designated sinking point by the crane ship to adapt to the stationing position of the platform ship;
[0026] S2. Two connection beams spaced apart along the width direction of the platform ship 10 are hingedly connected between the two temporary pile shoes of the suction cylinder at the same end of the corresponding platform ship, and two connection beams spaced apart along the length direction of the platform ship are hingedly connected between the two temporary pile shoes of the suction cylinder at the same side of the corresponding platform ship; the transport ship and the crane ship leave the site;
[0027] S3. The four temporary pile shoes of the suction cylinders use the pump skids on them to drive the suction cylinder group to sink to the specified depth, and then recover the pump skids to the ship;
[0028] S4, the platform ship enters the site and sails to the top of the four temporary pile shoes 8 of the suction cylinders, and lowers the four pile legs through its own positioning system to be inserted into the gravel layers of the temporary pile shoes of the four suction cylinders respectively; after the platform ship is stable, the wind power operation at the position can be carried out;
[0029] S5. After the platform ship completes the operation task at the position, it leaves the site. The barge enters the site and sails to the top of the two temporary pile shoes of the suction cylinders on either side of the platform ship. Then, divers or underwater robots are used to transport the pump skid to the top surface platform of each temporary pile shoe of the suction cylinder, so that the suction cylinder group is floated to a movable state by using multiple pump skids, and the bottom of the barge is embedded in the embedding groove set on the top platform of the two temporary pile shoes of the suction cylinders.
[0030] S6. The hooks of the eight mast cranes on the barge are lowered with lifting ropes, so that each mast crane hook is connected to the eight lifting ears on the two temporary pile shoes of the suction cylinders through the wire rope, so as to connect the barge and the two temporary pile shoes of the suction cylinders as a whole; the four temporary pile shoes of the suction cylinders are shifted to the next construction position in two times by driving the two temporary pile shoes of the suction cylinders to shift each time by the barge;
[0031] S7, repeating the above steps S3 to S6, with the cooperation of the barge, the platform ship completes the wind power installation work at all construction positions by repeatedly stationing and shifting;
[0032] S8. After completing the wind power installation work at the last construction site, the platform ship leaves the site and removes the connecting beams between the temporary pile shoes of the suction cylinders; the transport ship and the crane ship enter the site, and the crane ship lifts the four temporary pile shoes of the suction cylinders onto the transport ship for transportation back to the dock.
[0033] Compared with the existing technology, the temporary pile shoe of the suction cylinder for deep-sea wind power has a simple structure, reasonable design, and convenient use. It meets the positioning needs of the platform ship and can be selectively moved to the designated position with the operating ship to achieve repeated positioning. Compared with the existing wind power construction platform ship positioning operation, the temporary pile shoe of the suction cylinder for deep-sea wind power is used to achieve positioning operation. There is no need to insert the pile legs of the platform ship into the mud, which not only reduces the requirements for the platform ship lifting system, but also avoids the problem of low construction efficiency caused by pile punching and adjusting ballast water, effectively improving the efficiency and quality of offshore wind power construction. BRIEF DESCRIPTION OF THE DRAWINGS
[0034] Figure 1 It is a top view of a temporary pile shoe of a suction tube used for deep sea wind power in an embodiment of the present invention;
[0035] Figure 2 It is a side view of a temporary pile shoe of a suction tube used for deep sea wind power in an embodiment of the present invention;
[0036] Figure 3 It is a schematic structural diagram of a top platform of a temporary pile shoe of a suction tube used for deep sea wind power in an embodiment of the present invention;
[0037] Figure 4 It is a front view of a barge stationed by using a temporary pile shoe of a suction tube for deep sea wind power in an embodiment of the present invention;
[0038] Figure 5 A top view of a barge stationed using a temporary pile shoe of a suction tube for deep sea wind power in an embodiment of the present invention;
[0039] Figure 6 It is a front view of a platform vessel stationed using a temporary pile shoe of a suction tube for deep sea wind power in an embodiment of the present invention;
[0040] Figure 7 This is a top view of a platform vessel being positioned using temporary pile shoes of suction tubes for deep sea wind power in an embodiment of the present invention. DETAILED DESCRIPTION
[0041] The present invention will be further described below in conjunction with the accompanying drawings and specific embodiments, but the following embodiments are by no means intended to limit the present invention in any way.
