Bridge construction integrated monitoring and early warning system based on artificial intelligence

By introducing an artificial intelligence-based monitoring and early warning system into the bridge construction monitoring system, using sensors for accurate detection and real-time alarms through the alarm module, the problem that existing systems cannot accurately detect and alarm is solved, and construction safety is improved.

CN119649565AInactive Publication Date: 2025-03-18HUBEI LUQIAO GRP MUNICIPAL CONSTR ENG CO LTD

Patent Information

Application Number
CN202411956445.7
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-12-28
Publication Date
2025-03-18
Estimated Expiration
Not applicable · inactive patent

AI Technical Summary

Technical Problem

The existing bridge construction monitoring system cannot accurately detect the pressure, deformation and other parameters of the bridge, and cannot directly alarm when danger occurs.

Method used

The integrated monitoring and early warning system for bridge construction based on artificial intelligence is adopted, including a central data processor, bridge data acquisition module, bridge monitoring module, alarm module and display module. It is accurately detected through stress sensors, strain sensors, and displacement sensors, and real-time alarm and data display through alarm modules and display modules.

Benefits of technology

Accurate detection and real-time alarm of bridges are achieved, which can effectively prevent dangers during bridge construction and improve construction safety.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119649565A_ABST
    Figure CN119649565A_ABST
Patent Text Reader

Abstract

The invention provides a bridge construction integrated monitoring and early warning system based on artificial intelligence, which comprises a central data processor, a bridge data acquisition module, a bridge monitoring module, an alarm module and a display module, and is characterized in that the central data processor is wirelessly connected with the bridge data acquisition module and the bridge monitoring module, and the alarm module corresponds to the display module. The bridge monitoring module comprises a monitoring alarm device, the monitoring alarm device comprises a mounting frame, a camera and a protection structure are mounted on the mounting frame, the camera corresponds to the protection structure, and the alarm module comprises an alarm structure fixed on the mounting frame. A bridge can be directly detected through the stress sensor, the strain sensor and the displacement sensor of the monitoring structure, the accuracy is guaranteed, an alarm can be given through the alarm module, bridge information is displayed through the display module, and therefore danger can be prevented, the camera and the protection structure are installed on the installation frame, and the safety is improved. And auxiliary monitoring can be carried out through the camera.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of bridge construction, and in particular to an integrated monitoring and early warning system for bridge construction based on artificial intelligence. Background Art

[0002] A bridge generally refers to a structure erected over rivers, lakes, and seas to enable vehicles and pedestrians to pass smoothly. In order to adapt to the modern high-speed development of the transportation industry, a bridge is also extended to a building that is erected across mountain streams, poor geology, or to meet other traffic needs to make passage more convenient. The bridge construction process mainly refers to the bridge construction technology and construction organization, construction management, construction quality, etc. in accordance with the design content. During the bridge construction process, the bridge needs to be monitored to prevent danger. For example, the patent with announcement number CN215182384U discloses a bridge construction monitoring and early warning system. The utility model includes : A pre-installed plate, a protective box, a monitor, an environmental sensor, a protective top plate, a protective control structure and an equipment rapid erection structure, wherein the protective box is fixedly mounted on the top of the pre-installed plate, the equipment rapid erection structure is arranged on the pre-installed plate, the monitor is arranged in the protective box, the top of the protective box is an opening, movable blocks are fixedly mounted on both sides of the monitor, and movable grooves are provided on the inner walls on both sides of the protective box. The device detects the bridge through detectors and environmental sensors, but cannot directly and accurately detect the pressure, deformation, etc. of the bridge, is prone to errors, and cannot directly alarm when danger occurs.

[0003] To this end, the present invention provides an integrated monitoring and early warning system for bridge construction based on artificial intelligence. Summary of the invention

[0004] In view of the shortcomings of the prior art, the purpose of the present invention is to provide an integrated monitoring and early warning system for bridge construction based on artificial intelligence to solve the problems raised in the above-mentioned background technology. The present invention can directly detect the bridge through the stress sensor, strain sensor, and displacement sensor of the monitoring structure to ensure accuracy, and can give an alarm through the alarm module and display the bridge information through the display module, so as to prevent danger; it can perform auxiliary monitoring through the camera and protect the camera through the protective structure to prevent the camera from being damaged by the complex construction environment; it can also be powered by solar panels, and the installation position and angle of the solar panels can be changed to ensure the power supply effect.