[0042] Example 1
[0043] See also Figure 1 and Figure 2 The temporary pile shoe of the suction tube for deep-sea wind power generation comprises a top platform 1 and a suction tube group 2 which are arranged in sequence from top to bottom.
[0044] The top platform 1 is a platform with a groove in the center. The depth of the groove is 5m, and the diameter of the groove is larger than the outer diameter of the pile leg 6, so that the pile leg 6 can be matched with the groove to realize the positioning and plug-in connection between the structure and the pile leg 6 at the bottom of the platform ship; four lifting ears 105 are evenly distributed along the circumference on the top of the top platform 1; wherein the lifting ears 105 are made of high-strength alloy steel, with good strength and toughness to withstand huge tensile force; in actual offshore wind farm operations, the top platform 1 forms a reliable connection with the crane on the operating ship through the lifting ears 105, so that the temporary pile shoe of the suction cylinder that will be in a floating state can be moved to the next machine position with the operating ship.
[0045] In this embodiment, see Figure 3 The top platform 1 includes a horizontally arranged square platform plate 101, two first vertical plates 102 are vertically fixed at a group of opposite edges on the top surface, and two second vertical plates 103 are vertically fixed at another group of opposite edges on the top surface. The adjacent first vertical plates 102 and second vertical plates 103 are vertically connected and fixed, so that the top platform 1 forms a structure with a groove; the first vertical plates 102 and the second vertical plates 103 are both made of the same rectangular plate, and two horizontal plates 104 are symmetrically fixed on both sides of the top surfaces of the two first vertical plates 102, and the two horizontal plates 104 are simultaneously connected and fixed to the top side edges of the two second vertical plates 103, so that a top surface platform that can be used to install four lifting ears 105 is provided on the top of the four vertical plates, and at the same time has the function of strengthening the structural strength of the top platform 1; the top platform 1 is a steel frame structure as a whole, and meets the load-bearing and force requirements when the auxiliary operation ship is stationed.
[0046] As a preferred technical solution of this embodiment, since the barge does not have pile legs 6, in order to achieve the positioning connection between the structure and the barge, the top sides of the two first vertical plates 102 are respectively centrally provided with inverted trapezoidal notches 1021, and the width of the inverted trapezoidal notches 1021 is adapted to the width of the barge, so that an embedding groove is formed on the top side of the top platform 1; when the temporary pile shoe of the suction cylinder is used in conjunction with the barge, the bottom of the barge can be embedded and matched with the top platform 1.
[0047] A gravel layer 3 is laid in the groove of the top platform 1; wherein, the gravel layer 3 has a thickness of 3m and is formed by the accumulation of gravel with a diameter of 10mm to 50mm; the gravel layer 3 is used to insert the pile legs 6 at the bottom of the hull to stabilize the connection stability between the pile legs 6 and the top platform 1, and also has a buffering effect to achieve the purpose of dispersing the load transmitted by the superstructure, reducing local stress concentration, and reducing the impact force generated when the pile legs 6 are docked with the temporary pile shoes of the suction tube.
[0048] The suction cylinder group 2 includes four suction cylinders 201, which are evenly distributed along the circumference and fixed at the bottom of the top platform 1; the four regularly distributed suction cylinders 201 can ensure that the entire structure is evenly stressed; every two adjacent suction cylinders 201 are welded and fixedly connected by a connecting plate 202 to form a stable whole.