[0005] In order to achieve the above-mentioned purpose, the present invention is implemented through the following technical scheme: an integrated monitoring and early warning system for bridge construction based on artificial intelligence, including a central data processor, a bridge data acquisition module, a bridge monitoring module, an alarm module and a display module, the central data processor is wirelessly connected to the bridge data acquisition module and the bridge monitoring module, the alarm module and the display module correspond, the bridge monitoring module includes a monitoring alarm device, the monitoring alarm device includes a mounting frame, a camera and a protective structure are installed on the mounting frame, the camera corresponds to the protective structure, the alarm module includes an alarm structure fixed on the mounting frame, a first controller is installed on the mounting frame, and a power supply structure is installed on one side of the mounting frame, the bridge data acquisition module includes a monitoring device, the monitoring device includes an outer shell, a second controller is installed in the outer shell, and a monitoring structure is installed on the outer shell, and the first controller and the second controller are both wirelessly connected to the central data processor.

[0006] Furthermore, the alarm module also includes a short message sending alarm module, and the alarm structure is connected to the first controller via a data line.

[0007] Furthermore, the alarm structure includes an alarm and a plurality of indicator lights. A plurality of grooves are provided on the peripheral side of the mounting frame. The indicator lights are located in the grooves. The alarm is fixedly connected to the mounting frame.

[0008] Furthermore, the display module includes a Web-based visual monitoring platform for displaying real-time data, historical data, alarm information, etc. of bridge construction.

[0009] Furthermore, a sensor mounting plate is fixed on the housing, and the monitoring structure includes a stress sensor, a strain sensor, a displacement sensor, etc. The stress sensor, the strain sensor and the displacement sensor are all fixedly connected to the sensor mounting plate.

[0010] Furthermore, a mounting clamping plate is fixed on the lower side of the mounting frame, a bottom plate is installed on the lower side of the mounting frame, a fixing plate is fixed on the bottom plate, and the fixing plate and the mounting clamping plate are fixedly connected by bolts.

[0011] Furthermore, a through slot is formed on the mounting clamping plate, a fixed mounting plate is slidably fitted in the through slot, and the fixed mounting plate is fixedly connected to the mounting clamping plate by bolts.

[0012] Furthermore, one side of the fixed mounting plate is rotatably engaged with a first rotating shaft, both ends of the first rotating shaft are threadedly engaged with nuts, one side of the first rotating shaft is rotatably engaged with a mounting frame, the power supply structure includes a solar panel, the solar panel is fixedly connected to the mounting frame, a second rotating shaft is installed between the mounting frame and the first rotating shaft, and a positioning screw is installed between the second rotating shaft and the first rotating shaft.

[0013] Furthermore, a first battery is installed in the mounting frame, a second battery is installed in the outer shell, and the first battery corresponds to the solar panel.

[0014] Furthermore, the mounting frame is fixedly connected to the camera, and the protection structure includes a protection cover, which is made of a colorless and transparent material, and the protection cover is fixedly connected to the mounting frame by bolts.

[0015] Beneficial effects of the present invention: The integrated monitoring and early warning system for bridge construction based on artificial intelligence of the present invention comprises a shell; a second controller; a monitoring structure; a stress sensor; a strain sensor; a displacement sensor; a mounting frame; a camera; a protective structure; a power supply structure; and a solar panel.

[0016] A second controller is installed in the outer shell, and a monitoring structure is installed on the outer shell. The stress sensor, strain sensor, and displacement sensor of the monitoring structure can be used to directly detect the bridge to ensure accuracy, and an alarm can be issued through the alarm module. The bridge information can be displayed through the display module to prevent danger. A camera and a protective structure are installed on the mounting frame. The camera can be used for auxiliary monitoring. The camera can be protected by the protective structure to prevent the camera from being damaged by a complex construction environment. A power supply structure is installed on one side of the mounting frame. The power supply structure can be used to supply power through the solar panels, and the installation position and angle of the solar panels can be changed to ensure the power supply effect. BRIEF DESCRIPTION OF THE DRAWINGS

[0017] Figure 1 It is a schematic diagram of the integrated monitoring and early warning system for bridge construction based on artificial intelligence of the present invention;

[0018] Figure 2 It is a schematic diagram of the monitoring device in the integrated monitoring and early warning system for bridge construction based on artificial intelligence of the present invention;

[0019] Figure 3 It is a schematic diagram of the monitoring and alarm device in the integrated monitoring and early warning system for bridge construction based on artificial intelligence of the present invention;

[0020] Figure 4 It is a schematic diagram of the assembled three-dimensional structure of the monitoring and alarm device in the integrated monitoring and early warning system for bridge construction based on artificial intelligence of the present invention;

[0021] Figure 5 It is an exploded diagram of the monitoring and alarm device in the integrated monitoring and early warning system for bridge construction based on artificial intelligence of the present invention;

[0022] Figure 6 It is a schematic diagram of the assembly cross-sectional structure of the monitoring and alarm device in the integrated monitoring and early warning system for bridge construction based on artificial intelligence of the present invention;

[0023] Figure 7It is a schematic diagram of the assembly three-dimensional structure of the installation frame and solar panels in the integrated monitoring and early warning system for bridge construction based on artificial intelligence of the present invention;

[0024] Figure 8 It is a schematic diagram of the assembly cross-sectional structure of the installation frame and solar panels in the integrated monitoring and early warning system for bridge construction based on artificial intelligence of the present invention;

[0025] Fig. 9 It is a schematic diagram of the assembled three-dimensional structure of the monitoring device in the integrated monitoring and early warning system for bridge construction based on artificial intelligence of the present invention;

[0026] Fig.10 It is a schematic diagram of the assembly cross-sectional structure of the monitoring device in the integrated monitoring and early warning system for bridge construction based on artificial intelligence of the present invention;

[0027] In the figure: 1. monitoring alarm device; 2. mounting plate; 3. fixing plate; 4. bottom plate; 5. mounting frame; 6. protective cover; 7. camera; 8. through slot; 9. fixed mounting plate; 10. mounting frame; 11. first rotating shaft; 12. solar panel; 13. second rotating shaft; 14. positioning screw; 15. alarm; 16. groove; 17. indicator light; 18. first battery; 19. first controller; 20. monitoring device; 21. housing; 22. second controller; 23. second battery; 24. sensor mounting plate. DETAILED DESCRIPTION

[0028] In order to make the technical means, creative features, objectives and effects achieved by the present invention easy to understand, the present invention is further explained below in conjunction with specific implementation methods.

[0029] See also Figures 1 to 10 The present invention provides a technical solution: an integrated monitoring and early warning system for bridge construction based on artificial intelligence, comprising a central data processor, a bridge data acquisition module, a bridge monitoring module, an alarm module and a display module, wherein the central data processor is wirelessly connected to the bridge data acquisition module and the bridge monitoring module, and the alarm module and the display module correspond to each other, the bridge monitoring module comprises a monitoring and alarm device 1, the monitoring and alarm device 1 comprises a mounting frame 5, a camera 7 and a protective structure are mounted on the mounting frame 5, the camera 7 corresponds to the protective structure, the alarm module comprises an alarm structure fixed on the mounting frame 5, a first controller 19 is mounted on the mounting frame 5, a power supply structure is mounted on one side of the mounting frame 5, the bridge data acquisition module comprises a monitoring device 20, the monitoring device 20 comprises a shell 21, a second controller 22 is mounted in the shell 21, a monitoring structure is mounted on the shell 21, the first controller 19 and the second controller 22 are both wirelessly connected to the central data processor, the second controller 22 comprises a data acquisition and processing chip, and the first controller 19 comprises a single-chip microcomputer.