[0049] Four pipeline penetration openings are evenly distributed along the circumferential direction on the bottom surface of the top platform 1, so that the conveying pipes on the top of the four suction cylinders 201 pass through the four pipeline penetration openings respectively; an extension pipe 5 is connected to the end of each conveying pipe, and the length of the extension pipe 5 is 3.5m, so that after the top platform 1 is filled with the gravel layer 3, the other end of the extension pipe 5 can protrude above the gravel layer 3.
[0050] Four pump skids 4 are also arranged on the gravel layer 3 of the top platform 1, which respectively cooperate with the four suction cylinders 201 in the suction cylinder group 2 to drive the four suction cylinders 201 to sink to a stationary state or float to a movable state; the four pump skids 4 are movably arranged on the gravel layer 3 to facilitate removal when connected to the hull.
[0051] Each pump skid 4 includes a submersible pump, an air compressor and a small generator arranged in a box; wherein the small generator is electrically connected to the submersible pump and the air compressor respectively for power supply; during actual operation, the extension pipe 5 is connected to the corresponding port of the submersible pump or the air compressor according to the operation requirements.
[0052] The actual working principle of the above-mentioned pump skid 4 is as follows: when the suction cylinder 201 needs to drive the top platform 1 to sink and insert into the mud surface, the extension pipe 5 is directly connected to the atmosphere, and the suction cylinder 201 first relies on its own weight to drive the top platform 1 to gradually sink to the seabed until it is in a stable state; then the water inlet end of the submersible pump is connected to the extension pipe 5, and the water outlet end of the submersible pump enters the sea through the pipeline, and the submersible pump is started. The submersible pump draws the water in the suction cylinder 201 and discharges it into the sea, so that the suction cylinder 201 continues to sink under the action of negative pressure until it sinks to the specified depth position; at this time, the temporary pile shoe of the suction cylinder is stationed; when the suction cylinder When 201 needs to drive the top platform 1 to float up for displacement, the extension pipe 5 is connected to the water outlet end of the submersible pump, the water inlet end of the submersible pump enters the sea through the pipeline, the submersible pump is started, and the submersible pump injects seawater into the suction cylinder 201, so that the suction cylinder 201 drives the top platform 1 to float up to a certain height; then, the extension pipe 5 is connected to the air outlet end of the air compressor, and the air compressor is started, and the air compressor is used to inject air into the suction cylinder 201, so that the suction cylinder 201 continues to drive the top platform 1 to continue to float up and emerge from the water surface; at this time, the temporary pile shoe of the suction cylinder is in a floating state, so that it can be moved synchronously with the passing working ship or disassembled.
[0053] As a preferred technical solution of this embodiment, the pump skid 4 also includes a PLC controller; the water inlet end of the submersible pump is connected to the other end of the extension pipe 5 through a first delivery pipe, and the water inlet end of the submersible pump is also connected to the sea through a second delivery pipe; the water outlet end of the submersible pump is connected to the other end of the extension pipe 5 through a third delivery pipe, and the water outlet end of the submersible pump is also connected to the sea through a fourth delivery pipe; the air outlet end of the air compressor is connected to the other end of the extension pipe 5 through a fifth delivery pipe; a first electrically-controlled valve is provided on the first delivery pipe, a second electrically-controlled valve is provided on the second delivery pipe, a third electrically-controlled valve is provided on the third delivery pipe, a fourth electrically-controlled valve is provided on the fourth delivery pipe, and a fifth electrically-controlled valve is provided on the fifth delivery pipe; each electrically-controlled valve is electrically connected to the PLC controller respectively, so that the PLC controller can control the sinking and floating of each suction cylinder 201 according to actual operation.
[0054] As a preferred technical solution of this embodiment, in order to facilitate transfer, two lifting ears are symmetrically arranged on the outer side of the box body of each pump skid 4 to facilitate connection with the crane on the operating vessel for easy lifting.
[0055] Example 2
[0056] See also Figure 6 and Figure 7 The wind power construction method using the temporary pile shoe of the suction tube of Example 1 is implemented, and the steps are as follows:
[0057] S1. According to the requirement that two temporary suction tube pile shoes 8 are respectively configured at both ends of the bottom side of the platform ship 10, the transport ship transports four temporary suction tube pile shoes 8 and their connecting beams 11 to the designated position, and the four temporary suction tube pile shoes 8 are hoisted to the designated sinking point by the crane ship to adapt to the stationing position of the platform ship 10;
[0058] S2. Two connecting beams 11 spaced apart along the width direction of the platform ship 10 are hingedly connected between the two temporary pile shoes 8 of the suction cylinder at the same end of the corresponding platform ship 10, and two connecting beams 11 spaced apart along the length direction of the platform ship 10 are hingedly connected between the two temporary pile shoes 8 of the suction cylinder at the same side of the corresponding platform ship 10; wherein each connecting beam 11 has a truss structure, and its two ends are respectively hingedly connected to the walls of two suction cylinders arranged oppositely; then, the transport ship and the crane ship leave the site,
[0059] S3, the four suction cylinder temporary pile shoes 8 use the pump skids on them to drive the suction cylinder group to sink to the specified depth position, and then use divers or underwater robots to recover the pump skids on each suction cylinder temporary pile shoe 8 to the ship;
[0060] S4, the platform ship 10 enters the site and sails to the top of the four temporary pile shoes 8 of the suction cylinders, and lowers the four pile legs 6 through its own positioning system to be inserted into the gravel layers of the temporary pile shoe structures 8 of the four suction cylinders respectively; after the platform ship 10 is stable, the wind power operation at the position can be carried out;
[0061] S5. After the platform ship 10 completes the operation task at the position, divers or underwater robots are used to transport the pump skid to the top surface platform of each suction cylinder temporary pile shoe 8, so as to use multiple pump skids to float the suction cylinder group to a movable state;
[0062] S6. A total of eight winches 12 corresponding to the positions of the four temporary suction tube pile shoes 8 are arranged on both sides of the platform ship 10. The eight winches 12 lower steel wire ropes and are respectively connected to the two lifting ears on the four temporary suction tube pile shoes 8 located on one side of the ship's side, so that the platform ship 10 and the four temporary suction tube pile shoes are connected as one; the platform ship 10 is used to synchronously drive the four temporary suction tube pile shoes 8 to move to the next construction position, and the connection between the eight winches 12 and the lifting ears on the four temporary suction tube pile shoes 8 is released;
[0063] S7, repeating the above steps S3 to S6, the platform vessel 10 completes the wind power installation work at all construction positions by repeatedly stationing and shifting;
[0064] S8. After the wind power installation work at the last construction site is completed, the platform ship 10 leaves the site and removes the connecting beams between the temporary pile shoes 8 of the suction cylinders; the transport ship and the crane ship enter the site, and the crane ship lifts the four temporary pile shoes 8 of the suction cylinders onto the transport ship to be transported back to the dock.