[0030] In this embodiment, the alarm module also includes a text message sending alarm module. The alarm structure is connected to the first controller 19 via a data line. The alarm structure includes an alarm 15 and multiple indicator lights 17. Multiple grooves 16 are opened on the surrounding side of the mounting frame 5. The indicator lights 17 are located in the grooves 16. The alarm 15 is fixedly connected to the mounting frame 5.

[0031] Specifically, when abnormal data is detected, the alarm function can be triggered, and a signal can be sent to the first controller 19 through the central data processor, so that the first controller 19 controls the indicator light 17 to light up, and at the same time controls the alarm 15 to make a sound, so that an alarm can be sounded directly on the construction site, and a text message can be sent directly to the construction personnel's mobile phone through the central data processor for early warning.

[0032] The display module includes a Web-based visual monitoring platform, which is used to display real-time data, historical data and alarm information of bridge construction, making it convenient for construction managers to conduct remote monitoring and management.

[0033] A sensor mounting plate 24 is fixed on the housing 21 . The monitoring structure includes a stress sensor, a strain sensor, a displacement sensor, etc. The stress sensor, the strain sensor, and the displacement sensor are all fixedly connected to the sensor mounting plate 24 .

[0034] Specifically, high-precision stress sensors, strain sensors, and displacement sensors can detect the bridge status in real time, and send them to the central data processor in real time through the second controller 22. After being processed by the central data processor, they can be uploaded to the cloud, thereby facilitating data analysis.

[0035] A mounting clamping plate 2 is fixed to the lower side of the mounting frame 5 , a bottom plate 4 is installed to the lower side of the mounting frame 5 , a fixing plate 3 is fixed on the bottom plate 4 , and the fixing plate 3 is fixedly connected to the mounting clamping plate 2 by bolts.

[0036] Specifically, the device can be clamped and installed at a certain position through the installation clamping plate 2, and the device can also be installed on a surface through the bottom plate 4, thereby expanding the installation range of the device and facilitating the installation and fixation of the device.

[0037] A through groove 8 is provided on the mounting clamp plate 2, and a fixed mounting plate 9 is slidably fitted in the through groove 8. The fixed mounting plate 9 is fixedly connected to the mounting clamp plate 2 by bolts. A first rotating shaft 11 is rotatably fitted on one side of the fixed mounting plate 9. Nuts are threadedly fitted on both ends of the first rotating shaft 11. A mounting frame 10 is rotatably fitted on one side of the first rotating shaft 11. The power supply structure includes a solar panel 12, which is fixedly connected to the mounting frame 10. A second rotating shaft 13 is installed between the mounting frame 10 and the first rotating shaft 11, and a positioning screw 14 is installed between the second rotating shaft 13 and the first rotating shaft 11. A first battery 18 is installed in the mounting frame 5, and a second battery 23 is installed in the outer shell 21. The first battery 18 corresponds to the solar panel 12.

[0038] Specifically, the first battery 18 can be charged by the solar panel 12. When the solar panel 12 needs to be installed, the fixed mounting plate 9 can be slid into the through groove 8. After adjusting to a suitable position, it can be fixed by bolts. Then, the first rotating shaft 11 and the second rotating shaft 13 can be rotated to adjust the angle of the solar panel 12, thereby ensuring that the solar panel 12 can receive solar energy as much as possible.

[0039] The mounting frame 5 is fixedly connected to the camera 7 . The protection structure includes a protection cover 6 . The protection cover 6 is made of a colorless and transparent material. The protection cover 6 is fixedly connected to the mounting frame 5 by bolts.

[0040] Specifically, the camera 7 can be protected by the protective cover 6 , and the protective cover 6 can be replaced, thereby reducing the maintenance cost of the camera 7 .

[0041] In addition, it should be understood that although the present specification is described according to implementation modes, not every implementation mode contains only one independent technical solution. This description of the specification is only for the sake of clarity. Those skilled in the art should regard the specification as a whole. The technical solutions in each embodiment may also be appropriately combined to form other implementation modes that can be understood by those skilled in the art.