[0065] Example 3
[0066] See also Figure 3 to Figure 7 When the power of the platform ship 10 is insufficient to drive the four suction cylinder temporary pile shoes 8 at the same time, another wind power construction method needs to be adopted, and the steps are as follows:
[0067] S1. According to the requirement that two temporary suction tube pile shoes 8 are respectively configured at both ends of the bottom side of the platform ship 10, the transport ship transports four temporary suction tube pile shoes 8 and their connecting beams 11 to the designated position, and the four temporary suction tube pile shoes 8 are hoisted to the designated sinking point by the crane ship to adapt to the stationing position of the platform ship 10;
[0068] S2. Two connecting beams 11 spaced apart along the width direction of the platform ship 10 are hingedly connected between the two temporary pile shoes 8 of the suction cylinder at the same end of the corresponding platform ship 10, and two connecting beams 11 spaced apart along the length direction of the platform ship 10 are hingedly connected between the two temporary pile shoes 8 of the suction cylinder at the same side of the corresponding platform ship 10; wherein each connecting beam 11 has a truss structure, and its two ends are respectively hingedly connected to the walls of two suction cylinders arranged oppositely; then, the transport ship and the crane ship leave the site,
[0069] S3, the four suction cylinder temporary pile shoes 8 use the pump skids on them to drive the suction cylinder group to sink to the specified depth position, and then use divers or underwater robots to recover the pump skids on each suction cylinder temporary pile shoe 8 to the ship;
[0070] S4, the platform ship 10 enters the site and sails to the top of the four temporary pile shoes 8 of the suction cylinders, and lowers the four pile legs 6 through its own positioning system to be inserted into the gravel layers of the temporary pile shoe structures 8 of the four suction cylinders respectively; after the platform ship 10 is stable, the wind power operation at the position can be carried out;
[0071] S5. After the platform ship 10 completes the operation task at the position, it leaves the site. The barge 7 enters the site and sails to the top of the two temporary pile shoes 8 of the suction cylinders on either side of the platform ship 10. Then, a diver or an underwater robot is used to transport the pump skid to the top surface platform of each temporary pile shoe 8 of the suction cylinder, so that the suction cylinder group can float to a movable state by using multiple pump skids. At this time, the bottom of the barge is embedded in the embedding groove set on the top platform of the two temporary pile shoes 8 of the suction cylinders.
[0072] S6. The hooks of the eight mast cranes 9 on the barge 7 are lowered with lifting ropes, so that each mast crane hook is connected to the eight lifting ears on the two temporary pile shoes 8 of the suction cylinders through the wire rope, so as to connect the barge 7 and the two temporary pile shoes 8 of the suction cylinders as a whole; the four temporary pile shoes of the suction cylinders 8 are shifted to the next construction position in two times by driving the two temporary pile shoes of the suction cylinders 8 to shift each time by the barge 7;
[0073] S7, repeating the above steps S3 to S6, with the cooperation of the barge 7, the platform ship 10 completes the wind power installation work at all construction positions by repeatedly stationing and shifting;
[0074] S8. After the wind power installation work at the last construction site is completed, the platform ship 10 leaves the site and removes the connecting beams between the temporary pile shoes 8 of the suction cylinders; the transport ship and the crane ship enter the site, and the crane ship lifts the four temporary pile shoes 8 of the suction cylinders onto the transport ship to be transported back to the dock.
Claims
1. A temporary pile shoe for suction tubes used in deep sea wind power, characterized in that: The invention comprises a top platform (1) and a suction cylinder group (2) which are arranged in sequence from top to bottom; wherein the top platform (1) is a platform body with a groove at the center, and four lifting ears (105) are evenly arranged on the top of the platform along the circumferential direction; a crushed stone layer (3) is laid in the groove of the top platform (1); the suction cylinder group (2) comprises N suction cylinders (201) which are evenly arranged along the circumferential direction and fixed on the bottom of the top platform (1); the conveying pipes on the tops of the N suction cylinders (201) They are respectively passed through pipeline through-holes opened on the bottom surface of the top platform (1), and each delivery pipe end is connected to an extension pipe (5), and the other end of the extension pipe (5) protrudes above the gravel layer (3); N pump skids (4) are also movably arranged on the gravel layer (3) of the top platform (1), and they are respectively matched with the four suction cylinders (201) in the suction cylinder group (2) to drive the four suction cylinders (201) to sink to a stationary state, or float up to a movable state.
2. The temporary pile shoe for suction tube used for deep sea wind power according to claim 1 is characterized in that: The depth of the groove in the center of the top platform (1) is 4m to 5m.
3. The temporary pile shoe for suction tube used for deep sea wind power according to claim 1 is characterized in that: The top platform (1) comprises a horizontally arranged platform plate (101), two first vertical plates (102) being vertically fixed at a group of opposite edges on the top surface, two second vertical plates (103) being vertically fixed at another group of opposite edges on the top surface, and adjacent first vertical plates (102) and second vertical plates (103) being vertically connected and fixed; two horizontal plates (104) are symmetrically fixed on both sides of the top surfaces of the two first vertical plates (102), and the two horizontal plates are simultaneously connected and fixed to the top side edges of the two second vertical plates (103), so that a top surface platform capable of installing four lifting ears (105) is provided on the tops of the four vertical plates.
4. The temporary pile shoe for suction tube used for deep sea wind power according to claim 3 is characterized in that: An inverted trapezoidal notch (1021) is centrally provided on the top sides of the two first vertical plates (102), and the width of the inverted trapezoidal notch (1021) is adapted to the width of the barge, so that an embedding groove is formed on the top side of the top platform (1).
5. The temporary pile shoe for suction tube used for deep sea wind power according to claim 1 is characterized in that: The crushed material accumulation layer (3) has a thickness of 2.5 m to 3.5 m and is formed by the accumulation of crushed stones or flexible crushed materials with a diameter of 10 mm to 50 mm.
6. The temporary pile shoe for suction tube used for deep sea wind power according to claim 1 is characterized in that: Each pump skid (4) comprises a submersible pump, an air compressor and a generator arranged in a box; wherein the generator is electrically connected to the submersible pump and the air compressor respectively.
7. The temporary pile shoe for suction tube used for deep sea wind power according to claim 6 is characterized in that: The pump skid (4) also includes a PLC controller; the water inlet end of the submersible pump is connected to the other end of the extension pipe (5) through a first delivery pipe, and the water inlet end of the submersible pump is also connected to the sea through a second delivery pipe; the water outlet end of the submersible pump is connected to the other end of the extension pipe (5) through a third delivery pipe, and the water outlet end of the submersible pump is also connected to the sea through a fourth delivery pipe; the air outlet end of the air compressor is connected to the other end of the extension pipe (5) through a fifth delivery pipe; a first electrically controlled valve is provided on the first delivery pipe, a second electrically controlled valve is provided on the second delivery pipe, a third electrically controlled valve is provided on the third delivery pipe, a fourth electrically controlled valve is provided on the fourth delivery pipe, and a fifth electrically controlled valve is provided on the fifth delivery pipe; each electrically controlled valve is electrically connected to the PLC controller respectively.
8. The temporary pile shoe for suction tube used for deep sea wind power according to claim 6 or 7, characterized in that: Two lifting ears are symmetrically arranged on the outer side of the box body of each pump skid (4).
9. A barge wind power construction method using a temporary pile shoe of a suction tube for deep sea wind power as claimed in any one of claims 1 to 8, characterized in that: Here are the steps: S1. According to the requirement of configuring two temporary pile shoes of suction cylinders at both ends of the bottom side of the platform ship, the transport ship transports four temporary pile shoes of suction cylinders and their connecting beams to the designated machine position, and hoists the four temporary piles of suction cylinders to the designated sinking point by the crane ship to adapt to the stationing position of the platform ship; S2. Two connection beams spaced apart along the width direction of the platform ship 10 are hingedly connected between the two temporary pile shoes of the suction cylinder at the same end of the corresponding platform ship, and two connection beams spaced apart along the length direction of the platform ship are hingedly connected between the two temporary pile shoes of the suction cylinder at the same side of the corresponding platform ship; the transport ship and the crane ship leave the site; S3. The four temporary pile shoes of the suction cylinders use the pump skids on them to drive the suction cylinder group to sink to the specified depth, and then recover the pump skids to the ship; S4. The platform ship enters the site and sails to the top of the temporary pile shoes of the four suction cylinders. Through its own positioning system, it lowers the four pile legs and inserts them into the gravel layers of the temporary pile shoes of the four suction cylinders respectively. After the platform ship is stable, the wind power operation