Claims

1. An integrated monitoring and early warning system for bridge construction based on artificial intelligence, including a central data processor, a bridge data acquisition module, a bridge monitoring module, an alarm module and a display module, characterized in that: The central data processor is wirelessly connected to the bridge data acquisition module, the bridge monitoring module, the alarm module and the display module. The bridge monitoring module comprises a monitoring alarm device (1). The monitoring alarm device (1) comprises a mounting frame (5). A camera (7) and a protective structure are mounted on the mounting frame (5). The camera (7) corresponds to the protective structure. The alarm module comprises an alarm structure fixed on the mounting frame (5). A first controller (19) is mounted on the mounting frame (5). A power supply structure is mounted on one side of the mounting frame (5). The bridge data acquisition module comprises a monitoring device (20). The monitoring device (20) comprises a housing (21). A second controller (22) is mounted in the housing (21). The housing (21) is provided with a monitoring structure. Both the first controller (19) and the second controller (22) are wirelessly connected to the central data processor.

2. The integrated monitoring and early warning system for bridge construction based on artificial intelligence according to claim 1 is characterized by: The alarm module also includes a short message sending alarm module, and the alarm structure is connected to the first controller (19) via a data line.

3. The integrated monitoring and early warning system for bridge construction based on artificial intelligence according to claim 1 is characterized by: The alarm structure comprises an alarm (15) and a plurality of indicator lights (17); a plurality of grooves (16) are provided on the peripheral side of the mounting frame (5); the indicator lights (17) are located in the grooves (16); and the alarm (15) is fixedly connected to the mounting frame (5).

4. The integrated monitoring and early warning system for bridge construction based on artificial intelligence according to claim 1 is characterized by: The display module includes a Web-based visual monitoring platform for displaying real-time data, historical data, alarm information, etc. of bridge construction.

5. The integrated monitoring and early warning system for bridge construction based on artificial intelligence according to claim 1 is characterized by: A sensor mounting plate (24) is fixed on the housing (21); the monitoring structure comprises a stress sensor, a strain sensor, a displacement sensor, etc.; the stress sensor, the strain sensor and the displacement sensor are all fixedly connected to the sensor mounting plate (24).

6. The integrated monitoring and early warning system for bridge construction based on artificial intelligence according to claim 1 is characterized by: A mounting clamping plate (2) is fixed on the lower side of the mounting frame (5), a bottom plate (4) is installed on the lower side of the mounting frame (5), a fixing plate (3) is fixed on the bottom plate (4), and the fixing plate (3) and the mounting clamping plate (2) are fixedly connected by bolts.

7. The integrated monitoring and early warning system for bridge construction based on artificial intelligence according to claim 6 is characterized by: The mounting clamping plate (2) is provided with a through slot (8), a fixed mounting plate (9) is slidably fitted in the through slot (8), and the fixed mounting plate (9) is fixedly connected to the mounting clamping plate (2) by bolts.

8. The integrated monitoring and early warning system for bridge construction based on artificial intelligence according to claim 7 is characterized by: One side of the fixed mounting plate (9) is rotatably matched with a first rotating shaft (11), both ends of the first rotating shaft (11) are threadedly matched with nuts, one side of the first rotating shaft (11) is rotatably matched with a mounting frame (10), the power supply structure comprises a solar panel (12), the solar panel (12) is fixedly connected to the mounting frame (10), a second rotating shaft (13) is installed between the mounting frame (10) and the first rotating shaft (11), and a positioning screw (14) is installed between the second rotating shaft (13) and the first rotating shaft (11).

9. The integrated monitoring and early warning system for bridge construction based on artificial intelligence according to claim 8 is characterized by: The mounting frame (5) is provided with a first battery (18), the housing (21) is provided with a second battery (23), and the first battery (18) corresponds to the solar panel (12).

10. The integrated monitoring and early warning system for bridge construction based on artificial intelligence according to claim 1 is characterized by: The mounting frame (5) is fixedly connected to the camera (7); the protective structure comprises a protective cover (6); the protective cover (6) is made of a colorless and transparent material; the protective cover (6) is fixedly connected to the mounting frame (5) by bolts.

Citation Information

Patent Citations

  • A bridge construction monitoring and early warning system

    CN215182384U

Cited By

  • Bridge V-shaped pier top box girder formwork supporting construction method

    CN121580476A