at the position can be carried out; S5. After the platform ship completes the operation task at the position, it transports the pump skid to the top surface platform of the temporary pile shoes of each suction cylinder, so as to use multiple pump skids to float the suction cylinder group to a movable state; S6. A total of eight winches corresponding to the positions of the four temporary pile shoes of the suction cylinders are arranged on both sides of the platform ship. The eight winches lower steel wire ropes and are respectively connected to the two lifting ears on the temporary pile shoes of the four suction cylinders located on one side of the ship's side, so that the platform ship and the four temporary pile shoes of the suction cylinders are connected as one; the platform ship is used to synchronously drive the four temporary pile shoes of the suction cylinders to move to the next construction position, and the connection between the eight winches and the lifting ears on the temporary pile shoes of the four suction cylinders is released; S7, repeating the above steps S3 to S6, the platform ship completes the wind power installation work at all construction positions by repeatedly stationing and shifting; S8. After completing the wind power installation work at the last construction site, the platform ship leaves the site and removes the connecting beams between the temporary pile shoes of the suction cylinders; the transport ship and the crane ship enter the site, and the crane ship lifts the four temporary pile shoes of the suction cylinders onto the transport ship for transportation back to the dock.
10. A platform ship wind power construction method using a temporary pile shoe of a suction tube for deep sea wind power as claimed in any one of claims 1 to 8, characterized in that: Here are the steps: S1. According to the requirement of configuring two temporary pile shoes of suction cylinders at both ends of the bottom side of the platform ship, the transport ship transports four temporary pile shoes of suction cylinders and their connecting beams to the designated machine position, and hoists the four temporary piles of suction cylinders to the designated sinking point by the crane ship to adapt to the stationing position of the platform ship; S2. Two connection beams spaced apart along the width direction of the platform ship 10 are hingedly connected between the two temporary pile shoes of the suction cylinder at the same end of the corresponding platform ship, and two connection beams spaced apart along the length direction of the platform ship are hingedly connected between the two temporary pile shoes of the suction cylinder at the same side of the corresponding platform ship; the transport ship and the crane ship leave the site; S3. The four temporary pile shoes of the suction cylinders use the pump skids on them to drive the suction cylinder group to sink to the specified depth, and then recover the pump skids to the ship; S4, the platform ship enters the site and sails to the top of the four temporary pile shoes 8 of the suction cylinders, and lowers the four pile legs through its own positioning system to be inserted into the gravel layers of the temporary pile shoes of the four suction cylinders respectively; after the platform ship is stable, the wind power operation at the position can be carried out; S5. After the platform ship completes the operation task at the position, it leaves the site. The barge enters the site and sails to the top of the two temporary pile shoes of the suction cylinders on either side of the platform ship. Then, divers or underwater robots are used to transport the pump skid to the top surface platform of each temporary pile shoe of the suction cylinder, so that the suction cylinder group is floated to a movable state by using multiple pump skids, and the bottom of the barge is embedded in the embedding groove set on the top platform of the two temporary pile shoes of the suction cylinders. S6. The hooks of the eight mast cranes on the barge are lowered with lifting ropes, so that each mast crane hook is connected to the eight lifting ears on the two temporary pile shoes of the suction cylinders through the wire rope, so as to connect the barge and the two temporary pile shoes of the suction cylinders as a whole; the four temporary pile shoes of the suction cylinders are shifted to the next construction position in two times by driving the two temporary pile shoes of the suction cylinders to shift each time by the barge; S7, repeating the above steps S3 to S6, with the cooperation of the barge, the platform ship completes the wind power installation work at all construction positions by repeatedly stationing and shifting; S8. After completing the wind power installation work at the last construction site, the platform ship leaves the site and removes the connecting beams between the temporary pile shoes of the suction cylinders; the transport ship and the crane ship enter the site, and the crane ship lifts the four temporary pile shoes of the suction cylinders onto the transport ship for transportation back to the dock.